You are on page 1of 1

UPS connectivity for pilot plant units at RCD

Activity ID Activity Name Original Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Q-TARP693 UPS connectivity for pilot plant units at RCD
Q-TARP 37 03-Aug-21 22-Sep-21 22-Sep-21, Q-TARP693 UPS connectivity for pilot plant units at RCD

Q-TARP693.1 General
Q-TAR 3 03-Aug-2 05-Aug-2 05-Aug-21, Q-TARP693.1 General
A1000 Award Of Contract 1 03-Aug-2 03-Aug-2 Award Of Contract
A1010 Initial Kick Of Meeting 1 05-Aug-2 05-Aug-2 Initial Kick Of Meeting
Q-TARP693.2 Documentation
Q-TAR 14 09-Aug-2 25-Aug-2 25-Aug-21, Q-TARP693.2 Documentation

A1020 Material Approval & Other Documentation 14 09-Aug-2 25-Aug-2 Material Approval & Other Documentation
Q-TARP693.3 Procurement
Q-TAR 7 26-Aug-2 02-Sep-2 02-Sep-21, Q-TARP693.3 Procurement
A1030 Procurement Of Cable Trays 7 26-Aug-2 02-Sep-2 Procurement Of Cable Trays
A1040 Procurement Of Cables 5 26-Aug-2 31-Aug-2 Procurement Of Cables
A1050 Procurement Of DB & Other Accessories 5 26-Aug-2 31-Aug-2 Procurement Of DB & Other Accessories
Q-TARP693.4 Construction
Q-TAR 14 02-Sep-2 18-Sep-2 18-Sep-21, Q-TARP693.4 Construction
A1060 Installation Of Trays 6 02-Sep-2 08-Sep-2 Installation Of Trays
A1070 Installation Of Cables 5 08-Sep-2 13-Sep-2 Installation Of Cables
A1080 DB Installation 2 14-Sep-2 15-Sep-2 DB Installation
A1090 Testing 2 16-Sep-2 18-Sep-2 Testing
Q-TARP693.5 Final Documentation & Handover
Q-TAR 5 16-Sep-2 22-Sep-2 22-Sep-21, Q-TARP693.5 Final Documentation & Handover
A1100 Final Documentation 4 16-Sep-2 21-Sep-2 Final Documentation
A1110 Final Handover 1 22-Sep-2 22-Sep-2 Final Handover