Revise Schedule June July August September October November December January February March April May June July August
Floor Floor Framing Type Contractor qty
Start Finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
GF GF-2ND 15-Jun-20 11-Jan-21
CFRP Beam Lalaguna 3 9-Nov-20 11-Jan-21 64
L2 2ND-3RD 14-Dec-20 13-Apr-21
CFRP Column Lalaguna 6 11-Jan-21 31-May-21 141
Beam Lalaguna 2 11-Jan-21 31-May-21 141
L3 3RD-4TH 16-Nov-20 22-Feb-21
CFRP Shearwall Lalaguna 1 7-Dec-20 22-Feb-21 78
Column Lalaguna 3 7-Dec-20 22-Feb-21 78
Beam Lalaguna 3 7-Dec-20 22-Feb-21 78
L4 4TH-5TH 19-Oct-20 22-Feb-21
CFRP Shearwall Lalaguna 3 7-Dec-20 22-Feb-21 78
Column Lalaguna 2 7-Dec-20 22-Feb-21 78
Beam Lalaguna 3 7-Dec-20 22-Feb-21 78
L5 5TH-6TH beam lalaguna 6 7-Dec-20 15-Feb-21 71
L6 6TH-7TH 24-Aug-20 18-Jan-21
CFRP Beam Lalaguna 2 7-Dec-20 18-Jan-21 43
L7 7TH-8TH 27-Jul-20 13-Feb-21
CFRP Shearwall Lalaguna 1 7-Dec-20 20-Jan-21 45
Column Lalaguna 9 9-Nov-20 13-Feb-21 97
L8 8TH-9TH 2-Jul-20 5-Jan-21
CFRP Column Lalaguna 3 26-Oct-20 5-Jan-21 72
Beam Lalaguna 6 16-Sep-20 20-Nov-20 66
L9 9TH-10TH 30-Jul-20 25-Jan-21
CFRP Shearwall Lalaguna 1 26-Oct-20 15-Jan-21 82
Column Lalaguna 3 3-Sep-20 15-Jan-21 135
Beam Lalaguna 3 10-Sep-20 15-Jan-21 128
L10 10TH-11TH 2-Jul-20 21-Dec-20
CFRP Column Lalaguna 1 1-Sep-20 30-Dec-20 121
Beam Lalaguna 3 1-Sep-20 30-Dec-20 121
L11 11TH-12TH
2-Jul-20 27-Nov-20
CFRP Beam Lalaguna 2 2-Jul-20 27-Nov-20 149
L11 11TH-12TH 27-Nov-20
CFRP Shearwall Lalaguna 1 3-Jul-20 27-Nov-20 148
Column Lalaguna 1 13-Jul-20 27-Nov-20 138
Beam Lalaguna 4 23-Jul-20 27-Nov-20 128
L12 12TH-14TH 15-Jul-20 20-Dec-20
CFRP Beam Lalaguna 4 14-Aug-20 4-Dec-20 113
L14 14TH-15TH 15-Jul-20 20-Dec-20
CFRP Shearwall Lalaguna 1 15-Jul-20 20-Dec-20 159
Column Lalaguna 1 23-Jul-20 26-Dec-20 157
Beam Lalaguna 2 31-Jul-20 10-Dec-20 133
L15 15TH-16TH 15-Jun-20 20-Dec-20
CFRP Beam Lalaguna 1 20-Jul-20 27-Nov-20 131
L16 16TH-17TH 13-Jul-20 4-Jan-21
CFRP Column Lalaguna 1 13-Jul-20 8-Jan-21 180
Beam Lalaguna 2 21-Jul-20 20-Nov-20 123
L17 17TH-18TH 10-Aug-20 31-Jan-21
CFRP Column Lalaguna 1 10-Aug-20 27-Jan-21 171
Beam Lalaguna 5 17-Aug-20 9-Jan-21 146
L18 18TH-19TH 22-Jun-20 11-Jan-21
CFRP Column Lalaguna 3 29-Jul-20 26-Dec-20 151
L24 24TH-25TH CFRP Beam Lalaguna 3 30-Aug-20 14-Jan-21 138
L27 27TH-28TH 14-Dec-20 31-May-21
CFRP Beam Lalaguna 12 11-Jan-21 31-May-21 141
L28 28TH-29TH 9-Jan-21 31-May-21
Beam Lalaguna 4 11-Jan-21 31-May-21 141
L29 29TH-30TH 11-Nov-20 31-May-21
Column Lalaguna 4 11-Jan-21 31-May-21 141
L30 30TH-31TH 22-Oct-20 31-May-21
CFRP Shearwall Lalaguna 1 11-Jan-21 31-May-21 141
Column Lalaguna 3 11-Jan-21 31-May-21 141
L31 31TH-RD 19-Nov-20 31-May-21
CFRP Shearwall Lalaguna 1 11-Jan-21 31-May-21 141
Column Lalaguna 9 11-Jan-21 31-May-21 141
Page 2 of 4
Revise Schedule June July August September October November December January February March April May June July August
Floor Floor Framing Type Contractor qty
Start Finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
BEAMS CFRP (2) ECS 2 4-Jan-21 31-Jan-21 28
LEVEL 21
COLUMNS STEEL JACKET (3) ECS 3 26-Oct-20 13-Dec-20 49
SHEARWALLS CFRP (2) ECS 2 5-Oct-20 13-Dec-20 70
SHEARWALL STEEL JACKET (4) NEW ECS 4 28-Sep-20 14-Feb-21 140
LEVEL 22
SHEARWALL STEEL JACKET (5) NEW ECS 5 14-Dec-20 30-May-21 168
LEVEL 23
SHEARWALL STEEL JACKET (5) NEW ECS 5 14-Dec-20 30-May-21 168
LEVEL 24
SHEARWALL STEEL JACKET (2) NEW ECS 2 22-Feb-21 2-May-21 70
LEVEL 25
SHEARWALL STEEL JACKET (2) NEW ECS 2 2-Nov-20 10-Jan-20 -296
LEVEL 25 26th Floor Framing
BEAMS STEEL JACKET (12) ECS 12 3-Aug-20 9-May-21 280
BEAMS CFRP (4) ECS 4 3-Aug-20 9-May-21 280
LEVEL 26
COLUMNS STEEL JACKET (3) ECS 3 13-Jul-20 13-Dec-20 154
SHEARWALLS STEEL JACKET (4) ECS 4 14-Dec-20 18-Apr-21 126
SHEARWALLS CFRP (1) ECS 1 22-Jun-20 8-Nov-20 140
LEVEL 26 27th Framing
BEAMS STEEL JACKET (19) ECS 19 1-Sep-20 25-Apr-21 237
BEAMS CFRP (5) ECS 5 26-Oct-20 25-Apr-21 182
LEVEL 27
COLUMNS STEEL JACKET (16) ECS 16 7-Dec-20 30-May-21 175
SHEARWALLS STEEL JACKET (5) ECS 5 7-Dec-20 30-May-21 175
SLAB RETROFITTING
11th Floor Framing Slab Retrofittng (CFRP) ECS 10 11-Sep-20 27-Dec-20 108
Page 3 of 4
Revise Schedule June July August September October November December January February March April May June July August
Floor Floor Framing Type Contractor qty
Start Finish Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
L27 27TH-28TH
Steel Jacket Beam Filgarte 21 7-Mar-21 30-Jun-21 116
L28 28TH-29TH
Steel Jacket Shearwall Filgarte 5 1-Mar-21 30-Jun-21 122
Steel Jacket Column Filgarte 12 1-Mar-21 30-Jun-21 122
Commulative Weekly Planned Accomplishment 0.00 0.00 1.37 7.16 14.67 22.91 31.71 41.15 54.22 70.53 94.17 123.81 154.39 186.77 224.64 263.84 307.76 354.18 401.75 449.83 493.43 537.35 583.37 629.52 675.83 720.87 769.27 816.14 860.44 900.48 939.33 979.74 1017.29 1053.68 1090.64 1126.95 1168.85 1211.10 1259.85 1312.71 1373.28 1440.30 1506.51 1572.17 1637.83 1701.20 1761.76 1822.02 1881.62 1940.32 1995.29 2044.47 2090.76 2134.77 2173.82 2198.07 2216.85 2234.28 2249.45 2259.00
Commulative Weekly Planned % Accomplishment 0.00% 0.00% 0.06% 0.32% 0.65% 1.01% 1.40% 1.82% 2.40% 3.12% 4.17% 5.48% 6.83% 8.27% 9.94% 11.68% 13.62% 15.68% 17.78% 19.91% 21.84% 23.79% 25.82% 27.87% 29.92% 31.91% 34.05% 36.13% 38.09% 39.86% 41.58% 43.37% 45.03% 46.64% 48.28% 49.89% 51.74% 53.61% 55.77% 58.11% 60.79% 63.76% 66.69% 69.60% 72.50% 75.31% 77.99% 80.66% 83.29% 85.89% 88.33% 90.50% 92.55% 94.50% 96.23% 97.30% 98.13% 98.91% 99.58% 100.00%
Page 4 of 4