Date 7/27/2019

BKC Station Planned DWP R5 & Vs Actual Completion

Con & roof slab Grid 5-5.8 5.8-7.8 7.8-9.2 9.2-11 23-25 25-27 27-29 29-31 31-33 33-34 43-44

Activities South
Grid/
Shaft 04-05 05-06 06-08 08-10 10-11 11-13 14-16 16-18 18-20 20-22 22-24 24-26 26-28 28-30 30-32 32-34 34-36 36-38 38-40 40-42 North Shaft

DWP R5 3-Apr-20 21-Aug-19 11-Oct-19 11-Oct-19 22-Oct-19 4-Jan-20 15-Feb-20 17-Mar-20 17-Apr-20 7-Aug-20 21-Jun-20 21-May-20 20-Apr-20 20-Mar-20 18-Feb-20 18-Jan-20 27-Nov-19 23-Aug-20 31-Jul-20 18-Jun-20 18-May-20 14-Nov-19
Platform Slab
ACTUAL 16-Sep-20 20-Sep-20

DWP R5 4-Jun-20 24-Jun-19 12-Aug-19 12-Aug-19 27-Sep-19 20-Nov-19 31-Dec-19 31-Jan-20 1-Mar-20 6-Jun-20 6-May-20 5-Apr-20 4-Mar-20 3-Feb-20 3-Jan-20 3-Dec-19 3-Nov-19 28-Jul-20 3-Jun-20 3-May-20 2-Apr-20 18-Oct-19
Roof Slab
ACTUAL 31-Jan-20 1-Jan-20 15-Nov-19 26-Feb-20 22-Feb-20 25-Jan-20 13-Dec-19 26-Oct-19 26-Feb-20

DWP R5 6-Mar-20 17-May-19 24-Jun-19 24-Jun-19 12-Aug-19 20-Oct-19 30-Nov-19 31-Dec-19 31-Jan-20 4-Mar-20 3-Feb-20 3-Jan-20 3-Dec-19 3-Nov-19 1-Oct-19 21-Aug-19 29-Jul-19 3-Jun-20 3-May-20 2-Apr-20 1-Mar-20 23-Jun-19
Concourse to
Roof column
& wall
ACTUAL 20-Jan-20 28-Nov-19 11-Oct-19 18-Feb-20 17-Feb-20 3-Jan-20 22-Nov-19 9-Oct-19 15-Feb-20

DWP R5 2-Feb-20 16-Apr-19 16-May-19 17-May-19 24-Jun-19 18-Sep-19 31-Oct-19 30-Nov-19 31-Dec-19 3-Feb-20 3-Jan-20 3-Dec-19 3-Nov-19 1-Oct-19 21-Aug-19 30-Jun-19 21-May-19 3-May-20 2-Apr-20 1-Mar-20 31-Jan-20 13-May-19
Concourse
slab ACTUAL 24-Jan-20 18-Sep-19 14-Oct-19 19-Dec-19 20-Mar-20 14-Jan-20 5-Dec-19 16-Oct-19 9-Aug-19 31-Jan-20 22-Sep-19

Base Slab to DWP R5 3-Feb-19 15-Mar-19 15-Apr-19 16-Apr-19 17-May-19 28-Jul-19 28-Sep-19 31-Oct-19 30-Nov-19 12-Dec-19 12-Nov-19 12-Oct-19 20-Aug-19 13-Jun-19 10-May-19 9-Apr-19 8-Mar-19 6-Mar-20 5-Feb-20 5-Jan-20 31-Dec-19 1-Apr-19
Concourse
column & WD
wall ACTUAL 15-Jun-19 27-Sep-19 28-Aug-19 26-Jul-19 7-Jan-20 18-Mar-20 29-Dec-19 12-Nov-19 13-Sep-20 20-Jul-19 2-Jan-20

DWP R5 3-Jan-19 13-Feb-19 13-Feb-19 15-Mar-19 16-Apr-19 8-Jun-19 14-Aug-19 28-Sep-19 31-Oct-19 12-Nov-19 12-Oct-19 3-Sep-19 29-Jun-19 10-May-19 9-Apr-19 8-Mar-19 6-Feb-19 5-Feb-20 5-Jan-20 5-Dec-19 5-Nov-19 21-Jul-18
Base slab WD WD
ACTUAL 20-Jan-19 17-Feb-19 18-Feb-19 29-Mar-19 19-May-19 7-Dec-19 5-Mar-20 30-Jan-20 15-Nov-19 14-May-19 2-Apr-19 8-Mar-19 23-Apr-19 6-Mar-20 21-Jul-18

South Shaft 04-06 05-06 06-08 08-10 10-12 12-14 14-16 16-18 18-20 20-22 22-24 24-26 26-28 28-30 30-32 32-34 34-36 36-38 38-40 40-42 North Shaft

Con & roof slab Grid 5-5.8 5.8-7.8 7.8-9.2 9.2-11 23-25 25-27 27-29 29-31 31-33 33-34 43-44

Work Completed
Work In Progress
BKC Base Slab Grid 6-8 Date :02-04-2019

Time 2pm -3pm 3pm -4pm 4pm -5pm 5pm -6pm 6pm -7pm 7pm -8.30pm
Dispatched From Plant 1114 1144
Concrete Received Qty 1096.35 1120.35 1138 1162.35 1192.35 1216

Pump
CP1 360 375 381 387 399 405
CP2 363 372 372 376 382 391
BP 367.35 373.35 379 385 397 420

Poured Qty 1090.35 1120.35 1132 1148 1178 1216

Per Hrs 59.5 30 11.65 16 30 25.33

Total Avg Between 2 to 8.30 pm 28.75


Date 7/27/2019

BKC Station Planned (DWP R5 & Latest Three MRP) Vs Actual Completion

Activities South
Grid/
Shaft 04-05 05-06 06-08 08-9 09-11 '11-13 13-15 15-17 17-19 19-21 22-24 24-26 26-28 28-30 30-33 33-34 34-36 36-38 38-40 40-42 North Shaft

DWP R5 3-Apr-20 21-Aug-19 11-Oct-19 22-Oct-19 4-Jan-20 15-Feb-20 17-Mar-20 17-Apr-20 7-Aug-20 21-Jun-20 21-May-20 20-Apr-20 20-Mar-20 18-Feb-20 18-Jan-20 27-Nov-19 23-Aug-20 31-Jul-20 18-Jun-20 18-May-20 14-Nov-19

Platform Slab Latest 3MRP

ACTUAL

DWP R5 4-Jun-20 24-Jun-19 12-Aug-19 27-Sep-19 20-Nov-19 31-Dec-19 31-Jan-20 1-Mar-20 6-Jun-20 6-May-20 5-Apr-20 4-Mar-20 3-Feb-20 3-Jan-20 3-Dec-19 3-Nov-19 28-Jul-20 3-Jun-20 3-May-20 2-Apr-20 18-Oct-19

Roof Slab Latest 3MRP

ACTUAL

DWP R5 6-Mar-20 17-May-19 24-Jun-19 12-Aug-19 20-Oct-19 30-Nov-19 31-Dec-19 31-Jan-20 4-Mar-20 3-Feb-20 3-Jan-20 3-Dec-19 3-Nov-19 1-Oct-19 21-Aug-19 29-Jul-19 3-Jun-20 3-May-20 2-Apr-20 1-Mar-20 23-Jun-19

Concourse to
Roof column Latest 3MRP 25-Sep-19 26-Sep-19
& wall

ACTUAL

DWP R5 2-Feb-20 16-Apr-19 17-May-19 24-Jun-19 18-Sep-19 31-Oct-19 30-Nov-19 31-Dec-19 3-Feb-20 3-Jan-20 3-Dec-19 3-Nov-19 1-Oct-19 21-Aug-19 30-Jun-19 21-May-19 3-May-20 2-Apr-20 1-Mar-20 31-Jan-20 13-May-19
Concourse Latest 3MRP 1-Sep-19 22-Sep-19 13-Aug-19 14-Sep-19
slab
ACTUAL 13-Sep-19 9-Aug-19

DWP R5 3-Feb-19 15-Mar-19 16-Apr-19 17-May-19 28-Jul-19 28-Sep-19 31-Oct-19 30-Nov-19 12-Dec-19 12-Nov-19 12-Oct-19 20-Aug-19 13-Jun-19 10-May-19 9-Apr-19 8-Mar-19 6-Mar-20 5-Feb-20 5-Jan-20 31-Dec-19 1-Apr-19

Base Slab to
Concourse Latest 3MRP 3-Sep-19 29-Jul-19 15-Aug-19 15-Sep-19 11-Aug-19 10-Jun-19 5-Jul-19 12-Aug-19
column &
wall
ACTUAL 20-Jul-19

DWP R5 3-Jan-19 13-Feb-19 15-Mar-19 16-Apr-19 8-Jun-19 14-Aug-19 28-Sep-19 31-Oct-19 12-Nov-19 12-Oct-19 3-Sep-19 29-Jun-19 10-May-19 9-Apr-19 8-Mar-19 6-Feb-19 5-Feb-20 5-Jan-20 5-Dec-19 5-Nov-19 21-Jul-18

Base slab Latest 3MRP 19-Jan-19 28-Feb-19 26-Mar-19 6-May-19 12-Oct-19 1-Sep-19 14-May-19 7-Apr-19 12-Mar-19 15-Apr-19

ACTUAL 20-Jan-19 17-Feb-19 29-Mar-19 19-May-19 7-Dec-19 15-Nov-19 14-May-19 2-Apr-19 8-Mar-19 23-Apr-19 21-Jul-18

South Shaft 04-06 06-08 08-10 10-12 12-14 14-16 16-18 18-20 20-22 22-24 24-26 26-28 28-30 30-32 32-34 34-36 36-38 38-40 40-42 North Shaft

Work Completed
Work In Progress