CC-105 TA-EXPANSION TOROMOCHO (LB1)

Activity ID At Activity
Start Finish Inicio-LB1 Fin -LB1 2019 2020
Completion Name
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprMay
Duration
CC-105 TA-EXPANSION TOROMOCHO (LB1) 547 30-Oct-18 A 30-Apr-20 30-Oct-18 30-Apr-20

CC-105 547 30-Oct-18 A 30-Apr-20 30-Oct-18 30-Apr-20

MILESTONE 395 30-Oct-18 A 30-Nov-19 30-Oct-18 30-Nov-19


INGENIERIA POR EL PROPIETARIO 109 30-Oct-18 A 17-Feb-19 30-Oct-18 17-Feb-19
PROCURA POR EL PROPIETARIO 234 21-Nov-18 A 15-Jul-19 21-Nov-18 15-Jul-19
TRABAJOS PRELIMINARES 39 14-Nov-18 A 22-Dec-18 A 14-Nov-18 22-Dec-18
CONSTRUCCIÓN 349 15-Dec-18 A 30-Nov-19 15-Dec-18 30-Nov-19
AREA 2210 Flotation General 185 01-Apr-19 02-Oct-19 01-Apr-19 02-Oct-19
CIVIL 79 01-Apr-19 18-Jun-19 01-Apr-19 18-Jun-19
ESTRUCTURAS 40 27-May-19 05-Jul-19 27-May-19 05-Jul-19
TUBERIAS 45 19-Jun-19 02-Aug-19 19-Jun-19 02-Aug-19
ELECTRICIDAD 164 07-Apr-19 17-Sep-19 07-Apr-19 17-Sep-19
INSTRUMENTACIÓN 33 31-Aug-19 02-Oct-19 31-Aug-19 02-Oct-19
AREA 2211 Bulk Rougher Flotation 288 15-Dec-18 A 30-Sep-19 15-Dec-18 30-Sep-19
CIVIL 198 28-Dec-18 A 14-Jul-19 28-Dec-18 14-Jul-19
ESTRUCTURAS 144 21-Mar-19 11-Aug-19 21-Mar-19 11-Aug-19
MECANICA 218 15-Dec-18 A 22-Jul-19 15-Dec-18 22-Jul-19
TUBERIAS 153 17-Mar-19 16-Aug-19 17-Mar-19 16-Aug-19
ELECTRICIDAD 163 09-Apr-19 18-Sep-19 09-Apr-19 18-Sep-19
INSTRUMENTACIÓN 22 09-Sep-19 30-Sep-19 09-Sep-19 30-Sep-19
AREA 2212 Bulk Cleaner Flotation (TK08) 311 29-Dec-18 A 05-Nov-19 29-Dec-18 05-Nov-19
CIVIL 311 29-Dec-18 A 05-Nov-19 29-Dec-18 05-Nov-19
MECANICA 184 02-Apr-19 02-Oct-19 02-Apr-19 02-Oct-19
TUBERIAS 90 27-Jun-19 24-Sep-19 27-Jun-19 24-Sep-19
ELECTRICIDAD 226 17-Feb-19 30-Sep-19 17-Feb-19 30-Sep-19
INSTRUMENTACION 57 15-Aug-19 10-Oct-19 15-Aug-19 10-Oct-19
AREA 2460 Filter Plant 331 15-Dec-18 A 12-Nov-19 15-Dec-18 12-Nov-19
Obras Preliminares - Taller de mantenimiento hidrometalurgia 15 15-Dec-18 A 30-Dec-18 A 15-Dec-18 30-Dec-18
CIVIL 183 10-Jan-19 A 11-Jul-19 10-Jan-19 11-Jul-19
ESTRUCTURAS 193 21-Mar-19 29-Sep-19 21-Mar-19 29-Sep-19
MECANICA 150 07-May-19 03-Oct-19 07-May-19 03-Oct-19
TUBERIAS 134 02-Jul-19 12-Nov-19 02-Jul-19 12-Nov-19
ELECTRICIDAD 149 30-Apr-19 25-Sep-19 30-Apr-19 25-Sep-19
AREA 2560 Tailings Thickening General (RetiroAlcance) 232 03-Apr-19 20-Nov-19 03-Apr-19 20-Nov-19
AREA 2561 Tailings Thickeners 292 06-Feb-19 A 24-Nov-19 06-Feb-19 24-Nov-19
CIVIL 143 06-Feb-19 A 28-Jun-19 06-Feb-19 28-Jun-19
ESTRUCTURAS 10 23-Jun-19 02-Jul-19 23-Jun-19 02-Jul-19
MECANICA 217 22-Apr-19 24-Nov-19 22-Apr-19 24-Nov-19
TUBERIAS 60 21-Aug-19 19-Oct-19 21-Aug-19 19-Oct-19
ELECTRICIDAD 76 31-Aug-19 14-Nov-19 31-Aug-19 14-Nov-19
INSTRUMENTACION 19 12-Oct-19 30-Oct-19 12-Oct-19 30-Oct-19
AREA 4010 PIPERACKS - TAILINGS DISTRIBUTOR FEED LAUNDERAND TAILINGS DISTRIBUTOR
213 01-Apr-19 30-Oct-19 01-Apr-19 30-Oct-19
CIVIL 78 01-Apr-19 17-Jun-19 01-Apr-19 17-Jun-19
ESTRUCTURAS 166 18-May-19 30-Oct-19 18-May-19 30-Oct-19
GENERAL 64 16-Jan-19 A 20-Mar-19 16-Jan-19 20-Mar-19
TIE INS 197 21-Jan-19 A 05-Aug-19 21-Jan-19 05-Aug-19
ACTIVIDADES DE PRE-COMISIONADO 58 04-Oct-19 30-Nov-19 04-Oct-19 30-Nov-19
COMISIONADO 122 01-Dec-19 31-Mar-20 01-Dec-19 31-Mar-20
CIERRE Y TERMINO DE OBRA 30 01-Apr-20 30-Apr-20 01-Apr-20 30-Apr-20