Activity ID

Activity Name

CONSTRUCTION OF THE FORESHORE ROCK REVETMENT


CONSTRUCTION
Revetment
Quarry Material Supply
A28805
Quarry rock supply - section 600 - 570

BL Start

BL Finish

Start

Finish

08-Dec-14

09-Oct-15

25-Sep-14 A

08-Dec-14

09-Oct-15

25-Sep-14 A

08-Dec-14

09-Oct-15

08-Dec-14
08-Dec-14

09-Sep-15
12-Dec-14

Act %
Com

Orig
Dur

Rem
Dur

Total
Float

21-Oct-15

207

111

-89

21-Oct-15

207

111

-89

25-Sep-14 A

21-Oct-15

207

111

-89

25-Sep-14 A
25-Sep-14 A

15-Sep-15
20-May-15

75%

186
5

85
1

-80
-101

A32260

Quarry rock supply - section 570 - 540

07-Apr-15

11-Apr-15

13-Oct-14 A

21-May-15

75%

-80

A32270

Quarry rock supply - section 540 - 510

13-Apr-15

17-Apr-15

10-Nov-14 A

22-May-15

70%

-80

A32280

Quarry rock supply - section 510 - 480

20-Apr-15

24-Apr-15

17-Nov-14 A

25-May-15

60%

-80

A32290

Quarry rock supply - section 480 - 450

28-Mar-15

07-Apr-15

26-Nov-14 A

27-May-15

60%

-80

A32300

Quarry rock supply - section 450 - 420

08-May-15

13-May-15

09-Dec-14 A

02-Jun-15

60%

-80

A32310

Quarry rock supply - section 420 - 390

03-Jun-15

08-Jun-15

03-Jun-15

08-Jun-15

0%

-80

A32450

Quarry rock supply - section 600 - 630

26-Aug-15

03-Sep-15

26-Aug-15 A

10-Sep-15

75%

-80

A32460

Quarry rock supply - section 630 - 660

04-Sep-15

09-Sep-15

04-Sep-15 A

15-Sep-15

25%

-80

29-Apr-15
20-May-15
20-May-15

09-Oct-15
28-May-15
25-May-15

18-Mar-15 A
20-May-15
20-May-15

21-Oct-15
28-May-15
25-May-15

111
7
4

-89
-33
-33

0%

114
7
4

A28900

Grade II to berm

25-May-15

26-May-15

25-May-15

26-May-15

0%

-33

A28910

Grade I to crest

26-May-15

28-May-15

26-May-15

28-May-15

0%

-33

20-May-15
20-May-15

03-Jun-15
25-May-15

20-May-15
20-May-15

03-Jun-15
25-May-15

0%

9
4

9
4

-33
-31

25-May-15

26-May-15

0%

-31

Toe Type 1 - 3
Section 600 - 570
A28890
Grade III to berm

Section 570 - 540


A29000
Grade III to berm
A29010

Grade II to berm

25-May-15

26-May-15

A29020

Grade I to crest

28-May-15

03-Jun-15

28-May-15

03-Jun-15

0%

-33

29-Apr-15
29-Apr-15

05-Jun-15
29-Apr-15

18-Mar-15 A
18-Mar-15 A

05-Jun-15
25-May-15

0%

25
1

8
1

-34
-34

Section 540 - 510


A29100
Grade I to berm (110t)
A29110

Grade III to berm

26-May-15

02-Jun-15

26-May-15

02-Jun-15

0%

-34

A29120

Grade II to berm

03-Jun-15

03-Jun-15

03-Jun-15

03-Jun-15

0%

-34

A29130

Grade I to crest

04-Jun-15

05-Jun-15

04-Jun-15

05-Jun-15

0%

-34

Section 510 - 480


A29160
Protective bund and trial pit (LRE)

19-May-15
19-May-15

12-Jun-15
20-May-15

19-May-15
19-May-15

12-Jun-15
20-May-15

0%

18
2

18
2

-40
-98

A29170

Excavate front toe (LRE)

21-May-15

21-May-15

21-May-15

21-May-15

0%

-98

A29180

Grade II & I to front toe (250t+LRE)

22-May-15

23-May-15

22-May-15

23-May-15

0%

-98

A29190

Excavate back toe and berm (LRE+40t)

25-May-15

25-May-15

25-May-15

25-May-15

0%

-95

A29200

Grade II & I to back toe/bottom berm (250t+LRE)

04-Jun-15

06-Jun-15

04-Jun-15

06-Jun-15

0%

-100

A29210

Grade I to berm (110t)

06-Jun-15

08-Jun-15

06-Jun-15

08-Jun-15

0%

-40

A29220

Grade III to berm

08-Jun-15

12-Jun-15

08-Jun-15

12-Jun-15

0%

-40

20-May-15
20-May-15

05-Jun-15
22-May-15

20-May-15
20-May-15

05-Jun-15
22-May-15

0%

11
2

11
2

-97
-101

Section 480 - 450


A29250
Excavate insitu
A29260

Grade IIIq to platform

22-May-15

26-May-15

22-May-15

26-May-15

0%

-101

A29270

Protective bund and trial pit (LRE)

26-May-15

28-May-15

26-May-15

28-May-15

0%

-101

A29280

Excavate front toe (LRE)

28-May-15

02-Jun-15

28-May-15

02-Jun-15

0%

-101

A29290

Grade II & I to front toe (250t+LRE)

02-Jun-15

04-Jun-15

02-Jun-15

04-Jun-15

0%

-101

A29300

Excavate back toe and berm (LRE+40t)

04-Jun-15

05-Jun-15

04-Jun-15

05-Jun-15

0%

-97

25-May-15
25-May-15

09-Jun-15
25-May-15

25-May-15
25-May-15

09-Jun-15
25-May-15

0%

10
1

10
1

-100
-98

Section 450 - 420


A29360
Excavate insitu
A29370

Grade IIIq to platform

26-May-15

27-May-15

26-May-15

27-May-15

0%

-98

A29380

Protective bund and trial pit (LRE)

28-May-15

02-Jun-15

28-May-15

02-Jun-15

0%

-98

A29390

Excavate front toe (LRE)

03-Jun-15

03-Jun-15

03-Jun-15

03-Jun-15

0%

-98

A29400

Grade II & I to front toe (250t+LRE)

06-Jun-15

09-Jun-15

06-Jun-15

09-Jun-15

0%

-100

04-Jun-15
04-Jun-15

10-Jun-15
06-Jun-15

04-Jun-15
04-Jun-15

10-Jun-15
06-Jun-15

0%

5
2

5
2

-101
-101

0%

-101

50%

12
2

6
1

-72
-101

Section 420 - 390


A29470
Excavate insitu
A29480

Grade IIIq to platform

Section 600 - 630


A31050
Grade II & I to front toe (250t+LRE)
Remaining Level of Effort

Primary Baseline

Remaining ...

Actual Level of Effort

Actual Work

Critical Rem...

06-Jun-15

10-Jun-15

06-Jun-15

10-Jun-15

26-Aug-15
26-Aug-15

14-Sep-15
01-Sep-15

20-Apr-15 A
20-Apr-15 A

30-Sep-15
21-Sep-15

Warrant T1Y1

Page 1 of 2
TPT Buildings
To07 - Level 3 Three Week Lookahead Schedule

May 2015
10

June 2015
17

24

Date
25-Mar-15
25-Jan-13

31

Revision
Progress Update
Baseline

07

14

Checked Approved
BJ/AM
AW
BJ/AM
AW

Activity ID

Activity Name

BL Start

BL Finish

Start

Finish

Act %
Com

Orig
Dur

Rem
Dur

Total
Float

A31060

Excavate back toe and berm (LRE+40t)

26-Aug-15

27-Aug-15

23-Apr-15 A

21-Sep-15

30%

-100

A31070

Grade II & I to back toe/bottom berm (250t+LRE)

01-Sep-15

04-Sep-15

24-Apr-15 A

29-Sep-15

30%

-101

A31080

Grade I to berm (110t)

11-Sep-15

14-Sep-15

11-Sep-15 A

30-Sep-15

0%

-72

Section 630 - 660


A31140
Protective bund and trial pit (LRE)

20-Aug-15
20-Aug-15

22-Aug-15
22-Aug-15

16-Apr-15 A
16-Apr-15 A

14-Sep-15
14-Sep-15

75%

2
2

1
1

-97
-97

Section 720 - 750


A31460
Grade IIIq to platform

02-Oct-15
02-Oct-15

06-Oct-15
06-Oct-15

13-Apr-15 A
13-Apr-15 A

05-Oct-15
05-Oct-15

50%

3
3

2
2

-98
-98

Section 750 - 780


A31570
Grade IIIq to platform

07-Oct-15
07-Oct-15

09-Oct-15
09-Oct-15

07-Oct-15 A
07-Oct-15 A

21-Oct-15
21-Oct-15

0%

2
2

2
2

-101
-101

Section 780 - 810


A31670
Excavate insitu

07-Oct-15
07-Oct-15

08-Oct-15
08-Oct-15

07-Oct-15 A
07-Oct-15 A

20-Oct-15
20-Oct-15

0%

1
1

1
1

-98
-98

Remaining Level of Effort

Primary Baseline

Remaining ...

Actual Level of Effort

Actual Work

Critical Rem...

Warrant T1Y1

Page 2 of 2
TPT Buildings
To07 - Level 3 Three Week Lookahead Schedule

May 2015
10

June 2015
17

24

Date
25-Mar-15
25-Jan-13

31

Revision
Progress Update
Baseline

07

14

Checked Approved
BJ/AM
AW
BJ/AM
AW