You are on page 1of 2

Program Project

Salford Crescent Station Enhancement

Activity
Detail Design of Podium Structure

Days Start Date


20 20 10 20 9-Jul-12 9-Jul-12 9-Jul-12 16-Jul-12

End Date
3-Aug-12 3-Aug-12 20-Jul-12 13-Aug-12

Salford Crescent Station Enhancement

Cat 2 check for Staircase & Landing

10 10 5

13-Aug-12 13-Aug-12 20-Aug-12

24-Aug-12 24-Aug-12 24-Aug-12

Salford Crescent Station Enhancement

Cat 2 check for Liftshaft and Motor Room

8 8 8

21-Aug-12 21-Aug-12 21-Aug-12

30-Aug-12 30-Aug-12 30-Aug-12

Salford Crescent Station Enhancement

Cat 2 check for Footbridge Piers

10 10 10

13-Aug-12 13-Aug-12 13-Aug-12

24-Aug-12 24-Aug-12 24-Aug-12

Salford Crescent Station Enhancement

Detail Design for Canopy Structure

19 19 19 16

10-Jul-12 10-Jul-12 10-Jul-12 23-Jul-12

3-Aug-12 3-Aug-12 3-Aug-12 13-Aug-12

Salford Crescent Station Enhancement

Detailed Design for Lift shaft

30 30 30 5

9-Jul-12 9-Jul-12 9-Jul-12 16-Jul-12

17-Aug-12 17-Aug-12 17-Aug-12 20-Aug-12

Staff
Somnath Chakraborty Somajit Deb Bharath Kumar Subhadip Bairi Rashmi Kumari Deepak Potty Nandisha Ramesh Rakesh Khurshidjahan Nisar Balaji Gunasekharan

Emp ID
145827 130853 153583 168730 159868 170106 167092 172209 164071 176454