Mina Hotel Rev.

02 Classic Schedule Layout 31-Aug-15 16:40


Activity ID Activity Name Variance - BL Actual BL P roject BL P roject BL P roject Start Finish Performance Activity % Schedule % TotalOctober 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015
Project Finish Duration Duration Start Finish % Complete Complete Complete 28
Float05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16
Date
-123 333 210 01-Oct-14 28-Apr-15 01-Oct-14 A 29-Aug-15 97.02% 0% 18 29-Aug-1
MH-1 Mina Hotel Rev. 02
-16 46 30 01-Oct-14 30-Oct-14 01-Oct-14 A 15-Nov-14 A 100% 0% 15-Nov-14 A, MH-1.MOB MOBILIZATI ON
MH-1.MOB MOBILIZATION
A1000 Site Preparation -16 46 30 01-Oct-14 30-Oct-14 01-Oct-14 A 15-Nov-14 A 100% 100% 0% Site Preparation
-171 184 14 31-Oct-14 13-Nov-14 01-Nov-14 A 04-May-15 A 100% 0% 04-May-15 A, MH-1.DE M DEMOLITION
MH-1.DEM DEMOLITION
A1010 Work Begins -1 0 0 31-Oct-14 01-Nov-14 A 100% 100% 0% Work Begins, 01-Nov-14 A
A1020 1B & Typ. Flrs: Mark and remove existing blockwalls, kerbstone & interlock and other items) -142 146 9 31-Oct-14 08-Nov-14 05-Nov-14 A 30-Mar-15 A 100% 100% 0% 1B & Typ. Flrs: Mark and remove existing blockwalls, kerbstone & interlock and other items)
A1040 Clearing of debris -137 134 12 02-Nov-14 13-Nov-14 17-Nov-14 A 30-Mar-15 A 100% 100% 0% Clearing of debris
A1030 GF: Mark and remove existing blockwalls, kerbstone & interlock and other items -173 9 11 01-Nov-14 11-Nov-14 25-Apr-15 A 04-May-15 A 100% 100% 0% GF: Mark and remove existing blockwalls, kerbstone & interlock and other items
-217 264 47 04-Nov-14 20-Dec-14 04-Nov-14 A 25-Jul-15 A 100% 0% 25-Jul-15 A, MH-1.BW BLOCKWO
MH-1.BW BLOCKWORKS
A1209 Typical Floors: Setting out/ marking (2116sqm) -36 49 12 05-Nov-14 16-Nov-14 04-Nov-14 A 22-Dec-14 A 100% 100% 0% Typical Floors: Setting out/ marking (2116sqm)
A1210 1st Floor: Lay AAC Thermal insulation blocks (approx. 46sqm) -105 119 2 17-Nov-14 18-Nov-14 05-Nov-14 A 03-Mar-15 A 100% 100% 0% 1st Floor: Lay AAC Thermal insulation blocks (approx. 46sqm)
A1208 1st Basement, GF, Typ. Flrs: Prepare loading & unloading area (30sqm) -121 116 1 04-Nov-14 04-Nov-14 10-Nov-14 A 05-Mar-15 A 100% 100% 0% 1st Basement, GF, Typ. Flrs: Prepare loading & unloading area (30sqm)
A1720 2nd Floor: Lay AA C Thermal insulation blocks (approx. 46sqm) -103 109 2 19-Nov-14 20-Nov-14 15-Nov-14 A 03-Mar-15 A 100% 100% 0% 2nd Floor: Lay AA C Thermal insulation blocks (approx. 46sqm)
A1740 3rd Floor: Lay AAC Thermal insulation blocks (approx. 46sqm) -165 162 2 20-Nov-14 21-Nov-14 25-Nov-14 A 05-May-15 A 100% 100% 0% 3rd Floor: Lay AAC Thermal insulation blocks (approx. 46sqm)
A1760 4th Floor: Lay AAC Thermal insulation blocks (approx. 46sqm) -27 5 2 22-Nov-14 23-Nov-14 16-Dec-14 A 20-Dec-14 A 100% 100% 0% 4th Floor: Lay AAC Thermal insulation blocks (approx. 46sqm)
A1780 5th Floor: Lay AAC Thermal insulation blocks (approx. 46sqm) -25 3 2 24-Nov-14 25-Nov-14 18-Dec-14 A 20-Dec-14 A 100% 100% 0% 5th Floor: Lay AAC Thermal insulation blocks (approx. 46sqm)
A1800 6th Floor: Lay AAC Thermal insulation blocks (approx. 46sqm) -96 73 2 26-Nov-14 27-Nov-14 21-Dec-14 A 03-Mar-15 A 100% 100% 0% 6th Floor: Lay AAC Thermal insulation blocks (approx. 46sqm)
A1802 1st Basement: Setting out/marking -87 4 4 17-Nov-14 20-Nov-14 12-Feb-15 A 15-Feb-15 A 100% 100% 0% 1st Basement: Setting out/marking
A1805 1st Basement: Lay 1 layer 15cm CHB (353M) -71 5 5 07-Dec-14 11-Dec-14 16-Feb-15 A 20-Feb-15 A 100% 100% 0% 1st Basement: Lay 1 layer 15cm CHB (353M)
A1806 1st Basement: Lay 1 layer 10cm CHB(26m) -70 2 1 13-Dec-14 13-Dec-14 20-Feb-15 A 21-Feb-15 A 100% 100% 0% 1st Basement: Lay 1 layer 10cm CHB(26m)
A1804 1st Basement: Lay 10cm CHB (40sqm) -78 2 2 05-Dec-14 06-Dec-14 21-Feb-15 A 22-Feb-15 A 100% 100% 0% 1st Basement: Lay 10cm CHB (40sqm)
A1810 1st Basement: Install lintel beams (111m) -66 2 6 14-Dec-14 19-Dec-14 22-Feb-15 A 23-Feb-15 A 100% 100% 0% 1st Basement: Install lintel beams (111m)
A1803 1st Basement: Lay 15cm CHB (1337sqm) -86 6 7 28-Nov-14 04-Dec-14 23-Feb-15 A 28-Feb-15 A 100% 100% 0% 1st Basement: Lay 15cm CHB (1337sqm)
A1820 Ground Floor: Install lintel beams (20m) -217 41 1 20-Dec-14 20-Dec-14 15-Jun-15 A 25-Jul-15 A 100% 100% 0% Ground Floor: Install lintel beams (
-158 88 29 21-Dec-14 18-Jan-15 30-Mar-15 A 25-Jun-15 A 100% 0% 25-Jun-15 A , MH-1.PLASTER P LAS TERI NG
MH-1.PLASTER PLASTERING
A1850 1st Basement: Prepare surface for internal wall plaster (2120sqm) -166 88 10 01-Jan-15 10-Jan-15 30-Mar-15 A 25-Jun-15 A 100% 100% 0% 1st Basement: Prepare surface for internal wall plaster (2
A1860 1st Basement: Plaster internal wall (2120sqm) -126 30 12 07-Jan-15 18-Jan-15 25-Apr-15 A 24-May-15 A 100% 100% 0% 1st Basement: Plaster internal wall (2120sqm)
A1830 Typ. Floors & 1B: P repare surface for internal ceiling plaster (536sqm) -126 5 5 21-Dec-14 25-Dec-14 26-Apr-15 A 30-Apr-15 A 100% 100% 0% Typ. Floors & 1B: P repare surface for internal ceiling plaster (536sqm)
A1840 Typ. Floors & 1B: S pray plast er at internal ceiling (536sqm) -120 5 6 26-Dec-14 31-Dec-14 26-Apr-15 A 30-Apr-15 A 100% 100% 0% Typ. Floors & 1B: S pray plast er at internal ceiling (536sqm)
-29 27 17 21-Nov-14 07-Dec-14 10-Dec-14 A 05-Jan-15 A 100% 0% 05-Jan-15 A , MH-1.SCRDNG S CREEDING
MH-1.SCRDNG SCREEDING
A2003 1st Floor: Prepare surface (approx. 1314sqm) -15 3 5 23-Nov-14 27-Nov-14 10-Dec-14 A 12-Dec-14 A 100% 100% 0% 1st Floor: Prepare surface (approx. 1314sqm)
A2002 1st Floor: Leveling/marking -22 3 2 21-Nov-14 22-Nov-14 12-Dec-14 A 14-Dec-14 A 100% 100% 0% 1st Floor: Leveling/marking
A2004 1st Floor: Lay the screed (approx. 1314sqm) -19 4 5 24-Nov-14 28-Nov-14 14-Dec-14 A 17-Dec-14 A 100% 100% 0% 1st Floor: Lay the screed (approx. 1314sqm)
A2005 2nd Floor: Leveling/marking -23 3 2 23-Nov-14 24-Nov-14 15-Dec-14 A 17-Dec-14 A 100% 100% 0% 2nd Floor: Leveling/marking
A2006 2nd Floor: Prepare surface (approx. 1314sqm) -18 2 5 25-Nov-14 29-Nov-14 16-Dec-14 A 17-Dec-14 A 100% 100% 0% 2nd Floor: Prepare surface (approx. 1314sqm)
A2008 3rd Floor: Leveling/marking -22 3 2 25-Nov-14 26-Nov-14 16-Dec-14 A 18-Dec-14 A 100% 100% 0% 3rd Floor: Leveling/marking
A2009 3rd Floor: Prepare surface (approx. 1314sqm) -19 4 5 26-Nov-14 30-Nov-14 16-Dec-14 A 19-Dec-14 A 100% 100% 0% 3rd Floor: Prepare surface (approx. 1314sqm)
A2007 2nd Floor: Lay the screed (approx. 1314sqm) -20 4 5 26-Nov-14 30-Nov-14 17-Dec-14 A 20-Dec-14 A 100% 100% 0% 2nd Floor: Lay the screed (approx. 1314sqm)
A2010 3rd Floor: Lay the screed (approx. 1314sqm) -20 5 5 27-Nov-14 01-Dec-14 17-Dec-14 A 21-Dec-14 A 100% 100% 0% 3rd Floor: Lay the screed (approx. 1314sqm)
A2011 4th Floor: Leveling/marking -23 3 2 27-Nov-14 28-Nov-14 19-Dec-14 A 21-Dec-14 A 100% 100% 0% 4th Floor: Leveling/marking
A2012 4th Floor: Prepare surface (approx. 1314sqm) -20 3 5 28-Nov-14 02-Dec-14 20-Dec-14 A 22-Dec-14 A 100% 100% 0% 4th Floor: Prepare surface (approx. 1314sqm)
A2014 5th Floor: Leveling/marking -25 4 2 29-Nov-14 30-Nov-14 22-Dec-14 A 25-Dec-14 A 100% 100% 0% 5th Floor: Leveling/marking
A2015 5th Floor: Prepare surface (approx. 1314sqm) -22 4 5 30-Nov-14 04-Dec-14 23-Dec-14 A 26-Dec-14 A 100% 100% 0% 5th Floor: Prepare surface (approx. 1314sqm)
A2017 6th Floor: Leveling/marking -24 4 2 01-Dec-14 02-Dec-14 23-Dec-14 A 26-Dec-14 A 100% 100% 0% 6th Floor: Leveling/marking
A2013 4th Floor: Lay the screed (approx. 1314sqm) -23 3 5 29-Nov-14 03-Dec-14 24-Dec-14 A 26-Dec-14 A 100% 100% 0% 4th Floor: Lay the screed (approx. 1314sqm)
A2018 6th Floor: Prepare surface (approx. 1314sqm) -22 4 5 02-Dec-14 06-Dec-14 25-Dec-14 A 28-Dec-14 A 100% 100% 0% 6th Floor: Prepare surface (approx. 1314sqm)
A2019 6th Floor: Lay the screed (approx. 1314sqm) -29 12 5 03-Dec-14 07-Dec-14 25-Dec-14 A 05-Jan-15 A 100% 100% 0% 6th Floor: Lay the screed (approx. 1314sqm)
A2016 5th Floor: Lay the screed (approx. 1314sqm) -27 7 5 01-Dec-14 05-Dec-14 26-Dec-14 A 01-Jan-15 A 100% 100% 0% 5th Floor: Lay the screed (approx. 1314sqm)
-241 270 29 03-Dec-14 31-Dec-14 03-Dec-14 A 29-Aug-15 A 100% 0% 29-Aug-1
MH-1.WALL DRY WALL
A1870 Typ. Flrs & 1B: Setting out /marking 14 7 21 03-Dec-14 23-Dec-14 03-Dec-14 A 09-Dec-14 A 100% 100% 0% Typ. Flrs & 1B: Setting out /marking
A1880 Typ. Flrs & 1B: Fix dry wall f rames(12450sqm) -38 52 21 04-Dec-14 24-Dec-14 11-Dec-14 A 31-Jan-15 A 100% 100% 0% Typ. Flrs & 1B: Fix dry wall f rames(12450sqm)
A1890 Typ. Flrs & 1B:Install gypsum board (12450sqm) -61 69 21 05-Dec-14 25-Dec-14 18-Dec-14 A 24-Feb-15 A 100% 100% 0% Typ. Flrs & 1B:Install gypsum board (12450sqm)
A1900 Ground Floor: Setting out/marking -245 128 4 24-Dec-14 27-Dec-14 24-Apr-15 A 29-Aug-15 A 100% 100% 0% Ground F
A1920 Ground Floor: Install gypsum board (616sqm) -196 75 3 29-Dec-14 31-Dec-14 02-May-15 A 15-Jul-15 A 100% 100% 0% Ground Floor: Install gypsum board (616s
A1910 Ground Floor: Fix dry wall frames (616sqm) -143 16 3 26-Dec-14 28-Dec-14 05-May-15 A 20-May-15 A 100% 100% 0% Ground Floor: Fix dry wall frames (616sqm)
-93 122 42 05-Dec-14 15-Jan-15 18-Dec-14 A 18-Apr-15 A 100% 0% 18-Apr-15 A , MH-1.WATERPROOF WATERPROOFI NG WORKS
MH-1.WATERPROOF WATERPROOFING WORKS
A1950 2nd Floor: Apply wat erproof ing materials @ bathrooms (A=297.33sqm) -121 122 8 11-Dec-14 18-Dec-14 18-Dec-14 A 18-Apr-15 A 100% 100% 0% 2nd Floor: Apply wat erproof ing materials @ bathrooms (A=297.33sqm)
A1960 3rd Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm) -115 120 8 17-Dec-14 24-Dec-14 20-Dec-14 A 18-Apr-15 A 100% 100% 0% 3rd Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm)
A1940 1st Floor: Apply waterproofing materials @ bathrooms (A= 297. 33sqm) -127 117 8 05-Dec-14 12-Dec-14 23-Dec-14 A 18-Apr-15 A 100% 100% 0% 1st Floor: Apply waterproofing materials @ bathrooms (A= 297. 33sqm)
A2001 1st Basement: Apply wat erproof ing materials at bat hroom & kitchen (A =136sqm) -62 16 4 12-Jan-15 15-Jan-15 03-Mar-15 A 18-Mar-15 A 100% 100% 0% 1st Basement: Apply wat erproof ing materials at bat hroom & kitchen (A =136sqm)
A1970 4th Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm) -109 47 8 23-Dec-14 30-Dec-14 03-Mar-15 A 18-Apr-15 A 100% 100% 0% 4th Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm)
A1980 5th Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm) -103 47 8 29-Dec-14 05-Jan-15 03-Mar-15 A 18-Apr-15 A 100% 100% 0% 5th Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm)
A1990 6th Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm) -97 47 8 04-Jan-15 11-Jan-15 03-Mar-15 A 18-Apr-15 A 100% 100% 0% 6th Floor: Apply waterproofing mat erials @ bathrooms (A=297.33sqm)
A2000 Ground Flr: Apply waterproofing mat erials at bathrooms (A=87sqm) -95 47 4 10-Jan-15 13-Jan-15 03-Mar-15 A 18-Apr-15 A 100% 100% 0% Ground Flr: Apply waterproofing mat erials at bathrooms (A=87sqm)
-150 112 50 07-Jan-15 25-Feb-15 05-Apr-15 A 26-Jul-15 A 100% 0% 26-Jul-15 A, MH-1.CEILING FALS
MH-1.CEILING FALSE CEILING
A1243 Typ. Flrs & 1B: Setting out /marking in all rooms & bathrooms -174 104 7 18-Jan-15 24-Jan-15 05-Apr-15 A 17-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Setting out /marking in al
A1240 Typ. Flrs & 1B: Setting out /marking at lobby -185 101 6 07-Jan-15 12-Jan-15 07-Apr-15 A 17-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Setting out /marking at lo
A1244 Typ. Flrs & 1B: Fix ceiling frames in all rooms & bathrooms (7402sqm) -155 104 30 19-Jan-15 17-Feb-15 10-Apr-15 A 22-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Fix ceiling frames in
A1245 Typ. Flrs & 1B: Install ceiling board in all rooms & bathrooms (7402sqm) -157 82 24 26-Jan-15 18-Feb-15 05-May-15 A 25-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Install ceiling board
A1241 Typ. Flrs & 1B: Fix ceiling frames @ lobby (1561sqm) -156 44 10 08-Jan-15 17-Jan-15 10-May-15 A 22-Jun-15 A 100% 100% 0% Typ. Flrs & 1B: Fix ceiling frames @ lobby (1561sqm)
A1242 Typ. Flrs & 1B: Install ceiling board @ lobby (1561sqm) -189 67 7 11-Jan-15 17-Jan-15 20-May-15 A 26-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Install ceiling boar
A1263 Ground Floor: Setting out/marking @ lobby/corridor -133 1 1 06-Feb-15 06-Feb-15 19-Jun-15 A 19-Jun-15 A 100% 100% 0% Ground Floor: Setting out/marking @ lobby/corridor
A1266 Ground Floor: Setting out/marking @ all rooms, bathrooms and washrooms -124 1 1 15-Feb-15 15-Feb-15 19-Jun-15 A 19-Jun-15 A 100% 100% 0% Ground Floor: Setting out/marking @ all rooms, bathrooms a
A1267 Ground Floor: Fix ceiling frames @ all rooms, bathrooms and washrooms (146sqm) -124 2 2 16-Feb-15 17-Feb-15 20-Jun-15 A 21-Jun-15 A 100% 100% 0% Ground Floor: Fix ceiling frames @ all rooms, bathrooms an
A1264 Ground Floor: Fix ceiling frames @ lobby/corridor (293sqm) -131 2 5 07-Feb-15 11-Feb-15 21-Jun-15 A 22-Jun-15 A 100% 100% 0% Ground Floor: Fix ceiling frames @ lobby/corridor (293sqm
A1268 Ground Floor: Install ceiling board @ all rooms, bathrooms and washrooms (146sqm) -123 2 2 18-Feb-15 19-Feb-15 21-Jun-15 A 22-Jun-15 A 100% 100% 0% Ground Floor: Install ceiling board @ all rooms, bathrooms
A1265 Ground Floor: Install ceiling board @ lobby/corridor (293sqm) -126 2 5 12-Feb-15 16-Feb-15 21-Jun-15 A 22-Jun-15 A 100% 100% 0% Ground Floor: Install ceiling board @ lobby/corridor (293sq
A1269 Ground Floor: Setting out/marking @ staff rms, kitchen, pantry & others -146 2 2 20-Feb-15 21-Feb-15 16-Jul-15 A 17-Jul-15 A 100% 100% 0% Ground Floor: Setting out/marking @ sta
A1252 Typ. Flrs & 1B: Setting out /marking @ st aff rms, kitchen, pantry & others -169 2 3 27-Jan-15 29-Jan-15 16-Jul-15 A 17-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Setting out /marking @ s
A1261 Typ. Flrs & 1B: Fix ceiling frames @ staff rooms, kitchen, pantry (478sqm) -169 3 5 30-Jan-15 03-Feb-15 20-Jul-15 A 22-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Fix ceiling frames @
A1270 Ground Floor: Fix ceiling frames @ staff rms, kitchen, pantry & others (107sqm) -149 3 2 22-Feb-15 23-Feb-15 20-Jul-15 A 22-Jul-15 A 100% 100% 0% Ground Floor: Fix ceiling frames @ s
A1262 Typ. Flrs & 1B: Install ceiling board in st aff rms, kitchen, pantry etc (478sqm) -168 4 4 04-Feb-15 07-Feb-15 22-Jul-15 A 25-Jul-15 A 100% 100% 0% Typ. Flrs & 1B: Install ceiling board
A1271 Ground Floor: Install ceiling board @ staff rms, kitchen, pantry & others (107sqm) -150 4 2 24-Feb-15 25-Feb-15 22-Jul-15 A 25-Jul-15 A 100% 100% 0% Ground Floor: Install ceiling board
-133 104 85 11-Dec-14 05-Mar-15 12-Dec-14 A 16-Jul-15 70.27% 0% 18 16-Jul-15, MH-1.FIN TILES & STONE W
MH-1.FIN TILES & STONE WORKS
A2270 1st Floor: Fix wooden skirting at room & suite (925m) 0 0 12 12-Dec-14 23-Dec-14 12-Dec-14 23-Dec-14 0% 0% 0% 18 1st Floor: Fix wooden skirting at room & suite (925m)
A2250 1st Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m) 0 0 5 17-Dec-14 21-Dec-14 17-Dec-14 21-Dec-14 0% 0% 0% 18 1st Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m)
A2350 2nd Floor: Fix wooden skirting at room & suite (925m) 0 0 12 17-Dec-14 28-Dec-14 17-Dec-14 28-Dec-14 0% 0% 0% 18 2nd Floor: Fix wooden skirting at room & suite (925m)
A2330 2nd Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m) 0 0 5 22-Dec-14 26-Dec-14 22-Dec-14 26-Dec-14 0% 0% 0% 18 2nd Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m)
A2430 3rd Floor: Fix wooden skirting at room & suite (925m) 0 0 12 22-Dec-14 02-Jan-15 22-Dec-14 02-Jan-15 0% 0% 0% 18 3rd Floor: Fix wooden skirting at room & suite (925m)
A2410 3rd Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m) 0 0 5 27-Dec-14 31-Dec-14 27-Dec-14 31-Dec-14 0% 0% 0% 18 3rd Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m)
A2510 4th Floor: Fix wooden skirting at room & suite (925m) 0 0 12 27-Dec-14 07-Jan-15 27-Dec-14 07-Jan-15 0% 0% 0% 18 4th Floor: Fix wooden skirting at room & suite (925m)
A2480 4th Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm) 0 0 7 28-Dec-14 03-Jan-15 28-Dec-14 03-Jan-15 0% 0% 0% 18 4th Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm)
A2490 4th Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m) 0 0 5 01-Jan-15 05-Jan-15 01-Jan-15 05-Jan-15 0% 0% 0% 18 4th Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m)

Actual Level of Effort Remaining Work Baseline Milestone s... Page 1 of 2 TASK filter: All Activities

Actual Work Critical Remaining Work Milestone © Oracle Corporation


Mina Hotel Rev. 02 Classic Schedule Layout 31-Aug-15 16:40
Activity ID Activity Name Variance - BL Actual BL P roject BL P roject BL P roject Start Finish Performance Activity % Schedule % TotalOctober 2014 November 2014 December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015
Project Finish Duration Duration Start Finish % Complete Complete Complete Float05 12 19 26
28 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16
A2560 5th Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm) Date0 0 7 02-Jan-15 08-Jan-15 02-Jan-15 08-Jan-15 0% 0% 0% 18 5th Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm)
A2570 5th Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m) 0 0 5 06-Jan-15 10-Jan-15 06-Jan-15 10-Jan-15 0% 0% 0% 18 5th Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m)
A2590 5th Floor: Fix wooden skirting at room & suite (925m) 0 0 12 06-Jan-15 17-Jan-15 06-Jan-15 17-Jan-15 0% 0% 0% 18 5th Floor: Fix wooden skirting at room & suite (925m)
A2631 6th Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm) 0 0 7 12-Jan-15 18-Jan-15 12-Jan-15 18-Jan-15 0% 0% 0% 18 6th Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm)
A2632 6th Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m) 0 0 5 16-Jan-15 20-Jan-15 16-Jan-15 20-Jan-15 0% 0% 0% 18 6th Floor: Fix wooden coping above marble @ lobby/corridor b/w rooms & suites (155m)
A2670 6th Floor: Fix wooden skirting at room & suite (925m) 0 0 12 21-Jan-15 01-Feb-15 21-Jan-15 01-Feb-15 0% 0% 0% 18 6th Floor: Fix wooden skirting at room & suite (925m)
A2690 Ground Floor: Fix cer. tiles at pantry, HR, EO, Recep, lugg safe rm, consierge, (460sqm) 0 0 10 26-Jan-15 04-Feb-15 26-Jan-15 04-Feb-15 0% 0% 0% 18 Ground Floor: Fix cer. tiles at pantry, HR, EO, Recep, lugg safe rm, consierge, (460sqm)
A2710 Ground Floor: Fix cer. tiles at corridor wall (91sqm) 0 0 5 28-Jan-15 01-Feb-15 28-Jan-15 01-Feb-15 0% 0% 0% 18 Ground Floor: Fix cer. tiles at corridor wall (91sqm)
A2720 Ground Floor: Fix cer. tiles at ground floor area (541sqm) 0 0 10 28-Jan-15 06-Feb-15 28-Jan-15 06-Feb-15 0% 0% 0% 18 Ground Floor: Fix cer. tiles at ground floor area (541sqm)
A2730 Ground Floor: Fix floor & wall marble behind front desk counter & restaurant (120sqm) 0 0 6 01-Feb-15 06-Feb-15 01-Feb-15 06-Feb-15 0% 0% 0% 18 Ground Floor: Fix floor & wall marble behind front desk counter & restaurant (120sqm)
A2740 Ground Floor: Fix floor marble @ corridors, b/w HR&EO & meeting room (41sqm) 0 0 2 05-Feb-15 06-Feb-15 05-Feb-15 06-Feb-15 0% 0% 0% 18 Ground Floor: Fix floor marble @ corridors, b/w HR&EO & meeting room (41sqm)
A2630 6th Floor Fix cer. skirt ing at store(7m) -81 7 2 18-Jan-15 19-Jan-15 04-Apr-15 A 10-Apr-15 A 100% 100% 0% 6th Floor Fix cer. skirt ing at store(7m)
A2700 Ground Floor: Fix cer. skirting at HR, EO, Recep, lugg safe rm, consrge (157m) -69 7 5 27-Jan-15 31-Jan-15 04-Apr-15 A 10-Apr-15 A 100% 100% 0% Ground Floor: Fix cer. skirting at HR, EO, Recep, lugg safe rm, consrge (157m)
A2230 1st Floor Fix cer. skirting at st ore(7m) -134 3 2 19-Dec-14 20-Dec-14 01-May-15 A 03-May-15 A 100% 100% 0% 1st Floor Fix cer. skirting at st ore(7m)
A2742 1st Basement: Fix cer. skirting (740m) -133 76 7 27-Feb-15 05-Mar-15 02-May-15 A 16-Jul-15 A 100% 100% 0% 1st Basement: Fix cer. skirting (740m)
A2310 2nd Floor Fix cer. skirting at store(7m) -132 3 2 24-Dec-14 25-Dec-14 04-May-15 A 06-May-15 A 100% 100% 0% 2nd Floor Fix cer. skirting at store(7m)
A2210 1st Floor: Fix cer. Tiles @ bat hrooms F&W (906sqm) -147 12 10 11-Dec-14 20-Dec-14 05-May-15 A 16-May-15 A 100% 100% 0% 1st Floor: Fix cer. Tiles @ bat hrooms F&W (906sqm)
A2400 3rd Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm) -141 15 7 23-Dec-14 29-Dec-14 05-May-15 A 19-May-15 A 100% 100% 0% 3rd Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm)
A2760 Fix Threshold at ground floor (7m) -84 11 1 20-Feb-15 20-Feb-15 05-May-15 A 15-May-15 A 100% 100% 0% Fix Threshold at ground floor (7m)
A2420 3rd Floor: Fix wall paper above marble @ lobby/corridor b/w rooms & suites (260sqm) -166 46 10 27-Dec-14 05-Jan-15 06-May-15 A 20-Jun-15 A 100% 100% 0% 3rd Floor: Fix wall paper above marble @ lobby/corridor b/w
A2390 3rd Floor Fix cer. skirt ing at store(7m) -129 2 2 29-Dec-14 30-Dec-14 07-May-15 A 09-May-15 A 100% 100% 0% 3rd Floor Fix cer. skirt ing at store(7m)
A2240 1st Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm) -142 1 7 13-Dec-14 19-Dec-14 10-May-15 A 10-May-15 A 100% 100% 0% 1st Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm)
A2320 2nd Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm) -146 10 7 18-Dec-14 24-Dec-14 10-May-15 A 19-May-15 A 100% 100% 0% 2nd Floor: Fix wall marble at lobby/corridor b/w rooms & suites (205sqm)
A2470 4th Floor Fix cer. skirt ing at store(7m) -129 4 2 03-Jan-15 04-Jan-15 10-May-15 A 13-May-15 A 100% 100% 0% 4th Floor Fix cer. skirt ing at store(7m)
A2340 2nd Floor: Fix wall paper above marble @ lobby/corridor b/w rooms & suites (260sqm) -171 41 10 22-Dec-14 31-Dec-14 11-May-15 A 20-Jun-15 A 100% 100% 0% 2nd Floor: Fix wall paper above marble @ lobby/corridor b/w
A2550 5th Floor Fix cer. skirt ing at store(7m) -130 6 2 08-Jan-15 09-Jan-15 14-May-15 A 19-May-15 A 100% 100% 0% 5th Floor Fix cer. skirt ing at store(7m)
A2680 6th Floor: Fix external lime stone cladding (43.33sqm) -105 5 2 02-Feb-15 03-Feb-15 15-May-15 A 19-May-15 A 100% 100% 0% 6th Floor: Fix external lime stone cladding (43.33sqm)
A2750 Fix Threshold at 1st Basement & typ. flrs (452m) -77 5 12 20-Feb-15 03-Mar-15 15-May-15 A 19-May-15 A 100% 100% 0% Fix Threshold at 1st Basement & typ. flrs (452m)
A2220 1st Floor: Fix cer. Tiles @ st ore, pantry, linen F&W (110sqm) -160 12 3 16-Dec-14 18-Dec-14 16-May-15 A 27-May-15 A 100% 100% 0% 1st Floor: Fix cer. Tiles @ st ore, pantry, linen F&W (110sqm)
A2280 1st Floor: Fix external lime stone cladding (43.33sqm) -146 5 2 24-Dec-14 25-Dec-14 16-May-15 A 20-May-15 A 100% 100% 0% 1st Floor: Fix external lime stone cladding (43.33sqm)
A2290 2nd Floor: Fix cer. bathrooms F& W (906sqm) -153 13 10 17-Dec-14 26-Dec-14 16-May-15 A 28-May-15 A 100% 100% 0% 2nd Floor: Fix cer. bathrooms F& W (906sqm)
A2300 2nd Floor: Fix cer. Tiles @ store, pant ry, linen F&W (110sqm) -156 13 2 22-Dec-14 23-Dec-14 16-May-15 A 28-May-15 A 100% 100% 0% 2nd Floor: Fix cer. Tiles @ store, pant ry, linen F&W (110sqm)
A2360 2nd Floor: Fix external lime stone cladding (43.33sqm) -141 5 2 29-Dec-14 30-Dec-14 16-May-15 A 20-May-15 A 100% 100% 0% 2nd Floor: Fix external lime stone cladding (43.33sqm)
A2370 3rd Floor: Fix cer. bathrooms F&W (906sqm) -150 15 10 22-Dec-14 31-Dec-14 16-May-15 A 30-May-15 A 100% 100% 0% 3rd Floor: Fix cer. bathrooms F&W (906sqm)
A2380 3rd Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm) -153 15 2 27-Dec-14 28-Dec-14 16-May-15 A 30-May-15 A 100% 100% 0% 3rd Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm)
A2440 3rd Floor: Fix external lime stone cladding (43.33sqm) -136 5 2 03-Jan-15 04-Jan-15 16-May-15 A 20-May-15 A 100% 100% 0% 3rd Floor: Fix external lime stone cladding (43.33sqm)
A2450 4th Floor: Fix cer. bathrooms F&W (906sqm) -147 17 10 27-Dec-14 05-Jan-15 16-May-15 A 01-Jun-15 A 100% 100% 0% 4th Floor: Fix cer. bathrooms F&W (906sqm)
A2460 4th Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm) -150 17 2 01-Jan-15 02-Jan-15 16-May-15 A 01-Jun-15 A 100% 100% 0% 4th Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm)
A2530 5th Floor: Fix cer. bathrooms F&W (906sqm) -144 19 10 01-Jan-15 10-Jan-15 16-May-15 A 03-Jun-15 A 100% 100% 0% 5th Floor: Fix cer. bathrooms F&W (906sqm)
A2540 5th Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm) -147 19 2 06-Jan-15 07-Jan-15 16-May-15 A 03-Jun-15 A 100% 100% 0% 5th Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm)
A2520 4th Floor: Fix external lime stone cladding (43.33sqm) -131 4 2 08-Jan-15 09-Jan-15 17-May-15 A 20-May-15 A 100% 100% 0% 4th Floor: Fix external lime stone cladding (43.33sqm)
A2600 5th Floor: Fix external lime stone cladding (43.33sqm) -121 4 2 18-Jan-15 19-Jan-15 17-May-15 A 20-May-15 A 100% 100% 0% 5th Floor: Fix external lime stone cladding (43.33sqm)
A2610 6th Floor: Fix cer. bathrooms F&W (906sqm) -136 20 10 11-Jan-15 20-Jan-15 17-May-15 A 05-Jun-15 A 100% 100% 0% 6th Floor: Fix cer. bathrooms F&W (906sqm)
A2620 6th Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm) -139 20 2 16-Jan-15 17-Jan-15 17-May-15 A 05-Jun-15 A 100% 100% 0% 6th Floor: Fix cer. Tiles @ store, pantry, linen F&W (110sqm)
A2741 1st Basement: Fix cer. tiles (1830sqm) -95 15 20 07-Feb-15 26-Feb-15 18-May-15 A 01-Jun-15 A 100% 100% 0% 1st Basement: Fix cer. tiles (1830sqm)
A2260 1st Floor: Fix wall paper above marble @ lobby/corridor b/w rooms & suites (260sqm) -176 33 10 17-Dec-14 26-Dec-14 19-May-15 A 20-Jun-15 A 100% 100% 0% 1st Floor: Fix wall paper above marble @ lobby/corridor b/w
A2500 4th Floor: Fix wall paper above marble @ lobby/corridor b/w rooms & suites (260sqm) -161 33 10 01-Jan-15 10-Jan-15 19-May-15 A 20-Jun-15 A 100% 100% 0% 4th Floor: Fix wall paper above marble @ lobby/corridor b/w
A2580 5th Floor: Fix wall paper above marble @ lobby/corridor b/w rooms & suites (260sqm) -151 24 10 11-Jan-15 20-Jan-15 28-May-15 A 20-Jun-15 A 100% 100% 0% 5th Floor: Fix wall paper above marble @ lobby/corridor b/w
A2640 6th Floor: Fix wall paper above marble @ lobby/corridor b/w rooms & suites (260sqm) -151 11 10 16-Jan-15 25-Jan-15 15-Jun-15 A 25-Jun-15 A 100% 100% 0% 6th Floor: Fix wall paper above marble @ lobby/corridor
-140 183 64 01-Jan-15 05-Mar-15 22-Jan-15 A 23-Jul-15 A 100% 0% 23-Jul-15 A, MH-1.PAI NT PAINTIN
MH-1.PAINT PAINTING WORKS
A2770 Typ. Floors & 1B: P aint anti-fungas in walls & ceilings (4522sqm) -162 161 20 01-Jan-15 20-Jan-15 22-Jan-15 A 01-Jul-15 A 100% 100% 0% Typ. Floors & 1B: P aint anti-fungas in walls & ceiling
A2780 Typ. Floors & 1B: P repare surface for internal ceiling paint (7900sqm) -93 104 30 03-Jan-15 01-Feb-15 22-Jan-15 A 05-May-15 A 100% 100% 0% Typ. Floors & 1B: P repare surface for internal ceiling paint (7900sqm)
A2791 Typ. Floors & 1B: P repare surface for internal wall paint (19523sqm) -70 104 50 06-Jan-15 24-Feb-15 22-Jan-15 A 05-May-15 A 100% 100% 0% Typ. Floors & 1B: P repare surface for internal wall paint (19523sqm)
A2790 Typ. Floors & 1B: P aint internal ceiling (7900sqm) -156 144 35 06-Jan-15 09-Feb-15 22-Feb-15 A 15-Jul-15 A 100% 100% 0% Typ. Floors & 1B: P aint internal ceiling (79
A2792 Typ. Floors & 1B: P aint internal wall (19523sqm) -138 144 50 09-Jan-15 27-Feb-15 22-Feb-15 A 15-Jul-15 A 100% 100% 0% Typ. Floors & 1B: P aint internal wall (1952
A2800 Ground Floors: Prepare surface for internal ceiling paint (520sqm) -146 4 7 20-Feb-15 26-Feb-15 19-Jul-15 A 22-Jul-15 A 100% 100% 0% Ground Floors: Prepare surface for in
A2810 Ground Floors: Paint internal ceiling (520sqm) -140 3 7 27-Feb-15 05-Mar-15 21-Jul-15 A 23-Jul-15 A 100% 100% 0% Ground Floors: Paint internal ceiling
-85 9 8 26-Feb-15 05-Mar-15 21-May-15 A 29-May-15 A 100% 0% 29-May-15 A, MH-1.W INDOW S W INDOW S & WINDOW FRAMES & CUR
MH-1.WINDOWS WINDOWS & WINDOW FRAMES & CURTAIN WALLS
A2860 Install aluminum curtain walls (54sqm) -79 3 6 28-Feb-15 05-Mar-15 21-May-15 A 23-May-15 A 100% 100% 0% Install aluminum curtain walls (54sqm)
A2840 1st Basement, Typ. Floors: Install windows and window frames (48nos) -88 7 5 26-Feb-15 02-Mar-15 23-May-15 A 29-May-15 A 100% 100% 0% 1st Basement, Typ. Floors: Install windows and window frames (48nos)
A2850 Ground Floors: Install windows and window frames (6nos) -90 2 2 27-Feb-15 28-Feb-15 28-May-15 A 29-May-15 A 100% 100% 0% Ground Floors: Install windows and window frames (6nos)
-94 50 20 06-Mar-15 25-Mar-15 09-May-15 A 27-Jun-15 A 100% 0% 27-Jun-15 A , MH-1.DOORS DOORS & DOOR FRA ME
MH-1.DOORS DOORS & DOOR FRAMES
A2880 1st Basement: Install metal doors (16nos) -84 24 2 08-Mar-15 09-Mar-15 09-May-15 A 01-Jun-15 A 100% 100% 0% 1st Basement: Install metal doors (16nos)
A2890 Ground Floors: Install metal doors (4nos) -60 1 1 10-Mar-15 10-Mar-15 09-May-15 A 09-May-15 A 100% 100% 0% Ground Floors: Install metal doors (4nos)
A2900 Supply & Install wooden doors (502nos) - by Subcontractor -94 26 15 11-Mar-15 25-Mar-15 02-Jun-15 A 27-Jun-15 A 100% 100% 0% Supply & Install wooden doors (502nos) - by Subcontra
A2870 1st Basement, Typ. Floors: Install sub-frames for wooden doors (14nos) -112 20 2 06-Mar-15 07-Mar-15 08-Jun-15 A 27-Jun-15 A 100% 100% 0% 1st Basement, Typ. Floors: Install sub-frames for wood
-112 34 85 16-Jan-15 10-Apr-15 28-Jun-15 A 31-Jul-15 A 100% 0% 31-Jul-15 A, MH-1.MISC MI S
MH-1.MISC MISCELLANEOUS WORKS
A2912 Supply & install sanitary wares - by subcontractor -137 4 15 31-Jan-15 14-Feb-15 28-Jun-15 A 02-Jul-15 A 100% 100% 0% Supply & install sanitary wares - by subcontractor
A2910 Install wash basin counter without vanity (186nos) -182 32 15 16-Jan-15 30-Jan-15 30-Jun-15 A 31-Jul-15 A 100% 100% 0% Install wash basin counter with
A2920 Install wardrobe upstand (134sqm) -125 8 15 19-Feb-15 05-Mar-15 01-Jul-15 A 08-Jul-15 A 100% 100% 0% Install wardrobe upstand (134sqm)
A2930 Install locker in the ladies toilet (1 no) -120 1 1 06-Mar-15 06-Mar-15 04-Jul-15 A 04-Jul-15 A 100% 100% 0% Install locker in the ladies toilet (1 no)
A2940 Install locker in the male toilet (1 no) -102 1 1 25-Mar-15 25-Mar-15 05-Jul-15 A 05-Jul-15 A 100% 100% 0% Install locker in the male toilet (1 no)
A2970 Supply and install Front desk at ground floor - by subcontractor -87 1 1 10-Apr-15 10-Apr-15 06-Jul-15 A 06-Jul-15 A 100% 100% 0% Supply and install Front desk at ground floor - by
A2950 Supply and install pantry in typical floors - by Subcontractor -98 1 15 17-Mar-15 31-Mar-15 07-Jul-15 A 07-Jul-15 A 100% 100% 0% Supply and install pantry in typical floors - by Su
A2960 Supply & install cupboards - by Subcontractor -89 1 15 27-Mar-15 10-Apr-15 08-Jul-15 A 08-Jul-15 A 100% 100% 0% Supply & install cupboards - by Subcontractor
-112 53 157 23-Nov-14 28-Apr-15 27-Jun-15 A 18-Aug-15 A 100% 0% 18-Aug-15 A, MH
MH-1.MEPF Mechanical, Electrical, Plumbing, Fire Fighting Works
A2980 Supply and install security system - by subcontractor -82 2 15 24-Mar-15 07-Apr-15 27-Jun-15 A 28-Jun-15 A 100% 100% 0% Supply and install security system - by subcontractor
A2985 Supply and install electronic lock - by Subcontractor -79 2 15 29-Mar-15 12-Apr-15 29-Jun-15 A 30-Jun-15 A 100% 100% 0% Supply and install electronic lock - by Subcontractor
A2990 Supply and install light fittings - by subcontractor -73 2 20 31-Mar-15 19-Apr-15 30-Jun-15 A 01-Jul-15 A 100% 100% 0% Supply and install light fittings - by subcontractor
A2977 Supply and install BMS - by Subcontractor -99 1 15 18-Mar-15 01-Apr-15 09-Jul-15 A 09-Jul-15 A 100% 100% 0% Supply and install BMS - by Subcontractor
A2979 Supply and install dumb waiter - by subcontractor -95 1 15 23-Mar-15 06-Apr-15 10-Jul-15 A 10-Jul-15 A 100% 100% 0% Supply and install dumb waiter - by subcontra
A3000 Supply and install central dish - by subcontractor -83 1 20 31-Mar-15 19-Apr-15 11-Jul-15 A 11-Jul-15 A 100% 100% 0% Supply and install central dish - by subcontra
A3010 Supply and install music and public address - by Subcontractor -75 1 15 14-Apr-15 28-Apr-15 12-Jul-15 A 12-Jul-15 A 100% 100% 0% Supply and install music and public address
A2975 Mechanical, Electrical, Plumbing & Fire Fighting Works -140 19 120 23-Nov-14 22-Mar-15 22-Jul-15 A 09-Aug-15 A 100% 100% 0% Mechanical, Electrical, P
A3020 Hand-over complete -112 0 0 28-Apr-15 18-Aug-15 A 100% 100% 0% Hand-over compl

Actual Level of Effort Remaining Work Baseline Milestone s... Page 2 of 2 TASK filter: All Activities

Actual Work Critical Remaining Work Milestone © Oracle Corporation