Professional Documents
Culture Documents
Tiang Bore Dia. 100 cm Elevasi Test PDA Test CSL Pelaksanaan PDA CSL
LOKASI / STA Jumlah
Total bottom KET.
Jumlah Dalam No. No. TITIK
Panjang Pile Cap Jumlah Jumlah Start Finish Tgl Ket Tgl Ket
titik (m) titik titik
(m)
A.1 21 14,00 294,00 35.259 1 A1.10 1 A1.11 4-Oct-23 21-Oct-23 21 26-Oct-23 Ok 26-Oct-23 Ok pembesian
P.1 21 13,00 273,00 28.710 1 P1.07 1 P1.11 8-Oct-23 16-Oct-23 21 26-Oct-23 capwap 26-Oct-23 Ok
1 15+336
P.2 21 23,00 483,00 26.242 1 P2.04 1 P2.08 12-Oct-23 19-Oct-23 21 26-Oct-23 capwap 26-Oct-23 Ok
A.2 21 17,00 357,00 28.525 1 A2.10 1 A2.11 17-Oct-23 23-Oct-23 21 26-Oct-23 capwap 26-Oct-23 Ok
Jumlah Overpass-1 84 1.407,00 4 4 84
A.1 12 13,00 156,00 33.909 1 A1.5 1 A1.10 25-Sep-23 6-Oct-23 12 24-Oct-23 Ok 24-Oct-23 Ok pembesian
P.1 16 15,00 240,00 27.340 1 P1.7 1 P1.10 1-Oct-23 15-Oct-23 16 29-Oct-23 capwap 28-Oct-23 Ok
2 15+903
P.2 12 12,00 144,00 34.720 1 P2.8 1 P2.6 10-Oct-23 15-Oct-23 12 29-Oct-23 OK 28-Oct-23 Ok pembesian
A.2 12 12,00 144,00 42.852 1 A2.2 1 A2.6 20-Sep-23 24-Sep-23 12 24-Oct-23 OK 24-Oct-23 Ok pembesian
Jumlah Overpass-2 52 684,00 4 4 52
A.1 9 14,00 126,00 11.760 1 1
3 19+765 P.1 12 16,00 192,00 6.593 1 1
A.2 9 18,00 162,00 10.975 1 1
Jumlah Overpass-3 30 480,00
A.1 12 16,00 192,00 13.508 1 1
4 20+727 P.1 16 15,00 240,00 8.434 1 1
A.2 12 16,00 192,00 13.004 1 1
Jumlah Overpass-4 40 624,00