Monitoring Pemancangan SOP-3 (Sta.

20+930 ~ 22+235) Status s/d hari ini : Terlaksana (titik) Bobot


Diameter CSP : 80 cm 29 Oktober 2023 Utara : 304 21,348%
Jumlah Titik Pancang : 1.424 Waktu terjalani : Selatan : 339 23,806%
Start Pemancangan : 28 Juli 2023 93 hari kalender Total : 643 45,154%
SISI UTARA SISI SELATAN
Tanggal
Pemancangan No. Panjang Elevasi Terpancang No. Panjang Elevasi Terpancang
No. Keterangan No. Keterangan
Titik TP (m) Platform (m) Titik TP (m) Platform (m)

29-Oct-23 1 PH88 U4 22,00 11,70 preboring 14 m


2 PH87 U4 22,00 11,70 preboring 14 m
28-Oct-23 1 PH89 S4 22,00 19,70 preboring 14 m
2 PH90 S4 22,00 17,50 preboring 14 m
27-Oct-23 1 PH88 U3 22,00 12,20 preboring 14 m
26-Oct-23 1 PH88 U1 22,00 14,30 preboring 14 m
2 PH88 U2 22,00 12,50 preboring 14 m
24-Oct-23 1 PH90 S2 22,00 20,00 preboring 14 m
2 PH89 S2 22,00 19,50 preboring 14 m
23-Oct-23 1 PH01 S3 22,00 13,00 preboring 10 m
2 PH01 S4 22,00 13,00 preboring 10 m
22-Oct-23 1 A1 S2 22,00 13,50 preboring 10 m
2 A1 S7 22,00 14,00 preboring 10 m
3 PH88 S2 22,00 19,50 preboring 14 m
4 PH88 S1 22,00 19,50 preboring 14 m
20-Oct-23 1 A1 S3 22,00 13,00 preboring 10 m
2 A1 S4 22,00 13,50 preboring 10 m
3 A1 S8 22,00 14,00 preboring 10 m
4 A1 S9 22,00 13,00 preboring 10 m
19-Oct-23 1 PH91 S1 22,00 20,00 preboring 14 m
2 PH91 S2 22,00 20,00 preboring 14 m
17-Oct-23 1 PH87 S1 22,00 20,00 preboring 14 m
2 PH87 S2 22,00 19,50 preboring 14 m
3 PH87 S3 22,00 19,00 preboring 14 m
4 A1 S5 22,00 13,50 preboring 12 m
16-Oct-23 1 PH86 S1 22,00 19,50 preboring 14 m
2 PH86 S2 22,00 19,50 preboring 14 m
3 PH88 S3 22,00 18,50 preboring 14 m
14-Oct-23 1 PH86 S3 22,00 18,50 preboring 14 m
2 PH86 S4 22,00 19,00 preboring 14 m
13-Oct-23 1 PH85 S3 22,00 19,00 preboring 14 m
2 PH87 S4 22,00 18,50 preboring 14 m
3 PH88 S4 22,00 19,50 preboring 14 m
12-Oct-23 1 PH3 S1 22,00 16,00 preboring 12 m
2 PH3 S2 22,00 16,00 preboring 12 m
3 PH85 S1 22,00 20,00 preboring 14 m
4 PH85 S2 22,00 19,00 preboring 14 m
11-Oct-23 1 PH84 S1 22,00 19,50 preboring 14 m
2 PH84 S3 22,00 18,50 preboring 14 m
3 PH84 S4 22,00 18,00 preboring 14 m
4 PH85 S4 22,00 13,00 preboring 14 m
5 PH2 S3 22,00 15,50 preboring 10 m
6 PH3 S3 22,00 16,00 preboring 10 m
7 PH2 S4 22,00 14,00 preboring 10 m
10-Oct-23 1 PH83 S2 22,00 18,50 preboring 14 m
2 PH83 S1 22,00 19,00 preboring 14 m
3 PH4 S1 22,00 16,00 preboring 10 m
4 PH4 S2 22,00 16,00 preboring 10 m
5 PH3 S4 22,00 16,00 preboring 10 m
Monitoring Pemancangan SOP-3 (Sta. 20+930 ~ 22+235) Status s/d hari ini : Terlaksana (titik) Bobot
Diameter CSP : 80 cm 29 Oktober 2023 Utara : 304 21,348%
Jumlah Titik Pancang : 1.424 Waktu terjalani : Selatan : 339 23,806%
Start Pemancangan : 28 Juli 2023 93 hari kalender Total : 643 45,154%
SISI UTARA SISI SELATAN
Tanggal
Pemancangan No. Panjang Elevasi Terpancang No. Panjang Elevasi Terpancang
No. Keterangan No. Keterangan
Titik TP (m) Platform (m) Titik TP (m) Platform (m)

9-Oct-23 1 PH83 S4 22,00 18,00 preboring 14 m


2 PH83 S3 22,00 18,00 preboring 14 m
3 PH82 S3 22,00 17,50 preboring 14 m
4 PH82 S2 22,00 19,50 preboring 14 m
5 PH6 S2 22,00 16,00 preboring 10 m
6 PH6 S1 22,00 16,50 preboring 10 m
7 PH5 S1 22,00 15,50 preboring 10 m
8-Oct-23 1 PH7 S1 22,00 16,00 preboring 10 m
2 PH8 S1 22,00 17,00 preboring 10 m
3 PH8 S2 22,00 16,00 preboring 10 m
4 PH9 S2 22,00 16,00 preboring 10 m
5 PH9 S1 22,00 16,00 preboring 10 m
6 PH7 S2 22,00 17,00 preboring 10 m
7-Oct-23 1 PH81 S1 22,00 20,00 preboring 14 m
2 PH81 S2 22,00 20,00 preboring 14 m
3 PH82 S1 22,00 20,00 preboring 14 m
4 PH14 S1 22,00 18,00 preboring 10 m
5 PH13 S1 22,00 18,00 preboring 10 m
6 PH12 S1 22,00 17,00 preboring 10 m
7 PH11 S2 22,00 17,50 preboring 10 m
8 PH11 S1 22,00 17,00 preboring 10 m
9 PH10 S2 22,00 16,50 preboring 10 m
10 PH10 S1 22,00 16,00 preboring 10 m
6-Oct-23 1 PH14 S2 22,00 18,00 preboring 10 m
2 PH12 S2 22,00 17,00 preboring 10 m
3 PH13 S2 22,00 17,00 preboring 10 m
4 PH6 S3 22,00 15,00 preboring 10 m
5 PH4 S3 22,00 15,00 preboring 10 m
6 PH5 S3 22,00 15,50 preboring 10 m
4-Oct-23 1 PH87 U2 22,00 13,00 preboring 12 m 1 PH4 S4 22,00 16,00 preboring 10 m
2 PH87 U3 22,00 12,80 preboring 12 m
3-Oct-23 1 PH86 U4 22,00 13,00 preboring 14 m 1 PH5 S4 22,00 15,50 preboring 10 m
2 PH87 U1 22,00 19,00 preboring 14 m 2 PH6 S4 22,00 15,00 preboring 10 m
3 PH7 S3 22,00 15,00 preboring 10 m
4 PH8 S3 22,00 16,00 preboring 10 m
5 PH9 S3 22,00 17,00 preboring 10 m
2-Oct-23 1 PH86 U2 22,00 18,00 preboring 14 m
2 PH86 U3 22,00 12,50 preboring 14 m
1-Oct-23 1 PH86 U1 22,00 17,50 preboring 14 m 1 PH8 S4 22,00 17,00 preboring 10 m
2 PH85 U4 22,00 19,50 preboring 14 m 2 PH7 S4 22,00 17,00 preboring 10 m
3 PH85 U3 22,00 19,50 preboring 14 m
30-Sep-23 1 PH85 U1 22,00 15,00 preboring 14 m
2 PH85 U2 22,00 17,50 preboring 14 m

78 304 7.508,00 5.755,90 Jumlah 339 8.168,00 6.255,75 Jumlah


Monitoring Pemancangan SOP-3 (Sta. 20+930 ~ 22+235) Status s/d hari ini : Terlaksana (titik) Bobot
Diameter CSP : 80 cm 29 Oktober 2023 Utara : 304 21,348%
Jumlah Titik Pancang : 1.424 Waktu terjalani : Selatan : 339 23,806%
Start Pemancangan : 28 Juli 2023 93 hari kalender Total : 643 45,154%
SISI UTARA SISI SELATAN
Tanggal
Pemancangan No. Panjang Elevasi Terpancang No. Panjang Elevasi Terpancang
No. Keterangan No. Keterangan
Titik TP (m) Platform (m) Titik TP (m) Platform (m)

MONITORING TEST PDA SOP-3 ( QU = 436 ton )


SISI UTARA SISI SELATAN
Tanggal
PDA No. Tanggal umur No. Tanggal umur
Keterangan Keterangan
Titik pemancangan (hari) Titik pemancangan (hari)

18-Aug-23 PH28S1 6-Aug-23 12 RMX = 488 ton


PH38S1 10-Aug-23 8 RMX = 504 ton
PH44S1 13-Aug-23 5 RMX = 658 ton
PH52S2 15-Aug-23 3 RMX = 430 ton
28-Aug-23 PH09U4 6-Aug-23 22 RMX = 437 ton
PH17U1 31-Jul-23 28 RMX = 478 ton
20-Sep-23 PH60S2 18-Aug-23 33 RMX = 481 ton
PH71S2 28-Aug-23 23 RMX = 486 ton
24-Sep-23 PH41U4 5-Sep-23 19 RMX = 508 ton
PH54U3 15-Sep-23 9 RMX = 424 ton
PH59U3 17-Sep-23 7 RMX = 372 ton
25-Sep-23 PH59U3 25-Sep-23 0 RMX = 421 ton, setelah
dilakukan pancang ulang,
dgn penurunan tiang
0,50 m
PH59U4 25-Sep-23 0 RMX = 404 ton, setelah
dilakukan pancang ulang,
dgn penurunan tiang
2,50 m

11-Oct-23 PH71U3 15-Sep-23 26 RMX = 486 ton PH78S2 16-Sep-23 25 RMX = 459 ton
PH75U3 16-Sep-23 25 RMX = 409 ton
PH75U4 16-Sep-23 25 RMX = 598 ton
PH86U3 2-Oct-23 9 RMX = 707 ton (preboring)

PH32U1 22-Aug-23 50 RMX = 404 ton


PH32U2 22-Aug-23 50 RMX = 447 ton
PH38U3 2-Sep-23 39 RMX = 532 ton
28-Oct-23 PH83S1 10-Oct-23 18 RMX = 600 ton
PH08S1 8-Oct-23 20 RMX = 461 ton
A1. S7 28-Oct-23 0 RMX = 496 ton, setelah
dilakukan pemancangan
ulang, dgn penurunan
tiang pancang 1,50 m