PT.

ANEKA MINERAL MAKMUR


Project : Pengeboran Block VII - I
Lokasi : Desa Ululere dan Desa Kolono
Week : Week 2
start week : 5/30/2021

Weekly activity

Pengeboran 30-May-21 31-May-21 1-Jun-21 2-Jun-21


Transportation 112 120 60 188
Safety Talk/Meeting 10 0 0 0
Check Rig 0 0 10 0
Weather Problem 0 0 0 0
Pengeboran 0 0 0 0
Moving 0 0 60 366
Setting 0 0 0 0
Resting/Lunch 0 60 60 117
Technical Problem 264 330 230 0
Mechanical Problem 0 0 0 0
others 154 30 120 -131
Total 540 540 540 540
WEEK 3

PT. ANEKA MINERAL MAKMUR


Project : Pengeboran Block VII - I
Lokasi : Desa Ululere dan Desa Kolono
Week : Week 3
start week : 6/6/2021

Weekly activity

Pengeboran 6-Jun-21 7-Jun-21 8-Jun-21 9-Jun-21


Transportation 0 0 135 0
Safety Talk/Meeting 0 0 0 0
Check Rig 0 0 15 0
Weather Problem 0 0 0 0
Pengeboran 0 0 150 0
Moving 0 0 0 0
Setting 0 0 0 0
Resting/Lunch 0 0 60 0
Technical Problem 0 0 0 0
Mechanical Problem 0 0 45 0
others 540 540 135 540
Total 540 540 540 540

WEEK 4
PT. ANEKA MINERAL MAKMUR
Project : Pengeboran Block VII - I
Lokasi : Desa Ululere dan Desa Kolono
Week : Week 4
start week : 6/13/2021

Weekly activity

Pengeboran 13-Jun-21 14-Jun-21 15-Jun-21 16-Jun-21


Transportation 120 105 100 130
Safety Talk/Meeting 0 0 0 0
Check Rig 0 0 0 15
Weather Problem 60 180 240 0
Pengeboran 0 95 180 120
Moving 0 0 0 90
Setting 0 40 0 105
Resting/Lunch 60 60 60 60
Technical Problem 240 60 0 0
Mechanical Problem 60 0 0 0
others 0 0 -40 20
Total 540 540 540 540

WEEK 5
PT. ANEKA MINERAL MAKMUR
Project : Pengeboran Block VII - I
Lokasi : Desa Ululere dan Desa Kolono
Week : Week 5
start week : 6/20/2021

Weekly activity

Pengeboran 20-Jun-21 21-Jun-21 22-Jun-21 23-Jun-21


Transportation 80 85 90 90
Safety Talk/Meeting 10 15 10 15
Check Rig 10 15 15 15
Weather Problem 0 0 0 0
Pengeboran 310 365 195 280
Moving 30 0 30 30
Setting 40 0 90 50
Resting/Lunch 60 60 60 60
Technical Problem 0 0 50 0
Mechanical Problem 0 0 0 0
others 0 0 0 0
Total 540 540 540 540

Normal Activity
PT. ANEKA MINERAL MAKMUR
Project : Pengeboran Block VII - I
Lokasi : Desa Ululere dan Desa Kolono
Week : Week 4
start week : 6/13/2021

Weekly activity

Pengeboran 31-Dec-99 1-Jan-00 2-Jan-00 3-Jan-00


Transportation 60 60 60 60
Safety Talk/Meeting 15 15 15 15
Check Rig 0 10 0 0
Weather Problem 0 0 0 0
Pengeboran 385 315 385 385
Moving 0 60 0 0
Setting 20 20 20 20
Resting/Lunch 60 60 60 60
Technical Problem 0 0 0 0
Mechanical Problem 0 0 0 0
others 0 0 0 0
Total 540 540 540 540
WEEKLY WEEKLY
PRODUCTION
REPORT
DAILY DAILY
PRODUCTION

3-Jun-21 4-Jun-21 5-Jun-21 Week 2 % Bagan ini tidak tersedia dalam ve


65 135 100 780 20.63 Mengedit bentuk ini atau menyim
0 0 0 10 0.26
0 0 15 25 0.66
0 60 0 60 1.59
0 20 240 260 6.88
181 0 0 607 16.06
200 400 0 600 15.87
60 60 60 417 11.03
0 0 0 824 21.80
0 20 0 20 0.53
34 -155 125 177 4.68
540 540 540 3780 100

10-Jun-21 11-Jun-21 12-Jun-21 Week 3 % Bagan ini tidak tersedia dalam ve


92 100 95 422 11.16 Mengedit bentuk ini atau menyim
0 0 0 0 0.00
15 5 15 50 1.32
0 0 15 15 0.40
208 330 35 723 19.13
30 0 90 120 3.17
20 0 0 20 0.53
60 50 60 230 6.08
0 0 230 230 6.08
115 55 0 215 5.69
0 0 0 1755 46.43
540 540 540 3780 100

17-Jun-21 18-Jun-21 19-Jun-21 Week 4 % Bagan ini tidak tersedia dalam vers
135 75 100 765 20.24
15 0 0 15 0.40 Mengedit bentuk ini atau menyimp
15 10 15 55 1.46
0 160 0 640 16.93
165 180 275 1015 26.85
0 0 60 150 3.97
0 0 70 215 5.69
0 120 60 420 11.11
0 0 0 300 7.94
210 25 0 295 7.80
0 -30 -40 -90 -2.38
540 540 540 3780 100

24-Jun-21 25-Jun-21 26-Jun-21 Week 5 % Bagan ini tidak tersedia dalam vers
120 60 300 825 21.83
15 15 0 80 2.12 Mengedit bentuk ini atau menyimp
15 15 0 85 2.25
Bagan ini tidak tersedia dalam vers

Mengedit bentuk ini atau menyimp

0 0 0 0 0.00
330 120 0 1600 42.33
0 210 180 480 12.70
0 0 0 180 4.76
60 60 60 420 11.11
0 60 0 110 2.91
0 0 0 0 0.00
0 0 0 0 0.00
540 540 540 3780 100

4-Jan-00 5-Jan-00 6-Jan-00 Week 4 %


60 60 60 420 11.11
15 15 15 105 2.78
10 0 0 20 0.53
0 0 0 0 0.00
315 385 385 2555 67.59
60 0 0 120 3.17
20 20 20 140 3.70
60 60 60 420 11.11
0 0 0 0 0.00
0 0 0 0 0.00
0 0 0 0 0.00
540 540 540 3780 100
an ini tidak tersedia dalam versi Excel Anda.

gedit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan secara permanen.

an ini tidak tersedia dalam versi Excel Anda.

gedit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan secara permanen.
ini tidak tersedia dalam versi Excel Anda.

dit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan secara permanen.

ini tidak tersedia dalam versi Excel Anda.

dit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan secara permanen.
ini tidak tersedia dalam versi Excel Anda.

dit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan secara permanen.
secara permanen.

secara permanen.
Bagan ini tidak tersedia dalam versi Excel Anda.

ecara permanen. Mengedit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan s

Bagan ini tidak tersedia dalam versi Excel Anda.

ecara permanen. Mengedit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan s
Bagan ini tidak tersedia dalam versi Excel Anda.

ecara permanen. Mengedit bentuk ini atau menyimpan buku kerja ini ke dalam format file yang berbeda akan merusak bagan s
yang berbeda akan merusak bagan secara permanen.

yang berbeda akan merusak bagan secara permanen.


yang berbeda akan merusak bagan secara permanen.
WEEKLY RIG WEEKLY
PRODUCTION
REPORT
DAILY RIG DAILY
PRODUCTION D
A
Y

Daily activity 1

30-May-21
Pengeboran Waktu (menit) %
Transporta-
Transportation 112 21% tion Safety
21% Talk/Meet-
Safety Talk/Meeting 10 2% ing
Check Rig 0 0% 2%
Weather Problem 0 0%
others
Pengeboran 0 0% 29%
Moving 0 0%
Setting 0 0%
Resting/Lunch 0 0%
Technical Problem 264 49%
Mechanical Problem 0 0%
others 154 29%
Technical Problem
Total 540 100% 49%

D
WEEK 3 A
Y

Daily activity 1

6-Jun-21
Pengeboran Waktu (menit) %
Transportation 0 0%
Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 0 0%
Pengeboran 0 0%
Moving 0 0%
Setting 0 0%
Resting/Lunch 0 0%
Technical Problem 0 0% others
Mechanical Problem 0 0% 100%
others 540 100%
Total 540 100%
D
A
WEEK 4 Y

Daily activity 1

13-Jun-21
Pengeboran Waktu (menit) %
Transportation 120 22% Trans
Safety Talk/Meeting 0 0% porta-
Mechanical Problem tion
Check Rig 0 0% 11% 22%
Weather Problem 60 11%
Pengeboran 0 0% Weather
Moving 0 0% Problem
Tech- 11%
nical Resting/
Setting 0 0% Lunch
Prob- 11%
Resting/Lunch 60 11% lem
Technical Problem 240 44% 44%
Mechanical Problem 60 11%
others 0 0%
Total 540 100%
11%
lem
44%

D
A
WEEK 5 Y

Daily activity 1

20-Jun-21
Safety
Pengeboran Waktu (menit) % Talk/Meet- Check Rig
ing 2%
2%
Transportation 80 15%
Safety Talk/Meeting 10 2%
Check Rig 10 2%
Resting/Lunch Trans-
Weather Problem 0 0% Setting
11% portation
7%
15%
Pengeboran 310 57% Moving
6%
Moving 30 6%
Setting 40 7%
Resting/Lunch 60 11% Pengeboran
Technical Problem 0 0% 57%

Mechanical Problem 0 0%
others 0 0%
Total 540 100%
D
A
Y

Daily activity 2

31-May-21
Pengeboran Waktu (menit) % Transporta- Rig 0 activity
others tion
Transportation 120 22% 6% 25%

Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 0 0%
Pengeboran 0 0%
Moving 0 0%
Setting 0 0%
Resting/Lunch 60 0%
Technical Problem 330 61%
Mechanical Problem 0 0%
others 30 6%
Technical
Total 540 89% Problem
69%
D
A
Y

Daily activity 2

7-Jun-21
Pengeboran Waktu (menit) % Rig 0 activity
Transportation 0 0%
Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 0 0%
Pengeboran 0 0%
Moving 0 0%
Setting 0 0%
Resting/Lunch 0 0% others
Technical Problem 0 0% 100%
Mechanical Problem 0 0%
others 540 100%
Total 540 100%
D
A
Y

Daily activity 2

14-Jun-21
Pengeboran Waktu (menit) % Rig 0 activity
Transportation 105 19%
Safety Talk/Meeting 0 0% Technical Problem
Check Rig 0 0% 11%
Resting/Lunch
Transportation
Weather Problem 180 33% 11% 19%
Pengeboran 95 18% Setting
7%
Moving 0 0% Weather
Setting 40 7% Pengeboran Problem
18% 33%
Resting/Lunch 60 11%
Technical Problem 60 11%
Mechanical Problem 0 0%
others 0 0%
Total 540 100%
D
A
Y

Daily activity 2

21-Jun-21
Safety
Pengeboran Waktu (menit) % Talk/ Rig 0 activity
Meeting
3%
Transportation 85 16% Check
Rig
Safety Talk/Meeting 15 3% 3%
Check Rig 15 3%
Weather Problem Trans
0 0% Resting/Lunch porta-
Pengeboran 365 68% 11% tion
16%
Moving 0 0%
Setting 0 0%
Resting/Lunch 60 11%
Technical Problem 0 0% Pengeboran
Mechanical Problem 0 0% 68%
others 0 0%
Total 540 100%
D
A
Y

Daily Rig activity 3

1-Jun-21
others Transportation Rig 03
Pengeboran Waktu (menit) % 11%
22% activity
Transportation 60 11% Check Rig
Safety Talk/Meeting 0 0% 2%
Check Rig 10 2%
Weather Problem 0 0%
Pengeboran 0 0% Moving
Moving 60 11% 11%
Setting 0 0% Resting/
Resting/Lunch 60 11% Lunch
11%
Technical Problem 230 43%
Mechanical Problem 0 0%
others 120 22%
Technical
Total 540 100% Problem
43%
D
A
Y

Daily Rig activity 3

8-Jun-21
Pengeboran Waktu (menit) % Rig 03
Trans- activity
Transportation 135 25% portation
Safety Talk/Meeting 0 0% 25% Check Rig
Check Rig 15 3% 3%
Weather Problem 0 0%
Pengeboran 150 28%
Moving 0 0% others
25%
Setting 0 0%
Resting/Lunch 60 11% Mechan-
Technical Problem 0 0%
ical Prob- Resting/ Pengeb-
lem Lunch oran
Mechanical Problem 45 8% 8% 11% 28%
others 135 25%
Total 540 100%
D
A
Y

Daily Rig activity 3

15-Jun-21
Pengeboran Waktu (menit) % Rig 03
activity
Transportation 100 19%
Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 240 44%
Pengeboran 180 33%
others
Moving 0 0% 6%
Setting 0 0% Resting/Lunch
10%
Transportation
16%
Resting/Lunch 60 11% Pengeboran Weather
29% Problem
Technical Problem 0 0% 39%
Mechanical Problem 0 0%
others -40 -7%
Total 540 100%
D
A
Y

Daily Rig activity 3

22-Jun-21
Pengeboran Waktu (menit) % Rig 03
Safety
activity
Transportation 90 17% Talk/
Safety Talk/Meeting 10 2% Meeting
2%
Check Rig 15 3%
Weather Problem 0 0% Check
Technical Problem Rig
Pengeboran 195 36% 3%
9%
Moving 30 6% Resting/
Trans-
portation
Setting 90 17% Lunch
11%
17%
Setting
Resting/Lunch 60 11% 17%
Technical Problem 50 9% Moving Pengeb
6% oran
Mechanical Problem 0 0% 36%
others 0 0%
Total 540 100%
D
A
Y

Daily Activity 4

2-Jun-21
Pengeboran Waktu (menit) % Transporta- Rig 03
others tion
16% activity
Transportation 188 35% 23%
Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 0 0%
Pengeboran 0 0%
Moving 366 68%
Setting 0 0% Resting/
Resting/Lunch 117 22% Lunch
15%
Technical Problem 0 0%
Mechanical Problem 0 0% Moving
others -131 -24% 46%
Total 540 100%

D
A
Y

Daily Activity 4

9-Jun-21
Pengeboran Waktu (menit) % Transporta- Rig 03
others tion
16% activity
Transportation 0 0% 23%
Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 0 0%
Pengeboran 0 0%
Moving 0 0%
Setting 0 0% Resting/
Resting/Lunch 0 0% Lunch
15%
Technical Problem 0 0%
Mechanical Problem 0 0%
Moving
others 540 100% 46%
Total 540 100%
D
A
Y

Daily Activity 4

16-Jun-21
Pengeboran Waktu (menit) % Rig 03
activity
Transportation 130 24%
Safety Talk/Meeting 0 0%
Check Rig 15 3%
Weather Problem 0 0%
others
Pengeboran 120 22% Resting/ 4%
Moving 90 17% Lunch Transportation Check Rig
Setting 11% 24% 3%
Setting 105 19% 19%
Resting/Lunch 60 11%
Technical Problem 0 0% Pengeboran
Moving 22%
Mechanical Problem 0 0% 17%
others 20 4%
Total 540 100%
Pengeboran
Moving 22%
17%

D
A
Y

Daily Activity 4

23-Jun-21
Pengeboran Waktu (menit) % Resting/Lunch Rig 03
11%
Setting activity
Transportation 90 17% 9% Trans Check
porta- Rig
Safety Talk/Meeting 15 3% tion Moving
6%
3%
17% Safety
Check Rig 15 3% Talk/
Meeting
Weather Problem 0 0% 3%
Pengeboran 280 52%
Moving 30 6%
Setting 50 9%
Resting/Lunch 60 11%
Technical Problem 0 0%
Mechanical Problem 0 0% Pengeboran
others 0 0% 52%

Total 540 100%


D
A
Y

Daily activity 5

3-Jun-21
Pengeboran Waktu (menit) % Rig 03
Transportation activity
Transportation 65 12% 12%
Safety Talk/Meeting 0 0%
Check Rig 0 0% others
Weather Problem 0 0% 6%
Pengeboran 0 0% Resting/Lunch
11%
Moving 181 34%
Setting 200 37%
Resting/Lunch 60 11%
Setting Moving
Technical Problem 0 0% 37% 34%
Mechanical Problem 0 0%
others 34 6%
Total 540 100%

D
A
Y

Daily activity 5

10-Jun-21
Pengeboran Waktu (menit) % Rig 03
activity
Transportation 92 17%
Safety Talk/Meeting 0 0%
Check Rig 15 3%
Weather Problem 0 0%
Pengeboran 208 39% Mechanical Transporta- Check Rig
Resting/Lunch Problem tion 3%
Moving 30 6% 21% 17%
11%
Setting 20 4%
Resting/Lunch 60 11% Setting
Technical Problem 0 0% 4% Pengeboran
39%
Mechanical Problem 115 21%
others 0 0% Moving
6%
Total 540 100%
D
A
Y

Daily activity 5

17-Jun-21
Pengeboran Waktu (menit) % Rig 03
activity
Transportation 135 25%
Safety Talk/Meeting 15 3% Safety
Check Rig 15 3% Talk/Meet-
Weather Problem 0 0% ing
Transporta- 3%
Pengeboran 165 31% Mechanical tion
Moving 0 0% Problem 25%
Setting 0 0% 39%
Resting/Lunch 0 0%
Technical Problem 0 0%
Pengeboran Check Rig
Mechanical Problem 210 39% 31% 3%
others 0 0%
Total 540 100%
Pengeboran Check Rig
31% 3%

D
A
Y

Daily activity 5

24-Jun-21
Pengeboran Waktu (menit) % Rig 03
activity
Transportation 120 22% Safety
Talk/Meet-
Safety Talk/Meeting 15 3% ing
3%
Check Rig 15 3%
Transporta- Check Rig
Weather Problem 0 0% Resting/Lunch tion 3%
Pengeboran 11% 22%
330 61%
Moving 0 0%
Setting 0 0%
Resting/Lunch 60 11%
Pengeb-
Technical Problem 0 0% oran
Mechanical Problem 0 0% 61%
others 0 0%
Total 540 100%
D
A
Y

Daily activity 6

4-Jun-21
Pengeboran Waktu (menit) % Rig 03 activity
Weather
Transportation 135 25% Problem
7%
Safety Talk/Meeting 0 0% Mechanical
Check Rig 0 0% Problem
Weather Problem 2%
60 11%
others Pengeboran
Pengeboran 20 4% Transporta- 2%
Resting/Lunch 18%
Moving 0 0% tion
7%
Setting 400 74% 16%
Resting/Lunch 60 11%
Technical Problem 0 0% Setting
Mechanical Problem 20 4% 47%
others -155 -29%
Total 540 100%

D
A
Y

Daily activity 6

11-Jun-21
Pengeboran Waktu (menit) % Rig 03 activity
Transportation 100 19%
Safety Talk/Meeting 0 0%
Check Rig 5 1%
Weather Problem 0 0%
Pengeboran 330 61% Resting/Lunch Transporta-
9% tion
Moving 0 0% 19%
Setting 0 0% Mechanical Problem Check Rig
Resting/Lunch 50 9% 10% 1%
Technical Problem 0 0% Pengeboran
Mechanical Problem 55 10% 61%
others 0 0%
Total 540 100%
D
A
Y

Daily activity 6

18-Jun-21
Pengeboran Waktu (menit) % Rig 03 activity
Transportation Mechanical
75 14% Problem
Safety Talk/Meeting 0 0% 4%
Check Rig 10 2%
Check Rig
Weather Problem 160 30% 2%
others
Pengeboran 180 33% 5% Transportation
13%
Moving 0 0% Resting/Lunch
20%
Setting 0 0% Weather Prob-
Resting/Lunch 120 22% lem
27%
Technical Problem 0 0%
Pengeboran
Mechanical Problem 25 5% 30%
others -30 -6%
Total 540 100%
D
A
Y

Daily activity 6

25-Jun-21
Safety Check
Pengeboran Waktu (menit) % Rig 03 activity
Talk/ Rig
Meeting 3%
Transportation 60 11% 3%
Safety Talk/Meeting 15 3%
Check Rig 15 3%
Weather Problem 0 0% Resting/ Technical Problem
Pengeboran 120 22% Lunch 11% Transportation
11% 11%
Moving 210 39%
Setting 0 0%
Resting/Lunch 60 11% Pengeb
oran
Technical Problem 60 11% Moving 22%
Mechanical Problem 0 0% 39%

others 0 0%
Total 540 100%
D
Daily Rig activity A
Y

5-Jun-21 7

Pengeboran Waktu (menit) %


Transporta-
Transportation 100 19% tion
Safety Talk/Meeting 0 0% 19%
Check Rig 15 3%
Weather Problem 0 0%
others
Pengeboran 240 44% 23% Check Rig
Moving 0 0% Resting/ 3%
Setting 0 0% Lunch
Resting/Lunch 11%
60 11%
Pengeboran
Technical Problem 0 0% 44%
Mechanical Problem 0 0%
others 125 23%
Total 540 100%

D
Daily Rig activity A
Y

12-Jun-21 7

Pengeboran Waktu (menit) % Rig 03 activity


Transportation 95 18%
Safety Talk/Meeting 0 0%
Check Rig 15 3%
Weather Problem 15 3% Check Rig
Transporta- 3%
Pengeboran 35 6% tion
Technical Weather
Moving 90 17% Problem 18% Problem
Setting 0 0% 43% 3%
Resting/Lunch 60 11% Pengeboran
Technical Problem 230 43% Moving 6%
Mechanical Problem 0 0% 17%
others 0 0% Resting/Lunch
11%
Total 540 100%

D
Daily Rig activity A
Y

19-Jun-21 7

Pengeboran Waktu (menit) % Rig 03 activity


Transportation 100 19%
Safety Talk/Meeting 0 0%
Check Rig 15 3%
Weather Problem 0 0% Check Rig
Resting/Lunch others
Pengeboran 275 51% 10% 6% Transportation
2%
Moving 60 11% Setting
11% 16%
Setting 70 13%
Resting/Lunch 60 11% Pengeboran
Moving 44%
Technical Problem 0 0% 10%
Mechanical Problem 0 0%
others -40 -7%
Total 540 100%
Pengeboran
Moving 44%
10%

D
Daily Rig activity A
Y

26-Jun-21 7

Pengeboran Waktu (menit) % Rig 03 activity


Transportation 300 56%
Safety Talk/Meeting 0 0%
Check Rig 0 0%
Weather Problem 0 0%
Resting/Lunch
Pengeboran 0 0% 11%
Moving 180 33%
Setting 0 0%
Resting/Lunch 60 11% Moving
33%
Technical Problem 0 0%
Trans-
Mechanical Problem 0 0% portation
others 0 0% 56%

Total 540 100%


WEEKLY RIG WEEKLY
PRODUCTION
REPORT
DAILY RIG DAILY
PRODUCTION

Weekly II Production

Hari / Tanggal Meteran Per hari Plan Rata-Rata

5/30/2021 - 20.00
5/31/2021 - 20.00
6/1/2021 - 20.00
6/2/2021 - 20.00
6/3/2021 - 20.00
6/4/2021 4.00 20.00 4.00
6/5/2021 9.00 20.00 6.50
Total 13.00 140.00 1.50

Produksi Harian Kegiatan

10
Production (m)

5/30/2021 5/31/2021 6/1/2021 6/2/2021 6/3/2021 6/4/2021 6/5/2021

Weekly III Production

Hari / Tanggal Meteran Per hari Plan Rata-Rata

6/6/2021 - 20.00 4.33


6/7/2021 - 20.00 3.25
6/8/2021 3.00 20.00 3.20
6/9/2021 - 20.00 2.67
6/10/2021 6.00 20.00 3.14
6/11/2021 3.00 20.00 3.13
6/12/2021 3.50 20.00 3.17
Total 15.50 140.00 3.27

Produksi Harian Kegiatan

10
Production (m)

6/6/2021 6/7/2021 6/8/2021 6/9/2021 6/10/2021 6/11/2021 6/12/2021

Weekly IV Production

Hari / Tanggal Meteran Per hari Plan Rata-Rata

6/13/2021 - 20.00 2.85


6/14/2021 2.50 20.00 2.82
6/15/2021 3.00 20.00 2.83
6/16/2021 8.00 20.00 3.23
6/17/2021 5.50 20.00 3.39
6/18/2021 3.50 20.00 3.40
6/19/2021 8.50 20.00 3.72
Total 31.00 140.00 3.18

Produksi Harian Kegiatan

10
Production (m)

0
Production (m)
5

6/13/2021 6/14/2021 6/15/2021 6/16/2021 6/17/2021 6/18/2021 6/19/2021

Weekly V Production

Hari / Tanggal Meteran Per hari Plan Rata-Rata

6/20/2021 10.50 20.00 4.12


6/21/2021 8.00 20.00 4.33
6/22/2021 15.00 20.00 4.89
6/23/2021 10.00 20.00 5.15
6/24/2021 12.70 20.00 5.51
6/25/2021 3.30 20.00 5.41
6/26/2021 - 20.00 5.17
Total 59.50 140.00 4.94

Produksi Harian Kegiatan

20

15
Production (m)

10

6/20/2021 6/21/2021 6/22/2021 6/23/2021 6/24/2021 6/25/2021 6/26/2021


DIAGRAM PROGRES MINGGU II
25.00
20.00
15.00
10.00
5.00
-
1 2 3 4 5 6 7

Meteran Per hari Plan

2021 6/5/2021

DIAGRAM PROGRES MINGGU III


25.00
20.00
15.00
10.00
5.00
-
1 2 3 4 5 6 7

Meteran Per hari Plan


20.00
15.00
10.00
5.00
-
1 2 3 4 5 6 7

Meteran Per hari Plan

2021 6/12/2021

DIAGRAM PROGRES MINGGU IV


25.00
20.00
15.00
10.00
5.00
-
1 2 3 4 5 6 7

Meteran Per hari Plan Rata-Rata

an
8/2021 6/19/2021

DIAGRAM PROGRES MINGGU IV


25.00
20.00
15.00
10.00
5.00
-
1 2 3 4 5 6 7

Meteran Per hari Plan Rata-Rata

an

5/2021 6/26/2021
7

7
7

7
7
WEEKLY RIG WEEKLY
PRODUCTION
REPORT
DAILY
DAILY RIG PRODUCTION WEEK 3

Pengeboran Meteran

5/30/2021 0.00
Plan Daily 20.00
Total 0.00
Average/day

Diagram Rencana dan Aktual Diag


Pengeboran
25.00 25.00
Luas Area (Ha)

20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00
Meteran 'daily prod'!#

2
Pengeboran Meteran

5/31/2021 0.00
Plan Daily 20.00
Total 0.00
Average/day

Diagram Rencana dan Aktual Pengeb-


oran
1.00
0.80
0.60
0.40
0.20
0.00

Meteran
3

Pengeboran Meteran

6/1/2021 0.00
Plan Daily 20.00
Total 0.00
Average/day

Diagram Rencana dan Aktual Pengeb- D


oran
1.00 25.00
0.80 20.00
0.60 15.00
0.40 10.00
0.20 5.00
0.00 0.00

Meteran

Pengeboran Meteran

6/2/2021 0.00
Plan Daily 20.00
Total 0.00
Average/day

Diagram Rencana dan Aktual Pengeb- D


oran
1.00 1.00
0.80 0.80
0.60 0.60
0.40 0.40
0.20 0.20
0.00 0.00

Meteran

Pengeboran Meteran

6/3/2021 0.00
Plan Daily 20.00
Total 0.00
Average/day

Diagram Rencana dan Aktual Pengeb- Diag


oran
1.00 25.00
0.80 20.00
0.60 15.00
0.40 10.00
0.20 5.00
0.00 0.00

Meteran

Pengeboran Meteran

6/4/2021 4.00
Plan Daily 20.00
Total 4.00
Average/day 4.00 1

Diagram Rencana dan Aktual Pengeb- Dia


oran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/4/2021 Plan Daily

Pengeboran Meteran

6/5/2021 9.00
Plan Daily 20.00
Total 13.00
Average/day 6.50 2

Diagram Rencana dan Aktual D


Pengeboran
Diagram Rencana dan Aktual D
Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/5/2021 Plan Daily


WEEK 4

Pengeboran Meteran

6/6/2021 0.00
Plan Daily 20.00
Total 13.00 1
Average/day 4.33 3

Diagram Rencana dan Aktual Diagr


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00
6/6/2021 Plan Daily

2
Pengeboran Meteran

6/7/2021 0.00
Plan Daily 20.00
Total 13.00 2
Average/day 3.25 4

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/7/2021 Plan Daily


3

Pengeboran Meteran

6/8/2021 3.00
Plan Daily 20.00
Total 16.00 3
Average/day 3.20 5

Diagram Rencana dan Aktual Dia


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/8/2021 Plan Daily

Pengeboran Meteran

6/9/2021 0.00
Plan Daily 20.00
Total 16.00 4
Average/day 2.67 6

Diagram Rencana dan Aktual Di


Pengeboran
1.00 25.00
0.80 20.00
0.60 15.00
0.40 10.00
0.20 5.00
0.00 0.00

Meteran

Pengeboran Meteran

6/10/2021 6.00
Plan Daily 20.00
Total 22.00 5
Average/day 3.14 7

Diagram Rencana dan Aktual Diagr


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/10/2021 Plan Daily

Pengeboran Meteran

6/11/2021 3.00
Plan Daily 20.00
Total 25.00
Average/day 3.13 8

Diagram Rencana dan Aktual Diag


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/4/2021 Plan Daily

Pengeboran Meteran

6/12/2021 3.50
Plan Daily 20.00
Total 28.50 1
Average/day 3.17 9

Diagram Rencana dan Aktual Dia


Pengeboran
Diagram Rencana dan Aktual Dia
Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/12/2021 Plan Daily


WEEK 5

Pengeboran Meteran

6/13/2021 0.00
Plan Daily 20.00
Total 28.50 1
Average/day 2.85 10

Diagram Rencana dan Aktual Diagr


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00
6/6/2021 Plan Daily

2
Pengeboran Meteran

6/14/2021 2.50
Plan Daily 20.00
Total 31.00 2
Average/day 2.82 11

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/14/2021 Plan Daily


3

Pengeboran Meteran

6/15/2021 3.00
Plan Daily 20.00
Total 34.00 3
Average/day 2.83 12

Diagram Rencana dan Aktual Dia


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/15/2021 Plan Daily

Pengeboran Meteran

6/16/2021 8.00
Plan Daily 20.00
Total 42.00 4
Average/day 3.23 13

Diagram Rencana dan Aktual Di


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/16/2021 Plan Daily

Pengeboran Meteran

6/17/2021 5.50
Plan Daily 20.00
Total 47.50 5
Average/day 3.39 14

Diagram Rencana dan Aktual Diagr


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/17/2021 Plan Daily

Pengeboran Meteran

6/18/2021 3.50
Plan Daily 20.00
Total 51.00
Average/day 3.40 15

Diagram Rencana dan Aktual Diag


Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/18/2021 Plan Daily

Pengeboran Meteran

6/19/2021 8.50
Plan Daily 20.00
Total 59.50 1
Average/day 3.72 16

Diagram Rencana dan Aktual Dia


Pengeboran
Diagram Rencana dan Aktual Dia
Pengeboran
25.00 25.00
20.00 20.00
15.00 15.00
10.00 10.00
5.00 5.00
0.00 0.00

6/19/2021 Plan Daily


WEEK6

Pengeboran Meteran

6/20/2021 10.50
Plan Daily 20.00
Total 70.00 1
Average/day 4.12 17

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00
6/20/2021 Plan Daily

2
Pengeboran Meteran

6/21/2021 8.00
Plan Daily 20.00
Total 78.00 2
Average/day 4.33 18

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/21/2021 Plan Daily


3

Pengeboran Meteran

6/22/2021 15.00
Plan Daily 20.00
Total 93.00 3
Average/day 4.89 19

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/22/2021 Plan Daily

Pengeboran Meteran

6/23/2021 10.00
Plan Daily 20.00
Total 103.00 4
Average/day 5.15 20

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/23/2021 Plan Daily

Pengeboran Meteran

6/24/2021 12.70
Plan Daily 20.00
Total 115.70 5
Average/day 5.51 21

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/24/2021 Plan Daily

Pengeboran Meteran

6/25/2021 3.30
Plan Daily 20.00
Total 119.00
Average/day 5.41 22

Diagram Rencana dan Aktual


Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/25/2021 Plan Daily

Pengeboran Meteran

6/26/2021 0.00
Plan Daily 20.00
Total 119.00 1
Average/day 5.17 23

Diagram Rencana dan Aktual


Pengeboran
Diagram Rencana dan Aktual
Pengeboran
25.00
20.00
15.00
10.00
5.00
0.00

6/26/2021 Plan Daily


WEEKLY
WEEKLY RIG PRODUCTION
REPORT
DAILY RIG DAILY
PRODUCTION

Laporan Pekerjaan Pengeboran

No ID_HOLE BORE Y X Z EOH Loss Start (mm/dd/yy)


2 7I2304 9701281.000 377421.000 522.000 21.00 June 23, 2021
3 7I3104 9701281.000 377494.000 516.000 19.00 June 22, 2021
4 7I3904 9701295.037 377577.878 577.000 10.00 June 16, 2021
5 7I4704 9701303.120 377685.955 391.000 8.00 June 15, 2021
7 7I3112 9701366.000 377496.000 535.000 17.00 June 20, 2021
8 7I3912 9701388.000 377608.000 592.000 10.00 June 19, 2021
9 7I4712 9701379.903 377697.312 609.000 9.00 June 11, 2021
11 7I3920 9701472.945 377589.962 568.000 16.00 0.00 June 4, 2021
12 7I4720 9701458.468 377669.447 560.000 9.00 0.05 June 10, 2021
Finish (mm/dd/yy)
June 25, 2021
June 23, 2021
June 19, 2021
June 16, 2021
June 22, 2021
June 20, 2021
June 15, 2021
June 8, 2021
June 11, 2021
LAPORAN HARIAN KEGIATAN TESTPIT

SITE PROJECT : IUP BNB BLOCK VII I DAN H CUACA : Cerah


HARI/ TANGGAL : Rabu / 04-21-2021 PENGAWAS : Achyar

TENAGA KERJA PEKERJAAN HARI INI PETA KEMAJUAN PEKERJAAN


NO. JABATAN JUMLAH NO. URAIAN KEGIATAN WAKTU
1 Mine Geologist 1 Org 1 Mobilisasi Tim Ke titik Camp 8:00 9:00
2 Jr. Geologist 1 Org 2 Pembuatan Camp 9:00 17:00
3 Operator Exca 1 Org 3 Pengawalan Alat Masuk ke IUP BNB 10:00 16:00
4 Leader 1 Org 4 Demobilisasi Tim 17:00 17:50
5 TL 3 Org

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANAN PEKERJAAN


1 Mobil LV 1 Unit
2 Excavator 1 Unit

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA
1. Testpit Block VII - H
2. Persiapan Tim untuk Flying Camp

SAMPLE HOUSE

KENDALA
1. Akses masuk ke lokasi (Padatnya Kegiatan Hauling PT. URM dan Hauling Road yang masih
SAMPLE LAB basah/becek karena hujan dari malam hari.
LAPORAN H

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Jum'at / 05-21-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Geologist 1 Org 2
3 Jr. Geologist 1 Org 3
4 TL 4 Org 4

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit
2 RIG 1 Unit

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Pencarian Exca untuk disewa
2. Pengecekan alat rig untuk persiapan mobilisasi ke Titik per

SAMPLE HOUSE

KENDALA
1. adanya demo warga ululere sehingga tidak bisa melintas le
SAMPLE LAB

LAPORA

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Kamis / 05-22-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Geologist 1 Org 2
3 Jr. Geologist 1 Org 3
4 TL 2 Org 4

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit
2 RIG 1 Unit

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Pembuatan camp eksplorasi
2. Pencarian Exca

SAMPLE HOUSE

KENDALA
1. adanya demo warga ululere sehingga tidak bisa melintas le
SAMPLE LAB 2. belum ada exca yang mau masuk area ululere

LAPORA

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Minggu / 05-23-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Geologist 1 Org
3 Jr. Geologist 1 Org
4 TL 6 Org
5 Leader 1 Org

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit
2 RIG 1 Unit

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Melanjutkan Pembuatan Camp Eksplorasi

SAMPLE HOUSE

KENDALA
1. adanya demo warga ululere sehingga tidak bisa melintas le
SAMPLE LAB 2. belum ada exca yang mau masuk area ululere
3. Pekerjaan terhenti karena hujan pada pukul 14:00 wita

LAPORA

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Senin / 05-24-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Geologist 1 Org 2
3 Jr. Geologist 1 Org 3
4 TL 6 Org
5 Leader 1 Org

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit 1. Jalur dari kebun Pak Halo blum bisa di lalui, harus di perba
2 RIG 1 Unit

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Pembuatan Campfield
2. Moving rig dari kebun pak halo ketitik bor
3. Traveling alat menuju lokasi

SAMPLE HOUSE

KENDALA
1. hujan
SAMPLE LAB

LAPORAN H

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Selasa / 05-25-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 6 Org 3
4 Leader 1 Org
5 Operator 1 Org
6 Geologist 1 Org

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit 1. Perbaikan jalur
2 Excavator 1 Unit
3 Rig 1 Unit

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Pembuatan Camp
2. Belanja logistik camp
3.Belanja polimer Di Mahoni (Marowali Utara)

SAMPLE HOUSE

KENDALA
1. Hujan
SAMPLE LAB 2.Kerusakan Gear Saproket sehingga menunggu diganti

LAPORA

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Rabu / 05-26-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org
2 Jr. Geologist 1 Org
3 TL 4 Org
4 Leader 1 Org
5 Operator exca 0 Org
6 Geologist 1 Org

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit 1. Perbaikan jalur
2 Excavator 1 Unit
3 Rig 1 Unit
SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Pencarian Titik Mata air
2. Menunggu perbaikan exca

SAMPLE HOUSE

KENDALA
1. Hujan Seharian
SAMPLE LAB 2. Volume dan Debit Air Sungai Bertambah Sehingga tidak s

LAP

SITE PROJECT : IUP BNB BLOCK VII I


HARI/ TANGGAL : Selasa/ 05-27-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 7 Org
4 Driver 1 Org

ALAT PENUNJANG KEGIATAN PERSOALAN ASPEK KEAMANA


1 Mobil LV 1 Unit 1. Menunggu perbaikan excavator

SAMPLE FIELD
PEKERJAAN YANG AKAN DI LAKUKAN
1. Moving rig menggunakan wing wire
SAMPLE HOUSE

KENDALA
1. Excavator Breakdown
SAMPLE LAB 2. Cuaca
3. Jalur menuju titik belum bisa di lalui mobil lv

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : jum'at/ 05-28-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 8 Org

PENGGUNAAN BAHAN BAKAR PERSOALAN ASPEK KEAMANA


1 Solar Rig 1 Jergen 35

SAMPLE FIELD PEKERJAAN YANG AKAN DI LAKUKAN


1. Pembelian Bahan makanan persiapan campfield

SAMPLE HOUSE
KENDALA
1.Sling Rig tidak sanggup menarik.
SAMPLE LAB 2.Paku tidak cukup.

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Sabtu/ 05-29-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org
2 Jr. Geologist 2 Org
3 TL 0 Org

PENGGUNAAN BAHAN BAKAR PERSOALAN ASPEK KEAMANA


1 Solar Exca 6 Jergen 35 1. harus dibuat jalur mobil LV menuju camp field
2 Solar Masuk 6 Jergen 35

PERSEDIAAN SOLAR
1 Solar 9 Jergen
SAMPLE FIELD PEKERJAAN YANG AKAN DI LAKUKAN
1. Perbaikan Excavator
2. Setting air rig
3. Mobilisasi rig dititik pertama

SAMPLE HOUSE

KENDALA
1. Menunggu perbaikan exca
SAMPLE LAB
LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Minggu/ 05-30-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 8 Org 3
4

PENGGUNAAN BAHAN BAKAR PERSOALAN ASPEK KEAMANA


1. Perlunya perbaikan jalur

PERSEDIAAN SOLAR
1 Solar 9 Jergen
SAMPLE FIELD PEKERJAAN YANG AKAN DI LAKUKAN
1. Perbaikan Excavator
2. Mobilisasi Rig Menuju Rencana Lubang Bor

SAMPLE HOUSE

KENDALA
1. Menunggu perbaikan exca
SAMPLE LAB
LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Senin/ 05-31-2021

TENAGA KERJA PEKERJAAN HARI I


NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 6 Org
4 Operator 1 Org 7

PENGGUNAAN BAHAN BAKAR


1 Excavator 4 Jergen PERSOALAN ASPEK KEAMANA
1. jalur naik ke camp harus di perbaiki dan naik ke block VII-

PERSEDIAAN SOLAR
1 Solar 5 Jergen
SAMPLE FIELD PEKERJAAN YANG AKAN DI LAKUKAN
1. Perbaikan excavator
2. Moving rig
3. Pengaturan polypipe dari campfield ke rencana titik bor pe
4. Pengaturan pompa pada spullbak untuk ke titik pengeboran
SAMPLE HOUSE

KENDALA
1. Sparepart yang datang tidak sesuai dengan sparepart alat
SAMPLE LAB
LAPORAN HARIAN KEGIATAN PENGEBORAN

OCK VII I CUACA : Hujan


PENGAWAS : Abdi

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Menunggu LV 8:00 11:00
Melakukan Komunikasi ke URM untuk izin melintas 11:00 11:30
Istirahat Shalat Jum'at 11:30 12:30
Melakukan Komunikasi Ke pak Ramadhan (Babinsa) untuk 13:00 15:00
melintas lewat SR
Mobilisasi Rig menuju dekat kebun pak Halo 15:00 18:00

PERSOALAN ASPEK KEAMANAN PEKERJAAN

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Pencarian Exca untuk disewa
. Pengecekan alat rig untuk persiapan mobilisasi ke Titik pertama Pengeboran

KENDALA
. adanya demo warga ululere sehingga tidak bisa melintas lewat jalur URM

LAPORAN HARIAN KEGIATAN TESTPIT

OCK VII I CUACA : Cerah


PENGAWAS : Abdi

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Melakukan Komunikasi ke pihak URM 8:00 8:20
Melakukan Komunikasi ke pemilik Exca 8:20 12:00
Pencarian tempat preparasi area bahomotefe 14:00 15:00
Penjemputan Pak Akbar di Daerah Bungku 15:00 19:00

PERSOALAN ASPEK KEAMANAN PEKERJAAN

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Pembuatan camp eksplorasi
. Pencarian Exca

KENDALA
. adanya demo warga ululere sehingga tidak bisa melintas lewat jalur URM
. belum ada exca yang mau masuk area ululere

LAPORAN HARIAN KEGIATAN TESTPIT

OCK VII I CUACA : Hujan


PENGAWAS : Abdi

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Pembuatan Camp Ekplorasi (20%) 8:00 14:00

PERSOALAN ASPEK KEAMANAN PEKERJAAN

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Melanjutkan Pembuatan Camp Eksplorasi

KENDALA
. adanya demo warga ululere sehingga tidak bisa melintas lewat jalur URM
. belum ada exca yang mau masuk area ululere
. Pekerjaan terhenti karena hujan pada pukul 14:00 wita

LAPORAN HARIAN KEGIATAN TESTPIT

OCK VII I CUACA : mendung


PENGAWAS : Abdi

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Mobilisasi tim ke lokasi 8:00 9:00
Pembuatan Camp Ekplorasi (60%) 9:00 17:00
Mobilisasi Tim ke Mess 17:00 18:00
PERSOALAN ASPEK KEAMANAN PEKERJAAN
. Jalur dari kebun Pak Halo blum bisa di lalui, harus di perbaiki dulu

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Pembuatan Campfield
. Moving rig dari kebun pak halo ketitik bor
. Traveling alat menuju lokasi

KENDALA
. hujan

LAPORAN HARIAN KEGIATAN PENGEBORAN

OCK VII I CUACA : Hujan


PENGAWAS : Achyar

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Komisioning Dan Traveling Alat 8:00 15:30
Maintenance Jalur 15:30 17:00
Moving Tim Balik 17:00 17:30

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. Perbaikan jalur

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Pembuatan Camp
. Belanja logistik camp
.Belanja polimer Di Mahoni (Marowali Utara)

KENDALA
. Hujan
.Kerusakan Gear Saproket sehingga menunggu diganti

LAPORAN HARIAN KEGIATAN TESTPIT

OCK VII I CUACA : Hujan


PENGAWAS : Achyar

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU

Tidak Ada Progress Hari Ini

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. Perbaikan jalur
PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA
. Pencarian Titik Mata air
. Menunggu perbaikan exca

KENDALA
. Hujan Seharian
. Volume dan Debit Air Sungai Bertambah Sehingga tidak safety untuk di lalui

LAPORAN HARIAN KEGIATAN

OCK VII I CUACA : Mendung


PENGAWAS : Achyar

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
perbaikan camp 8:00 12:00
pembuatan spulbag 12:00 15:45

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. Menunggu perbaikan excavator

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Moving rig menggunakan wing wire
KENDALA
. Excavator Breakdown
. Cuaca
. Jalur menuju titik belum bisa di lalui mobil lv

LAPORAN HARIAN KEGIATAN

OCK VII - I CUACA : Mendung


PENGAWAS : Achyar

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Moving Rig dan pengetesan rig 8:00 16:00
Perbaikan Camp 8:00 16:45

PERSOALAN ASPEK KEAMANAN PEKERJAAN

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Pembelian Bahan makanan persiapan campfield
KENDALA
.Sling Rig tidak sanggup menarik.
.Paku tidak cukup.

LAPORAN HARIAN KEGIATAN

OCK VII - I CUACA : Cerah


PENGAWAS : Abdi

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU

Pembelian Bahan Makanan untuk di camp Field

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. harus dibuat jalur mobil LV menuju camp field

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Perbaikan Excavator
. Setting air rig
. Mobilisasi rig dititik pertama

KENDALA
. Menunggu perbaikan exca
LAPORAN HARIAN KEGIATAN

OCK VII - I CUACA : Cerah


PENGAWAS : Abdi

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Mobilisasi tim 10:25 11:29
Perbaikan Jalur Untuk LV 11:29 13:06
Pengaturan polypipe dari sungai ke campfield 13:06 16:30
Demobilisasi Tim 16:30 17:30

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. Perlunya perbaikan jalur

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Perbaikan Excavator
. Mobilisasi Rig Menuju Rencana Lubang Bor

KENDALA
. Menunggu perbaikan exca
LAPORAN HARIAN KEGIATAN

OCK VII - I CUACA : Mendung


PENGAWAS : Achyar dan Aswin

PEKERJAAN HARI INI


URAIAN KEGIATAN WAKTU
Mobilisasi tim 9:30 10:30
Pengaturan pompa air di sungai untuk pengisian spullbak di 10:30 16:00
campfield
Demobilisasi Tim 16:00 17:00

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. jalur naik ke camp harus di perbaiki dan naik ke block VII-I harus diperbaiki

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTNYA


. Perbaikan excavator
. Moving rig
. Pengaturan polypipe dari campfield ke rencana titik bor pertama
. Pengaturan pompa pada spullbak untuk ke titik pengeboran

KENDALA
. Sparepart yang datang tidak sesuai dengan sparepart alat
PETA KEMAJUAN PEKERJAAN
PETA KEMAJUAN PEKERJAAN

PETA KEMAJUAN PEKERJAAN


Pembuatan Camp Ekplorasi
Kebun warga

PETA KEMAJUAN PEKERJAAN

Sumber Air
Jalur Polypipe
Spullbak
Camp Field
Jalur Exca
Rencana Titik Bor
Rencana Jalur Rig

PETA KEMAJUAN PEKERJAAN


PETA KEMAJUAN PEKERJAAN
PETA KEMAJUAN PEKERJAAN
PETA KEMAJUAN PEKERJAAN
PETA KEMAJUAN PEKERJAAN
PETA KEMAJUAN PEKERJAAN
chyar dan Aswin

PETA KEMAJUAN PEKERJAAN


LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Senin / 1/6/2021
CUACA : Cerah
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5

PENGGUNAAN BAHAN BAKAR

1. jangan bekerja saat hujan deras karena areal pekerjaan mem

PERSEDIAAN SOLAR
1 Solar 5 Jergen
SAMPLE FIELD
1. Moving Rig sampai ke titik bor pertama
2. Setting polypipe sampai ke titik bor pertama
3. Pembenahan jalur naik ke camp field
4. Pembukaan jalur ke titik bor selanjutnya
SAMPLE HOUSE

1. belum ada tambahan polypipe


SAMPLE LAB

LAP
SITE PROJECT : IUP BNB BLOCK VII - I
HARI/ TANGGAL : Selasa / 2/6/2021
CUACA : Gerimis
PENGAWAS : Aswin

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 3 Jergen
2 Rig 1 Jergen 1. jangan bekerja saat hujan deras karena areal pekerjaan mem
3 Pompa 1 Jergen 2. Tali sling putus sehingga perlu penambahan sling
PERSEDIAAN SOLAR
1 Solar 0 Jergen
SAMPLE FIELD
1. Moving Rig sampai ke titik bor pertama
2. Setting polypipe sampai ke titik bor pertama
3. Pembukaan jalur ke titik bor selanjutnya
4. Pembuatan jalur landai dari campfield ke titik pertama
SAMPLE HOUSE

1. Areal yang cukup curam, sehingga perlu waktu lebih untuk


SAMPLE LAB

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Selasa / 3/6/2021
CUACA : Cerah
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 5 Jergen
2 Rig 0 Jergen 1. Mobil Operasional Mengalami kerusakan pada Master Kop
3 Pompa 0 Jergen 2. Kurangnya sumber daya manusia mengenai pengetahuan te
PERSEDIAAN SOLAR
1 Solar 7 Jergen
SAMPLE FIELD
1. (kendala no1) Mobil Operasional ditarik hingga sampai dib
2. (kendala no1) Mekanik di panggil kedalam lokasi
3. (kendala no1) Polypipe di antar menggunakan truck sewa 1
4. (kendala no2) Recruit SDM yang mengetahui tentang Perso
SAMPLE HOUSE

1. Pengeboran di titik 7I3920


SAMPLE LAB 2. Setting polypipe
3. perbaikan mobil operasional

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Jum'at / 4/6/2021
CUACA : Mendung
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 6 Jergen
2 Rig 0 Jergen 1. Mobil Operasional Mengalami kerusakan pada Master Kop
3 Pompa 0 Jergen 2. sparepart master kopling tidak ada di jual di bengkel area m
PERSEDIAAN SOLAR
1 Solar 1 Jergen
SAMPLE FIELD
1. (kendala no2) pesan sparepart dari makassar
2. (kendala no1) pinjam motor tenaga lokal

SAMPLE HOUSE

1. lanjut Pengeboran di titik 7I3920


SAMPLE LAB 2. menunggu pengiriman sparepart mobil lv (master kopling)
3. pembukaan jalur ke titik selanjutnya dan pembuatan path
4. moving alat ke titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Sabtu / 6/5/2021
CUACA : Mendung
PENGAWAS : Aswin Dan Achyar
TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Pelarangan Aktifitas oleh warga
PERSEDIAAN SOLAR
1 Solar 1 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. melakukan mediasi ke warga

SAMPLE HOUSE

1.Menunggu hasil mediasi warga yang di lakukan oleh Huma


SAMPLE LAB

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Minggu / 6/6/2021
CUACA : Mendung
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org
2 Jr. Geologist 2 Org
3 TL 9 Org
4 Operator 1 Org
5 Helper 1 Org
6 Support 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Pelarangan Aktifitas oleh warga
PERSEDIAAN SOLAR
1 Solar 1 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. melakukan mediasi ke warga

SAMPLE HOUSE

1.Menunggu hasil mediasi warga yang di lakukan oleh Huma


SAMPLE LAB

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Senin / 6/7/2021
CUACA : Mendung
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org
2 Jr. Geologist 2 Org
3 TL 9 Org
4 Operator 1 Org
5 Helper 1 Org
6 Support 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Pelarangan Aktifitas oleh warga
PERSEDIAAN SOLAR
1 Solar 1 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. melakukan mediasi ke warga

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I3920


SAMPLE LAB 2. Moving Rig ke titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Selasa / 6/8/2021
CUACA : Cerah
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR 8
1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Operator kabur dari pekerjaan
PERSEDIAAN SOLAR
1 Solar 1 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. ganti operator

SAMPLE HOUSE

1. Menunggu pengganti operator untuk moving ke titik 7I472


SAMPLE LAB 2. Moving ke titik 7I4720
3. Pengeboran titik 7I4720

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Rabu / 6/9/2021
CUACA : Cerah
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org
2 Jr. Geologist 2 Org
3 TL 9 Org
4 Operator 1 Org
5 Helper 1 Org
6 Support 1 Org
PENGGUNAAN BAHAN BAKAR
1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Operator kabur dari pekerjaan
PERSEDIAAN SOLAR
1 Solar 1 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. ganti operator

SAMPLE HOUSE

1. Menunggu pengganti operator untuk moving ke titik 7I472


SAMPLE LAB 2. Moving ke titik 7I4720
3. Pengeboran titik 7I4720

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Kamis / 6/10/2021
CUACA : Cerah
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR
1 Excavator 0 Jergen
2 Rig 1 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. pecah selang karena area pengeboran terlalu tinggi
PERSEDIAAN SOLAR
1 Solar 0 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. penambahan titik spullbak dan pompa sancin

SAMPLE HOUSE

1. Melanjutkan pengeboran
SAMPLE LAB 2. Moving ke titik 7I4712

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Jum'at / 6/11/2021
CUACA : Hujan
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Debit air yang naik terlalu sedikit
PERSEDIAAN SOLAR 3. Per sancin patah
1 Solar 0 Jergen
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. penambahan titik spullbak dan pompa sancin

SAMPLE HOUSE

1. Moving ke titik 7I4712


SAMPLE LAB 2. Pengeboran titik 7I4712
3. pembukaan jalur menujuk titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Sabtu / 6/12/2021
CUACA : Hujan
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Breakdown Mobil Operasional
3 Pompa 0 Jergen 2. Debit air yang naik terlalu sedikit
PERSEDIAAN SOLAR 3. Pipa Pecah
1 Solar 0 Jergen 4. Hujan
SAMPLE FIELD
1. Perbaikan mobil operasional atau sewa sementara mobil op
2. penambahan titik spullbak dan pompa sancin

SAMPLE HOUSE

1. Pembuatan Spullbak dekat area pengeboran


SAMPLE LAB 2. Melanjutkan pengeboran titik 7I4712
3. melansir solar naik ke camp

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Minggu / 6/13/2021
CUACA : Hujan
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 8 Jergen
2 Rig 0 Jergen 1. Mobil Operasional breakdown
3 Pompa 0 Jergen 2. Cuaca (Hujan)
PERSEDIAAN SOLAR
1 Solar 4 Jergen
SAMPLE FIELD
1. Mobil Operasional diperbaiki

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I4712


SAMPLE LAB 2. Moving ke titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Senin / 6/14/2021
CUACA : Hujan
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 2 Jergen 1. Mobil Operasional breakdown
3 Pompa 2 Jergen 2. Cuaca (Hujan)
PERSEDIAAN SOLAR
1 Solar 0 Jergen
SAMPLE FIELD
1. Mobil Operasional diperbaiki
SAMPLE HOUSE

1. Melanjutkan pengeboran 7I4712


SAMPLE LAB 2. Moving ke titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Selasa / 6/15/2021
CUACA : Hujan
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen 1. Mobil Operasional breakdown
3 Pompa 0 Jergen 2. Cuaca (Hujan)
PERSEDIAAN SOLAR
1 Solar 0 Jergen
SAMPLE FIELD
1. Mobil Operasional diperbaiki
SAMPLE HOUSE

1. Pengeboran 7I4704
SAMPLE LAB 2. Moving ke titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Rabu / 6/16/2021
CUACA : Mendung
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR 8
1 Excavator 0 Jergen 9
2 Rig 0 Jergen
3 Pompa 0 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR 2. Cuaca (Hujan)
1 Solar 0 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE
1. Melanjutkan pengeboran 7I3904
SAMPLE LAB 2. Moving ke titik selanjutnya

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Kamis / 6/17/2021
CUACA : Cerah
PENGAWAS : Aswin Dan Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR 2. Pipa Nosel Patah (Pipa dari tanki solar ke mesin)
1 Solar 0 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki


2. Sewa Motor untuk penggunaan di camp dan pengantaran lo
3. Mengganti pipa nosel atau di las kuningan
SAMPLE HOUSE
1. Melanjutkan pengeboran 7I3904
SAMPLE LAB 2. Moving ke titik selanjutnya
3. Pengantaran Solar dan kebutuhan lapangan (jas hujan, rom
4. Pengambilan data lapangan

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Jum'at / 6/18/2021
CUACA : Hujan
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR
1 Excavator 8 Jergen
2 Rig 1 Jergen
3 Pompa 1 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR 2. Cuaca
1 Solar 2 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki


2. Sewa Motor atau truck untuk penggunaan di camp dan pen

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I3904


SAMPLE LAB 2. Moving ke titik selanjutnya
3. Pengambilan data lapangan

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Sabtu / 6/19/2021
CUACA : Mendung
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR 8
1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR
1 Solar 2 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I3912


SAMPLE LAB 2. Moving ke titik selanjutnya
3. Pengambilan data lapangan
LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Minggu / 6/20/2021
CUACA : Mendung dan Gerimis
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR 8
1 Excavator 0 Jergen 9
2 Rig 0 Jergen
3 Pompa 0 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR
1 Solar 2 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I3112


SAMPLE LAB 2. Moving ke titik selanjutnya
3. Pengambilan data lapangan
LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Senin / 6/21/2021
CUACA : Mendung dan Gerimis
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR
1 Solar 2 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I3112


SAMPLE LAB 2. Moving ke titik selanjutnya
3. Pengambilan data lapangan
LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Selasa / 6/22/2021
CUACA : Mendung dan Gerimis
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR 8
1 Excavator 0 Jergen 9
2 Rig 1 Jergen
3 Pompa 1 Jergen 1. Mobil Operasional breakdown
PERSEDIAAN SOLAR 2. Kehabisan Kantong Sample / Kantong Sample terlalu Tipis
1 Solar 0 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki


2. Pembelian kantong sample yang lebih tebal

SAMPLE HOUSE

1. Melanjutkan pengeboran 7I3104


SAMPLE LAB 2. Moving ke titik selanjutnya
3. Pengambilan data lapangan

LAP
SITE PROJECT : IUP BNB BLOCK VII - I
HARI/ TANGGAL : Rabu / 6/23/2021
CUACA : Gerimis
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 5
6 Support 1 Org 6
7
PENGGUNAAN BAHAN BAKAR 8
1 Excavator 7 Jergen 9
2 Rig 1 Jergen 10
3 Pompa 1 Jergen
PERSEDIAAN SOLAR 1. Mobil Operasional breakdown
1 Solar 0 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE

1. Demobilisasi Tim dari camp field ke mess


SAMPLE LAB

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Kamis / 6/24/2021
CUACA : Cerah
PENGAWAS : Achyar

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 7
6 Support 1 Org 9

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen
PERSEDIAAN SOLAR 1. Mobil Operasional breakdown
1 Solar 0 Jergen 2. Susahnya komunikasi sehingga informasi selalu telat
SAMPLE FIELD

1. Mobil Operasional diperbaiki


2. Telpon satelit jika di daerah remote are
SAMPLE HOUSE

1. Demobilisasi Tim dari camp field ke mess


SAMPLE LAB
1 Sample Bor 50 Sample

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Jum'at / 6/25/2021
CUACA : Cerah
PENGAWAS : Achyar
TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org 3
4 Operator 1 Org 4
5 Helper 1 Org 7
6 Support 1 Org 9

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen
PERSEDIAAN SOLAR 1. Mobil Operasional breakdown
1 Solar 0 Jergen 2. Susahnya komunikasi sehingga informasi selalu telat
SAMPLE FIELD 3. Pompa di camp mati karena kehabisan solar sehingga spull

1. Mobil Operasional diperbaiki


2. Telpon satelit jika di daerah remote are
SAMPLE HOUSE 3. pompa di nyalakan kembali dan di monitor solarnya

1. Demobilisasi Tim dari camp field ke mess


SAMPLE LAB

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Sabtu / 6/26/2021
CUACA : Cerah
PENGAWAS : Abdi

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 1 Org 2
3 TL 9 Org
4 Operator 1 Org
5 Helper 1 Org
6 Support 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen
PERSEDIAAN SOLAR 1. Mobil Operasional breakdown
1 Solar 0 Jergen 2. Susahnya komunikasi sehingga informasi selalu telat
SAMPLE FIELD 3. Adanya permasalahan dengan warga yang mengaku punya

1. Mobil Operasional diperbaiki


2. Telpon satelit jika di daerah remote are
SAMPLE HOUSE 3. Pendekatan persuasif dengan warga yang bersangkutan ata

1. Demobilisasi Exca dari titik terakhir ke titik pertama di am


SAMPLE LAB
1 Sample Bor 48 Sample

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Minggu / 6/27/2021
CUACA : Cerah
PENGAWAS : Abdi

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org
3 Support 1 Org
4 Operator 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen
PERSEDIAAN SOLAR 1. Mobil Operasional breakdown
1 Solar 0 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE

SAMPLE LAB

LAP

SITE PROJECT : IUP BNB BLOCK VII - I


HARI/ TANGGAL : Senin / 6/28/2021
CUACA : Cerah
PENGAWAS : Abdi

TENAGA KERJA
NO. JABATAN JUMLAH NO.
1 Mine Geologist 1 Org 1
2 Jr. Geologist 2 Org 2
3 Support 1 Org 3
4 Operator 1 Org

PENGGUNAAN BAHAN BAKAR


1 Excavator 0 Jergen
2 Rig 0 Jergen
3 Pompa 0 Jergen
PERSEDIAAN SOLAR 1. Mobil Operasional breakdown
1 Solar 0 Jergen
SAMPLE FIELD

1. Mobil Operasional diperbaiki

SAMPLE HOUSE

1. Pengantaran sample ke lab PT. NMM


SAMPLE LAB
LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Perbaikan Alat
Mobilisasi Tim
Setting Polypipe
Maintenance jalur
Moving alat bor

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. jangan bekerja saat hujan deras karena areal pekerjaan memiliki medan yang licin

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTN


. Moving Rig sampai ke titik bor pertama
. Setting polypipe sampai ke titik bor pertama
. Pembenahan jalur naik ke camp field
. Pembukaan jalur ke titik bor selanjutnya

KENDALA
. belum ada tambahan polypipe

LAPORAN HARIAN KEGIATAN


OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
mobilisasi tim
moving Rig
Setting Polypipe
Maintenance jalur
Demobilisasi tim

PERSOALAN ASPEK KEAMANAN PEKERJAAN


. jangan bekerja saat hujan deras karena areal pekerjaan memiliki medan yang licin
. Tali sling putus sehingga perlu penambahan sling

PEKERJAAN YANG AKAN DI LAKUKAN HARI SELANJUTN


. Moving Rig sampai ke titik bor pertama
. Setting polypipe sampai ke titik bor pertama
. Pembukaan jalur ke titik bor selanjutnya
. Pembuatan jalur landai dari campfield ke titik pertama

KENDALA
. Areal yang cukup curam, sehingga perlu waktu lebih untuk bisa excavator menarik rig

LAPORAN HARIAN KEGIATAN

OCK VII - I
PEKERJAAN HARI INI
URAIAN KEGIATAN
mobilisasi tim
moving Rig
Isoma
Pembuatan Jalur Rig
Setting Polypipe
Demobilisasi Tim

KENDALA
. Mobil Operasional Mengalami kerusakan pada Master Kopling (bocor) sehingga mempengaruhi pengantaran sisa Polypipe
. Kurangnya sumber daya manusia mengenai pengetahuan tentang kesehatan mobil Operasional

SOLUSI
. (kendala no1) Mobil Operasional ditarik hingga sampai dibengkel
. (kendala no1) Mekanik di panggil kedalam lokasi
. (kendala no1) Polypipe di antar menggunakan truck sewa 1 hari
. (kendala no2) Recruit SDM yang mengetahui tentang Persoalan Mobil sekaligus menjadi driver

PEKERJAAN SELANJUTNYA
. Pengeboran di titik 7I3920
. Setting polypipe
. perbaikan mobil operasional

LAPORAN HARIAN KEGIATAN

OCK VII - I
PEKERJAAN HARI INI
URAIAN KEGIATAN
mobilisasi tim
Setting Polypipe
Perbaikan pompa
Isoma
Pengeboran pada titik 7I3920
Demobilisasi Tim

KENDALA
. Mobil Operasional Mengalami kerusakan pada Master Kopling (bocor)
. sparepart master kopling tidak ada di jual di bengkel area morowali dan kendari butuh satu minggu untuk pemesanan dan pengiriman

SOLUSI
. (kendala no2) pesan sparepart dari makassar
. (kendala no1) pinjam motor tenaga lokal

PEKERJAAN SELANJUTNYA
. lanjut Pengeboran di titik 7I3920
. menunggu pengiriman sparepart mobil lv (master kopling)
. pembukaan jalur ke titik selanjutnya dan pembuatan path
. moving alat ke titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I
PEKERJAAN HARI INI
URAIAN KEGIATAN
mobilisasi tim
Check rig
Pemberhentian oleh warga
Isoma
Pengeboran pada titik 7I3920
Demobilisasi Tim

KENDALA
. Breakdown Mobil Operasional
. Pelarangan Aktifitas oleh warga

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. melakukan mediasi ke warga

PEKERJAAN SELANJUTNYA
.Menunggu hasil mediasi warga yang di lakukan oleh Humas BNB

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Standby

KENDALA
. Breakdown Mobil Operasional
. Pelarangan Aktifitas oleh warga

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. melakukan mediasi ke warga

PEKERJAAN SELANJUTNYA
.Menunggu hasil mediasi warga yang di lakukan oleh Humas BNB

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Standby

KENDALA
. Breakdown Mobil Operasional
. Pelarangan Aktifitas oleh warga

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. melakukan mediasi ke warga

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3920
. Moving Rig ke titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
mobilisasi tim
Check rig
Perbaiki Polypipe yang bocor
Pengeboran pada titik 7I3920
Isoma
Persiapan untuk moving ke titik 7I4720
menunggu operator exca
demobilisasi tim
KENDALA
. Breakdown Mobil Operasional
. Operator kabur dari pekerjaan

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. ganti operator

PEKERJAAN SELANJUTNYA
. Menunggu pengganti operator untuk moving ke titik 7I4720
. Moving ke titik 7I4720
. Pengeboran titik 7I4720

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN

Standby
KENDALA
. Breakdown Mobil Operasional
. Operator kabur dari pekerjaan

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. ganti operator

PEKERJAAN SELANJUTNYA
. Menunggu pengganti operator untuk moving ke titik 7I4720
. Moving ke titik 7I4720
. Pengeboran titik 7I4720

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi tim
moving rig ke titik 7I4720
pengecekan rig dan melakukan setting rig persiapan pengeboran titik 7I4720
Pengeboran titik 7I4720
isoma
Demobilisasi tim
pengantaran operator baru ke lokasi
KENDALA
. Breakdown Mobil Operasional
. pecah selang karena area pengeboran terlalu tinggi

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. penambahan titik spullbak dan pompa sancin

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran
. Moving ke titik 7I4712

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi tim
Penggantian selang yang bocor
pengecekan rig
Pengeboran titik 7I4720
isoma
Demobilisasi tim

KENDALA
. Breakdown Mobil Operasional
. Debit air yang naik terlalu sedikit
. Per sancin patah

SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. penambahan titik spullbak dan pompa sancin

PEKERJAAN SELANJUTNYA
. Moving ke titik 7I4712
. Pengeboran titik 7I4712
. pembukaan jalur menujuk titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi tim
Check rig
Moving Rig ke titik 7I4712
Pengeboran titik 7I4720
isoma
Demobilisasi tim

KENDALA
. Breakdown Mobil Operasional
. Debit air yang naik terlalu sedikit
. Pipa Pecah
SOLUSI
. Perbaikan mobil operasional atau sewa sementara mobil operasional
. penambahan titik spullbak dan pompa sancin

PEKERJAAN SELANJUTNYA
. Pembuatan Spullbak dekat area pengeboran
. Melanjutkan pengeboran titik 7I4712
. melansir solar naik ke camp

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Pembuatan Spullbak
Melakukan perbaikan pompa sancin karena mengalami patah per
Isoma
menunggu stok solar dan pompa
Demobilisasi tim sekalian lansir solar dan pompa ke camp

KENDALA
. Mobil Operasional breakdown
. Cuaca (Hujan)

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I4712
. Moving ke titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Setting Pompa Suplay
Isoma
Pengeboran
Demobilisasi tim

KENDALA
. Mobil Operasional breakdown
. Cuaca (Hujan)

SOLUSI
. Mobil Operasional diperbaiki
PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I4712
. Moving ke titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Melakukan pengecekan rig
Isoma
Pengeboran
Demobilisasi tim

KENDALA
. Mobil Operasional breakdown
. Cuaca (Hujan)

SOLUSI
. Mobil Operasional diperbaiki
PEKERJAAN SELANJUTNYA
. Pengeboran 7I4704
. Moving ke titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Moving 7I4704
Pengecekan rig
Setting Rig 7I4704
Pengeboran 7I4704
Isoma
Moving 7I3904
Setting Rig 7I3904
Demobilisasi Tim
KENDALA
. Mobil Operasional breakdown
. Cuaca (Hujan)

SOLUSI
. Mobil Operasional diperbaiki
PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3904
. Moving ke titik selanjutnya

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Pengecekan rig 7I3904
Safety Talk
Pengeboran 7I3904
Demobilisasi Tim
Pengantaran logistik dari mess ke campfield

KENDALA
. Mobil Operasional breakdown
. Pipa Nosel Patah (Pipa dari tanki solar ke mesin)

SOLUSI
. Mobil Operasional diperbaiki
. Sewa Motor untuk penggunaan di camp dan pengantaran logistik
. Mengganti pipa nosel atau di las kuningan

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3904
. Moving ke titik selanjutnya
. Pengantaran Solar dan kebutuhan lapangan (jas hujan, rompi, karung dan kantong sampel)
. Pengambilan data lapangan

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Pengecekan rig 7I3904
Pemasangan Pipa Nosel
Istirahat
Pengeboran 7I3904
Demobilisasi Tim
Pengantaran Solar

KENDALA
. Mobil Operasional breakdown
. Cuaca

SOLUSI
. Mobil Operasional diperbaiki
. Sewa Motor atau truck untuk penggunaan di camp dan pengantaran logistik

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3904
. Moving ke titik selanjutnya
. Pengambilan data lapangan

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Pengecekan rig 7I3904
Pengeboran 7I3904
Moving Rig ke 7I3912
Setting Rig
Istirahat
Pengeboran 7I3912
Demobilisasi Tim

KENDALA
. Mobil Operasional breakdown

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3912
. Moving ke titik selanjutnya
. Pengambilan data lapangan
LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Pengecekan rig 7I3912
Safety Talk Meeting
Pengeboran 7I3912
Moving Ke Titik 7I3112
Setting Rig di Titik 7I3112
Istirahat
Pengeboran 7I3112
Demobilisasi Tim
KENDALA
. Mobil Operasional breakdown

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3112
. Moving ke titik selanjutnya
. Pengambilan data lapangan
LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Safety Talk Meeting
Pengecekan rig 7I3112
Pengeboran 7I3112
Istirahat
Demobilisasi tim

KENDALA
. Mobil Operasional breakdown

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3112
. Moving ke titik selanjutnya
. Pengambilan data lapangan
LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Safety Talk Meeting
Pengecekan rig di titik 7i3112
Pengeboran 7I3112
Moving Ke Titik 7I3104
Setting Rig di Titik 7I3104
Istirahat
Pengeboran 7I3112
Demobilisasi Tim
KENDALA
. Mobil Operasional breakdown
. Kehabisan Kantong Sample / Kantong Sample terlalu Tipis sehingga pemakaiannya harus di double yang menjadikan kantong sample hab

SOLUSI
. Mobil Operasional diperbaiki
. Pembelian kantong sample yang lebih tebal

PEKERJAAN SELANJUTNYA
. Melanjutkan pengeboran 7I3104
. Moving ke titik selanjutnya
. Pengambilan data lapangan

LAPORAN HARIAN KEGIATAN


OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Mobilisasi Tim
Safety Talk Meeting
Pengecekan rig di titik 7i3104
Pengeboran 7I3104
Moving Ke Titik 7I2304
Setting Rig di Titik 7I2304
Istirahat
Pengeboran 7I2304
Demobilisasi Tim
Pengantaran solar 9 jergen
KENDALA
. Mobil Operasional breakdown

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA
. Demobilisasi Tim dari camp field ke mess

LAPORAN HARIAN KEGIATAN

OCK VII - I
PEKERJAAN HARI INI
URAIAN KEGIATAN
Mobilisasi Tim
Safety Talk Meeting
Pengecekan rig di titik 7i2304
Pengeboran 7i2304
Istirahat
Demobilisasi Tim

KENDALA
. Mobil Operasional breakdown
. Susahnya komunikasi sehingga informasi selalu telat

SOLUSI
. Mobil Operasional diperbaiki
. Telpon satelit jika di daerah remote are

PEKERJAAN SELANJUTNYA
. Demobilisasi Tim dari camp field ke mess

LAPORAN HARIAN KEGIATAN

OCK VII - I
PEKERJAAN HARI INI
URAIAN KEGIATAN
Mobilisasi Tim
Safety Talk Meeting
Pengecekan rig di titik 7i2304
Pengeboran 7i2304
Istirahat
Moving Rig ke camp

KENDALA
. Mobil Operasional breakdown
. Susahnya komunikasi sehingga informasi selalu telat
. Pompa di camp mati karena kehabisan solar sehingga spullbak yang dekat lokasi kekurangan air

SOLUSI
. Mobil Operasional diperbaiki
. Telpon satelit jika di daerah remote are
. pompa di nyalakan kembali dan di monitor solarnya

PEKERJAAN SELANJUTNYA
. Demobilisasi Tim dari camp field ke mess

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Demobilisasi Tim, Rig Dan Exca
Istirahat

KENDALA
. Mobil Operasional breakdown
. Susahnya komunikasi sehingga informasi selalu telat
. Adanya permasalahan dengan warga yang mengaku punya lahan sehingga sampel dengan SB93 - SB101 dan SB115 - SB122

SOLUSI
. Mobil Operasional diperbaiki
. Telpon satelit jika di daerah remote are
. Pendekatan persuasif dengan warga yang bersangkutan atau mediasi dengan polisi

PEKERJAAN SELANJUTNYA
. Demobilisasi Exca dari titik terakhir ke titik pertama di ambil

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Demobilisasi Exca
KENDALA
. Mobil Operasional breakdown

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA

LAPORAN HARIAN KEGIATAN

OCK VII - I

PEKERJAAN HARI INI


URAIAN KEGIATAN
Inventarisasi Perlengkapan campfield dan mess
Pengambilan sample di rumah pak desa ulu lere
Demobilisasi Excavator naik ke mobil tronton
KENDALA
. Mobil Operasional breakdown

SOLUSI
. Mobil Operasional diperbaiki

PEKERJAAN SELANJUTNYA
. Pengantaran sample ke lab PT. NMM
WAKTU
8:00 13:30
10:00 11:00
11:00 16:00
13:30 16:00
16:00 17:00
WAKTU
7:15 10:23
10:23 16:09
10:23 16:09
15:00 16:09
16:09 16:30
WAKTU
8:00 8:45
9:15 12:00
12:00 13:00
13:00 13:20
13:20 16:40
16:40 17:00
WAKTU
7:15 8:00
8:00 15:40
11:40 12:00
12:00 13:00
15:40 16:00
16:00 16:30
WAKTU
7:00 8:00
8:00 8:15
8:15 12:00
12:00 13:00
13:00 16:00
16:00 16:40

WAKTU
WAKTU
WAKTU
7:00 8:30
8:30 8:45
8:45 9:30
9:30 12:00
12:00 13:00
13:00 15:00
15:00 16:15
16:15 17:00

WAKTU
WAKTU
7:00 8:00
8:00 8:30
8:30 9:20
9:20 16:05
12:00 13:00
16:05 16:40
7:00 9:38
WAKTU
7:00 8:00
8:00 8:25
8:25 8:30
8:30 16:00
11:00 13:00
16:00 16:40
WAKTU
7:00 8:00
8:00 8:15
9:30 11:00
11:00 11:35
12:00 13:00
16:00 16:35
WAKTU
8:00 9:00
9:00 11:00
11:00 12:00
12:00 13:00
13:00 16:00
16:00 17:00
WAKTU
10:00 11:00
11:00 14:30
12:00 13:00
14:30 16:05
16:05 16:50
WAKTU
11:00 12:00
12:00 12:15
12:15 13:00
13:00 16:00
16:00 16:40
WAKTU
7:00 8:30
8:30 9:00
9:00 9:15
9:15 10:00
10:00 14:00
12:00 13:00
14:00 15:00
15:00 16:00
16:00 16:40
WAKTU
7:00 8:15
8:15 8:30
8:30 8:45
8:45 11:30
12:00 13:00
13:00 15:00
WAKTU
9:40 10:25
10:25 10:35
10:35 11:00
11:00 13:00
13:00 16:00
16:00 16:30
14:00 16:00
WAKTU
7:00 8:00
8:00 8:15
8:15 8:50
8:50 9:50
9:50 11:00
12:00 13:00
11:00 16:00
16:00 16:40
WAKTU
7:00 7:40
7:40 7:50
7:50 8:00
8:00 10:30
10:30 11:00
11:00 12:00
12:00 13:00
13:00 16:00
16:00 16:40
WAKTU
7:00 7:45
7:45 8:00
8:00 8:15
8:15 16:00
12:00 13:00
16:00 16:40
WAKTU
7:00 7:50
7:50 8:00
8:00 8:15
8:15 9:00
9:00 9:30
9:30 11:00
12:00 13:00
11:00 14:30
14:30 16:10
WAKTU
7:00 8:00
8:00 8:15
8:15 8:30
8:30 14:00
14:00 14:30
14:30 15:20
12:00 13:00
15:20 16:00
16:00 16:30
7:30 10:30
WAKTU
7:00 8:00
8:00 8:15
8:15 8:30
8:30 16:00
12:00 13:00
16:00 17:00
WAKTU
7:00 8:00
8:00 8:15
8:15 8:30
8:30 12:00
12:00 13:00
13:00 16:30
WAKTU
7:00 19:00
12:00 13:00

WAKTU
7:00 14:00
WAKTU
7:00 17:00
19:30
7:00 10:00
No Tanggal Operator Unit HM Start HM Finish Working HM Aktifitas
1 ### Randy Kobelco PC 200 5702 5707 5 Traveling 1
2 ### 0 0 0 Breakdown (Gear Sproket Aus) 0
3 ### 0 0 0 Breakdown (Gear Sproket Aus) 0
4 ### 0 0 0 Breakdown (Gear Sproket Aus) 0
5 ### 0 0 0 Breakdown (Gear Sproket Aus) 0
6 ### Randy Kobelco PC 200 5707 5710 3 Perbaikan Jalan, kembali breakdown (Lepas Trek) 1
7 ### Randy Kobelco PC 200 5710 5710 0 excavator di perbaiki 0
8 6/1/2021 Randy Kobelco PC 200 5711 5715 4 moving alat bor 1
9 6/2/2021 Randy Kobelco PC 200 5715 5718 3 moving alat bor, pembuatan jalur naik ke titik pertama, membuat septy tank 1
10 6/3/2021 Randy Kobelco PC 200 5718 5723 5 moving alat bor, pembuatan jalur naik ke titik pertama 1
10 6/4/2021 Randy Kobelco PC 200 5723 5727 4 perbaiakan jalur, pengambilan polypipe , evakuasi mobil lv 1
11 6/5/2021 Randy Kobelco PC 200 5727 5729 2 Standby di hentikan masyarakat, ambil polypipe di bawah 1
12 6/6/2021 Randy Kobelco PC 200 5729 5729 0 Standby di hentikan masyarakat 1
13 6/7/2021 Randy Kobelco PC 200 5729 5729 0 Stanby dihentikan oleh masyarakat 1
14 6/8/2021 Randy Kobelco PC 200 5729 5729 0 Stanby tidak ada operator 0
15 6/9/2021 Randy Kobelco PC 200 5729 5729 0 Stanby tidak ada operator 0
16 ### Awi Kobelco PC 200 5730 5733 3 Pembuatan jalur rig dan moving rig 1
17 ### Awi Kobelco PC 200 5733 5737 4 Pembuatan jalur rig 1
18 ### Awi Kobelco PC 200 5737 5738 1 Moving Bor 1
19 ### Awi Kobelco PC 200 5738 5740 2 Melansir solar dan perbaikan jalan 1
20 ### Awi Kobelco PC 200 5740 5744 4 Langsir pompa ke lokasi dan setting polipipe 1
21 ### Awi Kobelco PC 200 5744 5744 0 Exca tidak bisa beroperasi karena jalanan licin akibat hujan 1
22 ### Awi Kobelco PC 200 5744 5749 5 Moving alat bor dan pembuatan jalur rig 1
23 ### Awi Kobelco PC 200 5749 5749 0 Standby 1
24 ### Awi Kobelco PC 200 5749 5750 1 Langsir Solar 1
25 ### Awi Kobelco PC 200 5750 5754 4 Moving rig dan pembuatan jalur rig 1
26 ### Awi Kobelco PC 200 5754 5759 5 Moving rig dan pembuatan jalur rig 1
27 ### Awi Kobelco PC 200 5759 5759 0 Standby 1
28 ### Awi Kobelco PC 200 5759 5761 2 Perbaikan dan pembukaan jalur rig 1
29 ### Awi Kobelco PC 200 5761 5765 4 Moving alat bor lansir solar 1
30 ### Awi Kobelco PC 200 5765 5767 2 Perbaikan jalur persiapan demobilisasi 1
31 ### Awi Kobelco PC 200 5767 5770 3 Moving rig untuk persiapan demobilisasi 1
32 ### Awi Kobelco PC 200 5770 5773 3 Traveling Demobilisasi 1
33 ### Awi Kobelco PC 200 5773 5776 3 Traveling Demobilisasi 1
34 ### Awi Kobelco PC 200 5776 5776 0 Demobiliasi Excavator ke Tronton 1

Kontrak HM 200
Kontrak Hari 30
Sisa HM 128
Sisa Hari 2
Nama
No Tanggal Operator Unit Start (m) Finish (m) Produksi (m) Keterangan
Lubang
1 ### Eli Jacro 175 - 0 0 0 Mobilisasi Masuk Ke Lokasi
2 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
3 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
4 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
5 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
6 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
7 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
8 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
9 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
10 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
11 ### Eli Jacro 175 - 0 0 0 Standby Menunggu Exca u/ moving 1
12 6/1/2021 Eli Jacro 175 - 0 0 0 Moving 1
13 6/2/2021 Eli Jacro 175 - 0 0 0 Moving 1
14 6/3/2021 Eli Jacro 175 - 0 0 0 Moving 1
15 6/4/2021 Eli Jacro 175 7I3920 0 4 4 pengeboran 1
16 6/5/2021 Eli Jacro 175 7I3920 4 13 9 pengeboran 1
17 6/6/2021 Eli Jacro 175 7I3920 0 0 0 pengeboran 1
18 6/7/2021 Eli Jacro 175 7I3920 0 0 0 pengeboran 1
19 6/8/2021 Eli Jacro 175 7I3920 13 16 3 pengeboran 1
20 6/9/2021 Eli Jacro 175 0 0 0 Standby Menunggu Exca u/ moving 1
21 ### Eli Jacro 175 7I4720 0 6 6 moving dan pengeboran 1
22 ### Eli Jacro 175 7I4720 6 9 3 pengeboran 1
23 ### Eli Jacro 175 7I4712 0 3.5 3.5 Moving dan pengeboran 1
24 ### Eli Jacro 175 7I4712 0 0 0 Pembuatan Spullbak 1
25 ### Eli Jacro 175 7I4712 3.5 6 2.5 pengeboran 1
26 ### Eli Jacro 175 7I4712 6 9 3 pengeboran 1
27 ### Eli Jacro 175 7I4704 0 8 8 Moving dan pengeboran 1
28 ### Eli Jacro 175 7I3904 0 5.5 5.5 Pengeboran 1
29 ### Eli Jacro 175 7I3904 5.5 9 3.5 Pengeboran 1
30 ### Eli Jacro 175 7I3904 9 10 1 Pengeboran 1
31 ### Eli Jacro 175 7I3912 0 7.5 7.5 Moving dan Pengeboran 1
32 ### Eli Jacro 175 7I3912 7.5 10 2.5 Moving dan Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2021
33 ### Eli Jacro 175 7I3112 0 8 8 Moving dan Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2021
34 ### Eli Jacro 175 7I3112 8 16 8 Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2021
35 ### Eli Jacro 175 7I3112 16 17 1 Moving dan Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2021
36 ### Eli Jacro 175 7I3104 0 14 14 Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2021
37 ### Eli Jacro 175 7I3104 14 19 5 Moving dan Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2021
38 ### Eli Jacro 175 7I2304 0 5 5 Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2022
39 ### Eli Jacro 175 7I2304 5 17.7 12.7 Pengeboran Kompensasi 3 hari dari tgl 21 Juni 2022
40 ### Eli Jacro 175 7I2305 17.7 21 3.3 Pengeboran dan Demobilisasi
41 ### Eli Jacro 175 7I2306 0 0 0 Demobilisasi Tim

Kontrak Hari 30
Sisa Hari 0
Juni 2021
Juni 2021
Juni 2021
Juni 2021
Juni 2021
Juni 2021
Juni 2022
Juni 2022
Bulan
Minggu MII MIII
Tanggal 1 2 3 4 5 6 7
No Kegiatan Hari ke 1 2 3 4 5 6 7

Minggu
Jum'at
Selasa

Kamis

Sabtu

Senin
Rabu
Hari ke

1 Perbaikan Excavator
2 Moving Alat Bor Ke titik Pertama
3 Setting polypipe dari Campfield Ke Block VII-I
4 Pengeboran pada Titik 7I4720
5 Pengeboran pada Titik 7I4712
6 Pengeboran pada Titik 7I4704
7 Pengeboran pada Titik 7I3904
8 Pengeboran pada Titik 7I3104
9 Pengeboran pada Titik 7I2304
10 Pengeboran pada Titik 7I1504
11 Pengeboran pada Titik 7I2312
12 Pengeboran pada Titik 7I3112
13 Pengeboran pada Titik 7I3912
14 Pengeboran pada Titik 7I3920
15 Pengeboran pada Titik 7I3120
16 Pengeboran pada Titik 7I3928
17 Analisa Sampel
19 Demobilisasi Rig dari lokasi ke desa dampala
20 Demobilisasi Tim Eksplorasi
21 Pembuatan Laporan Eksplorasi
22 Pengiriman Logistik ke campfield
23 Masa Sewa Rig
24 Masa Sewa Alat berat
: Realisasi Schedule
8
8
Selasa

9
Rabu 9
MIII

10
10

Kamis
11
11

Jum'at
12
12

Sabtu
13
13

Minggu
14
14

Senin

Selasa
Juni

15 16
15 16

Rabu
MIV

17
17

Kamis
18
18

Jum'at
19
19

Sabtu
20
20

Minggu
21
21

Senin
22
22

Selasa
23
23

Rabu
MV

24
24

Kamis
25
25

Jum'at
26
26

Sabtu
27
27
Minggu

28
Senin 28
29
29

Selasa
30
30

Rabu
MVI
1
31

Kamis
2
32

Jum'at
3
33

Sabtu
4
34

Minggu
5
35

Senin
6

Selasa
7

Rabu
MVII
8
36 37 38

Kamis
9
39

Jum'at
40
10

Sabtu
41
11

Minggu
42
12

Senin
Catatan

Perbaikan gear saproket


1 hari menuju camp field dari bawah, 1 hari menuju block VII-I dari campfield

Kemungkinan waktu lebih cepat jika lubang bor tidak terlalu dalam dan medan
untuk mobilisasi ke titik selanjut mudah di lalui

Waktu analisa sample per gelombang 1 minggu


Tenda yang masih bagus dan peralatan flying camp
Solar Masuk Pemakaian Solar Persediaan Solar
No Tanggal Peruntukan
(jergen) (jergen) (Jergen)
1 ### 10 10
2 ### 6 4 kobelco pc 200
3 ### 4
4 ### 4
5 ### 6 1 9 Jacro 175
6 ### 9
7 ### 9
8 ### 4 5 kobelco pc 200
9 6/1/2021 0 5 kobelco pc 200
10 6/2/2021 3 2 kobelco pc 200
11 6/2/2021 2 0 Rig dan Pompa
12 6/3/2021 12 5 7 kobelco pc 200
13 6/4/2021 6 1 kobelco pc 200
14 6/5/2021 0 1
15 6/6/2021 0 1
16 6/7/2021 0 1
17 6/8/2021 0 1
18 6/9/2021 0 1
19 ### 1 0 Rig dan Pompa
20 ### 0 0
21 ### 0 0
22 ### 12 8 4 Exca
23 ### 0 4 0 Rig dan Pompa
24 ### 0 0 0
25 ### 0 0 0
26 ### 0 0 0
27 ### 12 8 4 Exca
28 ### 0 2 2 Rig dan Pompa
29 ### 0 0 2
30 ### 0 0 2
31 ### 0 2 0 Rig dan Pompa
32 ### 9 5 4 Solar
33 ### 0 0 4
34 ### 0 0 4
35 ### 0 0 4
36 ### 0 0 4
Tanggal Solar Masuk Satuan Solar masuk Satuan Stok Solar Satuan
### 10 Jergen 280 Liter 112.0 liter
### 112.0 liter
### 112.0 liter
### 112.0 liter
### 6 Jergen 168 Liter 280.0 liter
### 280.0 liter
### 280.0 liter
### 168.0 liter
6/1/2021 163 liter
6/2/2021 74 liter
6/3/2021 12 Jergen 336 Liter 293 liter
6/4/2021 139 liter
6/5/2021 119 liter
6/6/2021 105 liter
6/7/2021 92 liter
6/8/2021 74 liter
6/9/2021 61 liter
### 42 liter
### 19 liter
### 4 liter
### 12 Jergen 336 Liter 103 liter
### 86 liter
### 65 liter
### 47 liter
### 27 liter
### 12 Jergen 336 Liter 118 liter
### 93 liter
### 67 liter
### 39 liter
### 17 liter
### 9 Jergen 252 Liter 48 liter
### 21 liter
### 3 liter
### 0 liter
### 0
Rig
Waktu Pengeboran Satuan Waktu Pengeboran Satuan Pemakaian Solar Satuan
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0.0 Liter
0 Menit 0.00 Jam 0 Liter
0 Menit 0.00 Jam 0 Liter
0 Menit 0.00 Jam 0 Liter
20 Menit 0.33 Jam 1 Liter
240 Menit 4.00 Jam 7 Liter
0 Menit 0.00 Jam 0 Liter
0 Menit 0.00 Jam 0 Liter
150 Menit 2.50 Jam 4 Liter
0 Menit 0.00 Jam 0 Liter
208 Menit 3.47 Jam 6 Liter
330 Menit 5.50 Jam 10 Liter
30 Menit 0.50 Jam 1 Liter
0 Menit 0.00 Jam 0 Liter
95 Menit 1.58 Jam 3 Liter
180 Menit 3.00 Jam 5 Liter
120 Menit 2.00 Jam 4 Liter
165 Menit 2.75 Jam 5 Liter
180 Menit 3.00 Jam 5 Liter
275 Menit 4.58 Jam 8 Liter
310 Menit 5.17 Jam 9 Liter
365 Menit 6.08 Jam 11 Liter
195 Menit 3.25 Jam 6 Liter
280 Menit 4.67 Jam 8 Liter
330 Menit 5.50 Jam 10 Liter
120 Menit 2.00 Jam 4 Liter
0 Menit 0.00 Jam 0 Liter
Pompa Disungai Pompa Spullbak Camp
Pemakaian Solar Satuan Pemakaian Solar (8jam Kerja) Satuan
0 Liter 0.0 liter
0 Liter 0.0 liter
0 Liter 0.0 liter
0 Liter 0.0 liter
0 Liter 0.0 liter
0 Liter 0.0 liter
0 Liter 0.0 liter
0 Liter 0.0 liter
5 Liter 0 liter
5 Liter 0 liter
5 Liter 0 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
10 Liter 3 Liter
3 Liter 0 Liter
Pompa Spullbak dekat lokasi
Pemakaian Solar (Jam Kerja Rig) Satuan HM Awal HM Akhir HM Selisih Pengisian Solar
0.0 Liter 702 707 5 6
0.0 Liter 707 707 0
0.0 Liter 707 707 0
0.0 Liter 707 707 0
0.0 Liter 707 707 0
0.0 Liter 707 707 0
0.0 Liter 707 710 3
0.0 Liter 710 710 0 4
0 Liter 710 715 5
0 Liter 715 718 3 3
0 Liter 718 723 5 4
0 Liter 723 727 4 5
0 Liter 727 729 2
0 Liter 729 729 0
0 Liter 729 729 0
0 Liter 729 729 0
0 Liter 729 729 0
0 Liter 729 733 4
0 Liter 733 737 4
0 Liter 737 738 1
0 Liter 738 740 2 8
1 Liter 740 744 4
2 Liter 744 744 0
1 Liter 744 749 5
2 Liter 749 749 0
2 Liter 749 750 1 8
3 Liter 750 754 4
4 Liter 754 759 5
4 Liter 759 759 0
2 Liter 759 761 2
3 Liter 761 765 4 7
4 Liter 765 767 2
1 Liter 767 770 3
0 Liter 770 773 3
773 776 3
Satuan Pengisian Solar Satuan Pemakaian Solar Satuan Solar Sisa Di Tanki
Jergen 168 liter 80 Liter 88
0 Liter 88
0 Liter 88
0 Liter 88
0 Liter 88
0 Liter 88
48 Liter 40
Jergen 112 liter 0 Liter 152
80 Liter 72
Jergen 84 liter 48 Liter 108
Jergen 112 liter 80 Liter 140
Jergen 140 liter 64 Liter 216
32 Liter 184
0 Liter 184
0 Liter 184
0 Liter 184
0 Liter 184
64 Liter 120
64 Liter 56
16 Liter 40
Jergen 224 liter 32 Liter 232
64 Liter 168
0 Liter 168
80 Liter 88
0 Liter 88
Jergen 224 liter 16 Liter 296
64 Liter 232
80 Liter 152
0 Liter 152
32 Liter 120
Jergen 196 liter 64 Liter 252
32 Liter 220
48 Liter 172
48 Liter 124
48 Liter 76
Satuan Pemakaian Rig per hari Satuan
Liter 0.5 Jergen
Liter
Liter Pemakaian Pompa 1 per hari Satuan
Liter 10 Liter
Liter Diliat dari pompa yang di sungai
Liter Pemakaian solar exca / HM Satuan
Liter 16 Liter
Liter
Liter
Liter
Liter Pemakaian Solar exca /3 hari (efektif kerja 5 jam / hari) Satuan
Liter 240 Liter
Liter Pemakaian Solar Pompa 1 / 3 hari (Efektif kerja 24 jam / hari) Satuan
Liter 30 Liter
Liter Pemakaian Solar Pompa 2 / 3 hari (Efektif kerja 8 jam / hari) Satuan
Liter 10 Liter
Liter Pemakaian Solar Pompa 3 / 3 hari (Efektif kerja 6 jam / hari) Satuan
Liter 7.5 Liter
Liter Pemakaian Solar Rig /3 hari (efektif kerja 6 jam / hari) Satuan
Liter 31.5 Liter
Liter Total Kebutuhan Satuan
Liter 319 Liter
Liter Grand Total Kebutuhan Satuan
Liter 280.354861111111 liter
Liter 10.0126736111111 Jergen
Liter
Liter
Liter
Liter
Liter
Liter
Liter
Liter
Liter
Liter
Pemakaian Rig per hari Satuan Pemakaian Perjam (Hitungan Kerja 8 jam) Satuan
14 Liter 1.75 Liter
include dengan pekerjaan berat dan ringan
Pemakaian Per Jam (Hitungan Kerja 24 Jam) Satuan
0.416666666666667 Liter