Weekly Site Management Report


03 August 2018 , Friday
Week #52 : 26 July 2018 to 01 August 2018
CONTENT
Project Information

General Accomplishment Report

Civil, Structural, and Architectural Works Updates

MEPF Updates

Manpower Loading

MEPF Equipment Updates

Architectural OSM Updates

OSM Delivery Package Updates

Billing & Change Order Monitoring

NCN Monitoring

RFI / Submittal Monitoring

Issues and Concerns


PROJECT INFORMATION
PROJECT DESCRIPTION

Name of Project :

Location :

Brief Description :

No. of Physical Floors :

Gross Floor Area(GFA) :

Total No. Of Units :


DESIGNERS / CONSULTANTS

Architectural Design :

Structrual Design :

Interior Design :

Landscape Design : TBD (Design and Build)

Electrical Design :

Mechanical Design :

Plumbing/ Sanitary Design : .

Fire Protection Design : .

Construction Manager : .
CONTRACTORS & SUPPLIERS
General Contractor
Civil, Structural & Architectural Works : .

MEPF Contractors
Electrical Works : .
Plumbing / Sanitary Works : .
Mechanical Works : .
Fire Protection Works : Other Trade Contractors
Landscape Works : TBD
Interior Fit-Out Works : TBD
Auxiliary Works (CCTV & FTTU) :

MEPF Equipment
Elevator System : .
Generator Set :
Sanitary / Fire Pro Pumps (Supply) : n
Blowers :
Ductless Exhaust Fan :
CONTRACTORS & SUPPLIERS
CSA OSM
Rebar (Supply) : Pag-Asa / Filipino Metal / Steel Asia
Cement (Supply) : Eirene Cement
Kitchen Countertop : Jamestone
Kitchen Cabinet : Graceline
Wooden Doors and Partition : Grand Nova Holdings Corp.
Aluminum Glass Doors and Windows : 21th Construction Devt. Corp.
Steel Doors : Metrotech
Hallway Tiles (Supply) : TJ&A Galleria
Unit Tiles (Supply) : Mariwasa
T&B Tiles (Supply) : Bestile Corp.
Balcony Tiles (Supply) : Multi-rich Home Decors
CONTRACTORS & SUPPLIERS
MEPF OSM
Kitchen Sink & Accessories (Supply) : Dynamic Brands Int’l.
Plumbing Fixtures (Supply) : Dynamic Brands Int’l.
Grease Trap (Supply) : Philglobal Asia
Fire Rated Cables (Supply) : Columbia Wires
Copper Wires (Supply) : London Industrial
Wiring Devices : Akari
PROJECT STATUS & MILESTONE DATES
PROJECT STATUS

Contract Start Date : July 1, 2017

Completion Date : December 31, 2019

Contract Duration in Months : 30 Months

in Days : 913 days

in Weeks : 120 Weeks

Construction Period Elapsed : 397 Days

: 52 Weeks

: 43.48%
PROJECT MILESTONES
ITEM DESCRIPTION MILESTONE DATE MILESTONE DATE
(TARGET) (ACTUAL)
1 Topping Off 08 August 2018
2 Mock-up units 16 August 2018
3 Watertightness October 2019
4 Elevator December 2018
5 Permanent Water 15 October 2018
6 Energization April 2019
7 Architectural Fit-out December 2019
8 Occupancy Permit December 2019

9 Turn-over Period – Conditional December 2019


Acceptance
GENERAL ACCOMPLISHMENT REPORT
GENERAL PERCENTAGE OF ACCOMPLISHMENT (POC)

CONSOLIDATED ACCOMPLISHMENT
(Various Contractors & Suppliers)
Previous To Date
This Period
As of 26 July 2018 As of 01 Aug 2018
Actual
Projected
Variance
Days Ahead /
Delay
POC BREAKDOWN
Accomplishment
Wt
Item Description % Target Actual Variance

I CSA Works
II MEPF Works
Electrical Works
Plumbing and Sanitary with Minor
Mechanical Works
Fire Protection Works
III MEPF Equipment
Elevator System
Generator System
Sanitary / Fire Pro Pumps (Supply)
Blowers
Ductless Exhaust Fan
POC BREAKDOWN
Accomplishment
Wt
Item Description % Target Actual Variance

IV CSA OSM
Kitchen Cabinet
Kitchen Countertop
Aluminium Glass Doors and Windows
Steel Doors
Wooden Doors and Partition
Reinforcing Bars (Supply)
Cement in Bulk (Supply)
Hallway Tiles (Supply)
Unit Tiles (Supply)
T&B Tiles (Supply)
Balcony Tiles (Supply)
POC BREAKDOWN
Accomplishment
Wt
Item Description % Target Actual Variance

V MEPF OSM
Copper Wires (Supply)
Fire-Rated Cables (Supply)
Wiring Devices (Supply)
Plumbing Fixtures & Accessories (Supply)
Kitchen Sink & Accessories (Supply)
Grease Trap (Supply)
VI Other Trade Contracts
Landscape Works
Interior Fit-Out Works
CCTV Auxiliary Works
FTTU Auxiliary Works
G R A N D T OT A L
PROGRESS PHOTOS

ROOF BEAM

12
11

10

09

08

Insert Photo 07

06

05

04

03

02

Front Elevation
Before
As of 25 July 2018
PROGRESS PHOTOS

ROOF BEAM

12
11

10

09

08

Insert Photo 07

06

05

04

03

02

Front Elevation
After
As of 01 August 2018
PROGRESS PHOTOS

ROOF BEAM

12
11

10

09

08

07

06

05

04

03

02

Rear Elevation
Before
As of 25 July 2018
PROGRESS PHOTOS

ROOF BEAM

12
11

10

09

08

Insert Photo 07

06

05

04

03

02

Right Elevation
After
As of 01 August 2018
PROGRESS PHOTOS

ROOF BEAM

12
11

10

09

08

Insert Photo 07

06

05

04

03

02

Left Elevation
Before
As of 25 July 2018
PROGRESS PHOTOS

ROOF BEAM

12
11

10

09

08

Insert Photo 07

06

05

04

03

02

Left Elevation
After
As of 01 August 2018
CIVIL, STRUCTURAL, & ARCHITECTURAL WORKS UPDATE
PERCENTAGE OF ACCOMPLISHMENT (POC)

CIVIL, STRUCTURAL, & ARCHITECTURAL WORKS


21th Construction Development Corporation
Previous To Date
This Period
As of 26 July 2018 As of 01 Aug 2018
Actual 39.278% 0.516% 39.794%
Projected 38.560% 1.356% 39.916%
Variance 0.718% -0.840% -0.122%
Days Ahead /
6 days -7 days -1 day
Delay
LAST WEEK’S PROJECTION

PROJECTION TARGET WT. POC POC STATUS TO DATE

DIVISION 1 - GENERAL REQUIREMENTS 0.05092%

DIVISION 3 - STRUCTURAL WORKS


3060 Structural Shapes for Trusses 0.00000%

DIVISION 4 - MASONRY WORKS


4010 Unit Masonry (Architectural Rebar to be Provided by the Conractor)
Interior Wall 0.21457%
Ground Floor 0.01951%
2nd Floor 0.01951%
3rd Floor 0.01951%
4th Floor 0.01951%
5th Floor 0.01951%
6th Floor 0.01951%
7th Floor 0.01951%
8th Floor 0.01951%
9th Floor 0.01951%
10th Floor 0.01951%
11th Floor 0.01951%
Exterior Wall 0.05210%
Ground Floor 0.00474%
2nd Floor 0.00474%
3rd Floor 0.00474%
4th Floor 0.00474%
5th Floor 0.00474%
6th Floor 0.00474%
7th Floor 0.00474%
8th Floor 0.00474%
9th Floor 0.00474%
10th Floor 0.00474%
11th Floor 0.00474%
Zoccalo 0.12868%
Ground Floor 0.01072%
2nd Floor 0.01072%
3rd Floor 0.01072%
4th Floor 0.01072%
5th Floor 0.01072%
6th Floor 0.01072%
7th Floor 0.01072%
8th Floor 0.01072%
9th Floor 0.01072%
10th Floor 0.01072%
11th Floor 0.01072%
12th Floor 0.01072%
Wheel Stoppers
Sealant & Caulking 0.03959%
Door Opening Preparations 0.02207%
Window Opening Preparations 0.00866%
Rubbed Concrete (ceiling / columns / RC w all / shearw all) 0.03250%
100mm thk Precast concrete interior w all 0.27498%
4" CHB Wall Including Rebars (planters box) 0.01356%

DIVISION 5 - METALS
5010 Metal Fabrication
Balcony Railing (25mm x 25mm pow der Coated Finish) 0.02574%

DIVISION 6 - THERMAL & MOISTURE PROTECTION


6010 Waterproofing
Membrane Waterproofing
Mineral (4.5kg.) torch-on membrane w aterproofing (Roof gutters,Genset
0.01502%
Room, Water Tank Area, Stair Deck, Elevator Deck)
Sanded 3mm torch-on membrane w aterproofing (balconies) 0.02120%
Sanded 3mm torch-on membrane w aterproofing (T&B) 0.02327%
Ground Floor 0.00388%
2nd Floor 0.00388%
3rd Floor 0.00388%
4th Floor 0.00388%
5th Floor 0.00388%
6th Floor 0.00388%
Cementitious w aterproofing (Back of Panel Board) 0.00818%
Sanded 3mm torch-on membrane w aterproofing (Garbage Room) 0.00145%
Ground Floor 0.00029%
2nd Floor 0.00029%
3rd Floor 0.00029%
4th Floor 0.00029%
5th Floor 0.00029%
Mineral (4.5kg.) torch-on membrane w aterproofing (Mechanical Deck) 0.00056%
Sanded 3mm torch-on membrane w aterproofing (EE room) 0.00114%

6030 Roof Covering


GA #24 Long Span Galvalum Roofing
Roof of Building including Insulation 0.13683%

DIVISION 7 - FINISHES
7010 Floor Finishes
FF-3, 300mmx300mm CERAMIC Tiles w / Waterproofing Membrane measured
0.00407%
separately (Tiles OSM)
FF-7, 300mmx300mm RUSTIC Tiles w ith w aterproofing membrane measured
0.00297%
separately (Tiles OSM)
FF-11, 600mmx600mm Ceramic Tiles (Tiles OSM), 0.00554%
FF-13, 600mmx600mm Homogenous Tiles (Tiles OSM) 0.03927%
7020 Wall Finishes
WF-1, Plain Cement smooth painted Finish 0.13346%
WF-2, 300mmx300mm Homogenous Tiles (Tiles OSM) 0.01965%
WF-3, Elastomeric Waterproof Coating by UKUSA or SKK 0.03171%
WF-13, Plain Cement Finish 0.00761%

7030 Ceiling Finishes


CF-1, 12mm thk gypsum board painted finish includingframing and other
details eg. Shadow line/gap, etc.
Hallw ays 0.01241%
Kitchen & Bulkhead 0.05778%
Toilet and Bath at Residential units 0.01179%
CF-3, poured concrete off-form skim coated painted finish
Living / Dining / Bedroom 0.04950%
Balcony 0.00377%

7050 Other Painting Works


Exterior Grooves 0.01067%

TOTAL 1.461%
LOOK AHEAD FOR NEXT WEEK

PROJECTION TARGET WT. POC POC STATUS TO DATE

DIVISION 1 - GENERAL REQUIREMENTS 0.05092%

DIVISION 3 - STRUCTURAL WORKS


3060 Structural Shapes for Trusses 0.00000%

DIVISION 4 - MASONRY WORKS


4010 Unit Masonry (Architectural Rebar to be Provided by the Conractor)
Interior Wall 0.21457%
Ground Floor 0.01951%
2nd Floor 0.01951%
3rd Floor 0.01951%
4th Floor 0.01951%
5th Floor 0.01951%
6th Floor 0.01951%
7th Floor 0.01951%
8th Floor 0.01951%
9th Floor 0.01951%
10th Floor 0.01951%
11th Floor 0.01951%
Exterior Wall 0.05210%
Ground Floor 0.00474%
2nd Floor 0.00474%
3rd Floor 0.00474%
4th Floor 0.00474%
5th Floor 0.00474%
6th Floor 0.00474%
7th Floor 0.00474%
8th Floor 0.00474%
9th Floor 0.00474%
10th Floor 0.00474%
11th Floor 0.00474%
Zoccalo 0.12868%
Ground Floor 0.01072%
2nd Floor 0.01072%
3rd Floor 0.01072%
4th Floor 0.01072%
5th Floor 0.01072%
6th Floor 0.01072%
7th Floor 0.01072%
8th Floor 0.01072%
9th Floor 0.01072%
10th Floor 0.01072%
11th Floor 0.01072%
12th Floor 0.01072%
Wheel Stoppers
Sealant & Caulking 0.03959%
Door Opening Preparations 0.02207%
Window Opening Preparations 0.00866%
Rubbed Concrete (ceiling / columns / RC w all / shearw all) 0.03250%
100mm thk Precast concrete interior w all 0.27498%
4" CHB Wall Including Rebars (planters box) 0.01356%

DIVISION 5 - METALS
5010 Metal Fabrication
Balcony Railing (25mm x 25mm pow der Coated Finish) 0.02574%

DIVISION 6 - THERMAL & MOISTURE PROTECTION


6010 Waterproofing
Membrane Waterproofing
Mineral (4.5kg.) torch-on membrane w aterproofing (Roof gutters,Genset
0.01502%
Room, Water Tank Area, Stair Deck, Elevator Deck)
Sanded 3mm torch-on membrane w aterproofing (balconies) 0.02120%
Sanded 3mm torch-on membrane w aterproofing (T&B) 0.02327%
Ground Floor 0.00388%
2nd Floor 0.00388%
3rd Floor 0.00388%
4th Floor 0.00388%
5th Floor 0.00388%
6th Floor 0.00388%
Cementitious w aterproofing (Back of Panel Board) 0.00818%
Sanded 3mm torch-on membrane w aterproofing (Garbage Room) 0.00145%
Ground Floor 0.00029%
2nd Floor 0.00029%
3rd Floor 0.00029%
4th Floor 0.00029%
5th Floor 0.00029%
Mineral (4.5kg.) torch-on membrane w aterproofing (Mechanical Deck) 0.00056%
Sanded 3mm torch-on membrane w aterproofing (EE room) 0.00114%

6030 Roof Covering


GA #24 Long Span Galvalum Roofing
Roof of Building including Insulation 0.13683%

DIVISION 7 - FINISHES
7010 Floor Finishes
FF-3, 300mmx300mm CERAMIC Tiles w / Waterproofing Membrane measured
0.00407%
separately (Tiles OSM)
FF-7, 300mmx300mm RUSTIC Tiles w ith w aterproofing membrane measured
0.00297%
separately (Tiles OSM)
FF-11, 600mmx600mm Ceramic Tiles (Tiles OSM), 0.00554%
FF-13, 600mmx600mm Homogenous Tiles (Tiles OSM) 0.03927%
7020 Wall Finishes
WF-1, Plain Cement smooth painted Finish 0.13346%
WF-2, 300mmx300mm Homogenous Tiles (Tiles OSM) 0.01965%
WF-3, Elastomeric Waterproof Coating by UKUSA or SKK 0.03171%
WF-13, Plain Cement Finish 0.00761%

7030 Ceiling Finishes


CF-1, 12mm thk gypsum board painted finish includingframing and other
details eg. Shadow line/gap, etc.
Hallw ays 0.01241%
Kitchen & Bulkhead 0.05778%
Toilet and Bath at Residential units 0.01179%
CF-3, poured concrete off-form skim coated painted finish
Living / Dining / Bedroom 0.04950%
Balcony 0.00377%

7050 Other Painting Works


Exterior Grooves 0.01067%

TOTAL 1.461%
STRUCTURAL UPDATES
STAIRS CONCRETING MONITORING
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
ROOF BEAM

12TH FLOOR

11TH FLOOR

10th FLOOR

9th FLOOR

8th FLOOR

7th FLOOR

6th FLOOR

5th FLOOR

4th FLOOR

3rd FLOOR

2nd FLOOR

1st FLOOR

FDN

Lapsed Upcoming Concreted

Upcoming Lapsed Concreted


Front Elevation
BACKFILLING MONITORING

Zone 1-A Zone 1-B Zone 3 Zone 2-A Zone 2-B

Backfilled , Compacted , & Passed FDT 9th Layer


COLUMN CONCRETING MONITORING
12TH Floor

Zone 1-A Zone 1-B 25 June 2018

29 May 2018 29 May 2018 Zone 3 Zone 2-A


29 June 2018
Zone 2-B
10 July 2018

Columns and Shearwalls at Roof Level Columns and Shearwalls at Lower Level

Actual Date of Concreting


ACTIVITY ZONE 1-A ZONE 1-B ZONE 3 ZONE 2-A ZONE 2-B

12th to Roof 27 May 2018 02 June 2018 07 June 2018 19 June 2018 20 June 2018

Note : Foundation to 12th floor columns already concreted


FTB CONCRETING MONITORING

Zone 1-A Zone 1-B Zone 3 Zone 2-A Zone 2-B


15 November 2017 14 February 2018
18 January 2018
11 October 2017 20 October 2017

Footing Tie Beam w/ Reinforcement Footing Tie Beam Concreted

Actual Date of Concreting


SLAB ON GRADE CONCRETING MONITORING
Ground Floor

Zone 1-A Zone 1-B Zone 3 Zone 2-A Zone 2-B


27 April 2018 09 May 2018 23 June 2018

SOG w/ Gravel Bedding / Reinforcement SOG Concreted

Actual Date of Concreting


ACTIVITY ZONE 1-A ZONE 1-B ZONE 3 ZONE 2-A ZONE 2-B

Slab - Ground floor 31 March 2018 05 April 2018 10 April 2018 06 May 2018 14 May 2018
2ND TO 12TH FLOOR BEAM & SLAB CONCRETING MONITORING

2nd Floor

Zone 1-A Zone 1-B Zone 3 Zone 2-A Zone 2-B


27 November 2017 01 December 2017
14 December 2017 26 January 2018 23 February 2018

2nd Floor Beam and Slab w/ Reinforcement 2nd Floor Beam and Slab Concreted

Actual Date of Concreting


ACTIVITY ZONE 1-A ZONE 1-B ZONE 3 ZONE 2-A ZONE 2-B

Slab - 2nd floor 30 November 2017 05 December 2017 10 December 2017 27 January 2018 07 February 2018

Note : 2nd to 12th floor slab already concreted


ROOF BEAMS CONCRETING MONITORING
Roof / Machine Deck

Zone 1-A Zone 1-B Zone 3 Zone 2-A Zone 2-B


01 August
30 June 2018 2018 11 July 2018

Roof Beam w/ Formworks or Reinforcement Roof Beam Concreted

Actual Date of Concreting


ACTIVITY ZONE 1-A ZONE 1-B ZONE 3 ZONE 2-A ZONE 2-B

Roof Beams 14 June 2018 09 June 2018 14 June 2018 26 June 2018 27 June 2018

Note : All roof beams concreted


ARCHITECTURAL UPDATES
WETWORKS MATRIX SCHEDULE VS. ACCOMPLISHMENT
Wet Works
Item Level Zocalo CHB Wall Plastering Rubcon
ETC To Date ETC To Date ETC To Date ETC To Date
1.0. Ground Floor 5-Sept 96.60% 26-Sept 99.00% 17-Oct 90.00% 12-Sept 100.00%

2.0. 2nd Floor 29-Aug 99.00% 12-Sept 99.00% 14-Nov 99.00% 30-Aug 100.00% 

3.0. 3rd Floor 29-Aug 99.00% 12-Sept 99.00% 26-Sept 99.00% 30-Aug 100.00%

4.0. 4th Floor 5-Sept 99.00% 12-Sept 99.00% 17-Oct 96.50% 12-Sept 100.00% 

5.0. 5th Floor 29-Aug 99.00% 19-Sept 99.00% 21-Nov 95.00% 30-Aug 100.00%

6.0. 6th Floor 10-Oct 99.00% 31-Oct 99.00% 2-Jan 81.50% 26-Sept 100.00%
7.0. 7th Floor 21-Nov 96.99% 12-Dec 99.00% 13-Feb 76.00% 10-Oct 100.00%
8.0. 8th Floor 21-Nov 92.50% 12-Dec 99.00% 13-Feb 63.50% 31-Oct 100.00%
9.0. 9th Floor 26-Dec 95.33% 23-Jan 97.38% 27-Mar 45.00% 21-Nov 100.00%
10.0. 10th Floor 26-Dec 93.35% 23-Jan 98.55% 27-Mar 35.00% 21-Nov 100.00%
11.0. 11th Floor 30-Jan 93.32% 20-Feb 92.71% 24-Apr 26.50% 2-Jan 90.50%
12.0. 12th Floor 30-Jan 92.33% 20-Feb 75.30% 24-Apr. 21.00% 25.00%
WETWORKS MATRIX SCHEDULE VS. ACCOMPLISHMENT
Wet Works
Item Level Pre-Cast Wall T&B Waterproofing Balcony Waterproofing
ETC To Date ETC To Date ETC To Date
1.0. Ground Floor 05-Sept 99.00% 26-Sept 100.00% 26-Sept

2.0. 2nd Floor 05-Sept 99.00% 24-Oct 100.00% 24-Oct 20.00%

3.0. 3rd Floor 05-Sept 99.00% 5-Sept 100.00% 5-Sept 100.00%

4.0. 4th Floor 05-Sept 99.00% 26-Sept 100.00% 26-Sept 20.00%

5.0. 5th Floor 19-Sept 99.00% 07-Nov 100.00% 07-Nov 15.00%

6.0. 6th Floor 03-Oct 99.00% 19-Dec 100.00% 19-Dec 15.00%


7.0. 7th Floor 17-Oct 99.00% 30-Jan 100.00% 30-Jan 15.00%
8.0. 8th Floor 31-Oct 70.60% 30-Jan 10.00% 30-Jan 10.00%
9.0. 9th Floor 14-Nov 43.40% 13-Mar 8.00% 13-Mar 5.00%
10.0. 10th Floor 28-Nov 0.53% 13-Mar 5.00% 13-Mar
11.0. 11th Floor 12-Dec 10-Apr 5.00% 10-Apr
12.0. 12th Floor 10-Apr 10-Apr
FINISHING WORKS MATRIX SCHEDULE
Wall , Ceiling, and Floor Finishes
Item Level Ceiling Wall Paint (WF-1) Floor Tile (FF-2/13)
ETC To Date ETC To Date ETC To Date
1.0. Ground Floor 12-Dec 37.17% 27-Feb 58.00% 2-Jan 40.00%

2.0. 2nd Floor 28-Nov 26.67% 30-Jan 38.00% 26-Dec 50.00%

3.0. 3rd Floor 3-oct 34.50% 19-Dec 53.00% 24-Oct 99.00%

4.0. 4th Floor 12-Dec 28.50% 27-Feb 44.00% 2-Jan 35.00%

5.0. 5th Floor 9-Jan 27.17% 27-Mar 46.00% 30-Jan 50.00%

6.0. 6th Floor 20-feb 20.50% 8-May 20.00% 13-Mar 6.05%


7.0. 7th Floor 3-Apr 11.83% 19-June 24-Apr 4.53%
8.0. 8th Floor 3-Apr 9.83% 19-June 24-Apr
9.0. 9th Floor 15-Mar 8.33% 31-Jul 5-June
10.0. 10th Floor 15-Mar 7.83% 31-Jul 5-June
11.0. 11th Floor 12-June 6.33% 28-Aug 3-July
12.0. 12th Floor 12-June 28-Aug 3-July
ZOCALO WORKS MONITORING
Ground Floor

Actual
LEGEND: % Manpower Required per Week manpower
C M L
PROJECTED 100.00% 2 1
COMPLETED   96.60% 1 - 1 2
1ST WEEK Nov 29– Dec. 05 2.40% 2 2
2ND WEEK March 2019 1.00% 2 2
ZOCALO WORKS MONITORING
2nd Floor

Actual
LEGEND: % Manpower Required per Week manpower
C M L
PROJECTED 100.00% 2 1
COMPLETED   99.00%
ALIMAK AREA March 2019 1.00%
ZOCALO WORKS MONITORING
3rd Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 2 1
COMPLETED   99.00% -
ALIMAK AREA March 2019 1.00%
ZOCALO WORKS MONITORING
4th Floor

Actual
LEGEND: % Manpower Required per Week Manpower
C M L C/L
PROJECTED 100.00% 2 1 1
COMPLETED   99.00% -
ALIMAK AREA March 2019 1.00%
ZOCALO WORKS MONITORING
5th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 2 1
COMPLETED   99.00% - -
ALIMAK AREA March 2019 1.00%
ZOCALO WORKS MONITORING
6th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 2 1
COMPLETED   99.00%
1ST WEEK March 2019 1.00%
2ND WEEK
ZOCALO WORKS MONITORING
7th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 92.47% 2 1 2
COMPLETED   96.99% 1 - 1
Nov 29– Dec. 05 Nov 29– Dec. 05 2.01% 2 1
2ND WEEK March 2019 1.00% 2 1
ZOCALO WORKS MONITORING
8th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 89.53% 2 1 3
COMPLETED   92.50% 2 - 1
Nov 29– Dec. 05 Nov 29– Dec. 05 5.24% 2 1
2ND WEEK Dec. 06 - 12 1.26% 2 1
ZOCALO WORKS MONITORING
9th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 65.62% 2 1 4
COMPLETED   95.33% 2 - 2
1ST WEEK Nov 29– Dec. 0 5.70% 2 1
2ND WEEK Dec. 06 - 12 1.97% 2 1
ZOCALO WORKS MONITORING
10th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 46.15% 2 1 4
COMPLETED   94.66% 2 - 2
1ST WEEK Nov 29– Dec. 0 4.37% 2 1
2ND WEEK Dec. 06 - 12 0.07% 2 1
ZOCALO WORKS MONITORING
11th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 7.69% 2 1 4
COMPLETED   93.32% 2 - 2
1ST WEEK Nov 29– Dec. 0 5.00% 2 1
2ND WEEK Dec. 06 - 12 1.68% 2 1
ZOCALO WORKS MONITORING
12th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 7.69% 2 1 4
COMPLETED   92.33% 2 - 2
1ST WEEK Nov 29– Dec. 0 5.00% 2 1
2ND WEEK Dec. 06 - 12 2.67% 2 1
CHB LAYING MONITORING
Ground Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 100.00% 3 3
COMPLETED   99.00% - 2 2 4
1ST WEEK March 2019 1.00% - 3
2ND WEEK
CHB LAYING MONITORING
2nd Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 100.00% 3 3
COMPLETED   99.00% -
D - ALIMAK March 2019 1.00% -
D - ALIMAK -
CHB LAYING MONITORING
3rd Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 3 3
COMPLETED   99.00% -
1ST WEEK March 2019 1.00% -
2ND WEEK -
CHB LAYING MONITORING
4th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 3 3
COMPLETED   99.60% -
1ST WEEK March 2019 0.40% -
2ND WEEK -
CHB LAYING MONITORING
5th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 3 3 0
COMPLETED   99.00% -
ALIMAK AREA March 2019 1.00% -
CHB LAYING MONITORING
6th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 4 3
COMPLETED   99.00% -
1ST WEEK March 2019 1.00% -
2ND WEEK
CHB LAYING MONITORING
7th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 95.95% 4 3
COMPLETED   99.00% -
1ST WEEK March 2019 100% -
2ND WEEK
CHB LAYING MONITORING
8th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 93.68% 4 3
COMPLETED   99.00% -
1ST WEEK March 2019 1.00% -
2ND WEEK
CHB LAYING MONITORING
9th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 21.43% 4 3 10
COMPLETED   97.38% - 6 4
1ST WEEK Nov 29– Dec. 05 2.62% - 4 3
2ND WEEK Dec. 06 - 12 - 1 1
CHB LAYING MONITORING
10th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 21.43% 4 3 10
COMPLETED   98.55% - 6 4
1ST WEEK Nov 29– Dec. 0 1.45% - 4 3
2ND WEEK Dec. 06 - 12 0.00% - 4 3
CHB LAYING MONITORING
11th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 00.00% 4 3 8
COMPLETED   92.71% - 4 4
1ST WEEK Nov 29– Dec. 05 7.14% - 4 3
2ND WEEK Dec. 06 - 12 0.15% - 4 3
CHB LAYING MONITORING
12th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 00.00% 4 3 8
COMPLETED   75.30% - 5 3
1ST WEEK Nov 29– Dec. 05 7.14% - 4 3
2ND WEEK Dec. 06 - 12 7.14% - 4 3
PLASTERING WORKS MONITORING
Ground Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 3 3
COMPLETED   90.00% - 5 5 10
1ST WEEK Nov 29– Dec. 05 9.00% - 4 2
2ND WEEK March 2019 1.00% - 3 2
PLASTERING WORKS MONITORING
2nd Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 3 3
COMPLETED   99.00% -
1ST WEEK March 2019 1.00% -
2ND WEEK
PLASTERING WORKS MONITORING
3rd Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 3 3 8
COMPLETED   98.00% - 5 3
1ST WEEK Nov 29– Dec. 05 1.00% - 4 4
2ND WEEK March 2019 1.00% - 2 2
PLASTERING WORKS MONITORING
4th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 100.00% 6 6
COMPLETED   96.50% - 6 4 10
1ST WEEK Nov 29– Dec. 05 2.50% - 8 8
2ND WEEK March 2019 1.00% - 8 6
PLASTERING WORKS MONITORING
5th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 91.15% 4 4 9
COMPLETED   95.00% - 6 3
1ST WEEK Nov 29– Dec. 05 4.42% - 4 4
2ND WEEK Dec. 06 - 09 4.42% - 4 4
PLASTERING WORKS MONITORING
6th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 61.34% 4 4 8
COMPLETED   81.50% - 4 4
1ST WEEK Nov 29– Dec. 05 5.52% - 4 4
2ND WEEK Dec. 06 - 09 5.52% - 4 4
PLASTERING WORKS MONITORING
7th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 30.45% 4 4 6
COMPLETED   76.00% - 4 2
1ST WEEK Nov 29– Dec. 05 5.35% - 7 4
2ND WEEK Dec. 06 - 09 5.35% - 4 4
PLASTERING WORKS MONITORING
8th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 30.18% 4 4 8
COMPLETED   63.50% - 6 4
1ST WEEK Nov 29– Dec. 05 5.56% - 5 5
2ND WEEK Dec. 06 - 09 5.56% - 4 4
PLASTERING WORKS MONITORING
9th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 00.00% 4 4 8
COMPLETED   45.00% - 6 2
1ST WEEK Nov 29– Dec. 05 5.56% - 7 4
2ND WEEK Dec. 06 - 09 5.56% - 4 4
PLASTERING WORKS MONITORING
10th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 00.00% 4 4 6
COMPLETED   35.00% - 4 2
1ST WEEK Nov 29– Dec. 05 5.56% - 7 4
2ND WEEK Dec. 06 - 09 5.56% - 4 4
PLASTERING WORKS MONITORING
11th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 00.00% 4 4 6
COMPLETED   35.00% - 4 2
1ST WEEK Nov 29– Dec. 05 5.56% - 7 4
2ND WEEK Dec. 06 - 09 5.56% - 4 4
PLASTERING WORKS MONITORING
12th Floor

LEGEND: % Manpower Required per Week Actual Manpower


C M L
PROJECTED 00.00% 4 4 6
COMPLETED   35.00% - 4 2
1ST WEEK Nov 29– Dec. 05 5.56% - 7 4
2ND WEEK Dec. 06 - 09 5.56% - 4 4
RUBBED CONCRETE WORKS WORKS MONITORING
Ground Floor

LEGEND: % Manpower Required per Week Actual Manpower


C P L
PROJECTED 100.00% 3 1
COMPLETED   99.10% -
1ST WEEK March 2019 0.90% - 2 1
RUBBED CONCRETE WORKS WORKS MONITORING
2nd Floor

LEGEND: % Manpower Required per Week Actual Manpower


C P L
PROJECTED 100.00% 2 1 1
COMPLETED   99.00% - 1 -
1ST WEEK March 2019 1.00% - 2 1
RUBBED CONCRETE WORKS WORKS MONITORING
3rd Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 100.00% 2 1 0
COMPLETED   99.50% - - -
1ST WEEK March 2019 0.50% - 2 1
RUBBED CONCRETE WORKS WORKS MONITORING
4th Floor

LEGEND: % Manpower Required per Week Actual manpower


C P L
PROJECTED 100.00% 2 1 2
COMPLETED   99.00% - 2 1
1ST WEEK March 2019 1.00% - 1 1
RUBBED CONCRETE WORKS WORKS MONITORING
5th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 100.00% 2 1 0
COMPLETED   99.00% - - -
1ST WEEK March 2019 1.00% - 1 1
2ND WEEK
RUBBED CONCRETE WORKS WORKS MONITORING
6th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 100.00% 2 1
COMPLETED   99.00% - 1 1
1ST WEEK March 2019 1.00% -
2ND WEEK
RUBBED CONCRETE WORKS WORKS MONITORING
7th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 100.00% 2 1 1
COMPLETED   99.00% - 2 1
1ST WEEK March 2019 1.00% - 1
2ND WEEK
RUBBED CONCRETE WORKS WORKS MONITORING
8th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 82.00% 2 1 3
COMPLETED   99.00% - 2 2
1ST WEEK March 2019 1.00% - 2 1
2ND WEEK
RUBBED CONCRETE WORKS WORKS MONITORING
9th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 60.00% 2 1 4
COMPLETED   99.00% - 2 2
1ST WEEK March 2019 1.00% - 2 1
2ND WEEK 2 1
RUBBED CONCRETE WORKS WORKS MONITORING
10th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 40.00% 2 1 6
COMPLETED   99.00% - 4 2
1ST WEEK March 2019 1.00% - 4 2
2ND WEEK
RUBBED CONCRETE WORKS WORKS MONITORING
11th Floor

LEGEND: % Manpower Required per Week Actual manpower


C M L
PROJECTED 30.00% 2 1 6
COMPLETED   90.00% - 4 2
1ST WEEK Nov 29– Dec. 05 10.00% - 4 2
2ND WEEK 2 1
SEQUENTIAL MONITORING OF ARCHITECTURAL WORKS
PER UNIT
MASONRY TO FINISHING WORKS
Living, Dining, Kitchen, & Bedroom
Zoccalo CHB Lintel Beam
Floor Total No.
Level of Units Installed Installed CHB Main Balcony & Bed rm
ETC Zocalo ETC (100) ETC Door Doors & Window

Ground 39 5-Sept 39 26-Sept 32 10-Oct 34 36


2nd 50 29-Aug 50 12-Sept 48 26-Sept 50 50
3rd 53 29-Aug 53 12-Sept 52 26-Sept 53 53
4th 53 5-Sept 53 12-Sept 52 10-Oct 53 53
5th 53 29-Aug 53 19-Sept 52 3-Oct 53 53
6th 53 10-Oct 49 31-Oct 42 14-Nov 39 47
7th 53 21-Nov 51 12-Dec 46 26-Dec 26 21
8th 53 21-Nov 51 12-Dec 45 26-Dec  25 25
9th 53 26-Dec 49 23-Jan 28 6-Feb 5   7
10th 53 26-Dec 49 23-Jan  12 6-Feb 14 13
11th 53 30-Jan 43 20-Feb   6-Mar    
12th 53 30-Jan 46 20-Feb   6-Mar    
Total 619 586 409 352 358
MASONRY TO FINISHING WORKS
Living, Dining, Kitchen, & Bedroom
Plastering Pre-Cast Seismic Gap Sealant
Total No.
Floor Level
of Units Installed Stiffener Pre-Cast Installed
ETC Plastered ETC Pre-Cast column Sealant ETC Sealant

Ground 39 17-Oct 29 02-Sept 39 32

2nd 50 14-Nov 49 04-July 50 49


3rd 53 26-Sept 52 14-June 53 53 10 25
4th 53 17-Oct 50 24-Jul 53 37
5th 53 21-Nov 52 13-Aug 53 51 46 50

6th 53 2-Jan 28 22-Sept 24 10

7th 53 13-Feb 39 12-Oct 14


8th 53 13-Feb 19 01-Nov
9th 53 27-Mar 24 21-Nov
10th 53 27-Mar 14 11-Dec
11th 53 24-Apr 31-Dec
12th 53 24-Apr.
Total 619 356 286 232 56 75
MASONRY TO FINISHING WORKS
Living, Dining, Kitchen, & Bedroom
Tiling Works Ceiling Works/ Cladding
Total No.
Floor Level of Units Installed
ETC Tile Grouting ETC Framing Board Up

Ground 39 19-Dec 21-Nov 26

2nd 50 21-Nov 24-Oct 44

3rd 53 17-Oct 46 5 19-Sept 48 7


4th 53 28-Nov 2 7-Nov 25
5th 53 19-Dec 3 24-Oct 39

6th 53 30-Jan 5-Dec

7th 53 27-Feb 2-Jan

8th 53 27-Feb 2-Jan


9th 53 27-Mar 30-Jan
10th 53 27-Mar 30-Jan

11th 53 17-April 20-Feb

12th 53 17-April 17-April

Total 619 51 5 182 7


MASONRY TO FINISHING WORKS
Living, Dining, Kitchen, & Bedroom
Painting Works
Floor Total No.
Level of Units Wall
ETC
Skim coat Primary 1 2 final
Ground 39 23-Jan 9
2nd 50 26-Dec 5
3rd 53 19-Sept 25 25 5 5
4th 53 23-Jan
5th 53 20-Feb

6th 53 3-April

7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 39 25 5 5
MASONRY TO FINISHING WORKS
Living, Dining, Kitchen, & Bedroom
Painting Works
Floor Total No. Ceiling ( gypsum) Ceiling ( off-form)
Level of Units
ETC Skim Skim
Primary 1 2 final Primary 1 2 final
coat coat

Ground 39 23-Jan
2nd 50 26-Dec
3rd 53 19-Sept 5 5 5 5 5 5 5 5
4th 53 23-Jan
5th 53 20-Feb
6th 53 3-April
7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 5 5 5 5 5 5 5 5
MASONRY TO FINISHING WORKS
Balcony
Zoccalo CHB Membrane Waterproofing
Floor Total No.
Level of Units Installed Installed
ETC ETC ETC Installed Approved Topping
Zocalo CHB
Ground 39 5-Sept 28 26-Sept 18 26-Sept
2nd 50 29-Aug 47 12-Sept 50 24-Oct
3rd 53 29-Aug 53 12-Sept 53 5-Sept 53 53 53
4th 53 5-Sept 50 12-Sept 50 26-Sept 6 6 6
5th 53 29-Aug 53 19-Sept 50 07-Nov
6th 53 10-Oct 46 31-Oct 46 19-Dec
7th 53 21-Nov 2 12-Dec 30-Jan
8th 53 21-Nov 12-Dec 30-Jan
9th 53 26-Dec 23-Jan 13-Mar
10th 53 26-Dec 32 23-Jan 13-Mar
11th 53 30-Jan 20-Feb 10-Apr
12th 53 30-Jan 20-Feb 10-Apr
Total 619 279 267 59 59 59
MASONRY TO FINISHING WORKS
Balcony
Plastering Works Tiling Works
Floor Total No. of
Level Units Installed
ETC Plastered ETC Tiles Grouting

Ground 39 17-Oct 8 19-Dec

2nd 50 14-Nov 44 21-Nov

3rd 53 26-Sept 53 17-Oct 5

4th 53 17-Oct 47 28-Nov


5th 53 21-Nov 42 19-Dec

6th 53 2-Jan 33 30-Jan

7th 53 13-Feb 27-Feb

8th 53 13-Feb 27-Feb

9th 53 27-Mar 27-Mar

10th 53 27-Mar 27-Mar

11th 53 24-Apr 17-April

12th 53 24-Apr. 17-April


Total 619 227 5
MASONRY TO FINISHING WORKS
Balcony
Pipe chase cladding Steel railings
Floor Total No. of
Level Units
ETC Framing Board-up ETC Fabricated Installed

Ground 39 17-Oct 19-Dec


2nd 50 19-Sept 21-Nov
3rd 53 15-Aug 6 5 17-Oct 6 6
4th 53 22-Aug 28-Nov
5th 53 03-Oct 19-Dec

6th 53 14-Nov 30-Jan

7th 53 12-Dec 27-Feb


8th 53 12-Dec 27-Feb
9th 53 9-Jan 27-Mar
10th 53 9-Jan 27-Mar
11th 53 30-Jan 17-April
12th 53 13-Feb 17-April
Total 619 6 5 6 6
MASONRY TO FINISHING WORKS
Balcony
Painting Works
Floor Total No. Wall Ceiling & Cladding
Level of Units
ETC Skim Skim
Primary 1 2 final Primary 1 2 final
coat coat
Ground 39 23-Jan
2nd 50 26-Dec 21
3rd 53 19-Sept 28 28 5 5 5 5
4th 53 23-Jan 25
5th 53 20-Feb 19

6th 53 3-April

7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 93 28 5 5 5 5
MASONRY TO FINISHING WORKS
T&B
Zoccalo CHB Plastering Works
Floor Total No.
Level of Units Installed Installed Installed Groove
ETC ETC ETC Plastered
Zocalo CHB (150) CHB (100) Line

Ground 39 5-Sept 39 26-Sept 39 39 17-Oct 2


2nd 50 29-Aug 50 12-Sept 50 50 14-Nov
3rd 53 29-Aug 53 12-Sept 53 53 26-Sept 26 5
4th 53 5-Sept 53 12-Sept 52 52 17-Oct 2
5th 53 29-Aug 53 19-Sept 53 53 21-Nov 3

6th 53 10-Oct 53 31-Oct 53 53 2-Jan


7th 53 21-Nov 53 12-Dec 53 53 13-Feb
8th 53 21-Nov 53 12-Dec 53 53 13-Feb
9th 53 26-Dec 53 23-Jan 42 42 27-Mar
10th 53 26-Dec 53 23-Jan 28 28 27-Mar
11th 53 30-Jan 41 20-Feb 11 11 24-Apr
12th 53 30-Jan 26 20-Feb 3 3 24-Apr.
Total 619 580 490 490 33 5
MASONRY TO FINISHING WORKS
T&B
Lintel Beam Ceiling Works
Floor Level Total No. of Units
T&B
ETC Door ETC Framing Board Up

Ground 39 05-Sept 39 21-Nov


2nd 50 08-Aug 50 24-Oct
3rd 53 15-Aug 53 19-Sept 5 5
4th 53 22-Aug 53 7-Nov
5th 53 15-Aug 53 24-Oct
6th 53 26-Sept 46 5-Dec
7th 53 24-Oct 33 2-Jan
8th 53 24-Oct 26 2-Jan
9th 53 21-Nov  24 30-Jan
10th 53 21-Nov  24 30-Jan
11th 53 12-Dec   20-Feb
12th 53 12-Dec   17-April
Total 619 401 5 5
MASONRY TO FINISHING WORKS
T&B
Tiling Works Membrane Waterproofing
Floor Total No.
Level of Units Installed Installed Protective
ETC Grouting ETC Installed Approved
Floor Tiles Wall Tiles Topping

Ground 39 19-Dec 1 7 26-Sept 26 16 16


2nd 50 21-Nov 2 24-Oct 27 37 37
3rd 53 17-Oct 30 34 5 5-Sept 53 53 53
4th 53 28-Nov 3 3 26-Sept 53 44 44
5th 53 19-Dec 3 3 07-Nov 30 29 29
6th 53 30-Jan 19-Dec 12 12 12
7th 53 27-Feb 30-Jan
8th 53 27-Feb 30-Jan
9th 53 27-Mar 13-Mar
10th 53 27-Mar 13-Mar
11th 53 17-April 10-Apr
12th 53 17-April 10-Apr
Total 619 37 49 5 201 149 149
MASONRY TO FINISHING WORKS
T&B
Painting Works
Floor Total No. Wall Ceiling
Level of Units
ETC Skim Skim
Primer 1 2 Final Primer 1 2 Final
coat coat
Ground 39 23-Jan
2nd 50 26-Dec
3rd 53 19-Sept 5 5 5 5 5 5
4th 53 23-Jan
5th 53 20-Feb
6th 53 3-April
7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 5 5 5 5 5 5
PROGRESS PHOTOS
Ground Floor – Wing A

Unit Skimcoat at Unit

Hallway
PROGRESS PHOTOS
Ground Floor – Wing B

Rectification of Skimcoat at Unit


Hollow Tiles

Hallway
PROGRESS PHOTOS
Second Floor – Wing A

Installation of Unit
Partition

Hallway
PROGRESS PHOTOS
Second Floor – Wing B

Unit Plastering of Wall at


T&B

Hallway
PROGRESS PHOTOS
Third Floor – Wing A

Mock Up
Tile Grout at Unit

Hallway
PROGRESS PHOTOS
Third Floor – Wing B

Housekeeping

Hallway
PROGRESS PHOTOS
Fourth Floor – Wing A

Unit Skimcoat of Board Up

Hallway
PROGRESS PHOTOS
Fourth Floor – Wing B

Installation of Installation of Ceiling


Partition Framing

Hallway
PROGRESS PHOTOS
Fifth Floor – Wing A

Framing Installation of
Installation Partition

Hallway
PROGRESS PHOTOS
Fifth Floor – Wing B

Partition Installation Rectification of Door


Opening

Hallway
PROGRESS PHOTOS
Sixth Floor – Wing A

Floor Tiles Door & Window


Frame Installation

Hallway
PROGRESS PHOTOS
Sixth Floor – Wing B

Skimcoat at Unit Door & Window


Frame Installation

Hallway
PROGRESS PHOTOS
Seventh Floor – Wing A

Tiles at T&B Door & Window


Frame Installation

Hallway
PROGRESS PHOTOS
Seventh Floor – Wing B

Plastering of Wall Door & Window


@ T&B Frame Installation

Hallway
PROGRESS PHOTOS
Eight Floor – Wing A

Plastering at T&B Wall Waterproofing at


Balcony

Hallway
PROGRESS PHOTOS
Eight Floor – Wing B

Waterproofing at Plastering
Balcony

Hallway
PROGRESS PHOTOS
Ninth Floor – Wing A

Plastering of T&B Waterproofing at


Wall Balcony
Hallway
PROGRESS PHOTOS
Ninth Floor – Wing B

Installation of Precast
Tiles
Hallway
PROGRESS PHOTOS
Tenth Floor – Wing A

Formworks of Plastering of T&B


Lintel Beam Opening
Hallway
PROGRESS PHOTOS
Tenth Floor – Wing B

Rectified Waterproofing
Window Opening

Hallway
PROGRESS PHOTOS
Eleventh Floor – Wing A

Rectification of Main CHB Laying at


Door Opening Balcony

Hallway
PROGRESS PHOTOS
Eleventh Floor – Wing B

Waterproofing
Plastering of Wall

Hallway
PROGRESS PHOTOS
Twelfth Floor – Wing A

Plastering at Unit Door & Window


Opening
Hallway
PROGRESS PHOTOS
Twelfth Floor – Wing B

Unit Waterproofing

Hallway
MOCK-UP UNITS
MOCK-UNITS PROGRESS PHOTOS
M-01 : End Unit, Family Suite

Kitchen
Balcony Area
Bedroom 1

Bedroom 2
T&B
MOCK-UNITS PROGRESS PHOTOS
M-08 : Mid Unit, Family Suite

kitchen

Bedroom 2 Bedroom 1 Balcony Area


T&B
MOCK-UNITS PROGRESS PHOTOS
M-10 : Mid Unit, Family Suite

Kitchen Area

Bedroom 1 Bedroom 2 Balcony Area


T&B
MOCK-UNITS PROGRESS PHOTOS
M-09 :End Unit, Family Suite

Kitchen Area
Bedroom 1 Balcony

T&B Bedroom 2
MOCK-UNITS PROGRESS PHOTOS
M-06 : Mid Unit, Straight Cut

Kitchen Area

T&B
Bedroom Balcony Area
MEPF UPDATES
ELECTRICAL WORKS
OSM DELIVERY UPDATE (SUPPLY PACKAGES ONLY)
OSM DELIVERY MONITORING

Balance
Delivered Balance
Description GMQ Unit Requested to Date for from GMQ
Delivery
A B C D E F=D–E H=B-D
1 Rebar Grade 40
2 Rebar Grade 60
3 Cement
4 Copper Wires
5 Fire Rated Cables
6 Hallway Tiles
7 Unit Tiles
8 T&B Tiles
9 Balcony Tiles
10 Plumbing Fixtures
11 Kitchen Sink
OSM DELIVERY MONITORING

Balance
Delivered Balance
Description GMQ Unit Requested to Date for from GMQ
Delivery
A B C D E F=D–E H=B-D
12 Grease Trap
13
14
15
16
17
18
19
20
21
22
BILLING & CHANGE ORDER MONITORING
BILLING MONITORING
Contractor Billing Date of Date of Date of Date of COPA Date of actual Projected date of Remarks
# Initial Final Submissio Approval transmittal by release of cheque
Submission Submissio n to SMDC Notificaion contractor to
to ARInet n to CMD SMDC (standard +2.5
Arknet accounting weeks after
transmittal to
SMDC accounting)
21th CDC 9 03 May 11 May 11 May 11 May 2018 11 May 2018 29 May 2018 Released
2018 2018 2018
21th CDC 10 04 June 05 June 25 June 25 June 2018 25 June 2018 13 July 2018 Released
2018 2018 2018
21th CDC 11 02 July 2018 12 July 19 July 19 July 2018 19 July 2018 06 August 2018 Released
2018 2018
WORK AUTHORIZATION ORDER (WAO) MONITORING
Contractor WAO# Description Date of Initial Date of Date of Date of Remarks
Transmittal to Submission Submission to Submission to
ARKnet of final to ASYA SMDC
ARKnet
21th CDC SMFRB5- Additional cost due 01 Feb 2018 13 Feb 2018 20 Feb 2018 Transmitted to ASYA
21TH- to design revision.
CDC-001
CHANGE ORDER (CO) MONITORING
Contractor CO# Description Date of WAO Date of SMDC Remarks
Approval Routing

21th CDC SMFRB5- Additional cost due to


21TH-CDC- design revision.
001
NCN MONITORING
NCN MONITORING

Contractor Total No. of NCNs No. of Open No. of Closed Compliance Rate
to Date NCNs to Date NCNs to Date
21th CDC 113
Sincere
Irvine
Phases

Total
NCN MONITORING
Contractor NCN No. Description Date Issued Date Due Date Replied Remarks

Irvine Ncn-fp-001-18 No Manpower On Site January 29, 2018 February 5, 2018 February 5, 2018 Closed

Irvine Ncn-fp-002-18 Pouring Guard March 8, 2018 March 15, 2018 March 8, 2018 Closed

Irvine Ncn-fp-003-18 No Engineer On Site And Pipe Sleeve March 9, 2018 March 16, 2018 March 16, 2018 Closed
Works
Irvine Ncn-fp-004-18 Failed To Comply Submission Of Sample April 25, 2018 April 26, 2018 May 4, 2018 Closed
Board Of Fire Stop Sealant
Irvine Ncn-fp-005-18 Wrong Layout Of Branchline July 10, 2018 July 11, 2018 July 30, 2018 Closed

Irvine Ncn-fp-006-18 Still Not Complying With Wrong Layout July 17, 2018 July 18, 2018 July 30, 2018 Closed
Of Branchline

Sincere Ncn-b5-spl-001-18 Turn Over Of Sog Zone 1a 1b April 10, 2018 April 10, 2018 April 12, 2018 Closed

Sincere Ncn-b5-spl-002-18 Used Different Brand Of Pipes And May 3, 2018 May 5, 2018 May 5, 2018 Closed
Fittings

Sincere Ncn-b5-spl-031-18 Housekeeping May 29, 2018 May 29, 2018 May 30, 2018 Closed

Sincere Ncn-b5-spl-004-18 Improper Way Of Sleeving June 5, 2018 June 7, 2018 June 11, 2018 For Observation
RFI / SUBMITTAL MONITORING
RFI / SUBMITTAL MONITORING
Type of Orig. Revised
Item Reference No. & Description Document Commitment Commitment Remarks
Date Date
ISSUES AND CONCERNS
ISSUES AND CONCERNS
Orig. Revised
Item Original Concern Entity Commitment Commitment Remarks
Date Date
End of Report