Professional Documents
Culture Documents
PROJECT NAME
Owner :
INSERT PERSPECTIVE
External CM:
MEPF Updates
Manpower Loading
NCN Monitoring
Name of Project :
Location :
Brief Description :
Architectural Design :
Structrual Design :
Interior Design :
Electrical Design :
Mechanical Design :
Construction Manager : .
CONTRACTORS & SUPPLIERS
General Contractor
Civil, Structural & Architectural Works : .
MEPF Contractors
Electrical Works : .
Plumbing / Sanitary Works : .
Mechanical Works : .
Fire Protection Works : Other Trade Contractors
Landscape Works : TBD
Interior Fit-Out Works : TBD
Auxiliary Works (CCTV & FTTU) :
MEPF Equipment
Elevator System : .
Generator Set :
Sanitary / Fire Pro Pumps (Supply) : n
Blowers :
Ductless Exhaust Fan :
CONTRACTORS & SUPPLIERS
CSA OSM
Rebar (Supply) : Pag-Asa / Filipino Metal / Steel Asia
Cement (Supply) : Eirene Cement
Kitchen Countertop : Jamestone
Kitchen Cabinet : Graceline
Wooden Doors and Partition : Grand Nova Holdings Corp.
Aluminum Glass Doors and Windows : 21th Construction Devt. Corp.
Steel Doors : Metrotech
Hallway Tiles (Supply) : TJ&A Galleria
Unit Tiles (Supply) : Mariwasa
T&B Tiles (Supply) : Bestile Corp.
Balcony Tiles (Supply) : Multi-rich Home Decors
CONTRACTORS & SUPPLIERS
MEPF OSM
Kitchen Sink & Accessories (Supply) : Dynamic Brands Int’l.
Plumbing Fixtures (Supply) : Dynamic Brands Int’l.
Grease Trap (Supply) : Philglobal Asia
Fire Rated Cables (Supply) : Columbia Wires
Copper Wires (Supply) : London Industrial
Wiring Devices : Akari
PROJECT STATUS & MILESTONE DATES
PROJECT STATUS
: 52 Weeks
: 43.48%
PROJECT MILESTONES
ITEM DESCRIPTION MILESTONE DATE MILESTONE DATE
(TARGET) (ACTUAL)
1 Topping Off 08 August 2018
2 Mock-up units 16 August 2018
3 Watertightness October 2019
4 Elevator December 2018
5 Permanent Water 15 October 2018
6 Energization April 2019
7 Architectural Fit-out December 2019
8 Occupancy Permit December 2019
CONSOLIDATED ACCOMPLISHMENT
(Various Contractors & Suppliers)
Previous To Date
This Period
As of 26 July 2018 As of 01 Aug 2018
Actual
Projected
Variance
Days Ahead /
Delay
POC BREAKDOWN
Accomplishment
Wt
Item Description % Target Actual Variance
I CSA Works
II MEPF Works
Electrical Works
Plumbing and Sanitary with Minor
Mechanical Works
Fire Protection Works
III MEPF Equipment
Elevator System
Generator System
Sanitary / Fire Pro Pumps (Supply)
Blowers
Ductless Exhaust Fan
POC BREAKDOWN
Accomplishment
Wt
Item Description % Target Actual Variance
IV CSA OSM
Kitchen Cabinet
Kitchen Countertop
Aluminium Glass Doors and Windows
Steel Doors
Wooden Doors and Partition
Reinforcing Bars (Supply)
Cement in Bulk (Supply)
Hallway Tiles (Supply)
Unit Tiles (Supply)
T&B Tiles (Supply)
Balcony Tiles (Supply)
POC BREAKDOWN
Accomplishment
Wt
Item Description % Target Actual Variance
V MEPF OSM
Copper Wires (Supply)
Fire-Rated Cables (Supply)
Wiring Devices (Supply)
Plumbing Fixtures & Accessories (Supply)
Kitchen Sink & Accessories (Supply)
Grease Trap (Supply)
VI Other Trade Contracts
Landscape Works
Interior Fit-Out Works
CCTV Auxiliary Works
FTTU Auxiliary Works
G R A N D T OT A L
PROGRESS PHOTOS
ROOF BEAM
12
11
10
09
08
Insert Photo 07
06
05
04
03
02
Front Elevation
Before
As of 25 July 2018
PROGRESS PHOTOS
ROOF BEAM
12
11
10
09
08
Insert Photo 07
06
05
04
03
02
Front Elevation
After
As of 01 August 2018
PROGRESS PHOTOS
ROOF BEAM
12
11
10
09
08
07
06
05
04
03
02
Rear Elevation
Before
As of 25 July 2018
PROGRESS PHOTOS
ROOF BEAM
12
11
10
09
08
Insert Photo 07
06
05
04
03
02
Right Elevation
After
As of 01 August 2018
PROGRESS PHOTOS
ROOF BEAM
12
11
10
09
08
Insert Photo 07
06
05
04
03
02
Left Elevation
Before
As of 25 July 2018
PROGRESS PHOTOS
ROOF BEAM
12
11
10
09
08
Insert Photo 07
06
05
04
03
02
Left Elevation
After
As of 01 August 2018
CIVIL, STRUCTURAL, & ARCHITECTURAL WORKS UPDATE
PERCENTAGE OF ACCOMPLISHMENT (POC)
DIVISION 5 - METALS
5010 Metal Fabrication
Balcony Railing (25mm x 25mm pow der Coated Finish) 0.02574%
DIVISION 7 - FINISHES
7010 Floor Finishes
FF-3, 300mmx300mm CERAMIC Tiles w / Waterproofing Membrane measured
0.00407%
separately (Tiles OSM)
FF-7, 300mmx300mm RUSTIC Tiles w ith w aterproofing membrane measured
0.00297%
separately (Tiles OSM)
FF-11, 600mmx600mm Ceramic Tiles (Tiles OSM), 0.00554%
FF-13, 600mmx600mm Homogenous Tiles (Tiles OSM) 0.03927%
7020 Wall Finishes
WF-1, Plain Cement smooth painted Finish 0.13346%
WF-2, 300mmx300mm Homogenous Tiles (Tiles OSM) 0.01965%
WF-3, Elastomeric Waterproof Coating by UKUSA or SKK 0.03171%
WF-13, Plain Cement Finish 0.00761%
TOTAL 1.461%
LOOK AHEAD FOR NEXT WEEK
DIVISION 5 - METALS
5010 Metal Fabrication
Balcony Railing (25mm x 25mm pow der Coated Finish) 0.02574%
DIVISION 7 - FINISHES
7010 Floor Finishes
FF-3, 300mmx300mm CERAMIC Tiles w / Waterproofing Membrane measured
0.00407%
separately (Tiles OSM)
FF-7, 300mmx300mm RUSTIC Tiles w ith w aterproofing membrane measured
0.00297%
separately (Tiles OSM)
FF-11, 600mmx600mm Ceramic Tiles (Tiles OSM), 0.00554%
FF-13, 600mmx600mm Homogenous Tiles (Tiles OSM) 0.03927%
7020 Wall Finishes
WF-1, Plain Cement smooth painted Finish 0.13346%
WF-2, 300mmx300mm Homogenous Tiles (Tiles OSM) 0.01965%
WF-3, Elastomeric Waterproof Coating by UKUSA or SKK 0.03171%
WF-13, Plain Cement Finish 0.00761%
TOTAL 1.461%
STRUCTURAL UPDATES
STAIRS CONCRETING MONITORING
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
ROOF BEAM
12TH FLOOR
11TH FLOOR
10th FLOOR
9th FLOOR
8th FLOOR
7th FLOOR
6th FLOOR
5th FLOOR
4th FLOOR
3rd FLOOR
2nd FLOOR
1st FLOOR
FDN
Columns and Shearwalls at Roof Level Columns and Shearwalls at Lower Level
12th to Roof 27 May 2018 02 June 2018 07 June 2018 19 June 2018 20 June 2018
Slab - Ground floor 31 March 2018 05 April 2018 10 April 2018 06 May 2018 14 May 2018
2ND TO 12TH FLOOR BEAM & SLAB CONCRETING MONITORING
2nd Floor
2nd Floor Beam and Slab w/ Reinforcement 2nd Floor Beam and Slab Concreted
Slab - 2nd floor 30 November 2017 05 December 2017 10 December 2017 27 January 2018 07 February 2018
Roof Beams 14 June 2018 09 June 2018 14 June 2018 26 June 2018 27 June 2018
2.0. 2nd Floor 29-Aug 99.00% 12-Sept 99.00% 14-Nov 99.00% 30-Aug 100.00%
3.0. 3rd Floor 29-Aug 99.00% 12-Sept 99.00% 26-Sept 99.00% 30-Aug 100.00%
4.0. 4th Floor 5-Sept 99.00% 12-Sept 99.00% 17-Oct 96.50% 12-Sept 100.00%
5.0. 5th Floor 29-Aug 99.00% 19-Sept 99.00% 21-Nov 95.00% 30-Aug 100.00%
6.0. 6th Floor 10-Oct 99.00% 31-Oct 99.00% 2-Jan 81.50% 26-Sept 100.00%
7.0. 7th Floor 21-Nov 96.99% 12-Dec 99.00% 13-Feb 76.00% 10-Oct 100.00%
8.0. 8th Floor 21-Nov 92.50% 12-Dec 99.00% 13-Feb 63.50% 31-Oct 100.00%
9.0. 9th Floor 26-Dec 95.33% 23-Jan 97.38% 27-Mar 45.00% 21-Nov 100.00%
10.0. 10th Floor 26-Dec 93.35% 23-Jan 98.55% 27-Mar 35.00% 21-Nov 100.00%
11.0. 11th Floor 30-Jan 93.32% 20-Feb 92.71% 24-Apr 26.50% 2-Jan 90.50%
12.0. 12th Floor 30-Jan 92.33% 20-Feb 75.30% 24-Apr. 21.00% 25.00%
WETWORKS MATRIX SCHEDULE VS. ACCOMPLISHMENT
Wet Works
Item Level Pre-Cast Wall T&B Waterproofing Balcony Waterproofing
ETC To Date ETC To Date ETC To Date
1.0. Ground Floor 05-Sept 99.00% 26-Sept 100.00% 26-Sept
Actual
LEGEND: % Manpower Required per Week manpower
C M L
PROJECTED 100.00% 2 1
COMPLETED 96.60% 1 - 1 2
1ST WEEK Nov 29– Dec. 05 2.40% 2 2
2ND WEEK March 2019 1.00% 2 2
ZOCALO WORKS MONITORING
2nd Floor
Actual
LEGEND: % Manpower Required per Week manpower
C M L
PROJECTED 100.00% 2 1
COMPLETED 99.00%
ALIMAK AREA March 2019 1.00%
ZOCALO WORKS MONITORING
3rd Floor
Actual
LEGEND: % Manpower Required per Week Manpower
C M L C/L
PROJECTED 100.00% 2 1 1
COMPLETED 99.00% -
ALIMAK AREA March 2019 1.00%
ZOCALO WORKS MONITORING
5th Floor
6th 53 3-April
7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 39 25 5 5
MASONRY TO FINISHING WORKS
Living, Dining, Kitchen, & Bedroom
Painting Works
Floor Total No. Ceiling ( gypsum) Ceiling ( off-form)
Level of Units
ETC Skim Skim
Primary 1 2 final Primary 1 2 final
coat coat
Ground 39 23-Jan
2nd 50 26-Dec
3rd 53 19-Sept 5 5 5 5 5 5 5 5
4th 53 23-Jan
5th 53 20-Feb
6th 53 3-April
7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 5 5 5 5 5 5 5 5
MASONRY TO FINISHING WORKS
Balcony
Zoccalo CHB Membrane Waterproofing
Floor Total No.
Level of Units Installed Installed
ETC ETC ETC Installed Approved Topping
Zocalo CHB
Ground 39 5-Sept 28 26-Sept 18 26-Sept
2nd 50 29-Aug 47 12-Sept 50 24-Oct
3rd 53 29-Aug 53 12-Sept 53 5-Sept 53 53 53
4th 53 5-Sept 50 12-Sept 50 26-Sept 6 6 6
5th 53 29-Aug 53 19-Sept 50 07-Nov
6th 53 10-Oct 46 31-Oct 46 19-Dec
7th 53 21-Nov 2 12-Dec 30-Jan
8th 53 21-Nov 12-Dec 30-Jan
9th 53 26-Dec 23-Jan 13-Mar
10th 53 26-Dec 32 23-Jan 13-Mar
11th 53 30-Jan 20-Feb 10-Apr
12th 53 30-Jan 20-Feb 10-Apr
Total 619 279 267 59 59 59
MASONRY TO FINISHING WORKS
Balcony
Plastering Works Tiling Works
Floor Total No. of
Level Units Installed
ETC Plastered ETC Tiles Grouting
6th 53 3-April
7th 53 17-April
8th 53 17-April
9th 53 22-May
10th 53 22-May
11th 53 19-June
12th 53 19-June
Total 619 93 28 5 5 5 5
MASONRY TO FINISHING WORKS
T&B
Zoccalo CHB Plastering Works
Floor Total No.
Level of Units Installed Installed Installed Groove
ETC ETC ETC Plastered
Zocalo CHB (150) CHB (100) Line
Hallway
PROGRESS PHOTOS
Ground Floor – Wing B
Hallway
PROGRESS PHOTOS
Second Floor – Wing A
Installation of Unit
Partition
Hallway
PROGRESS PHOTOS
Second Floor – Wing B
Hallway
PROGRESS PHOTOS
Third Floor – Wing A
Mock Up
Tile Grout at Unit
Hallway
PROGRESS PHOTOS
Third Floor – Wing B
Housekeeping
Hallway
PROGRESS PHOTOS
Fourth Floor – Wing A
Hallway
PROGRESS PHOTOS
Fourth Floor – Wing B
Hallway
PROGRESS PHOTOS
Fifth Floor – Wing A
Framing Installation of
Installation Partition
Hallway
PROGRESS PHOTOS
Fifth Floor – Wing B
Hallway
PROGRESS PHOTOS
Sixth Floor – Wing A
Hallway
PROGRESS PHOTOS
Sixth Floor – Wing B
Hallway
PROGRESS PHOTOS
Seventh Floor – Wing A
Hallway
PROGRESS PHOTOS
Seventh Floor – Wing B
Hallway
PROGRESS PHOTOS
Eight Floor – Wing A
Hallway
PROGRESS PHOTOS
Eight Floor – Wing B
Waterproofing at Plastering
Balcony
Hallway
PROGRESS PHOTOS
Ninth Floor – Wing A
Installation of Precast
Tiles
Hallway
PROGRESS PHOTOS
Tenth Floor – Wing A
Rectified Waterproofing
Window Opening
Hallway
PROGRESS PHOTOS
Eleventh Floor – Wing A
Hallway
PROGRESS PHOTOS
Eleventh Floor – Wing B
Waterproofing
Plastering of Wall
Hallway
PROGRESS PHOTOS
Twelfth Floor – Wing A
Unit Waterproofing
Hallway
MOCK-UP UNITS
MOCK-UNITS PROGRESS PHOTOS
M-01 : End Unit, Family Suite
Kitchen
Balcony Area
Bedroom 1
Bedroom 2
T&B
MOCK-UNITS PROGRESS PHOTOS
M-08 : Mid Unit, Family Suite
kitchen
Kitchen Area
Kitchen Area
Bedroom 1 Balcony
T&B Bedroom 2
MOCK-UNITS PROGRESS PHOTOS
M-06 : Mid Unit, Straight Cut
Kitchen Area
T&B
Bedroom Balcony Area
MEPF UPDATES
ELECTRICAL WORKS
OSM DELIVERY UPDATE (SUPPLY PACKAGES ONLY)
OSM DELIVERY MONITORING
Balance
Delivered Balance
Description GMQ Unit Requested to Date for from GMQ
Delivery
A B C D E F=D–E H=B-D
1 Rebar Grade 40
2 Rebar Grade 60
3 Cement
4 Copper Wires
5 Fire Rated Cables
6 Hallway Tiles
7 Unit Tiles
8 T&B Tiles
9 Balcony Tiles
10 Plumbing Fixtures
11 Kitchen Sink
OSM DELIVERY MONITORING
Balance
Delivered Balance
Description GMQ Unit Requested to Date for from GMQ
Delivery
A B C D E F=D–E H=B-D
12 Grease Trap
13
14
15
16
17
18
19
20
21
22
BILLING & CHANGE ORDER MONITORING
BILLING MONITORING
Contractor Billing Date of Date of Date of Date of COPA Date of actual Projected date of Remarks
# Initial Final Submissio Approval transmittal by release of cheque
Submission Submissio n to SMDC Notificaion contractor to
to ARInet n to CMD SMDC (standard +2.5
Arknet accounting weeks after
transmittal to
SMDC accounting)
21th CDC 9 03 May 11 May 11 May 11 May 2018 11 May 2018 29 May 2018 Released
2018 2018 2018
21th CDC 10 04 June 05 June 25 June 25 June 2018 25 June 2018 13 July 2018 Released
2018 2018 2018
21th CDC 11 02 July 2018 12 July 19 July 19 July 2018 19 July 2018 06 August 2018 Released
2018 2018
WORK AUTHORIZATION ORDER (WAO) MONITORING
Contractor WAO# Description Date of Initial Date of Date of Date of Remarks
Transmittal to Submission Submission to Submission to
ARKnet of final to ASYA SMDC
ARKnet
21th CDC SMFRB5- Additional cost due 01 Feb 2018 13 Feb 2018 20 Feb 2018 Transmitted to ASYA
21TH- to design revision.
CDC-001
CHANGE ORDER (CO) MONITORING
Contractor CO# Description Date of WAO Date of SMDC Remarks
Approval Routing
Contractor Total No. of NCNs No. of Open No. of Closed Compliance Rate
to Date NCNs to Date NCNs to Date
21th CDC 113
Sincere
Irvine
Phases
Total
NCN MONITORING
Contractor NCN No. Description Date Issued Date Due Date Replied Remarks
Irvine Ncn-fp-001-18 No Manpower On Site January 29, 2018 February 5, 2018 February 5, 2018 Closed
Irvine Ncn-fp-002-18 Pouring Guard March 8, 2018 March 15, 2018 March 8, 2018 Closed
Irvine Ncn-fp-003-18 No Engineer On Site And Pipe Sleeve March 9, 2018 March 16, 2018 March 16, 2018 Closed
Works
Irvine Ncn-fp-004-18 Failed To Comply Submission Of Sample April 25, 2018 April 26, 2018 May 4, 2018 Closed
Board Of Fire Stop Sealant
Irvine Ncn-fp-005-18 Wrong Layout Of Branchline July 10, 2018 July 11, 2018 July 30, 2018 Closed
Irvine Ncn-fp-006-18 Still Not Complying With Wrong Layout July 17, 2018 July 18, 2018 July 30, 2018 Closed
Of Branchline
Sincere Ncn-b5-spl-001-18 Turn Over Of Sog Zone 1a 1b April 10, 2018 April 10, 2018 April 12, 2018 Closed
Sincere Ncn-b5-spl-002-18 Used Different Brand Of Pipes And May 3, 2018 May 5, 2018 May 5, 2018 Closed
Fittings
Sincere Ncn-b5-spl-031-18 Housekeeping May 29, 2018 May 29, 2018 May 30, 2018 Closed
Sincere Ncn-b5-spl-004-18 Improper Way Of Sleeving June 5, 2018 June 7, 2018 June 11, 2018 For Observation
RFI / SUBMITTAL MONITORING
RFI / SUBMITTAL MONITORING
Type of Orig. Revised
Item Reference No. & Description Document Commitment Commitment Remarks
Date Date
ISSUES AND CONCERNS
ISSUES AND CONCERNS
Orig. Revised
Item Original Concern Entity Commitment Commitment Remarks
Date Date
End of Report