S.NO Description
A GENERAL
Kick Off Meeting / Meetings 14.08.2018 (kick off) 23.08.2018 (Meeting at 04.10.2018 ( 25.10.2018 (at site) 27.11.2018 ( at office)
Client place)
B Vendor drawings
Both PH and AQC Boiler load data Approval 8/28/2018 8/28/2018 9/1/2018
IV TG Building
31.10.18 ( LVL +5.5M ,+11.0, 12.11.18 ( LVL +5.5M , 22.1.19 (comments send after
PH BOILER +16.0M& STAIRCASE +10.5, +16.0M 14.12.18 ( LVL +5.5M , +16.0M) confirmation recived from axis Duct
COMMENTED AND SEND COMMENTED AND SEND structure support)
STATUS PH AND AQC BOILER DUCT LAYOUT ENGINEERING
S.NO Description
22.11.18
27.11.18
Expansion joints 15.11.218 /29.11.18 11/30/2018
(M/sTurbovent)
(M /s Mahindra)
27.11.18 (M/s 29.11.2018
Slide Gates 11/22/2018 11/29/2018
anval) (M/s Hyquip
27.11.18 (M/s 29.11.2018
Rotary air locks 11/22/2018 11/29/2018
anval) (M/s Hyquip
Expansion belows 11/22/2018
NVT Comments on Offer Drawing Comment on
SJCL Comments LNV Clarified LNVT
V2 received Drawing
15.10.2018
(Regarding duct
LOL
10/11/2018 size,Temp.,MOC 10/22/2018 19.11.18 ###
& electrical
issue)
11/29/2018
11/30/2018
11/30/2018
STATUS OF SJCL WHR (MY HOME) PH AND AQC BOILER DUCT LAYOUT ENGINEERING
MY HOME POWER CONSULTANCY SERVICES LIMITED, PW-18-445, dated 01.08.2018
Dt:12.10.2018
S.NO Description Date Mail Sent (dt) Mail Received (dt) Remarks
I GENERAL
Kick Off Meeting 8/14/2018
Preliminary Duct layout GA drawings for PH 8/17/2018
& AQC Boiler
Visit the SJCL Site for Disscussing the
22.08.18 & Mr.Phaniraj Visit the site and collected the
Preliminary layout and further details 23.08.18 data
collecting purpose
Both PH and AQC Boiler load data received 8/28/2018 From M/s Nantong
M/s Nantong comment on Boiler load 8/31/2018 8/31/2018 Clarify those comments on same day
Final PH and AQC Boiler Load data 9/1/2018 From M/s Nantong
II PH Boiler
Client asked Duct Structure loads acting on 9/10/2018 Civil Person need Dead , live, wind and
Boiler slab@16.00mLVL siemic x,y z loads
Updated the Duct structure loads acting on 17.09.2018 Loads recievd from Mr.Ponselvan on
Boiler Slab @ 16.00mm lvl on GA (Revision-1) 17.09.18, same day updated and send
M/s SJCL Comments Updated with M/s SJCL meeting held on 4.10.18, Civil
Individual Floor plans and loads on existing 09.10.2018 and electrical comment raised, those
(Revision-2) points also updated and relased GA dwgs
Building for civil clearance.
Client asked Duct Structure loads acting on Civil Person need Deal , live, wind and
Boiler slab@8.00mLVL 9/10/2018 siemic x,y z loads
Updated the Duct structure loads acting on 18.09.2018 Loads recievd from Mr.Ponselvan on
Boiler Slab @ 16.00mm lvl on GA (Revision-1) 18.09.18, same day updated and send
PH Duct 3
AQC Duct 3
Fabrication drawing preparing
PH Duct 15
AQC Duct 15
Specification
Damper 3
Discharge Below 2
Rotary air lock 2
Slide gate 2
Chain Conveyor 2
STATUS OF DRAWINGS RECEIVED FROM AXIS CONSULATANT
mail Received
S.NO Description Comments send from LNV
From Axis
PH DUCT SUPPORT BASE PLATE Individual floor plant lvl, members are
DETAILS & REACTIONS AND 1/24/2019 not matching with elevation,
STRUCTURAL GA commented and send on 24.01.19
PH DUCT SUPPORT BASE PLATE
Check found ok , samething send to
DETAILS & REACTIONS AND 1/25/2019 Client for civil clearance.
STRUCTURAL GA
AQC
over telephone ask the FND details to
Boiler Foudation Details Received 12/4/2019 be match with Nantang and ask them
to send revised Dwg.
Revsied Boiler Foudation Details Load reaction and stadd cross check
showing Base plate hole, Bolts qty etc., 12/5/2019 with Axis and send samething to Client.
After checking the STADD, Mr.
Boiler duct Supporting structure FND
Detail on +8.00M LVL 12/7/2019 Ponuselvan send comments related lvl,
and load reaction etc.,on 7.12.19