CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Veracruz CPP Terminal Phase 2 - New Tanks, Me&I And Civil

Prepared for:

Vopak Terminal Veracruz


Veracruz, Mexico

Rev Date Description Originator Discipline PM


Checker Approval
P 07/23/2018 Issue for Internal Review TFRP GALR CHES
A 08/01/2018 Issue for Comments AFMR JARC CHES

PAGE 1 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

TABLE OF CONTENTS

1.0 OBJECTIVE .......................................................................................................................................... 3


2.0 SCOPE ................................................................................................................................................. 3
3.0 REFERENCE ......................................................................................................................................... 3
3.1 Reference Standards .............................................................................................................. 3
3.2 Reference Documents ............................................................................................................ 3
4.0 METHODOLOGY ................................................................................................................................. 3
5.0 CIVIL DATA .......................................................................................................................................... 4
6.0 DESIGN DATA, THICKNESS, WEIGHTS AND CAPACITIES..................................................................... 5
7.0 TANK CALCULATION ........................................................................................................................... 6

PAGE 2 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

1.0 OBJECTIVE

The objective of this document is to present the mechanical calculations of the atmospheric
vertical diesel storage tanks TK-8301/02/03 and atmospheric vertical gasoline storage tanks TK-
9101/02/03/04/05/06 for Vopak Terminal Veracruz for the project “VERACRUZ CPP’s PHASE 2”.

2.0 SCOPE

The Calculation report shows preliminary thickness, weights and dimensions calculated under
design conditions in accordance with data project (based on the data sheet and specifications) and
the API STANDARD 650.

3.0 REFERENCE

3.1 Reference Standards

 API 650 12a Ed. Welded Tanks for oil Storage


 API-2000 Venting Atmospheric and Low Pressure Storage Tanks

3.2 Reference Documents

 1045-BB1-ME-DS-001 Tanks data sheets


 1045-BB1-ME-SP-001 Diesel tanks specification
 1045-BB1-ME-SP-002 Gasoline tanks specification

4.0 METHODOLOGY

The development of calculations was made using the AMETank 7.7 program.

PAGE 3 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

5.0 CIVIL DATA

Seismic Spectrum Data:

Classification about its used A (API 650 equivalence, Seismic use Group II)
Seismic Site Class C (Very dense soil and soft rock with 360 m/s < Vs ≤ 760 m/s)

Wind Data:
Design Wind Velocity: 180 km/h
Hurrican area (gusts of wind of 270 km/h)

PAGE 4 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

6.0 DESIGN DATA, THICKNESS, WEIGHTS AND CAPACITIES

Tabla 1. SUMMARY RESULTS


Equipment TAG TK-8301/02/03 TK-9101/02/03/04/05/06

Product DIESEL GASOLINE

Specific Gravity 0.87 (For calculation 1) 0.7 (For calculation 1)


Bottom Slope -0.57 -0.57
Tank Inside Diameter [mm] 21170 23180
Tank Height [mm] 24380 24380
Design Press [Pa] ATM ATM
Operating Press [Pa] ATM ATM
Design Temperature [°C] 90 90
Operating Temp. [°C] 30 40
HHLL [mm] 23380 23380
HLL [mm] 22930 22930
NLL [mm] 22730 22730
LLL [mm] 1180 1180
3
Nominal capacity [m ] 7989 9557
3
Net Working Capacity [m ] (btw HLL &
7585 9094
LLL)
Empty Weight [kg] 222891 251536
Operation Weight [kg] 8213082.11 9831025.338
Hydrotest Weight [kg] 8628431.63 10328990.527
MAWP [kPa] 0.9331 0.8558
MAWV [kPa] -0.2442 0.4495
Roof Thickness [mm] A283M-C : 5 mm (0.1875 in) A283M-C : 5 mm (0.1875 in)
Shell Thickness [mm]
Shell (1) A283M-C : 22,225 mm (0.875 in) A283M-C : 22,225 mm (0.875 in)
Shell (2) A283M-C : 22.22 mm (0.875 in) A283M-C : 22.22 mm (0.875 in)
Shell (3) A283M-C : 17.4625 mm (0.6875 in) A283M-C : 17.4625 mm (0.6875 in)
Shell (4) A283M-C : 15.88 mm (0.625 in) A283M-C : 15.88 mm (0.625 in)
Shell (5) A283M-C : 14.2875 mm (0.5625 in) A283M-C : 14.2875 mm (0.5625 in)
Shell (6) A283M-C : 12.7 mm (0.5 in) A283M-C : 12.7 mm (0.5 in)
Shell (7) A283M-C : 9.53 mm (0.375 in) A283M-C : 9.53 mm (0.375 in)
Shell (8) A283M-C : 7.93 mm (0.3125 in) A283M-C : 7.93 mm (0.3125 in)
Shell (9) A283M-C : 6.35 mm (0.25 in) A283M-C : 6.35 mm (0.25 in)
Shell (10) A283M-C : 6.35 mm (0.25 in) A283M-C : 6.35 mm (0.25 in)
Bottom Thickness [mm] A283M-C : 8 mm (0.315 in) A283M-C : 8 mm (0.315 in)

PAGE 5 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

7.0 TANK CALCULATION

See Appendixes 1 and 2

PAGE 6 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Appendix 1 – Mechanical Calculation diesel tanks

PAGE 7 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

AMETANK REPORT
TABLE OF CONTENTS

SUMMARY OF DESIGN DATA AND REMARKS

ROOF DESIGN

ROOF SUMMARY OF RESULTS

SHELL COURSE DESIGN

SHELL SUMMARY OF RESULTS

BOTTOM DESIGN

BOTTOM SUMMARY OF RESULTS

WIND MOMENT

SEISMIC SITE GROUND MOTION

SEISMIC CALCULATIONS

ANCHOR BOLT DESIGN

ANCHOR BOLT SUMMARY OF RESULTS

CAPACITIES AND WEIGHTS

MAWP & MAWV SUMMARY


PAGE 8 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

No Warnings!!

SUMMARY OF DESIGN DATA AND REMARKS Back

Date of Calcs. : 23-Jul-2018


Mfg. or Insp. Date :
Designer : THOMAS
Project :
Tag Number :
Plant : PURCHASER DESCRIPTION CITY AND STATE
Plant Location : TERMICAL VERACRUZ
Site : VERACRUZ
Design Basis : API-650 12th Edition, March 2013

TANK NAMEPLATE INFORMATION

Pressure Combination Factor 0.4


Design Standard API-650 12th Edition, March 2013
Appendices Used E
Roof A283M-C : 5 mm
Shell (1) A283M-C : 22.225 mm
Shell (2) A283M-C : 22.225 mm
Shell (3) A283M-C : 17.4625 mm
Shell (4) A283M-C : 15.875 mm
Shell (5) A283M-C : 14.2875 mm
Shell (6) A283M-C : 12.7 mm
Shell (7) A283M-C : 9.525 mm
Shell (8) A283M-C : 7.93 mm
Shell (9) A283M-C : 6.35 mm
Shell (10) A283M-C : 6.35 mm
Bottom A283M-C : 8 mm

Design Internal Pressure = 0 KPa or 0 mmh2o


Design External Pressure = -0 KPa or -0 mmh2o

PAGE 9 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

MAWP = 0.9331 KPa or 95.1592 mmh2o


MAWV = -0.2442 KPa or -24.9079 mmh2o

D of Tank = 21.17 m
OD of Tank = 21.2145 m
ID of Tank = 21.17 m
CL of Tank = 21.1922 m
Shell Height = 24.38 m
S.G of Contents = 1
Max Liq. Level = 23.88 m
Min Liq. Level = 1.18 m
Design Temperature = 90 ºC
Tank Joint Efficiency = 1
Ground Snow Load = 0 KPa
Roof Live Load = 1 KPa
Additional Roof Dead Load = 1.9613 KPa
Basic Wind Velocity = 101.4 kph
Wind Importance Factor = 1

Using Seismic Method: API-650 - Site Specific

DESIGNER REMARKS

Remarks or Comments

PAGE 10 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

SUMMARY OF SHELL RESULTS

t-
Min min
CA Tensile Sd St t-min t-min t-
Shel Width Materia J Yield Weight Weight t-Des t-Test Ext- t-min Statu
(mm Strengt (MPa (MPa Erectio Seismi Actual
l# (mm) l E Strengt (N) CA (N) (mm) (mm) Pe (mm) s
) h (MPa) ) ) n (mm) c (mm) (mm)
h (MPa) (mm
)
2438. A283M- 276,88 257,09 19.444 15.883 19.444
1 1.59 1 205 380 137 154 6 14.0433 NA 22.225 OK
4 C 1 2 2 3 2
2438. A283M- 276,88 257,09 17.597 14.240 17.597
2 1.59 1 205 380 137 154 6 12.7559 NA 22.225 OK
4 C 1 2 9 8 9
2438. A283M- 217,59 197,80 15.751 12.598 15.751 17.462
3 1.59 1 205 380 137 154 6 11.261 NA OK
4 C 8 0 6 3 6 5
2438. A283M- 197,83 178,03 13.905 10.955 13.905
4 1.59 1 205 380 137 154 6 9.9166 NA 15.875 OK
4 C 1 0 3 8 3
2438. A283M- 178,06 158,25 14.287
5 1.59 1 205 380 137 154 6 12.059 9.3133 8.5815 NA 12.059 OK
4 C 2 8 5
2438. A283M- 158,28 138,48 10.212 10.212
6 1.59 1 205 380 137 154 6 7.6709 7.2588 NA 12.7 OK
4 C 9 2 7 7
2438. A283M- 118,73
7 1.59 1 205 380 137 154 98,921 6 8.3664 6.0284 5.8328 NA 8.3664 9.525 OK
4 C 4
2438. A283M-
8 1.59 1 205 380 137 154 98,859 79,043 6 6.5201 4.3859 4.5524 NA 6.5201 7.93 OK
4 C
2438. A283M-
9 1.59 1 205 380 137 154 79,168 59,349 6 4.6738 2.7434 3.3272 NA 6 6.35 OK
4 C
2434. A283M-
10 1.59 1 205 380 137 154 79,038 59,252 6 2.8275 1.1009 2.2874 NA 6 6.35 OK
4 C

Total Weight of Shell = 1,681,345.6907 N (171449.51 kg)

CONE ROOF

Plates Material = A283M-C


Structural Material = A36M
t.required = 5 mm
t.actual = 5 mm
Roof corrosion allowance = 0 mm
Roof Joint Efficiency = 1
Plates Overlap Weight = 15,619.9086 N (1592,78 kg)
Plates Weight = 135,606.5648 N (13828 kg)

PAGE 11 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RAFTERS:

Thru Rafters and Jack Rafters

Qty At Radius (m) Size Length (m) W (N/m) Ind. Weight (N) Total Weight (N)
22 10.585 W10X30 10.0053 437.8171 4,380.5128 96,371.2828
22 5.2956 W10X12 5.3403 175.1268 935.2435 20,575.3579

Rafters Total Weight = 116,946.6407 N (11925.23 kg)

GIRDERS:

Header Channel

Qty At Radius (m) Size Length (m) W (N/m) Ind. Weight (N) Total Weight (N)
22 5.2956 C4X5.4 1.2054 78.807 94.9987 2,089.9731

Girders Total Weight = 2,089.9731 N (213.11 kg)

COLUMNS:

Qty At Radius (m) Size Length (m) W (N/m) Ind. Weight (N) Total Weight (N)
1 5.2925 16" SCH STD 24.627 914.1156 22,510.6177 22,510.6177

Columns Total Weight = 22,510.6177 N (2295.44 kg)

Bottom Type : Cone-Up Bottom Floor

Bottom Material = A283M-C


t.required = 8 mm
t.actual = 8 mm
Bottom corrosion allowance = 2 mm
Bottom Joint Efficiency = 1
Total Weight of Bottom = 190,739.3848 N (19450 kg)

ANCHOR BOLT : (23) M30 mm UNC Bolts, A36M

PAGE 12 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

TOP END STIFFENER : Detail A

Size = l80x80x10
Material = A36M
Weight = 7,754.7971 N (790.768 kg)

STRUCTURALLY SUPPORTED CONICAL ROOF Back

A = Actual Part. Area of Roof-to-shell Juncture per API-650 (cm^2)


A-min = Minimum participating area (cm^2) per API-650 5.10.5.2
a-min-A = Minimum participating area due to full design pressure per API-650 F.5.1 (cm^2)
a-min-Roof = Minimum participating area per API-650 App. F.5.2 (cm^2)
Add-DL = Added Dead load (kPa)
Afr = Area of frangible roof (mm^2)
Alpha = 1/2 the included apex angle of cone (degrees)
Aroof = Contributing Area due to roof plates (cm^2)
Ashell = Contributing Area due to shell plates (cm^2)
CA = Roof corrosion allowance (mm)
D = Tank Nominal Diameter per API-650 5.6.1.1 Note 1 (m)
density = Density of roof (kg/mm3)
DL = Dead load (kPa)
DLR = Nominal weight of roof plate plus weight of roof plates overlap plus any attached structural (N)
DLs = Total weight of the shell and any framing (but not roof plates) supported by the shell and roof (N)
e.1b = Gravity Roof Load (1) - Balanced (kPa)
e.1u = Gravity Roof Load (1) - Unbalanced (kPa)
e.2b = Gravity Roof Load (2) - Balanced (kPa)
e.2u = Gravity Roof Load (2) - Unbalanced (kPa)
Fp = Pressure Combination Factor
Fy = smallest of the yield strength (MPa)
Fy-roof = Minimum yield strength for shell material (Table 5-2a) (MPa)
Fy-shell = Minimum yield strength for shell material (Table 5-2a) (MPa)
Fy-stiff = Minimum yield strength for stiffener material (Table 5-2a) (MPa)
hr = Roof height (m)
ID = Tank Inner Diameter (m)
Insulation = Roof Insulation (m)
JEr = Roof joint efficiency
Lr = Entered Roof Live Load (kPa)
Lr-1 = Computed Roof Live Load, including External Pressure
Max-p = Max Roof Load due to participating Area (kPa)
Net-Uplift = Uplift due to internal pressure minus nominal weight of shell, roof and attached framing (N), per API-
650 F.1.2
P = Minimum participating area (kPa)
P-ext-2 = Max external pressure due to roof shell joint area (kPa)
PAGE 13 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

P-F51 = Max design pressure reversing a-min-A calculation (kPa)


P-F6 = Calculated minimum failure pressure (kPa)
P-max-ext-T = Total max external pressure due to roof actual thickness and roof participating area (kPa)
P-max-internal = Maximum design pressure and test procedure per API-650 F.4, F.5. (kPa)
P-Std = Max pressure pressure allowed per API-650 App. F.1 & F.7 (kPa)
P-Uplift = Uplift case per API-650 1.1.1 (N)
P-weight = Dead load of roof plate (kPa)
Pe = External Pressure (kPa)
Pf-anchor = Failure pressure for anchor design (kPa)
pt = Roof cone pitch (mm) rise per 12 (mm)
Pv = Internal Pressure (kPa)
R = Roof horizontal radius (m)
Ra = Roof surface area (cm^2)
Roof-wc = Weight corroded of roof plates (N)
S = Ground Snow Load per ASCE 7-05 Fig 7-1 (kPa)
Sb = Balanced Design Snow Load per API-650 Section 5.2.1.h.1 (kPa)
Shell-wc = Weight corroded of shell (N)
Su = Unbalanced Design Snow Load per API-650 Section 5.2.1.h.2 (kPa)
T = Balanced Roof Design Load per API-650 Appendix R (kPa)
t-calc = Minimum nominal roof plates thickness per API-650 Section 5.10.5.1 (mm)
t-Ins = thickness of Roof Insulation (m)
Theta = Angle of cone to the horizontal (degrees)
U = Unbalanced Roof Design Load per API-650 Appendix R (kPa)
Wc = Maximum width of participating shell per API-650 Fig. F-2 (mm)
Wh = Maximum width of participating roof per API-650 Fig. F-2 (mm)

Roof Design Per API-650

Note: Tank Pressure Combination Factor Fp = 0.4

D = 21.17 m
ID = 21.17 m
CA = 0 mm
R = 10.585 m
Fp = 0.4
JEr = 1
JEs = 1
JEst = 1
Insulation = 0 m
Add-DL = 1.9613 kPa
Lr = 1 kPa
S = 0 kPa
PAGE 14 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sb = 0 kPa
Su = 0 kPa
density = 0.000007841 kg/mm3
P-weight = 0.3853 KPa
Pe = 0 kPa
pt = 0.75 mm rise per 12 mm
t-actual = 5 mm
Fy-roof = 205 MPa
Fy-shell = 205 MPa
Fy-stiff = 250 MPa
Shell-wc = 1,483,324.0111 N
Roof-wc = 135,606.5648 N
P-Std = 18 kPa, Per API-650 F.1.3
t-1 = 6.35 mm
CA-1 = 1.59 mm
Sd = 137 MPa

Theta = TAN^-1 (pt/12)


Theta = TAN^-1 (0.75/12)
Theta = 3.5763 degrees

Alpha = 90 - Theta
Alpha = 90 - 3.5763
Alpha = 86.4237 degrees

Ap-Vert = D^2 * TAN(Theta)/4


Ap-Vert = 21.17^2 * TAN(3.5763)/4
Ap-Vert = 7.0026 m^2

Horizontal Projected Area of Roof per API-650 5.2.1.f

Xw = D * 0.5
Xw = 21.17 * 0.5
Xw = 10.585 m

Ap = PI * (D/2)^2
Ap = PI * (21.17/2)^2
Ap = 351.991 m^2

DL = Insulation + P-weight + Add-DL


DL = 0 + 0.3853 + 1.9613
DL = 2.3466 kPa
PAGE 15 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Roof Loads per API-650 5.2.2

e.1b = DL + MAX(Sb , Lr) + (0.4 * Pe)


e.1b = 2.3466 + MAX(0 , 1) + (0.4 * 0)
e.1b = 3.3466 kPa

e.2b = DL + Pe + (0.4 * MAX(Sb , Lr))


e.2b = 2.3466 + 0 + (0.4 * MAX(0 , 1))
e.2b = 2.7466 kPa

T = MAX(e.1b , e.2b)
T = MAX(3.3466 , 2.7466)
T = 3.3466 kPa

e.1u = DL + MAX(Su , Lr) + (0.4 * Pe)


e.1u = 2.3466 + MAX(0 , 1) + (0.4 * 0)
e.1u = 3.3466 kPa

e.2u = DL + Pe + (0.4 * MAX(Su , Lr))


e.2u = 2.3466 + 0 + (0.4 * MAX(0 , 1))
e.2u = 2.7466 kPa

U = MAX(e.1u , e.2u)
U = MAX(3.3466 , 2.7466)
U = 3.3466 kPa

Lr-1 = MAX(T , U)
Lr-1 = MAX(3.3466 , 3.3466)
Lr-1 = 3.3466 kPa

Ra = PI * R * SQRT(R^2 + hr^2)
Ra = PI * 10.585 * SQRT(10.585^2 + 0.6616^2)
Ra = 3,526,778.4337 cm^2 or 352.6778 m^2

Roof Plates Weight = density * Ra * t-actual


Roof Plates Weight = 0.000007841 * 3,526,778.4337 * 5
Roof plates Weight = 135,606.5648 N (13828 kg)

PAGE 16 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

BAY 1 DETAILS

MINIMUM # OF RAFTERS

l = Maximum rafter spacing per API-650 5.10.4.4 (mm)


l-actual-1 = Actual rafter spacing (mm)
Max-T1-1 = Due to roof thickness (kPa)
N-actual-1 = Actual number of rafter
N-min-1 = Minimum number of rafter
P = Uniform pressure as determined from load combinations described in Appendix R (kPa)
P-ext-1-1 = Due to roof thickness vacuum limited by actual rafter spacing (kPa)
R-1 = Outer radius (mm)
RLoad-Max-1 = Maximun roof load based on actual rafter spacing (kPa)
t-calc-1 = Minimum roof thickness based on actual rafter spacing (mm)

FOR OUTER SHELL RING

P = Lr-1
P = 3.3466 kPa

R-1 = 10585 mm

l = MIN(((t-Roof - CA-Roof) * SQRT((1.5 * Fy-Roof)/P)) , 2100.0)


l = MIN(((5 - 0) * SQRT((1.5 * 205) / 3.3466)) , 2100)
l = MIN(1515.6244 , 2100)
l = 1515.6244 mm

N-min-1 = (2 * PI * R-1)/l
N-min-1 = (2 * PI * 10585)/1515.6244
N-min-1 = 44

N-min-1 must be a multiple of 1, therefore N-min-1 = 44.

N-actual-1 = 44

l-actual-1 = (2 * PI * R-1)/N-actual-1
l-actual-1 = (2 * PI * 10585)/44
l-actual-1 = 1511.5345 mm

PAGE 17 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Minimum roof thickness based on actual rafter spacing

t-calc-1 = l-actual-1/SQRT((1.5 * Fy-Roof)/P) + CA-Roof


t-calc-1 = 1511.5345/SQRT((1.5 * 205)/3.3466) + 0
t-calc-1 = 4.9865 mm

NOTE: Governs for roof plate thickness.

RLoad-Max-1 = (1.5 * Fy-Roof)/(l-actual-1/(t-Roof - CA-Roof))^2


RLoad-Max-1 = (1.5 * 205)/(1511.5345/(5 - 0))^2
RLoad-Max-1 = 3.3647 kPa

Max-T1-1 = RLoad-Max-1
Max-T1-1 = 3.3647 kPa

P-ext-1-1 = Max-T1-1 - DL - (0.4 * MAX(Sb , Lr))


P-ext-1-1 = 3.3647 - 2.3466 - (0.4 * MAX(0 , 1))
P-ext-1-1 = -0.6181 kPa

Pa-rafter-3-1 = P-ext-1-1
Pa-rafter-3-1 = -0.6181 kPa

t-required-1 = MAX(4.9865 , (5 + 0))


t-required-1 = 5 mm

RAFTER DESIGN

Average-p-width-1 = Average plate width (m)


Average-r-s-inner-1 = Average rafter spacing on inner girder (m)
Average-r-s-shell-1 = Average rafter spacing on shell (m)
Max-P-1 = Load allowed for each rafter in ring (MPa)
Max-r-span-1 = Maximum rafter span (m)
Max-T1-rafter-1 = Due to roof thickness (kPa)
Mmax-rafter-1 = Maximum moment bending (mm-kg)
P = Uniform pressure as determined from load combinations described in Appendix R (kPa)
P-ext-2-1 = Vacuum limited by rafter type (kPa)
R-1 = Outer radius (mm)
R-Inner-1 = Inner radius (m)
Rafter-Weight-1 = (Kg/m)
Sx-rafter-actual-1 = Actual elastic section modulus about the x axis (cm^3)

PAGE 18 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sx-rafter-Req'd-1 = Required elastic section modulus about the x axis (cm^3)


Theta = Angle of cone to the horizontal (degrees)
W-Max-rafter-1 = Maximum stress allowed for each rafter in ring (N/mm)
W-rafter-1 = (kg/m)

SPAN TO SHELL

P = 3.3466 kPa
Rafter-Weight-1 = 44.6449 Kg/m
Theta = 3.5763 degrees
R-1 = 10662 mm
R-Inner1 = 608 mm

Max-r-span-1 = (R-1 - R-Inner-1)/COS(Theta)


Max-r-span-1 = (10662 - 608)/COS(3.5763)
Max-r-span-1 = 10.0053 m

Average-r-s-inner-1 = (2 * PI * R-Inner-1)/N-actual-1
Average-r-s-inner-1 = (2 * PI * 608)/44
Average-r-s-inner-1 = 0.0868 m

Average-r-s-shell-1 = (2 * PI * R-1)/N-actual-1
Average-r-s-shell-1 = (2 * PI * 10662)/44
Average-r-s-shell-1 = 1.5225 m

Average-p-width-1 = (Average-r-s-inner-1 + Average-r-s-shell-1)/2


Average-p-width-1 = (0.0868 + 1.5225)/2
Average-p-width-1 = 0.8047 m

W-rafter-1 = (P * Average-p-width-1) + Rafter-Weight-1


W-rafter-1 = (341.3517 * 0.8047) + 44.6449
W-rafter-1 = 319.246 Kgf/m

Mmax-rafter-1 = (W-rafter-1 * Max-r-span-1^2)/8


Mmax-rafter-1 = (319.246 * 10.0053^2)/8
Mmax-rafter-1 = 3,994,846 mm-kgf

Sx-rafter-Req'd-1 = Mmax-rafter-1/Sd
Sx-rafter-Req'd-1 = 3,994,846/160
Sx-rafter-Req'd-1 = 244.8504 cm^3

PAGE 19 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sx-actual-1 = 530.9409 cm^3

W-Max-rafter-1 = (Sx-rafter-actual-1 * Sd * 8)/Max-r-span-1^2)


W-Max-rafter-1 = (530.9409 * 160 * 8)/10.0053^2)
W-Max-rafter-1 = 6.7887 N/mm

Max-P-1 = (W-Max-rafter-1 - Rafter-Weight-1)/Average-p-width-1


Max-P-1 = 0.0084 MPa

Max-T1-rafter-1 = Max-P-1
Max-T1-rafter-1 = 8.4 kPa

P-ext-2-1 = Max-T1-rafter-1 - DL - (Fp * MAX(S , Lr))


P-ext-2-1 = 8.4 - 2.3466 - (0.4 * MAX(0 , 1))
P-ext-2-1 = -5.6346 kPa

P2-rafter-3-1 = P-ext-2-1
P2-rafter-3-1 = -5.6346 kPa

Limited by rafter type

CENTER COLUMN

A-actual-1 = Actual area of column (mm^2)


A-req-1 = Required area of column (mm^2)
C-length-1 = Column length (mm)
E-c = Modulus of elasticity of the column material (MPa)
Fa-1 = Allowable compressive stress per API-650 5.10.3.4 (MPa)
Fy-c = Allowable design stress (MPa)
Max-P-column-1 = Maximum Load allowed for each column in ring (MPa)
Max-T1-column-1 = Due to roof thickness (kPa)
P-c-1 = Total roof load supported by each column (N)
P-ext-3-1 = Vacuum limited by column type (kPa)
Pa-column-3-1 = Vacuum limited by column type (kPa)
Pa-column-3-1 = Vacuum limited by column type (kPa)
R-c-1 = Per API-650 5.10.3.3
Radius-Gyr-1 = Radius of gyration
Radius-Gyr-req-1 = Radius of gyration required
W-column-1 = Total weight of column (N)
W-Max-column-1 = Maximum weight allowed for each column in ring (N)

W-column-1 = 22,510.6177 N
PAGE 20 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Fy-c = 241.3165 MPa


E-c = 197,190.0782 MPa
A-actual-1 = 118.7596 cm^2
C-length-1 = 24.627 m
Radius-Gyr-1 = 140.3165 mm

If C-length-1/Radius-Gyr-1 must be less than 180, then

Radius-Gyr-req-1 = C-length-1/180
Radius-Gyr-req-1 = 24.627/180
Radius-Gyr-req-1 = 136.8171 mm

Per API-650 5.10.3.3

R-c-1 = C-length-1/Radius-Gyr-1
R-c-1 = 24.627/140.3165
R-c-1 = 175.5109

Rafter-L-1 = (- R-1 - R-Inner1)/COS(Theta)


Rafter-L-1 = (- 10585 - 0)/COS(3.5763)
Rafter-L-1 = 10005 mm

P-c-1 = W-column-1 + (W-girder-1 * Girder-Length-1)


P-c-1 = 22,510.6177 + (0 * 0)
P-c-1 = 22,510.6177 N

Since R-c-1 > 120, using API-650 Formulas in 5.10.3.4

Fa-1 = (/ (* 12 (EXPT PI 2) E-c) (* 23 (EXPT R-c-1 2)))


Fa-1 = (/ (* 12 (EXPT PI 2) 197,190.0782) (* 23 (EXPT 175.5109 2)))

Per API-650 M.3.5


Fa is not modified Since Design Temp. <= 93.3333 ºC.
(API-650 M.3.5 N.A.)

Fa-1 = 45.6273 MPa

A-req-1 = P-c-1/Fa-1
A-req-1 = 22,510.6177/45.6273
A-req-1 = 493.3584 mm^2
PAGE 21 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

W-Max-column-1 = (Fa-1 * A-actual-1) - W-column-1


W-Max-column-1 = (45.6273 * 118.7596) - 22,510.6177
W-Max-column-1 = 539,572.5236 N

Max-P-column-1 = ((W-Max-column-1/((Rafter-L-1 * N-actual-1)/2)) - Rafter-Weight-1)/(AVERAGE Average-r-s-


inner-1 , Average-r-s-shell-1)
Max-P-column-1 = ((539,572.5236/((10005 * 44)/2)) - 44.6449)/(AVERAGE 0 , 1.5115)
Max-P-column-1 = 0.003 MPa

Max-T1-column-1 = Max-P-column-1
Max-T1-column-1 = 3 kPa

P-ext-3-1 = Max-T1-column-1 - DL - (Fp * MAX(S , Lr))


P-ext-3-1 = 3 - 2.3466 - (0.4 * MAX(0 , 1))
P-ext-3-1 = -0.2442 kPa

Pa-column-3-1 = P-ext-3-1
Pa-column-3-1 = -0.2442 kPa

Limited by column type

P-max-ext-T = MAX(P-ext-1-1 , P-ext-2-1 , P-ext-3-1)


P-max-ext-T = MAX(-0.6181 , -5.6346 , -0.2442)
P-max-ext-T = -0.2442 kPa

TOP MEMBER DESIGN


CA_roof (Thickness of roof plate) = 0 mm
CA_shell (Thickness of shell plate) = 1.59 mm
D (Shell nominal diameter) = 21.1922 m
ID (Shell inside diameter) = 21.17 m
Theta angle (Angle between the roof and a horizontal plane at the roof-to-shell junction) = 3.5763 deg
tc (Thickness of shell plate) = 6.35 mm
th (Thickness of roof plate) = 5 mm

Shell inside radius


Rc = ID / 2 = 21170.0 / 2 = 10585.0 mm

Shell nominal diameter (D) = 21.1922 m

Length of normal to roof


R2 = Rc / SIN(Theta angle) = 10585.0 / SIN(3.5763) = 169690.4589 mm
PAGE 22 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Thickness of corroded roof plate


th_corroded = th - CA_roof = 5 - 0 = 5 mm

Thickness of corroded shell plate


tc_corroded = tc - CA_shell = 6.35 - 1.59 = 4.76 mm

Maximum width of participating roof API-650 Figure F-2


Wh = MIN((0.3 * SQRT((R2 * th_corroded))) , 300)
= MIN((0.3 * SQRT((169690.4589 * 5))) , 300)
= 276.3344 mm

Maximum width of participating shell API-650 Figure F-2


Wc = 0.6 * SQRT((Rc * tc_corroded)) = 0.6 * SQRT((10585.0 * 4.76)) = 134.6791 mm

Nominal weight of shell plates and framing


DLS = Ws + W_framing = 1.6813456908E6 + 66056.2431 = 1.7474019339E6 N

Nominal weight of roof plates and attached structural


DLR = Wr + W_structural = 135606.5648 + 15474.7835 = 151081.3483 N

Compression Ring Detail a Properties

ID (Shell inside diameter) = 21.17 m


Size (Compression ring size) = l80x80x10
Wc (Length of contributing shell) = 134.6791 mm
Wh (Length of contributing roof) = 276.3344 mm
tc (Thickness of shell plate) = 4.76 mm
th (Thickness of roof plate) = 5 mm

Angle vertical leg size (l_vert) = 80 mm


Angle horizontal leg size (l_horz) = 80 mm
Angle thickness (t_angle) = 10.0 mm
Angle area (A_angle) = 1510.0 mm^2
Angle centroid (c_angle) = 23.4 mm
Angle moment of inertia (I_angle) = 875000.0 mm^4

Contributing shell moment of inertia


I_shell = (Wc * (tc_corroded^3)) / 12
= (134.6791 * (4.76^3)) / 12
= 1210.4303 mm^4

Contributing shell area


A_shell = Wc * tc_corroded = 134.6791 * 4.76 = 641.0724 mm^2
PAGE 23 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Contributing roof area


A_roof = Wh * th_corroded = 276.3344 * 5 = 1381.6721 mm^2

Detail total area


A_detail = A_shell + A_roof + A_angle
= 641.0724 + 1381.6721 + 1510.0
= 3532.7445 mm^2

Find combined moment of inertia about shell inside axis with negative value toward center

Description Variable Equation Value Unit


Shell centroid d_shell tc_corroded / 2 2.3800 mm
Stiffener centroid d_stiff c_angle + tc_corroded 28.1600 mm
moment of inertia of
I_1 I_angle + (A_angle * (d_stiff^2)) 2072408.2560 mm^4
first body
moment of inertia of
I_2 I_shell + (A_shell * (d_shell^2)) 4841.7210 mm^4
second body
Total area A_sum A_angle + A_shell 2151.0724 mm^2
Sum of moments of
I_sum I_1 + I_2 2077249.9770 mm^4
inertia's
((d_stiff * A_angle) + (d_shell *
Combined centroid c_combined 20.4769 mm
A_shell)) / (A_angle + A_shell)
Combined moment of I_sum - (A_sum *
I_combined 1175295.5779 mm^4
inertia (c_combined^2))
Distance from neutral
e1 c_combined 20.4769 mm
axis to edge 1 (inside)
Distance from neutral
e2 (tc_corroded + l_horz) - e1 64.2831 mm
axis to edge 2 (outside)
Combined stiffener
S I_combined / MAX(e1 , e2) 18283.1267 mm^3
shell section modulus

PAGE 24 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Roof Design Requirements

Compression region maximum area for frangible roof API-650 5.10.2.6 a) 5)


Afr = DLS / (2 * pi * Fy * TAN(Theta angle))
= 1.7474019339E6 / (2 * pi * 205 * TAN(3.5763))
= 21705.9633 mm^2

A_actual < Afr ==> Compression region actual cross sectional area is within the limit

Appendix F Requirements

A_actual (Area resisting compressive force) = 3532.7445 mm^2


D (Tank nominal diameter) = 21.1922 m
DLR (Nominal weight of roof plates and attached structural) = 151081.3483 N
DLS (Nominal weight of shell plates and framing) = 1.7474019339E6 N
Fy (Minimum specified yield-strength of the materials in the roof-to-shell junction) = 205 MPa
ID (Tank inside diameter) = 21.17 m
Mw (Wind moment) = 3.0691874815E6 N.m
P (Design pressure) = 0.0 kPa
Theta angle (Angle between the roof and a horizontal plane at the roof-to-shell junction) = 3.5763 deg
W_framing (Weight of framing supported by the shell and roof) = 66056.2431 N
W_structural (Weight of roof attached structural) = 15474.7835 N
Wr (Roof plates weight) = 135606.5648 N
Ws (Shell plates weight) = 1.6813456908E6 N

Uplift due to internal pressure API-650 F.1.2


P_uplift = P * pi * ((ID^2) / 4) = 0.0 * pi * ((21.17^2) / 4) = 0.0 N

Tank design does not have to meet App. F requirements.

Maximum design pressure API 650 F.4.1


P_F41 = ((A_actual * Fy * TAN(Theta angle)) / (200 * (D^2))) + ((0.00127 * DLR) / (D^2))
= ((3532.7445 * 205 * TAN(3.5763)) / (200 * (21.1922^2))) + ((0.00127 * 151081.3483) / (21.1922^2))
= 0.9312 kPa

Failure pressure for frangible roof API 650 F.6


P_F6 = (1.6 * P_F41) - ((0.000746 * DLR) / (D^2))
= (1.6 * 0.9312) - ((0.000746 * 151081.3483) / (21.1922^2))
= 1.2389 kPa

Maximum design pressure API 650 F.4.3


P_F43 = 0.8 * P_F6 = 0.8 * 1.2389 = 0.9911 kPa
PAGE 25 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Maximum design pressure


P_max = MIN(P_F41 , P_F43) = MIN(0.9312 , 0.9911) = 0.9312 kPa

P <= P_max ==> Design pressure is less than maximum allowable pressure

Maximum allowable internal pressure


P_max_internal = MIN(P_std , P_max) = MIN(18 , 0.9312) = 0.9312 kPa

SUMMARY OF ROOF RESULTS Back

Material = A283M-C
Structural Material = A36M
t-actual = 5 mm
t-required = 5 mm
t-calc = 4.9865 mm
P-Max-Internal = 0.9312 kPa
P-Max-External = -0.2442 kPa
Roof Plates Weight = 135,606.5648 N (13828 kg)
Weight of Rafters = 116,946.6407 N (11925.236 kg)
Weight of Girders = 2,089.9731 N (213.117 kg)
Weight of Columns = 22,510.6177 N (2295.44 kg)

SHELL COURSE DESIGN (Bottom course is #1) Back

API-650 ONE FOOT METHOD

D = Tank Nominal diameter (m) per API-650 5.6.1.1 Note 1


H = Max liquid level (m)
I-p = Design internal pressure (kPa)
L = Factor
I-p = 0 kPa
D = 21.17 m
H = 23.88 m
L = (500 * D (t-1 - Ca-1))^0.5
L = (500 * 21.17 (22.225 - 1.59))^0.5 = 467.3558

Course # 1

Ca-1 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
PAGE 26 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

H' = Effective liquid head at design pressure (m)


hmax-1 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-1 = Max pressure at design (kPa)
pmax-int-shell-1 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-1 = Shell actual thickness (mm)
t-calc-1 = Shell thickness design condition td (mm)
t-seismic-1 = See E.6.2.4 table in SEISMIC calculations.
t-test-1 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-1 = 1.59 mm
JE = 1
t-1 = 22.225 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 23.88
H' = 23.88 m

t-calc-1 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-1 (per API-650 5.6.3.2)


t-calc-1 = (4.9 * 21.17 * (23.88 - 0.3) * 1)/137 + 1.59
t-calc-1 = 19.4442 mm

hmax-1 = Sd * (t-1 - CA-1)/(2.6 * D * G) + 1


hmax-1 = 137 * (22.225 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-1 = 27.5511 m

pmax-1 = (hmax-1 - H) * 9.8 * G


pmax-1 = (27.5511 - 23.88) * 9.8 * 1
pmax-1 = 35.9771 kPa

pmax-int-shell-1 = pmax-1
pmax-int-shell-1 = 35.9771 kPa

PAGE 27 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Hydrostatic Test Condition G = 1

H' = H
H' = 23.88
H' = 23.88 m

t-test-1 = (* 4.9 D (H' - 0.3))/St


t-test-1 = (* 4.9 21.17 (23.88 - 0.3))/154
t-test-1 = 15.8833 mm

Course # 2

Ca-2 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-2 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-2 = Max pressure at design (kPa)
pmax-int-shell-2 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-2 = Shell actual thickness (mm)
t-calc-2 = Shell thickness design condition td (mm)
t-seismic-2 = See E.6.2.4 table in SEISMIC calculations.
t-test-2 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-2 = 1.59 mm
JE = 1
t-2 = 22.225 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 21.4416
H' = 21.4416 m

t-calc-2 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-2 (per API-650 5.6.3.2)


t-calc-2 = (4.9 * 21.17 * (21.4416 - 0.3) * 1)/137 + 1.59
PAGE 28 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-calc-2 = 17.5979 mm

hmax-2 = Sd * (t-2 - CA-2)/(2.6 * D * G) + 1


hmax-2 = 137 * (22.225 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-2 = 27.5511 m

pmax-2 = (hmax-2 - H) * 9.8 * G


pmax-2 = (27.5511 - 21.4416) * 9.8 * 1
pmax-2 = 59.8734 kPa

pmax-int-shell-2 = MIN(pmax-int-shell-1 pmax-2)


pmax-int-shell-2 = MIN(35.9771 59.8734)
pmax-int-shell-2 = 35.9771 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 21.4416
H' = 21.4416 m

t-test-2 = (* 4.9 D (H' - 0.3))/St


t-test-2 = (* 4.9 21.17 (21.4416 - 0.3))/154
t-test-2 = 14.2408 mm

Course # 3

Ca-3 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-3 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-3 = Max pressure at design (kPa)
pmax-int-shell-3 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-3 = Shell actual thickness (mm)
t-calc-3 = Shell thickness design condition td (mm)
t-seismic-3 = See E.6.2.4 table in SEISMIC calculations.
t-test-3 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
PAGE 29 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Ca-3 = 1.59 mm
JE = 1
t-3 = 17.4625 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 19.0032
H' = 19.0032 m

t-calc-3 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-3 (per API-650 5.6.3.2)


t-calc-3 = (4.9 * 21.17 * (19.0032 - 0.3) * 1)/137 + 1.59
t-calc-3 = 15.7516 mm

hmax-3 = Sd * (t-3 - CA-3)/(2.6 * D * G) + 1


hmax-3 = 137 * (17.4625 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-3 = 21.2628 m

pmax-3 = (hmax-3 - H) * 9.8 * G


pmax-3 = (21.2628 - 19.0032) * 9.8 * 1
pmax-3 = 22.1436 kPa

pmax-int-shell-3 = MIN(pmax-int-shell-2 pmax-3)


pmax-int-shell-3 = MIN(35.9771 22.1436)
pmax-int-shell-3 = 22.1436 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 19.0032
H' = 19.0032 m

t-test-3 = (* 4.9 D (H' - 0.3))/St


t-test-3 = (* 4.9 21.17 (19.0032 - 0.3))/154
t-test-3 = 12.5983 mm

Course # 4

Ca-4 = Corrosion allowance per API-650 5.3.2 (mm)


PAGE 30 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

G = Design specific gravity of the liquid to be stored


H' = Effective liquid head at design pressure (m)
hmax-4 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-4 = Max pressure at design (kPa)
pmax-int-shell-4 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-4 = Shell actual thickness (mm)
t-calc-4 = Shell thickness design condition td (mm)
t-seismic-4 = See E.6.2.4 table in SEISMIC calculations.
t-test-4 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-4 = 1.59 mm
JE = 1
t-4 = 15.875 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 16.5648
H' = 16.5648 m

t-calc-4 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-4 (per API-650 5.6.3.2)


t-calc-4 = (4.9 * 21.17 * (16.5648 - 0.3) * 1)/137 + 1.59
t-calc-4 = 13.9053 mm

hmax-4 = Sd * (t-4 - CA-4)/(2.6 * D * G) + 1


hmax-4 = 137 * (15.875 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-4 = 19.1666 m

pmax-4 = (hmax-4 - H) * 9.8 * G


pmax-4 = (19.1666 - 16.5648) * 9.8 * 1
pmax-4 = 25.4979 kPa

pmax-int-shell-4 = MIN(pmax-int-shell-3 pmax-4)


pmax-int-shell-4 = MIN(22.1436 25.4979)
pmax-int-shell-4 = 22.1436 kPa
PAGE 31 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Hydrostatic Test Condition G = 1

H' = H
H' = 16.5648
H' = 16.5648 m

t-test-4 = (* 4.9 D (H' - 0.3))/St


t-test-4 = (* 4.9 21.17 (16.5648 - 0.3))/154
t-test-4 = 10.9558 mm

Course # 5

Ca-5 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-5 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-5 = Max pressure at design (kPa)
pmax-int-shell-5 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-5 = Shell actual thickness (mm)
t-calc-5 = Shell thickness design condition td (mm)
t-seismic-5 = See E.6.2.4 table in SEISMIC calculations.
t-test-5 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-5 = 1.59 mm
JE = 1
t-5 = 14.2875 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 14.1264
H' = 14.1264 m

t-calc-5 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-5 (per API-650 5.6.3.2)


PAGE 32 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-calc-5 = (4.9 * 21.17 * (14.1264 - 0.3) * 1)/137 + 1.59


t-calc-5 = 12.059 mm

hmax-5 = Sd * (t-5 - CA-5)/(2.6 * D * G) + 1


hmax-5 = 137 * (14.2875 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-5 = 17.0705 m

pmax-5 = (hmax-5 - H) * 9.8 * G


pmax-5 = (17.0705 - 14.1264) * 9.8 * 1
pmax-5 = 28.8522 kPa

pmax-int-shell-5 = MIN(pmax-int-shell-4 pmax-5)


pmax-int-shell-5 = MIN(22.1436 28.8522)
pmax-int-shell-5 = 22.1436 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 14.1264
H' = 14.1264 m

t-test-5 = (* 4.9 D (H' - 0.3))/St


t-test-5 = (* 4.9 21.17 (14.1264 - 0.3))/154
t-test-5 = 9.3133 mm

Course # 6

Ca-6 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-6 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-6 = Max pressure at design (kPa)
pmax-int-shell-6 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-6 = Shell actual thickness (mm)
t-calc-6 = Shell thickness design condition td (mm)
t-seismic-6 = See E.6.2.4 table in SEISMIC calculations.
t-test-6 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
PAGE 33 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Width = 2.4384 m
Ca-6 = 1.59 mm
JE = 1
t-6 = 12.7 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 11.688
H' = 11.688 m

t-calc-6 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-6 (per API-650 5.6.3.2)


t-calc-6 = (4.9 * 21.17 * (11.688 - 0.3) * 1)/137 + 1.59
t-calc-6 = 10.2127 mm

hmax-6 = Sd * (t-6 - CA-6)/(2.6 * D * G) + 1


hmax-6 = 137 * (12.7 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-6 = 14.9744 m

pmax-6 = (hmax-6 - H) * 9.8 * G


pmax-6 = (14.9744 - 11.688) * 9.8 * 1
pmax-6 = 32.2065 kPa

pmax-int-shell-6 = MIN(pmax-int-shell-5 pmax-6)


pmax-int-shell-6 = MIN(22.1436 32.2065)
pmax-int-shell-6 = 22.1436 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 11.688
H' = 11.688 m

t-test-6 = (* 4.9 D (H' - 0.3))/St


t-test-6 = (* 4.9 21.17 (11.688 - 0.3))/154
t-test-6 = 7.6709 mm

PAGE 34 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Course # 7

Ca-7 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-7 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-7 = Max pressure at design (kPa)
pmax-int-shell-7 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-7 = Shell actual thickness (mm)
t-calc-7 = Shell thickness design condition td (mm)
t-seismic-7 = See E.6.2.4 table in SEISMIC calculations.
t-test-7 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-7 = 1.59 mm
JE = 1
t-7 = 9.525 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 9.2496
H' = 9.2496 m

t-calc-7 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-7 (per API-650 5.6.3.2)


t-calc-7 = (4.9 * 21.17 * (9.2496 - 0.3) * 1)/137 + 1.59
t-calc-7 = 8.3664 mm

hmax-7 = Sd * (t-7 - CA-7)/(2.6 * D * G) + 1


hmax-7 = 137 * (9.525 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-7 = 10.7821 m

pmax-7 = (hmax-7 - H) * 9.8 * G


pmax-7 = (10.7821 - 9.2496) * 9.8 * 1
pmax-7 = 15.0188 kPa
PAGE 35 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

pmax-int-shell-7 = MIN(pmax-int-shell-6 pmax-7)


pmax-int-shell-7 = MIN(22.1436 15.0188)
pmax-int-shell-7 = 15.0188 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 9.2496
H' = 9.2496 m

t-test-7 = (* 4.9 D (H' - 0.3))/St


t-test-7 = (* 4.9 21.17 (9.2496 - 0.3))/154
t-test-7 = 6.0284 mm

Course # 8

Ca-8 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-8 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-8 = Max pressure at design (kPa)
pmax-int-shell-8 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-8 = Shell actual thickness (mm)
t-calc-8 = Shell thickness design condition td (mm)
t-seismic-8 = See E.6.2.4 table in SEISMIC calculations.
t-test-8 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-8 = 1.59 mm
JE = 1
t-8 = 7.93 mm
Sd = 137 MPa
St = 154 MPa

PAGE 36 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Design Condition G = 1 (per API-650)

H' = H
H' = 6.8112
H' = 6.8112 m

t-calc-8 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-8 (per API-650 5.6.3.2)


t-calc-8 = (4.9 * 21.17 * (6.8112 - 0.3) * 1)/137 + 1.59
t-calc-8 = 6.5201 mm

hmax-8 = Sd * (t-8 - CA-8)/(2.6 * D * G) + 1


hmax-8 = 137 * (7.93 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-8 = 8.6761 m

pmax-8 = (hmax-8 - H) * 9.8 * G


pmax-8 = (8.6761 - 6.8112) * 9.8 * 1
pmax-8 = 18.276 kPa

pmax-int-shell-8 = MIN(pmax-int-shell-7 pmax-8)


pmax-int-shell-8 = MIN(15.0188 18.276)
pmax-int-shell-8 = 15.0188 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 6.8112
H' = 6.8112 m

t-test-8 = (* 4.9 D (H' - 0.3))/St


t-test-8 = (* 4.9 21.17 (6.8112 - 0.3))/154
t-test-8 = 4.3859 mm

Course # 9

Ca-9 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-9 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-9 = Max pressure at design (kPa)
pmax-int-shell-9 = Max internal pressure at design (kPa)

PAGE 37 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-9 = Shell actual thickness (mm)
t-calc-9 = Shell thickness design condition td (mm)
t-seismic-9 = See E.6.2.4 table in SEISMIC calculations.
t-test-9 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-9 = 1.59 mm
JE = 1
t-9 = 6.35 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 4.3728
H' = 4.3728 m

t-calc-9 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-9 (per API-650 5.6.3.2)


t-calc-9 = (4.9 * 21.17 * (4.3728 - 0.3) * 1)/137 + 1.59
t-calc-9 = 4.6738 mm

hmax-9 = Sd * (t-9 - CA-9)/(2.6 * D * G) + 1


hmax-9 = 137 * (6.35 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-9 = 6.5899 m

pmax-9 = (hmax-9 - H) * 9.8 * G


pmax-9 = (6.5899 - 4.3728) * 9.8 * 1
pmax-9 = 21.7273 kPa

pmax-int-shell-9 = MIN(pmax-int-shell-8 pmax-9)


pmax-int-shell-9 = MIN(15.0188 21.7273)
pmax-int-shell-9 = 15.0188 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 4.3728
H' = 4.3728 m
PAGE 38 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-test-9 = (* 4.9 D (H' - 0.3))/St


t-test-9 = (* 4.9 21.17 (4.3728 - 0.3))/154
t-test-9 = 2.7434 mm

Course # 10
Ca-10 = Corrosion allowance per API-650 5.3.2 (mm)
G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-10 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-10 = Max pressure at design (kPa)
pmax-int-shell-10 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-10 = Shell actual thickness (mm)
t-calc-10 = Shell thickness design condition td (mm)
t-seismic-10 = See E.6.2.4 table in SEISMIC calculations.
t-test-10 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4344 m
Ca-10 = 1.59 mm
JE = 1
t-10 = 6.35 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)


H' = H
H' = 1.9344
H' = 1.9344 m

t-calc-10 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-10 (per API-650 5.6.3.2)


t-calc-10 = (4.9 * 21.17 * (1.9344 - 0.3) * 1)/137 + 1.59
t-calc-10 = 2.8275 mm

hmax-10 = Sd * (t-10 - CA-10)/(2.6 * D * G) + 1


hmax-10 = 137 * (6.35 - 1.59)/(2.6 * 21.17 * 1) + 1
hmax-10 = 6.5899 m

pmax-10 = (hmax-10 - H) * 9.8 * G


pmax-10 = (6.5899 - 1.9344) * 9.8 * 1

PAGE 39 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

pmax-10 = 45.6237 kPa

pmax-int-shell-10 = MIN(pmax-int-shell-9 pmax-10)


pmax-int-shell-10 = MIN(15.0188 45.6237)
pmax-int-shell-10 = 15.0188 kPa

Hydrostatic Test Condition G = 1


H' = H
H' = 1.9344
H' = 1.9344 m

t-test-10 = (* 4.9 D (H' - 0.3))/St


t-test-10 = (* 4.9 21.17 (1.9344 - 0.3))/154
t-test-10 = 1.1009 mm

SUMMARY OF SHELL RESULTS Back


t-min-Seismic = See API-650 E.6.1.4, table in SEISMIC calculations.
Shell API-650 Summary (Bottom is 1)
t-
Min min
CA Tensile Sd St t-min t-min t-
Shel Width Materia J Yield Weight Weight t-Des t-Test Ext- t-min Statu
(mm Strengt (MPa (MPa Erectio Seismi Actual
l# (mm) l E Strengt (N) CA (N) (mm) (mm) Pe (mm) s
) h (MPa) ) ) n (mm) c (mm) (mm)
h (MPa) (mm
)
2438. A283M- 276,88 257,09 19.444 15.883 19.444
1 1.59 1 205 380 137 154 6 14.0433 NA 22.225 OK
4 C 1 2 2 3 2
2438. A283M- 276,88 257,09 17.597 14.240 17.597
2 1.59 1 205 380 137 154 6 12.7559 NA 22.225 OK
4 C 1 2 9 8 9
2438. A283M- 217,59 197,80 15.751 12.598 15.751 17.462
3 1.59 1 205 380 137 154 6 11.261 NA OK
4 C 8 0 6 3 6 5
2438. A283M- 197,83 178,03 13.905 10.955 13.905
4 1.59 1 205 380 137 154 6 9.9166 NA 15.875 OK
4 C 1 0 3 8 3
2438. A283M- 178,06 158,25 14.287
5 1.59 1 205 380 137 154 6 12.059 9.3133 8.5815 NA 12.059 OK
4 C 2 8 5
2438. A283M- 158,28 138,48 10.212 10.212
6 1.59 1 205 380 137 154 6 7.6709 7.2588 NA 12.7 OK
4 C 9 2 7 7
2438. A283M- 118,73
7 1.59 1 205 380 137 154 98,921 6 8.3664 6.0284 5.8328 NA 8.3664 9.525 OK
4 C 4
2438. A283M-
8 1.59 1 205 380 137 154 98,859 79,043 6 6.5201 4.3859 4.5524 NA 6.5201 7.93 OK
4 C
2438. A283M-
9 1.59 1 205 380 137 154 79,168 59,349 6 4.6738 2.7434 3.3272 NA 6 6.35 OK
4 C
2434. A283M-
10 1.59 1 205 380 137 154 79,038 59,252 6 2.8275 1.1009 2.2874 NA 6 6.35 OK
4 C

Total Weight = 1,681,345.6907 N (171449.51 kg)


PAGE 40 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

INTERMEDIATE STIFFENER CALCULATIONS PER API-650 Section 5.9.7

D = Nominal diameter of the tank shell (m)


Hu = Vertical Distance Between the Intermediate Stiffener (Per API-650 5.9.7) (m)
L_act = Actual Transform Height Spacing between Stiffeners (m)
L_0 = Uniform Maximum Transform Height Spacing between Stiffineres (m)
V = Design wind speed (km/h)
Wtr = Transposed width of each shell course (m)
Zi = Required Intermediate Stiffener Section Modulus (per API-650 5.9.6.1) (cm^3)
Zi-actual = Actual Top Comp Ring Section Modulus (cm^3)

D = 21.17 m
V = 101.4 km/h
ME = 1

Hu = ME * 9.47 * tsmin * (SQRT (tsmin / D)^3) * (190 / V)^2


Hu = 1 * 9.47 * 6.35 * (SQRT (6.35 / 21.17)^3) * (190 / 101.4)^2
Hu = 34.6844 m (Maximum Height of Unstiffened Shell)

Transforming courses (1) to (10)

Wtr = Course-width * (SQRT (t-uniform / t-course)^5)


Wtr-1 = 2.4384 * (SQRT (6.35 / 22.225)^5) = 0.1064 m
Wtr-2 = 2.4384 * (SQRT (6.35 / 22.225)^5) = 0.1064 m
Wtr-3 = 2.4384 * (SQRT (6.35 / 17.4625)^5) = 0.1944 m
Wtr-4 = 2.4384 * (SQRT (6.35 / 15.875)^5) = 0.2467 m
Wtr-5 = 2.4384 * (SQRT (6.35 / 14.2875)^5) = 0.3211 m
Wtr-6 = 2.4384 * (SQRT (6.35 / 12.7)^5) = 0.4311 m
Wtr-7 = 2.4384 * (SQRT (6.35 / 9.525)^5) = 0.8849 m
Wtr-8 = 2.4384 * (SQRT (6.35 / 7.93)^5) = 1.3991 m
Wtr-9 = 2.4384 * (SQRT (6.35 / 6.35)^5) = 2.4384 m
Wtr-10 = 2.4344 * (SQRT (6.35 / 6.35)^5) = 2.4344 m

Wtr = SUM(Wtr-n)
Wtr = 8.5629 m

PAGE 41 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

For uniformly spaced stiffeners

L_0 = Hts/# of Stiffeners + 1


L_0 = 8.5629/(0 + 1)
L_0 = 8.5629 m

L_act = Wrt
L_act = 8.5629 m

Number of Intermediate Stiffeners Sufficient Since Hu >= L_act

SUMMARY OF SHELL STIFFENING RESULTS


Number of Intermediate stiffeners req'd (NS) = 0

FLAT BOTTOM: ANNULAR PLATE DESIGN Back

Ann-a = Area of annular ring (cm^2)


Ann-d = Density of annular ring (kg/mm3)
Ann-t-actual = Actual annular ring thickness (mm)
Ann-t-min = Minimum annular ring plates thickness per API-650 5.5.3 TABLE 5-1a (mm)
Ann-w-actual = Actual annular ring width (mm)
Ann-w-min = Minimum annular ring width per API-650 5.5.2 (mm)
Ba = Area of bottom (cm^2)
Bottom-OD = Bottom diameter (m)
ca-1 = Bottom (1st) shell course corrosion allowance
ca-Ann = Annular ring corrosion allowance (mm)
Ca-bottom = Bottom corrosion allowance (mm)
D = Nominal diameter per API-650 5.6.1.1 Note 1 (m)
D-bottom = Density of bottom (kg/mm3)
G = Design specific gravity of the liquid to be stored
H = Max liquid level (m)
H' = Effective liquid head at design pressure (m)
R = Nominal radius (m)
S = Maximum Stress in first shell course per API 650 Table 5.1.a
S1 = Product stress in the first shell course per API 650 Table 5.1.a
S2 = Hydrostatic test stress in the first shell course per API 650 Table 5.1.a
Sd = Allowable design stress for the design condition in bottom (1st) shell course (MPa) per API 650 5.6.3.2
St = Allowable stress for the hydrostatic test condition in bottom (1st) shell course (MPa) per API 650 5.6.3.2
t-1 = Bottom (1st) shell course thickness (mm)
t-actual = Actual bottom thickness (mm)
t-calc = Minimum nominal bottom plates thickness per API-650 5.4.1 (mm)
PAGE 42 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-min = Minimum nominal bottom plates thickness per API-650 5.4.1 (mm)
t-test-1 = Bottom (1st) shell course test thickness (mm)
td-1 = Bottom (1st) shell course design thickness (mm)

Material = A283M-C
t-actual = 8 mm
Annular Ring Material = A283M-C
Ann-t-actual = 8 mm
Ann-w-actual = 762 mm

Calculation of Hydrostatic Test Stress & Product Stress (per API-650 Section 5.5.1)

Bottom-OD = 19.8685 m
JE = 1
D-bottom = 0.00000784 kg/mm3
t-1 = 22.225 mm
ca-1 = 1.59 mm
G=1
H = 23.88 m
H' = 23.88 m
St = 154 MPa
Sd = 137 MPa
Ca-bottom = 2 mm
ca-Ann = 2 mm
Ann-d = 0.000007 kg/mm3

Product stress in first shell course

S1 = ((td-1 - ca-1) / (t-1 - ca-1)) * Sd


S1 = ((19.4442 - 1.59) / (22.225 - 1.59)) * 137
S1 = 118.5376 MPa

Hydrostatic test stress in first shell course

S2 = (t-test-1 / t-1) * St
S2 = (15.8833 / 22.225) * 154
S2 = 110.0573 MPa

S = Max (S1, S2)


S = Max (118.5376 , 110.0573)
S = 118.5376 MPa

PAGE 43 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

API-650 Table 5.1a required thickness of annular ring excluding corrosion allowance is 6 mm
Annular ring required thickness = 6 + ca-Ann = 6 + 2
Annular ring required thickness = 8 mm

Weight of Bottom plate

BA = PI * ((Bottom-OD / 2) - Ann-w-actual)^2
BA = PI * ((19868 / 2) - 762)^2
BA = 264,301,283.4419 mm^2

Ann-a = PI/4 * Bottom-OD^2 - BA


Ann-a = PI/4 * 19868^2 - 264,301,283.4419
Ann-a = 45,738,808.4126 mm^2

weight = (D-bottom * t-actual * BA) + (Ann-d * Ann-t-actual * Ann-A)


weight = (0.00000784 * 8 * 264,301,283.4419) + (0.000007 * 8 * 45,738,808.4126)
weight = 19,450.0043 kg or 190,739.3848 N

API-650

t-min = 6.0 + Ca-bottom


t-min = 6.0 + 2
t-min = 8 mm

t-calc = t-min
t-calc = 8 mm

API-650 5.5

Ann-t-min = 8 mm

Ann-w-min = (215 * Ann-t-actual)/(H * G)^0.5


Ann-w-min = (215 * 8)/(23.88 * 1)^0.5
Ann-w-min = 600 mm Note: API-650 until the inner radius of the shell.
Ann-w-min = 711.225 mm Note: including chime distance, overlap and shell thickness.

SUMMARY OF BOTTOM RESULTS Back

Material = A283M-C

PAGE 44 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-actual = 8 mm
t-req = 8 mm
Annular Ring Material = A283M-C
Ann-t-actual = 8 mm
Ann-w-actual = 762 mm
Ann-t-min = 8 mm
Ann-w-min = 711.225 mm

NET UPLIFT DUE TO INTERNAL PRESSURE

Net-Uplift = 0 N, (See roof report for calculations)

WIND MOMENT (Per API-650 SECTION 5.11) Back

A = Area resisting the compressive force, as illustrated in Figure F.1


P-F41 = Design pressure determined in F.4.1
P-v = Internal pressure

Wind Velocity per API-650 ASCE 7-10

V_entered = 130 kph


Vs (Wind Velocity) = 0.78 * V_entered = 101.4 kph

Vf = (Vs / 190)^2
Vf = (101.4 / 190)^2
Vf (Velocity Factor) = 0.2848

PWS = 0.86 * Vf
PWS = 0.2449 kPa

PWR = 1.44 * Vf
PWR = 0.4101 kPa

API-650 5.2.1.k Uplift Check

P-F41 = (A * Fy * TAN(Theta))/(200 * D^2) + (0.00127 * DLR)/D^2


P-F41 = (3532.74 * 205 * TAN(3.5763))/(200 * 21.17^2) + ((0.00127 * 151081) / 21.17^2)
P-F41 = 0.9331 kPa

Wind-Uplift = MIN(PWR , (1.6 * P-F41 - Pv))


Wind-Uplift = MIN(0.4101 , 1.493)
PAGE 45 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Wind-Uplift = 0.4101 kPa

Ap-Vert (Vertical Projected Area of Roof) = 7.0026 m^2

Horizontal Projected Area of Roof (Per API-650 5.2.1.f)

Xw (Moment Arm of UPLIFT wind force on roof) = 10.585 m


Ap (Projected Area of roof for wind moment) = 351.991 m^2

M-roof (Moment Due to Wind Force on Roof) = Wind-Uplift * Ap * Xw


M-roof = (410.1391 * 351.991 * 10.585)
M-roof = 1,528,107 N-m

Xs (Height from bottom to the Shell's center of gravity) = Shell Height/2


Xs = (24.38/2)
Xs = 12.19 m

As (Projected Area of Shell) = Shell Height * (D + 2 * t-ins)


As = 24.38 * (21.17 + 2 * 0)
As = 516.1246 m^2

M-Shell (Moment Due to Wind Force on Shell) = (PWS * As * (Shell Height / 2))
M-Shell = (0.2449 * 516.1246 * (24.38 / 2))
M-Shell = 1,541,081 N-m

Mw (Wind moment) = M-roof + M-shell


Mw = 1,528,107 + 1,541,081
Mw = 3,069,187.4814 N-m

RESISTANCE TO OVERTURNING (per API-650 5.11.2)

DLR = Nominal weight of roof plate plus weight of roof plates overlap plus any attached structural.
DLS = Nominal weight of the shell and any framing (but not roof plates) support by the shell and roof.
F-friction = Maximum of 40% of weight of tank
MDL = Moment about the shell-to-bottom joint from the nominal weight of the shell
MDLR = Moment about the shell-to-bottom joint from the nominal weight of the roof plate plus any attached
structural.
MF = Stabilizing moment due to bottom plate and liquid weight
MPi = Destabilizing moment about the shell-to-bottom joint from design pressure
Mw = Destabilizing wind moment

PAGE 46 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

tb = Bottom plate thickness less C.A.


wl = Circumferential loading of contents along shell-to-bottom joint

An unanchored tank must meet with this criteria:

Mw = 3,069,187 m-N
DLS = 1,747,401.9339 N
DLR = 151,081.3482 N

MPi = P * (Pi * D^2 / 4) * (D / 2)


MPi = 0 * (3.1416 * 21.17^2 / 4) * (21.17 / 2)
MPi = 0 m-N

MDL = DLS * (D/2)


MDL = 1,747,401.9339 * 21.17/2
MDL = 18,496,249 N-m

MDLR = DLR * (D/2)


MDLR = 151,081.3482 * 21.17/2
MDLR = 1,599,196 N-m

tb = 6 mm

wl = (min [59 * tb * SQRT(fy-btm * H-liq)] [140.8 * H-liq * D])


wl = (min [59 * 6 * SQRT(205 * 23.88)] [140.8 * 23.88 * 21.17])
wl = 24,768.3658 N/m

MF = (D/2) * wl * Pi * D
MF = 10.585 * 24,768.3658 * 3.1416 * 21.17
MF = 17,436,485 m-N

Criteria 3

M-shell + Fp * Mpi < MDL /1.5 + MDLR


1,541,080.8516 + 0.4 * 0 < 18,496,249 / 1.5 + 1,599,196
Since 1,541,081 < 13,930,029, Tank is stable

PAGE 47 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RESISTANCE TO SLIDING (per API-650 5.11.4)

F-wind = Vf * 18 * As
F-wind = 0.2848 * 18 * 516.1246
F-wind = 122,629 N

F-friction = 0.4 * [(W-roof-corroded * g) + (W-shell-corroded * g) + (W-btm-corroded * g) + (W-roof-struct * g)]


F-friction = 0.4 * [(13,828 * 9.8) + (151,257 * 9.8) + (15,305 * 9.8) + (47,668 * 9.8)]
F-friction = 894,595 N

No anchorage needed to resist sliding since


F-friction > F-wind

Anchorage Requirement

Tank does not require anchorage

PAGE 48 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Back

SITE GROUND MOTION CALCULATIONS


Af (Acceleration Coefficient for Sloshing Wave Height) = 0.0029
Anchorage_System (Anchorage System) = mechanically anchored
Av (Vertical Ground Acceleration Coefficient) = 0.0027
D (Nominal Tank Diameter) = 21.17 m
H (Maximum Design Product Level) = 23.88 m
I (Importance Factor) = 1.25
K (Spectral Acceleration Adjustment Coefficient) = 1.5
Q (MCE to Design Level Scale Factor) = 1
Rwc (Convective Force Reduction Factor) = 2
Rwi (Impulsive Force Reduction Factor) = 4
Sac (Convective Design Spectral Response Acceleration Parameter at Any Period) = 0.0012
Sai (Impulsive Design Spectral Response Acceleration Parameter at Any Period) = 0.0056
Seismic_Site_Class (Seismic Site Class) = seismic site class c
Seismic_Use_Group (Seismic Use Group) = seismic use group ii
TL (Regional Dependent Transistion Period for Longer Period Ground Motion) = 3 sec

Sloshing Coefficient API 650 Section E.4.5.2


Ks = 0.578 / SQRT(TANH(((3.68 * Liq_max) / D)))
= 0.578 / SQRT(TANH(((3.68 * 23.88) / 21.17)))
= 0.5781

Convective Natural Period API 650 Section E.4.5.2


Tc = 1.8 * Ks * SQRT(D) = 1.8 * 0.5781 * SQRT(21.17) = 4.7882 sec

Impulsive Design Response Spectrum Acceleration Coefficient API 650 Sections E.4.6.2
Ai = Q * (I / Rwi) * Sai = 1 * (1.25 / 4) * 0.0056 = 0.0018

Convective Design Response Spectrum Acceleration Coefficient API 650 Sections E.4.6.2
Ac = Q * K * (I / Rwc) * Sac = 1 * 1.5 * (1.25 / 2) * 0.0012 = 0.0011

Ac = MIN(Ac , Ai) = MIN(0.0011 , 0.0018) = 0.0011

Design Spectral Response Acceleration at Short Period API 650 Sections E.4.6.1
SDS = Ai * (Rwi / I) = 0.0018 * (4 / 1.25) = 0.0058

Design Spectral Response Acceleration at a Period of 1 Second API 650 Sections E.4.6.1
SD1 = (Ac / K) * ((Tc^2) / TL) * (Rwc / I)
= (0.0011 / 1.5) * ((4.7882^2) / 3) * (2 / 1.25)
= 0.009

PAGE 49 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Vertical Ground Acceleration Coefficient API 650 Section E.6.1.3 and E.2.2
Av = (2 / 3) * 0.7 * SDS = (2 / 3) * 0.7 * 0.0058 = 0.0027

Vertical Ground Acceleration Coefficient Specified by user (Av) = 0.0027

SEISMIC CALCULATIONS Back

< Mapped ASCE7 Method >


Ac = Convective spectral acceleration parameter
Ai = Impulsive spectral acceleration parameter
Av = Vertical Earthquake Acceleration Coefficient
Ci = Coefficient for impulsive period of tank system (Fig. E-1)
D/H = Ratio of Tank Diameter to Design Liquid Level
Density = Density of tank product (SG * 62.42786)
Fc = Allowable longitudinal shell-membrane compressive stress
Fty = Minimum specified yield strength of shell course
Fy = Minimum yield strength of bottom annulus
Ge = Effective specific gravity including vertical seismic effects
I = Importance factor defined by Seismic Use Group
k = Coefficient to adjust spectral acceleration from 5% - 0.5% damping
L = Required Annular Ring Width
Ls = Actual Annular Plate Width
Mrw = Ringwall moment-portion of the total overturning moment that acts at the base of the tank shell perimeter
Ms = Slab moment (used for slab and pile cap design)
Pa = Anchorage chair design load
Pab = Anchor seismic design load
Q = Scaling factor from the MCE to design level spectral accelerations
RCG = Height from Top of Shell to Roof Center of Gravity
Rwc = Force reduction factor for the convective mode using allowable stress design methods (Table E-4)
Rwi = Force reduction factor for the impulsive mode using allowable stress design methods (Table E-4)
S0 = Design Spectral Response Param. (5% damped) for 0-second Periods (T = 0.0 sec)
Sd1 = The design spectral response acceleration param. (5% damped) at 1 second based on ASCE7 methods per
API 650 E.2.2
Sds = The design spectral response acceleration param. (5% damped) at short periods (T = 0.2 sec) based on
ASCE7 methods per API 650 E.2.2
SigC = Maximum longitudinal shell compression stress
SigC-anchored = Maximum longitudinal shell compression stress
SUG = Seismic Use Group (Importance factors depends on SUG)
T-L = Regional Dependent Transition Period for Long Period Ground Motion (Per ASCE 7-05, fig. 22-15)
ta = Actual Annular Plate Thickness less C.A.
ts1 = Thickness of bottom Shell course minus C.A.
tu = Equivalent uniform thickness of tank shell
V = Total design base shear
PAGE 50 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Vc = Design base shear due to convective component from effective sloshing weight
Vi = Design base shear due to impulsive component from effective weight of tank and contents
wa = Force resisting uplift in annular region
Wab = Design uplift load on anchor per unit circumferential length
Wc = Effective Convective (Sloshing) Portion of the Liquid Weight
Weff = Effective Weight Contributing to Seismic Response
Wf = Weight of Floor (Incl. Annular Ring)
Wi = Effective Impulsive Portion of the Liquid Weight
wint = Uplift load due to design pressure acting at base of shell
Wp = Total weight of Tank Contents based on S.G.
Wr = Weight Fixed Roof, framing and 10 % of Design Snow Load & Insul.
Wrs = Roof Load Acting on Shell, Including 10% of Snow Load
Ws = Weight of Shell (Incl. Shell Stiffeners & Insul.)
wt = Shell and roof weight acting at base of shell
Xc = Height to center of action of the lateral seismic force related to the convective liquid force for ringwall moment
Xcs = Height to center of action of the lateral seismic force related to the convective liquid force for the slab
moment
Xi = Height to center of action of the lateral seismic force related to the impulsive liquid force for ringwall moment
Xis = Height to center of action of the lateral seismic force related to the impulsive liquid force for the slab moment
Xr = Height from Bottom of Shell to Roof Center of Gravity
Xs = Height from Bottom to the Shell's Center of Gravity
g = 9.8 m/s^2

WEIGHTS

Ws = 172,223 kgf or 1,688,928.6135 N


Wf = 19,450 kgf or 190,739.3848 N
Wr = 13,828 kgf or 135,606.5648 N

EFFECTIVE WEIGHT OF PRODUCT

D/H = 0.8865
Wp = 8,405,546 kgf

Wi = (1 - (0.218 * D/H)) * Wp
Wi = (1 - (0.218 * 0.8865)) * 8,405,546
Wi = 6,781,086 kgf

Wc = 0.23 * D/H * TANH (3.67 * H/D) * Wp


Wc = 0.23 * 0.8865 * TANH (3.67 * 1.128) * 8,405,546
Wc = 1,713,010 kgf

PAGE 51 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Weff = Wi + Wc
Weff = 6,781,086 + 1,713,010
Weff = 8,494,096.6145 kgf

Wrs = 10,371 kgf

DESIGN LOADS

Vi = Ai * (Ws + Wr + Wf + Wi)
Vi = 0.0018 * (172,223 + 13,828 + 19,450 + 6,781,086)
Vi = 12,576 kgf

Vc = Ac * Wc
Vc = 0.0011 * 1,713,010
Vc = 1,884.3114 kgf

V = SQRT (Vi^2 + Vc^2)


V = SQRT (12,576^2 + 1,884.3114^2)
V = 12,716.2416 kgf

CENTER OF ACTION FOR EFFECTIVE LATERAL FORCES

Xs = 11.94 m
RCG = 1/3 * R * (TAND (Theta))
RCG = 1/3 * 10585 * (TAND (3.5763))
RCG = 220.5208 mm or 0.2205 m

Xr = Shell Height + RCG


Xr = 24.38 + 0.2205
Xr = 24.6005 m

CENTER OF ACTION FOR RINGWALL OVERTURNING MOMENT

Xi = (0.5 - (0.094 * D/H)) * H


Xi = (0.5 - (0.094 * 0.8865)) * 23.88
Xi = 9.95 m

Xc = (1 - (COSH (3.67 * H/D) - 1) / ((3.67 * H/D) * SINH (3.67 * H/D))) * H


Xc = (1 - (COSH (3.67 * 1.128) - 1) / ((3.67 * 1.128) * SINH (3.67 * 1.128))) * 23.88
Xc = 18.2925 m

PAGE 52 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

CENTER OF ACTION FOR SLAB OVERTURNING MOMENT

Xis = (0.5 + (0.06 * D/H)) * H)


Xis = (0.5 + (0.06 * 0.8865)) * 23.88)
Xis = 13.2102 m

Xcs = (1 - (COSH (3.67 * H/D) - 1.937) / ((3.67 * H/D) * SINH(3.67 * H/D))) * H


Xcs = (1 - (COSH (3.67 * 1.128) - 1.937) / ((3.67 * 1.128) * SINH(3.67 * 1.128))) * 23.88
Xcs = 18.4647 m

Dynamic Liquid Hoop Forces

Width
SHELL Y (m) Ni (N/mm) Nc (N/mm) Nh (N/mm) SigT+ (MPa) SigT- (MPa)
(m)
= 1.85 * Ac * G * D^2 * (COSH = (+ Nh (SQRT (Ni^2 + = (- Nh (SQRT (Ni^2 +
= 2.6 * Ai * = 4.9011293 * Y
SUMMARY (3.68 * (H - Y)) / D) / (COSH (3.68 Nc^2 + (Av * Nh / 2.5)^2))) Nc^2 + (Av * Nh / 2.5)^2)))
G * D^2 *D*G
* H / D)) / t-n / t-n
Shell 1 2.4384 23.5752 2.0974 0.0287 2,446.0898 110.212 109.9085
Shell 2 2.4384 21.1368 2.0974 0.032 2,193.0889 98.819 98.5343
Shell 3 2.4384 18.6984 2.0974 0.0411 1,940.0881 111.27 110.9304
Shell 4 2.4384 16.26 2.0974 0.0578 1,687.0873 106.4482 106.0981
Shell 5 2.4384 13.8216 2.0701 0.0849 1,434.0864 100.5545 100.1924
Shell 6 2.4384 11.3832 1.9367 0.1276 1,181.0856 93.1817 92.8159
Shell 7 2.4384 8.9448 1.704 0.1936 928.0847 97.6452 97.2281
Shell 8 2.4384 6.5064 1.372 0.2949 675.0839 85.3298 84.9309
Shell 9 2.4384 4.068 0.9406 0.45 422.083 66.649 66.2905
Shell 10 2.4344 1.6296 0.41 0.6871 169.0822 26.7563 26.4978

Overturning Moment

Mrw = ((Ai * [(Wi * g) * Xi + (Ws * g) * Xs + (Wr * g) * Xr])^2 + [Ac * (Wc * g) * Xc]^2)^0.5


Mrw = ((0.0018 * [(6,781,086 * 9.8) * 9.95 + (172,223 * 9.8) * 11.94 + (13,828 * 9.8) * 24.6005])^2 + [0.0011 *
(1,713,010 * 9.8) * 18.2925]^2)^0.5
Mrw = 1,278,799.2162 N-m

Ms = ((Ai * [(Wi * g) * Xis + (Ws * g) * Xs + (Wr * g) * Xr])^2 + [Ac * (Wc * g) * Xcs]^2)^0.5


Ms = ((0.0018 * [(6,781,086 * 9.8) * 13.2102 + (172,223 * 9.8) * 11.94 + (13,828 * 9.8) * 24.6005])^2 + [0.0011 *
(1,713,010 * 9.8) * 18.4647]^2)^0.5
Ms = 1,659,024.1285 N-m

PAGE 53 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RESISTANCE TO DESIGN LOADS

Fy = 205 MPa

Ge = S.G. * (1- 0.4 * Av)


Ge = 1 * (1- 0.4 * 0.0027)
Ge = 0.9989

wa = MIN (99 * ta * (Fy * H * Ge)^0.5 , 201.1 * H * D * Ge)


wa = MIN (99 * 6 * (205 * 23.88 * 0.9989)^0.5) , 201.1 * 23.88 * 21.17 * 0.9989)
wa = MIN ( 41,538.0295 , 101,554.2164)
wa = 41,538.0295 N/m

wt = (Wrs + Ws) / (Pi * D)


wt = (10,371 + 172,223) / (3.1416 * 21.17)
wt = 26,923.7769 N/m

wint = P * (Pi * D^2 / 4) / (Pi * D)


wint = 0 * (3.1416 * 21.17^2 / 4) / (3.1416 * 21.17)
wint = 0 N/m

Annular Ring Requirements

L = MIN (0.035 * D , MAX (0.45 , 0.01723 * ta * (Fy / (H * Ge))^0.5))


L = MIN (0.035 * 21.17 , MAX (0.45 , 0.01723 * 6 * (205 / (23.88 * 0.9989))^0.5))
L = MIN (0.741 , MAX (0.45 , 0.3031))
L = 0.45 m

Ls = 0.762 m
Since Ls > L.

Anchorage Ratio

J = Mrw / (D^2 * [wt * (1 - 0.4 * Av)] + wa - 0.4 * wint


J = 1,278,799.2162 / (21.17^2 * [26,923.7769 * (1 - 0.4 * 0.0027)] + 41,538.0295 - 0.4 * 0
J = 0.0417

Since J <= 0.785, The tank is self-anchored, per API 650 Table E-6

PAGE 54 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Maximum Longitudinal Shell-Membrane Compressive Stress

ts1 = 20.635 mm
SigC = [wt * (1 + (0.4 * Av)) + (1.273 * Mrw) / D^2] * (1 / (1,000 * ts))
SigC = [26,923.7769 * (1 + (0.4 * 0.0027)) + (1.273 * 1,278,799.2162) / 21.17^2] * (1 / (1,000 * 20.635))
SigC = 1.4822 MPa

Allowable Longitudinal Shell-Membrane Compression Stress

Fty = 205 MPa

Criteria for Fc

Since [G * H * D^2 / ts1^2] < 44


Since [1 * 23.88 * 21.17^2 / 20.635^2] < 44
Since 25.1343 < 44 Then Fc = (83 * ts) / (2.5 * D) + (7.5 * SQRT(G * H))

Fc = (83 * ts) / (2.5 * D) + (7.5 * SQRT(SG * H))


Fc = (83 * 20.635) / (2.5 * 21.17) + (7.5 * SQRT(1 * 23.88))
Fc = 69.0113 MPa

Hoop Stresses

SHELL SUMMARY SigT+ Sd * 1.333 Fy * 0.9 * E Allowable Membrane t-Min Shell Ok


Shell 1 110.212 182.621 184.5 182.621 14.0432 OK
Shell 2 98.819 182.621 184.5 182.621 12.7559 OK
Shell 3 111.27 182.621 184.5 182.621 11.261 OK
Shell 4 106.4482 182.621 184.5 182.621 9.9166 OK
Shell 5 100.5545 182.621 184.5 182.621 8.5814 OK
Shell 6 93.1817 182.621 184.5 182.621 7.2588 OK
Shell 7 97.6452 182.621 184.5 182.621 5.8327 OK
Shell 8 85.3298 182.621 184.5 182.621 4.5523 OK
Shell 9 66.649 182.621 184.5 182.621 3.3272 OK
Shell 10 26.7563 182.621 184.5 182.621 2.2874 OK

PAGE 55 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Mechanically Anchored

Number of anchor = 23
Max spacing = 3 m
Actual spacing = 2.9256 m
Minimum # anchor = 23

Wab = (1.273 * Mrw) / D^2 - wt * (1 - 0.4 * Av) + wint


Wab = (1.273 * 1,278,799.2162) / 21.17^2 - 26,923.7769 * (1 - 0.4 * 0.0027) + 0
Wab = -23,262.3379 N/m

Pab = Wab * Pi * D / Na
Pab = -23,262.3379 * 3.1416 * 21.17 / 23
Pab = -67,266.10082010458 N

Pa = 3 * Pab
Pa = 3 * -67,266.10082010458
Pa = -201,798.30246031372 N

Shell Compression in Mechanically-Anchored Tanks

SigC-anchored = [Wt * (1 + (0.4 * Av)) + (1.273 * Mrw) / D^2] * (1 / (1,000 * ts))


SigC-anchored = [26,923.7769 * (1 + (0.4 * 0.0027)) + (1.273 * 1,278,799.2162) / 21.17^2] * (1 / (1,000 * 20.635))
SigC-anchored = 1.4822 MPa

Fc = 69.0113 MPa

SigC-anchored <= Fc Then the design is acceptable.

Detailing Requirements (Anchorage)

SUG = II
Sds = 0.0058 g or 0.58 %g

Freeboard - Sloshing

TL-sloshing = 4 sec
I-sloshing = 1.25
Tc = 4.7882
k = 1.5
Sd1 = 0.009 g or 0.9 %g
PAGE 56 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Af = 0.0029 g per API 650 E.7.2

Delta-s = 0.42 * D * Af
Delta-s = 0.42 * 21.17 * 0.0029
Delta-s = 0.0258 m

0.7 * Delta-s = 0.018 m

Since Sds < 0.33g and SUG = II per API 650 Table E-7.
a. A freeboard of O.7*Delta-s is recommended for economic considerations but not required.

Sliding Resistance

mu = 0.4 (friction coefficient)


V = 12,716.2416 kgf

Vs = mu * (Ws + Wr + Wf + Wp) * (1 - 0.4 * Av)


Vs = 0.4 * (172,223 + 13,828 + 19,450 + 8,405,546) * (1 - 0.4 * 0.0027)
Vs = 3,440,698.7536 kgf

Since V <= Vs Then the tank will not experience major sliding and does not require additional lateral anchorage,
per API 650 E.7.6.

Local Shear Transfer

Vmax = 2 * V / (Pi * D)
Vmax = 2 * 12,716.2416 / (3.1416 * 21.17)
Vmax = 382.4001 kgf/m

PAGE 57 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

ANCHOR BOLT DESIGN Back

Bolt Material : A36M


Sy = 250 MPa

UPLIFT LOAD CASES, PER API-650 TABLE 5-21b

A-s-r = Bolt Root Area Req'd


bt = Uplift load per bolt
D = Tank D (m)
Fp = Pressure Combination Factor
Mrw = Seismic Ringwall Moment (Nm)
N = Anchor bolt quantity
P = Design pressure (pa)
Pf = Failure pressure per F.6 (KPa)
Pt = Test pressure per F.7.6 = 1.25 * P = 0 (pa)
sd = Allowable Anchor Bolt Stress (MPa)
Shell-sd-at-anchor = Allowable Shell Stress at Anchor Attachment (MPa)
t-actual = Actual Roof plate thickness (mm)
t-h = Roof plate thickness less CA (mm)
Vf = Velocity factor (kph)
W1 = Dead Load of Shell minus C.A. and Any Dead Load minus C.A. other than Roof Plate Acting on Shell
W2 = Dead Load of Shell minus C.A. and Any Dead Load minus C.A. including Roof Plate minus C.A. Acting on
Shell
W3 = Dead Load of New Shell and Any Dead Load other than Roof Plate Acting on Shell

For Tank with Structural Supported Roof

W1 = W-shell-corroded + Shell Insulation


W1 = 1,483,324.0111 + 0
W1 = 1,483,324.0111 N

W2 = W-shell-corroded + Shell Insulation + Corroded Roof Plates Supported by Shell + Roof Dead Load Supported
by Shell
W2 = 1,483,324.0111 + 0 + 135,606.5648 + 0
W2 = 1,618,930.5759 N

W3 = New Shell + Shell Insulation


W3 = 1,681,345.6907 + 0
W3 = 1,681,345.6907 N

Uplift Case 1: Design Pressure Only


PAGE 58 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

U = [(P - 0.08 * t-h) * D^2 * 785] - W1


U = [(0 - 0.08 * 5) * 21.17^2 * 785] - 1,483,324.0111
U = -1,624,049.045717705 N

bt = U/N
bt = -70,610.82807468282 N

sd = 104.1666 MPa
Shell-sd-at-anchor = 136.6666 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 2: Test Pressure Only

U = [(Pt - 0.08 * t-h) * D^2 * 785] - W1


U = [(0 - 0.08 * 5) * 21.17^2 * 785] - 1,483,324.0111
U = -1,624,049.045717705 N

bt = U/N
bt = -70,610.82807468282 N

sd = 138.8888 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 3: Failure Pressure Only

Pf (failure pressure per F.6) = 1.2383 KPa

Uplift Case 4: Wind Load Only

PWR = Wind-Uplift per API 650 Table 5-21a, 5-21b


PWS = Wind-Pressure per API 650 Table 5-21a, 5-21b
PWR = 0.4101 KPa
PWS = 244.9441 N/m^2
MWH = PWS * D * (H^2 / 2) per API 650 Table 5-21a, 5-21b
MWH = 244.9441 * 21.17 * (24.38^2 / 2)
MWH = 1,541,080.8516 Nm

PAGE 59 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

U = PWR * D^2 * 785 + (4 * MWH / D) - W2


U = 0.4101 * 21.17^2 * 785 + (4 * 1,541,080.8516 / 21.17) - 1,618,930.5759
U = -1,183,456.4476155706 N

bt = U/N
bt = -51,454.62815719872 N

sd = 200 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 5: Seismic Load Only

U = [4 * Mrw / D] - W2 * (1 - 0.4 * Av)


U = [4 * 1,278,799 / 21.17] - 1,618,930.5759 * (1 - 0.4 * 0.0027)
U = -1,375,557.338035122 N

bt = U/N
bt = -59,806.84078413574 N

sd = 200 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 6: Design Pressure + Wind Load

U = [(Fp * P + PWR - 0.08 * t-h) * D^2 * 785] + [4 * MWH / D] - W1


U = [(0.4 * 0 + 0.4101 - 0.08 * 5) * 21.17^2 * 785] + [4 * 1,541,080.8516 / 21.17] - 1,483,324.0111
U = -1,188,574.9174060647 N

bt = U/N
bt = -51,677.170322002814 N

sd = 138.8888 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

PAGE 60 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Uplift Case 7: Design Pressure + Seismic Load

U = [(Fp * P - 0.08 * t-h) * D^2 * 785] + [4 * Mrw / D] - W1 * (1 - 0.4 * Av)


U = [(0.4 * 0 - 0.08 * 5) * 21.17^2 * 785] + [4 * 1,278,799 / 21.17] - 1,483,324.0111 * (1 - 0.4 * 0.0027)
U = -1,380,822.2629156103 N

bt = U/N
bt = -60,035.75056154827 N

sd = 200 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 8: Frangibility Pressure

U = [(3 * Pf - 0.08 * t-actual) * D^2 * 785] - W3


U = [(3 * -0.2515 - 0.08 * 5) * 21.17^2 * 785] - 1,681,345.6907
U = -2,087,494.9704997935 N

bt = U/N
bt = -90,760.65089129537 N

sd = 250 MPa
Shell-sd-at-anchor = 205 MPa

A-s-r = N.A., since Load per Bolt is zero

ANCHOR BOLT SUMMARY Back

Bolt Root Area Req'd = 0 mm^2


Bolt Diameter (d) = 30 mm (M30)
Threads per centimeters (n) = 0.2857

A-s = Actual Bolt Root Area


A-s = (pi / 4) * (d - 33.02 / n)^2
A-s = 0.7854 * (30 - 33.02 / 0.2857)^2
A-s = 508.7055 mm^2

PAGE 61 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Exclusive of Corrosion
Bolt Diameter Req'd = 4.294 mm (per ANSI B1.1)
Actual Bolt Diameter = 30 mm (M30)
Bolt Diameter Meets Requirements

ANCHORAGE REQUIREMENTS

Wind or Uplift calculations require anchorage


Minimum # Anchor Bolts = 23
per API-650 5.12.3
Actual # Anchor Bolts = 23
Anchorage Meets Spacing Requirements

ANCHOR CHAIR DESIGN

(from AISI 'Steel Plate Engr Data' Dec. 92, Vol. 2, Part VII)

Entered Parameters

Chair Material : A36M


Top Plate Type : DISCRETE
Chair Style : VERT. TAPERED
Top Plate Width (a) : 254 mm
Top Plate Length (b) : 204 mm
Vertical Plate Width (k) : 127 mm
Top Plate Thickness (c) : 26 mm
Bolt Eccentricity (e) : 102 mm
Outside of Top Plate to Hole Edge (f) : 80 mm
Distance Between Vertical Plates (g) : 108 mm
Chair Height (h) : 712 mm
Vertical Plates Thickness (j) : 28 mm
Bottom Plate thickness (m) : 8 mm
Shell Course + Repad Thickness (t) : 22.225 mm
Nominal Radius to Tank Centerline (r) : 10596 mm
Design Load per Bolt (P) : 0 N
Bolt Diameter (d) = 30 mm (M30)
Threads per unit length (n) = 0.2857

Bolt Yield Load = A-s * Sy


Bolt Yield Load = 508.7055 * 250
Bolt Yield Load = 127,176.3859 N

PAGE 62 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Seismic Design Bolt Load (Pa) = -201,798.30246031372 N


Anchor Chairs will be designed to withstand
Design Load per Bolt
Anchor Chair Design Load, (P) : 0 N

For anchor Chair Material: A36M


(per API-650 Table 5-2b, Sd-Chair = 160 MPa

Since bottom t > 10 mm, and Seismic anchorage required (J) <= 1.45,
or Wind Speed is < 160.9344 kph,
h-min is 153 mm.

For Discrete Top Plate,


Max. Chair Height Recommended : h <= 3 * a

h-max = 3 * a
h-max = 3 * 254 = 762 mm.

h-actual = 712 mm.

e-min = 0.886 * d + 15
e-min = 0.886 * 30 + 15 = 41.58 mm.

e-actual = 102 mm.

g-min = d + 26
g-min = 30 + 26 = 56 mm.

g-actual = 108 mm.

f-min = d/2 + 4
f-min = 30/2 + 4 = 19 mm.

c-min = SQRT[P / Sd-Chair / f * (0.375 * g - 0.22 * d)]


c-min = SQRT[0 / 160 / 80 * (0.375 * 108 - 0.22 * 30)] = 0 mm.

c-actual = 26 mm.

j-min = MAX(13, [0.04 * (h - c)])


j-min = MAX(13, [0.04 * (712 - 26)]) = 27.44 mm.

PAGE 63 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

j-actual = 28 mm.

b-min = e-min + d + 7
b-min = 41.58 + 30 + 7 = 78.58 mm.

Stress due to Top Plate Thickness


S-actual-Top-Plate = P / (f * c^2) * (0.375 * g - 0.22 * d)
S-actual-Top-Plate = 0 / (80 * 26^2) * (0.375 * 108 - 0.22 * 30) = 0 MPa

Shell Stress due to Chair Height (For discrete Top Plate)


S-actual-ChairHeight = P * e / t^2 * F3
Where F3 = F1 + F2

now F1 = (1.32 * z) / (F6 + F7)


where F6 = (1.43 * a * h^2) / (r * t)
and F7 = (4 * a * h^2)^(1/3)
and z = 26 / (F4 * F5 + 26)
where F4 = (0.177 * a * m) / SQRT(r * t)
and F5 = (m / t)^2

yields F5 = (8 / 22.225)^2
F5 = 0.1295
yields F4 = (0.177 * 254 * 8) / SQRT(10,585 * 22.225)
F4 = 0.7415
yields z = 26 / (0.7415 * 0.1295 + 26)
z = 0.9963
yields F7 = (4 * 254 * 712^2)^(1/3)
F7 = 801.588
yields F6 = (1.43 * 254 * 712^2) / (10,585 * 22.225)
F6 = 782.7031
yields F1 = (1.32 * 0.9963) / (782.7031 + 801.588)
F1 = 0.0008
now F2 = 0.031 / SQRT(r * t)
yields F2 = 0.031 / SQRT(10,585 * 22.225)
F2 = 0.002
yields F3 = 0.0008 + 0.002
F3 = 0.0028
yields S-actual-ChairHeight = 0 * 102 / 22.225^2 * 0.0028
yields S-actual-ChairHeight = 0 MPa

Maximum Recommended Stress is 170 MPa for the Shell


PAGE 64 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

(per API-650 E.6.2.1.2)


Sd-ChairHeight = 170 MPa

ANCHOR CHAIR SUMMARY

S-actual-Top-Plate Meets Design Calculations


(within 105% of Sd-Chair)
S-actual-Top-Plate/Sd-Chair
0/160 = 0%
S-actual-ChairHeight Meets Design Calculations
(within 105% of Sd-ChairHeight)
S-actual-ChairHeight/Sd-ChairHeight
0/170 = 0%

PAGE 65 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

NORMAL AND EMERGENCY VENTING (API-2000 6th EDITION) Back

NORMAL VENTING

T_boil (Product boiling point) = 70.0 degc


T_flash (Product flash point) = 0.0 degc
Vpe (Maximum emptying rate) = 590.46 m^3/hr
Vpf (Maximum filling rate) = 1362.6 m^3/hr
Vtk (Tank capacity) = 8647.6214 m^3

In-breathing

Required in-breathing flow rate due to liquid movement API-2000 A.3.4.1.1


Vip = 0.94 * Vpe = 0.94 * 590.46 = 555.0324 m^3/hr

As per API-2000 A.3.4.1.2 Table A.3 Column 2, Required in-breathing flow rate due to thermal effects (VIT) =
1115.2097 m^3/hr

Total required in-breathing volumetric flow rate


Vi = Vip + VIT = 555.0324 + 1115.2097 = 1670.2421 m^3/hr

Out-breathing

(T_flash < 37.8) OR (T_boil < 148.9) ==> Use API-2000 section A.3.4.2.2

Required out-breathing flow rate due to liquid movement API-2000 A.3.4.2.2


Vop = 2.02 * Vpf = 2.02 * 1362.6 = 2752.452 m^3/hr

As per API-2000 A.3.4.2.2 Table A.3 Column 4, Required out-breathing flow rate due to thermal effects (VOT) =
1115.2097 m^3/hr

Total required out-breathing volumetric flow rate


Vo = Vop + VOT = 2752.452 + 1115.2097 = 3867.6617 m^3/hr

EMERGENCY VENTING

As per API-2000 4.3.3.2, Since roof is frangible, it is not necessary to consider additional equirements for
emergency venting

PAGE 66 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

PLAN VIEW APPURTENANCE

CUST. OUTSIDE INSIDE RADIUS REF


MARK DESCRIPTION ORIENT REMARKS
MARK PROJ (mm) PROJ (mm) (mm) DWG
RM01 24" ROOF MANWAY 281mm 0mm 0' 0mm
RN01 10" ROOF NOZZLE 229mm 0mm 0' 0mm
RN02 8" ROOF NOZZLE 203mm 0mm 0' 0mm
RN02 8" ROOF NOZZLE 203mm 0mm 0' 0mm
RN03 2" ROOF NOZZLE 152mm 0mm 0' 0mm
RN03 2" ROOF NOZZLE 152mm 0mm 0' 0mm
RN04 6" ROOF NOZZLE 203mm 0mm 0' 0mm
RN04 6" ROOF NOZZLE 203mm 0mm 0' 0mm
10" GOOSENECK
RV01 229mm 0mm 0' 0mm
ROOF VENT
RV02 24" FREEVENT 178mm 0mm 0' 0mm RN97
WR01A WINGRAIL -- -- 0' 10508mm

ELEVATION VIEW APPURTENANCE

CUST. OUTSIDE INSIDE ELEVATION REF


MARK DESCRIPTION ORIENT REMARKS
MARK PROJ (mm) PROJ (mm) (mm) DWG
ANCHOR SEE
AC01A -- -- --
CHAIRS TABLE
NP01A STD API -- -- 0' 1016mm
ROOF
RPA01A -- -- 0' --
PLATFORM
30" SHELL
SM01 260mm 0mm 0' 900mm
MANWAY
SM01 30" SHELL 260mm 0mm 0' 900mm

PAGE 67 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

MANWAY
16" SHELL
SN01 250mm 0mm 0' 531mm
NOZZLE
12" SHELL
SN02 225mm 0mm 0' 449mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN03 175mm 0mm 0' 259mm
NOZZLE
2" SHELL
SN04 150mm 0mm 0' 175mm
NOZZLE
2" SHELL
SN04 150mm 0mm 0' 175mm
NOZZLE
2" SHELL
SN04 150mm 0mm 0' 175mm
NOZZLE
6" SHELL
SN05 200mm 0mm 0' 306mm
NOZZLE
6" SHELL
SN05 200mm 0mm 0' 306mm
NOZZLE

Nozzle R-2 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 10 in SCH 60 TYPE RFSO

t_rpr = (Re Pad Required Thickness)

PAGE 68 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_n = (Thickness of Neck)


Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 273.05
Required Area = 1365.25 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 273.05
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 5] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 678.7763 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 1365.25 - 0 - 678.7763
A-rpr = 686.4737 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (686.4737 / 273.05) + 0
t_rpr = 2.5141 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 10 in
Repad Size (OD) Must be 550 mm

PAGE 69 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Nozzle R-4 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 8 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 219.075
Required Area = 1095.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 219.075
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 5] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 678.7763 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 1095.375 - 0 - 678.7763
A-rpr = 416.5987 mm^2

t_rpr = (A_rpr / D) + repad_CA


PAGE 70 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (416.5987 / 219.075) + 0


t_rpr = 1.9016 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 8 in
Repad Size (OD) Must be 450 mm

Nozzle R-5 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 2 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 60.325
Required Area = 301.625 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 60.325
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.5372 - 0) + 5] * (5.5372 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 176.1835 mm^2
PAGE 71 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 301.625 - 0 - 176.1835
A-rpr = 125.4415 mm^2

Since Nozzle size <= NPS 2 (per API-650 5.7.2), t_rpr = 0

No Reinforcement Pad required.

Nozzle R-6 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 6 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 168.275
Required Area = 841.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 168.275
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
PAGE 72 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Nozzle Neck Area = [4 * (10.9728 - 0) + 5] * (10.9728 - 0) * MIN((103.4213/137) 1)


Available Nozzle Neck Area = 529.2346 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 841.375 - 0 - 529.2346
A-rpr = 312.1404 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (312.1404 / 168.275) + 0
t_rpr = 1.8549 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 6 in
Repad Size (OD) Must be 375 mm

Nozzle R-7 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 2 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 60.325
Required Area = 301.625 mm^2
PAGE 73 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 60.325
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.5372 - 0) + 5] * (5.5372 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 176.1835 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 301.625 - 0 - 176.1835
A-rpr = 125.4415 mm^2

Since Nozzle size <= NPS 2 (per API-650 5.7.2), t_rpr = 0

No Reinforcement Pad required.

Nozzle R-8 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 8 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


PAGE 74 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Required Area = 5 * 219.075


Required Area = 1095.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 219.075
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 5] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 678.7763 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 1095.375 - 0 - 678.7763
A-rpr = 416.5987 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (416.5987 / 219.075) + 0
t_rpr = 1.9016 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 8 in
Repad Size (OD) Must be 450 mm

Nozzle R-10 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 6 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
PAGE 75 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14, or API-650 FIG
5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 168.275
Required Area = 841.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 168.275
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (10.9728 - 0) + 5] * (10.9728 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 529.2346 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 841.375 - 0 - 529.2346
A-rpr = 312.1404 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (312.1404 / 168.275) + 0
t_rpr = 1.8549 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 6 in
Repad Size (OD) Must be 375 mm

Nozzle S-2 Reinforcement Requirements

NOZZLE Description : 16 in SCH 40 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

PAGE 76 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

MOUNTED ON SHELL 1 : Elevation = 0.531 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 406.4
Required Area = 7255.9431 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 406.4
Available Shell Area = 1130.1209 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 20.635] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 1278.3621 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 7255.9431 - 1130.1209 - 1278.3621
A-rpr = 4847.4602 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (4847.4602 / 406.4) + 0
t_rpr = 11.9278 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 16 in
Repad Size (L x W) Must be 850 x 1035 mm

Nozzle S-3 Reinforcement Requirements

NOZZLE Description : 12 in SCH XS TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
PAGE 77 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sd_n = (Stress of Neck Material)


Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.449 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 323.85
Required Area = 5782.0797 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 323.85
Available Shell Area = 900.5651 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 20.635] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 1278.3621 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 5782.0797 - 900.5651 - 1278.3621
A-rpr = 3603.1525 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (3603.1525 / 323.85) + 0
t_rpr = 11.126 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 12 in
Repad Size (L x W) Must be 685 x 840 mm

PAGE 78 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Nozzle S-4 Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm
PAGE 79 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-8A Reinforcement Requirements

NOZZLE Description : 2 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.175 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 60.325
Required Area = 1077.0541 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 60.325
Available Shell Area = 167.7523 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.54 - 0) + 20.635] * (5.54 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 437.871 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 1077.0541 - 167.7523 - 437.871
A-rpr = 471.4308 mm^2
PAGE 80 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (471.4308 / 60.325) + 0
t_rpr = 7.8148 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 2 in
Repad Size (L x W) Must be 203 x 203 mm

Nozzle S-9A Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2
PAGE 81 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-9B Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2
PAGE 82 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-9C Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2
PAGE 83 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-9D Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)
PAGE 84 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-5 Reinforcement Requirements

NOZZLE Description : 2 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.175 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
PAGE 85 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_c = 20.635 mm (Course t less C.A.)


t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 60.325
Required Area = 1077.0541 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 60.325
Available Shell Area = 167.7523 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.54 - 0) + 20.635] * (5.54 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 437.871 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 1077.0541 - 167.7523 - 437.871
A-rpr = 471.4308 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (471.4308 / 60.325) + 0
t_rpr = 7.8148 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 2 in
Repad Size (L x W) Must be 203 x 203 mm

Nozzle S-6 Reinforcement Requirements

NOZZLE Description : 6 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.306 ft


PAGE 86 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 168.275
Required Area = 3004.414 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 168.275
Available Shell Area = 467.9407 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (10.97 - 0) + 20.635] * (10.97 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 1046.9167 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 3004.414 - 467.9407 - 1046.9167
A-rpr = 1489.5566 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1489.5566 / 168.275) + 0
t_rpr = 8.8519 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 6 in
Repad Size (L x W) Must be 400 x 495 mm

Nozzle S-7 Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
PAGE 87 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sd_s = (Stress of Shell Course Material)


CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-10 Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO


PAGE 88 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 114.3
Required Area = 2040.734 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 114.3
Available Shell Area = 317.8465 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2040.734 - 317.8465 - 754.6263
A-rpr = 968.2612 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (968.2612 / 114.3) + 0
t_rpr = 8.4712 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

PAGE 89 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Nozzle R-11 Reinforcement Requirements

NOZZLE Description : 2 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.175 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 60.325
Required Area = 1077.0541 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 60.325
Available Shell Area = 167.7523 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.54 - 0) + 20.635] * (5.54 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 437.871 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 1077.0541 - 167.7523 - 437.871
A-rpr = 471.4308 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (471.4308 / 60.325) + 0
t_rpr = 7.8148 mm

PAGE 90 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Reinforcement Pad is required.


Based on Shell Nozzle Size of 2 in
Repad Size (L x W) Must be 203 x 203 mm

Nozzle R-12 Reinforcement Requirements

NOZZLE Description : 6 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.306 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 168.275
Required Area = 3004.414 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 168.275
Available Shell Area = 467.9407 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (10.97 - 0) + 20.635] * (10.97 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 1046.9167 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 3004.414 - 467.9407 - 1046.9167
A-rpr = 1489.5566 mm^2

PAGE 91 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1489.5566 / 168.275) + 0
t_rpr = 8.8519 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 6 in
Repad Size (L x W) Must be 400 x 495 mm

Manway S1-A Reinforcement Requirements

MANWAY Description : 30 in SCH --

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.9 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL MANWAY REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 793.75
Required Area = 14172 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 793.75
Available Shell Area = 2207.2673 mm^2

Available Manway Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Manway Neck Area = [4 * (15.875 - 0) + 20.635] * (15.875 - 0) * MIN((137/137) 1)
Available Manway Neck Area = 2318.385 mm^2
PAGE 92 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

A-rpr = (Required Area - Available Shell Area - Available Manway Neck Area)
A-rpr = 14172 - 2207.2673 - 2318.385
A-rpr = 9646.1116 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (9646.1116 / 793.75) + 0
t_rpr = 12.1526 mm

Reinforcement Pad is required.


Based on Shell Manway Size of 30 in
Repad Size (L x W) Must be 1543.05 x 1866.9 mm

Manway S1-2 Reinforcement Requirements

MANWAY Description : 30 in SCH --

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.9 ft

COURSE PARAMETERS:
t-calc = 19.4442 mm
t_cr = 17.8542 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 17.8542 mm

(SHELL MANWAY REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 17.8542 * 793.75
Required Area = 14172 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 17.8542) * 793.75
Available Shell Area = 2207.2673 mm^2
PAGE 93 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Manway Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Manway Neck Area = [4 * (15.875 - 0) + 20.635] * (15.875 - 0) * MIN((137/137) 1)
Available Manway Neck Area = 2318.385 mm^2

A-rpr = (Required Area - Available Shell Area - Available Manway Neck Area)
A-rpr = 14172 - 2207.2673 - 2318.385
A-rpr = 9646.1116 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (9646.1116 / 793.75) + 0
t_rpr = 12.1526 mm

Reinforcement Pad is required.


Based on Shell Manway Size of 30 in
Repad Size (L x W) Must be 1543.05 x 1866.9 mm

Manway R-1 Reinforcement Requirements

(Per API-650 Section 5.8.4 and other references below)


MANWAY Description : 24 in SCH -- TYPE
t_rpr = (Re Pad Required Thickness)
MOUNTED ON ROOF: Elevation = 25.0466 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF MANWAY,REF. API-650 FIG 5-16, TABLE 5-13)

Required Area = t_Basis * D


Required Area = 5 * 623.6
Required Area = 3118 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 623.6
Available Roof Area = 0 mm^2

PAGE 94 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Manway Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Manway Neck Area = [4 * (7 - 0) + 5] * (7 - 0) * MIN((137/137) 1)
Available Manway Neck Area = 288.29 mm^2

A-rpr = (Required Area - Available Roof Area - Available Manway Neck Area)
A-rpr = 3118 - 0 - 288.29
A-rpr = 2829.71 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (2829.71 / 623.6) + 0
t_rpr = 4.5377 mm

Reinforcement Pad is required.


Based on Roof Manway Size of 24 in
Repad Size (OD) Must be 1150 mm

CAPACITIES and WEIGHTS Back

Maximum Capacity (to Max Liq Level) : 8,394 M^3


Capacity to Top of Shell (to Tank Height) : 8,570 M^3
Working Capacity (to Normal Working Level) : 7,989 M^3
Net working Capacity (Working Capacity - Min Capacity) : 7,585 M^3
Minimum Capacity (to Min Liq Level) : 404 M^3

Component New Condition (N) New Condition (Kg) Corroded (N) Corroded (Kg)
SHELL 1,681,346 171,450 1,483,325 151,257
ROOF 135,607 13,829 135,607 13,829
RAFTERS 116,947 11,926 192,743 19,655
GIRDERS 0 0 0 0
FRAMING 0 0 0 0
COLUMNS 22,511 2,296 22,511 2,296
BOTTOM 190,740 19,451 150,090 15,305
STAIRWAYS 17,339 1,768 17,339 1,768
STIFFENERS 7,755 791 7,755 791
WIND GIRDERS 0 0 0 0
ANCHOR CHAIRS 13,534 1,380 13,534 1,380
INSULATION 0 0 0 0
TOTAL 2,185,779 222,891 2,022,904 206,281

PAGE 95 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Weight of Tank, Empty : 2,185,779 N (222891 kg)


Weight of Tank, Full of Product (SG = 1) : 84,616,026.6809 N (8628431.626 kg)
Weight of Tank, Full of Water : 84,616,024.9071 N (8628431.44 kg)
Net Working Weight, Full of Product : 80,542,838.5516 N (8213082.11 kg)
Net Working Weight Full of Water : 80,542,838.5516 N (8213082.11 kg)

Foundation Area Req'd : 264.3012 m^2


Foundation Loading, Empty : 8,270.0279 N/m^2
Foundation Loading, Full of Product : 311,879.8615 N/m^2
Foundation Loading, Full of Water : 311,879.8548 N/m^2

SURFACE AREAS
Roof : 352.6778 m^2
Shell : 1,621.4532 m^2
Bottom : 264.3012 m^2

Wind Moment : 3,069,187.4814 N-m


Seismic Moment : 1,659,024.1285 N-m

MISCELLANEOUS ATTACHED ROOF ITEMS


MISCELLANEOUS ATTACHED SHELL ITEMS

MAWP & MAWV SUMMARY Back

MAWP = Maximum calculated internal pressure


MAWV = Maximum calculated external pressure

MAXIMUM CALCULATED INTERNAL PRESSURE


MAWP = 18 kPa or 1,835.658 mmh2o (per API-650 App. F.1.3 & F.7)
MAWP = 35.9771 kPa or 3,668.9806 mmh2o (due to shell)
MAWP = 0.9331 kPa or 95.1585 mmh2o (due to roof)
TANK MAWP = 0.9331 kPa or 95.1592 mmh2o

MAXIMUM CALCULATED EXTERNAL PRESSURE


MAWV = -6.9 kPa or -703.6689 mmh2o (per API-650 V.1)
MAWV = N/A (due to shell) (API-650 App.V not applicable)
MAWV = -0.2442 kPa or -24.9038 mmh2o (due to roof)
TANK MAWV = -0.2442 kPa or -24.9079 mmh2o

PAGE 96 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Appendix 2 – Mechanical Calculation gasoline tanks

PAGE 97 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

AMETANK REPORT
TABLE OF CONTENTS

SUMMARY OF DESIGN DATA AND REMARKS

ROOF DESIGN

ROOF SUMMARY OF RESULTS

SHELL COURSE DESIGN

SHELL SUMMARY OF RESULTS

BOTTOM DESIGN

BOTTOM SUMMARY OF RESULTS

WIND MOMENT

SEISMIC SITE GROUND MOTION

SEISMIC CALCULATIONS

ANCHOR BOLT DESIGN

ANCHOR BOLT SUMMARY OF RESULTS

CAPACITIES AND WEIGHTS

MAWP & MAWV SUMMARY


PAGE 98 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

No Warnings!!

SUMMARY OF DESIGN DATA AND REMARKS Back

Date of Calcs. : 23-Jul-2018


Mfg. or Insp. Date :
Designer : THOMAS
Project :
Tag Number :
Plant : PURCHASER DESCRIPTION CITY AND STATE
Plant Location : TERMICAL VERACRUZ
Site : VERACRUZ
Design Basis : API-650 12th Edition, March 2013

TANK NAMEPLATE INFORMATION

Pressure Combination Factor 0.4


Design Standard API-650 12th Edition, March 2013
Appendices Used E
Roof A283M-C : 5 mm
Shell (1) A283M-C : 22.225 mm
Shell (2) A283M-C : 22.225 mm
Shell (3) A283M-C : 17.4625 mm
Shell (4) A283M-C : 15.875 mm
Shell (5) A283M-C : 14.2875 mm
Shell (6) A283M-C : 12.7 mm
Shell (7) A283M-C : 9.525 mm
Shell (8) A283M-C : 7.93 mm
Shell (9) A283M-C : 6.35 mm
Shell (10) A283M-C : 6.35 mm
Bottom A283M-C : 8 mm

PAGE 99 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Design Internal Pressure = 0 KPa or 0 mmh2o


Design External Pressure = -0 KPa or -0 mmh2o

MAWP = 0.8558 KPa or 87.2771 mmh2o


MAWV = 0.4495 KPa or 45.8409 mmh2o

D of Tank = 23.18 m
OD of Tank = 23.2245 m
ID of Tank = 23.18 m
CL of Tank = 23.2022 m
Shell Height = 24.38 m
S.G of Contents = 1
Max Liq. Level = 23.88 m
Min Liq. Level = 1.18 m
Design Temperature = 90 ºC
Tank Joint Efficiency = 1
Ground Snow Load = 0 KPa
Roof Live Load = 1 KPa
Additional Roof Dead Load = 2.942 KPa
Basic Wind Velocity = 140.4 kph
Wind Importance Factor = 1

Using Seismic Method: API-650 - Site Specific

DESIGNER REMARKS

Remarks or Comments

PAGE 100 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

SUMMARY OF SHELL RESULTS

t-
Min Tensil
t-min t-min min t-
CA Yield e Sd St Weig
Width Materia J Weig Erecti t-Des t-Test Seism Ext- t-min Actua
Shell # (m Streng Streng (MP (MP ht CA Status
(mm) l E ht (N) on (mm) (mm) ic Pe (mm) l
m) th th a) a) (N)
(mm) (mm) (m (mm)
(MPa) (MPa)
m)
A283M- 1.5 303,1 281,5 21.13 17.39 15.22 21.13 22.22
1 2438.4 1 205 380 137 154 6 NA OK
C 9 97 25 94 13 63 94 5
A283M- 1.5 303,1 281,5 19.11 15.59 13.81 19.11 22.22
2 2438.4 1 205 380 137 154 6 NA OK
C 9 97 25 78 29 68 78 5
A283M- 1.5 238,2 216,5 17.09 13.79 17.09 17.46
3 2438.4 1 205 380 137 154 6 12.18 NA OK
C 9 75 95 62 45 62 25
A283M- 1.5 216,6 194,9 15.07 11.99 10.70 15.07 15.87
4 2438.4 1 205 380 137 154 6 NA OK
C 9 29 45 46 6 8 46 5
A283M- 1.5 194,9 173,2 13.05 10.19 9.245 13.05 14.28
5 2438.4 1 205 380 137 154 6 NA OK
C 9 79 93 3 76 9 3 75
A283M- 1.5 173,3 151,6 11.03 8.399 7.797 11.03
6 2438.4 1 205 380 137 154 6 NA 12.7 OK
C 9 27 37 14 2 5 14
A283M- 1.5 130,0 108,3 9.009 6.600 6.235 9.009
7 2438.4 1 205 380 137 154 6 NA 9.525 OK
C 9 13 17 8 7 9 8
A283M- 1.5 108,2 86,55 6.988 4.802 4.833 6.988
8 2438.4 1 205 380 137 154 6 NA 7.93 OK
C 9 49 0 2 3 8 2
A283M- 1.5 86,68 64,98 4.966 3.003 3.492
9 2438.4 1 205 380 137 154 6 NA 6 6.35 OK
C 9 7 5 6 9 3
A283M- 1.5 86,54 64,87 1.205 2.353
10 2434.4 1 205 380 137 154 6 2.945 NA 6 6.35 OK
C 9 5 9 4 9

Total Weight of Shell = 1,841,102.142 N

CONE ROOF

Plates Material = A283M-C


Structural Material = A36M
t.required = 5 mm
t.actual = 5 mm
Roof corrosion allowance = 0 mm
Roof Joint Efficiency = 1
Plates Overlap Weight = 2,739.6454 N (615,89 kg)
Plates Weight = 162,579.5292 N (16578,49 kg)

PAGE 101 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RAFTERS:

Thru Rafters and Jack Rafters

Qty At Radius (m) Size Length (m) W (N/m) Ind. Weight (N) Total Weight (N)
28 11.59 W10X30 10.8459 437.8171 4,748.5581 132,959.6285
28 5.7981 W10X12 5.8263 175.1268 1,020.3555 28,569.9542

Rafters Total Weight = 161,529.5828 N (16471.43 kg)

GIRDERS:

Header Channel

Qty At Radius (m) Size Length (m) W (N/m) Ind. Weight (N) Total Weight (N)
28 5.7981 C4X5.4 0.9977 78.807 78.6269 2,201.5556

Girders Total Weight = 2,201.5556 N (224.49 kg)

COLUMNS:

Qty At Radius (m) Size Length (m) W (N/m) Ind. Weight (N) Total Weight (N)
1 5.795 16" SCH 40 24.6694 1,209.0703 29,825.3064 29,825.3064

Columns Total Weight = 29,825.3064 N (3041.33 kg)

Bottom Type : Cone-Up Bottom Floor

Bottom Material = A283M-C


t.required = 8 mm
t.actual = 8 mm
Bottom corrosion allowance = 2 mm
Bottom Joint Efficiency = 1

PAGE 102 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Total Weight of Bottom = 231,283.9541 N (23584.39 kg)

ANCHOR BOLT : (25) M30 mm UNC Bolts, A36M

TOP END STIFFENER : Detail A

Size = l80x80x10
Material = A36M
Weight = 8,487.8716 N (865.52 kg)

STRUCTURALLY SUPPORTED CONICAL ROOF Back

A = Actual Part. Area of Roof-to-shell Juncture per API-650 (cm^2)


A-min = Minimum participating area (cm^2) per API-650 5.10.5.2
a-min-A = Minimum participating area due to full design pressure per API-650 F.5.1 (cm^2)
a-min-Roof = Minimum participating area per API-650 App. F.5.2 (cm^2)
Add-DL = Added Dead load (kPa)
Afr = Area of frangible roof (mm^2)
Alpha = 1/2 the included apex angle of cone (degrees)
Aroof = Contributing Area due to roof plates (cm^2)
Ashell = Contributing Area due to shell plates (cm^2)
CA = Roof corrosion allowance (mm)
D = Tank Nominal Diameter per API-650 5.6.1.1 Note 1 (m)
density = Density of roof (kg/mm3)
DL = Dead load (kPa)
DLR = Nominal weight of roof plate plus weight of roof plates overlap plus any attached structural
(N)
DLs = Total weight of the shell and any framing (but not roof plates) supported by the shell and roof
(N)
e.1b = Gravity Roof Load (1) - Balanced (kPa)
e.1u = Gravity Roof Load (1) - Unbalanced (kPa)
e.2b = Gravity Roof Load (2) - Balanced (kPa)
e.2u = Gravity Roof Load (2) - Unbalanced (kPa)
Fp = Pressure Combination Factor
Fy = smallest of the yield strength (MPa)
Fy-roof = Minimum yield strength for shell material (Table 5-2a) (MPa)
Fy-shell = Minimum yield strength for shell material (Table 5-2a) (MPa)
Fy-stiff = Minimum yield strength for stiffener material (Table 5-2a) (MPa)
hr = Roof height (m)

PAGE 103 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

ID = Tank Inner Diameter (m)


Insulation = Roof Insulation (m)
JEr = Roof joint efficiency
Lr = Entered Roof Live Load (kPa)
Lr-1 = Computed Roof Live Load, including External Pressure
Max-p = Max Roof Load due to participating Area (kPa)
Net-Uplift = Uplift due to internal pressure minus nominal weight of shell, roof and attached framing
(N), per API-650 F.1.2
P = Minimum participating area (kPa)
P-ext-2 = Max external pressure due to roof shell joint area (kPa)
P-F51 = Max design pressure reversing a-min-A calculation (kPa)
P-F6 = Calculated minimum failure pressure (kPa)
P-max-ext-T = Total max external pressure due to roof actual thickness and roof participating area
(kPa)
P-max-internal = Maximum design pressure and test procedure per API-650 F.4, F.5. (kPa)
P-Std = Max pressure pressure allowed per API-650 App. F.1 & F.7 (kPa)
P-Uplift = Uplift case per API-650 1.1.1 (N)
P-weight = Dead load of roof plate (kPa)
Pe = External Pressure (kPa)
Pf-anchor = Failure pressure for anchor design (kPa)
pt = Roof cone pitch (mm) rise per 12 (mm)
Pv = Internal Pressure (kPa)
R = Roof horizontal radius (m)
Ra = Roof surface area (cm^2)
Roof-wc = Weight corroded of roof plates (N)
S = Ground Snow Load per ASCE 7-05 Fig 7-1 (kPa)
Sb = Balanced Design Snow Load per API-650 Section 5.2.1.h.1 (kPa)
Shell-wc = Weight corroded of shell (N)
Su = Unbalanced Design Snow Load per API-650 Section 5.2.1.h.2 (kPa)
T = Balanced Roof Design Load per API-650 Appendix R (kPa)
t-calc = Minimum nominal roof plates thickness per API-650 Section 5.10.5.1 (mm)
t-Ins = thickness of Roof Insulation (m)
Theta = Angle of cone to the horizontal (degrees)
U = Unbalanced Roof Design Load per API-650 Appendix R (kPa)
Wc = Maximum width of participating shell per API-650 Fig. F-2 (mm)
Wh = Maximum width of participating roof per API-650 Fig. F-2 (mm)

Roof Design Per API-650

Note: Tank Pressure Combination Factor Fp = 0.4

PAGE 104 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

D = 23.18 m
ID = 23.18 m
CA = 0 mm
R = 11.59 m
Fp = 0.4
JEr = 1
JEs = 1
JEst = 1
Insulation = 0 m
Add-DL = 2.942 kPa
Lr = 1 kPa
S = 0 kPa
Sb = 0 kPa
Su = 0 kPa
density = 0.000007841 kg/mm3
P-weight = 0.3853 KPa
Pe = 0 kPa
pt = 0.75 mm rise per 12 mm
t-actual = 5 mm
Fy-roof = 205 MPa
Fy-shell = 205 MPa
Fy-stiff = 250 MPa
Shell-wc = 1,624,256.5761 N
Roof-wc = 162,579.5292 N
P-Std = 18 kPa, Per API-650 F.1.3
t-1 = 6.35 mm
CA-1 = 1.59 mm
Sd = 137 MPa

Theta = TAN^-1 (pt/12)


Theta = TAN^-1 (0.75/12)
Theta = 3.5763 degrees

Alpha = 90 - Theta
Alpha = 90 - 3.5763
Alpha = 86.4237 degrees

Ap-Vert = D^2 * TAN(Theta)/4


Ap-Vert = 23.18^2 * TAN(3.5763)/4
Ap-Vert = 8.3955 m^2

PAGE 105 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Horizontal Projected Area of Roof per API-650 5.2.1.f

Xw = D * 0.5
Xw = 23.18 * 0.5
Xw = 11.59 m

Ap = PI * (D/2)^2
Ap = PI * (23.18/2)^2
Ap = 422.0041 m^2

DL = Insulation + P-weight + Add-DL


DL = 0 + 0.3853 + 2.942
DL = 3.3273 kPa

Roof Loads per API-650 5.2.2

e.1b = DL + MAX(Sb , Lr) + (0.4 * Pe)


e.1b = 3.3273 + MAX(0 , 1) + (0.4 * 0)
e.1b = 4.3273 kPa

e.2b = DL + Pe + (0.4 * MAX(Sb , Lr))


e.2b = 3.3273 + 0 + (0.4 * MAX(0 , 1))
e.2b = 3.7273 kPa

T = MAX(e.1b , e.2b)
T = MAX(4.3273 , 3.7273)
T = 4.3273 kPa

e.1u = DL + MAX(Su , Lr) + (0.4 * Pe)


e.1u = 3.3273 + MAX(0 , 1) + (0.4 * 0)
e.1u = 4.3273 kPa

e.2u = DL + Pe + (0.4 * MAX(Su , Lr))


e.2u = 3.3273 + 0 + (0.4 * MAX(0 , 1))
e.2u = 3.7273 kPa

U = MAX(e.1u , e.2u)
U = MAX(4.3273 , 3.7273)
U = 4.3273 kPa

PAGE 106 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Lr-1 = MAX(T , U)
Lr-1 = MAX(4.3273 , 4.3273)
Lr-1 = 4.3273 kPa

Ra = PI * R * SQRT(R^2 + hr^2)
Ra = PI * 11.59 * SQRT(11.59^2 + 0.7244^2)
Ra = 4,228,275.9568 cm^2 or 422.8276 m^2

Roof Plates Weight = density * Ra * t-actual


Roof Plates Weight = 0.000007841 * 4,228,275.9568 * 5
Roof plates Weight = 162,579.5292 N (16578.49 kg)

BAY 1 DETAILS

MINIMUM # OF RAFTERS

l = Maximum rafter spacing per API-650 5.10.4.4 (mm)


l-actual-1 = Actual rafter spacing (mm)
Max-T1-1 = Due to roof thickness (kPa)
N-actual-1 = Actual number of rafter
N-min-1 = Minimum number of rafter
P = Uniform pressure as determined from load combinations described in Appendix R (kPa)
P-ext-1-1 = Due to roof thickness vacuum limited by actual rafter spacing (kPa)
R-1 = Outer radius (mm)
RLoad-Max-1 = Maximun roof load based on actual rafter spacing (kPa)
t-calc-1 = Minimum roof thickness based on actual rafter spacing (mm)

FOR OUTER SHELL RING

P = Lr-1
P = 4.3273 kPa

R-1 = 11590 mm

l = MIN(((t-Roof - CA-Roof) * SQRT((1.5 * Fy-Roof)/P)) , 2100.0)


l = MIN(((5 - 0) * SQRT((1.5 * 205) / 4.3273)) , 2100)
l = MIN(1332.8661 , 2100)
l = 1332.8661 mm

PAGE 107 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

N-min-1 = (2 * PI * R-1)/l
N-min-1 = (2 * PI * 11590)/1332.8661
N-min-1 = 55

N-min-1 must be a multiple of 1, therefore N-min-1 = 55.

N-actual-1 = 56

l-actual-1 = (2 * PI * R-1)/N-actual-1
l-actual-1 = (2 * PI * 11590)/56
l-actual-1 = 1300.395 mm

Minimum roof thickness based on actual rafter spacing

t-calc-1 = l-actual-1/SQRT((1.5 * Fy-Roof)/P) + CA-Roof


t-calc-1 = 1300.395/SQRT((1.5 * 205)/4.3273) + 0
t-calc-1 = 4.8782 mm

NOTE: Governs for roof plate thickness.

RLoad-Max-1 = (1.5 * Fy-Roof)/(l-actual-1/(t-Roof - CA-Roof))^2


RLoad-Max-1 = (1.5 * 205)/(1300.395/(5 - 0))^2
RLoad-Max-1 = 4.5461 kPa

Max-T1-1 = RLoad-Max-1
Max-T1-1 = 4.5461 kPa

P-ext-1-1 = Max-T1-1 - DL - (0.4 * MAX(Sb , Lr))


P-ext-1-1 = 4.5461 - 3.3273 - (0.4 * MAX(0 , 1))
P-ext-1-1 = -0.8188 kPa

Pa-rafter-3-1 = P-ext-1-1
Pa-rafter-3-1 = -0.8188 kPa

t-required-1 = MAX(4.8782 , (5 + 0))


t-required-1 = 5 mm

PAGE 108 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RAFTER DESIGN

Average-p-width-1 = Average plate width (m)


Average-r-s-inner-1 = Average rafter spacing on inner girder (m)
Average-r-s-shell-1 = Average rafter spacing on shell (m)
Max-P-1 = Load allowed for each rafter in ring (MPa)
Max-r-span-1 = Maximum rafter span (m)
Max-T1-rafter-1 = Due to roof thickness (kPa)
Mmax-rafter-1 = Maximum moment bending (mm-kg)
P = Uniform pressure as determined from load combinations described in Appendix R (kPa)
P-ext-2-1 = Vacuum limited by rafter type (kPa)
R-1 = Outer radius (mm)
R-Inner-1 = Inner radius (m)
Rafter-Weight-1 = (Kg/m)
Sx-rafter-actual-1 = Actual elastic section modulus about the x axis (cm^3)
Sx-rafter-Req'd-1 = Required elastic section modulus about the x axis (cm^3)
Theta = Angle of cone to the horizontal (degrees)
W-Max-rafter-1 = Maximum stress allowed for each rafter in ring (N/mm)
W-rafter-1 = (kg/m)

SPAN TO SHELL

P = 4.3273 kPa
Rafter-Weight-1 = 44.6449 Kg/m
Theta = 3.5763 degrees
R-1 = 11667 mm
R-Inner1 = 774 mm

Max-r-span-1 = (R-1 - R-Inner-1)/COS(Theta)


Max-r-span-1 = (11667 - 774)/COS(3.5763)
Max-r-span-1 = 10.846 m

Average-r-s-inner-1 = (2 * PI * R-Inner-1)/N-actual-1
Average-r-s-inner-1 = (2 * PI * 774)/56
Average-r-s-inner-1 = 0.0868 m

Average-r-s-shell-1 = (2 * PI * R-1)/N-actual-1
Average-r-s-shell-1 = (2 * PI * 11667)/56
Average-r-s-shell-1 = 1.309 m

PAGE 109 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Average-p-width-1 = (Average-r-s-inner-1 + Average-r-s-shell-1)/2


Average-p-width-1 = (0.0868 + 1.309)/2
Average-p-width-1 = 0.6979 m

W-rafter-1 = (P * Average-p-width-1) + Rafter-Weight-1


W-rafter-1 = (441.3796 * 0.6979) + 44.6449
W-rafter-1 = 352.6149 Kgf/m

Mmax-rafter-1 = (W-rafter-1 * Max-r-span-1^2)/8


Mmax-rafter-1 = (352.6149 * 10.846^2)/8
Mmax-rafter-1 = 5,185,001 mm-kgf

Sx-rafter-Req'd-1 = Mmax-rafter-1/Sd
Sx-rafter-Req'd-1 = 5,185,001/160
Sx-rafter-Req'd-1 = 317.7968 cm^3

Sx-actual-1 = 530.9409 cm^3

W-Max-rafter-1 = (Sx-rafter-actual-1 * Sd * 8)/Max-r-span-1^2)


W-Max-rafter-1 = (530.9409 * 160 * 8)/10.846^2)
W-Max-rafter-1 = 5.7772 N/mm

Max-P-1 = (W-Max-rafter-1 - Rafter-Weight-1)/Average-p-width-1


Max-P-1 = 0.0082 MPa

Max-T1-rafter-1 = Max-P-1
Max-T1-rafter-1 = 8.2 kPa

P-ext-2-1 = Max-T1-rafter-1 - DL - (Fp * MAX(S , Lr))


P-ext-2-1 = 8.2 - 3.3273 - (0.4 * MAX(0 , 1))
P-ext-2-1 = -4.4863 kPa

P2-rafter-3-1 = P-ext-2-1
P2-rafter-3-1 = -4.4863 kPa

Limited by rafter type

PAGE 110 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

CENTER COLUMN

A-actual-1 = Actual area of column (mm^2)


A-req-1 = Required area of column (mm^2)
C-length-1 = Column length (mm)
E-c = Modulus of elasticity of the column material (MPa)
Fa-1 = Allowable compressive stress per API-650 5.10.3.4 (MPa)
Fy-c = Allowable design stress (MPa)
Max-P-column-1 = Maximum Load allowed for each column in ring (MPa)
Max-T1-column-1 = Due to roof thickness (kPa)
P-c-1 = Total roof load supported by each column (N)
P-ext-3-1 = Vacuum limited by column type (kPa)
Pa-column-3-1 = Vacuum limited by column type (kPa)
Pa-column-3-1 = Vacuum limited by column type (kPa)
R-c-1 = Per API-650 5.10.3.3
Radius-Gyr-1 = Radius of gyration
Radius-Gyr-req-1 = Radius of gyration required
W-column-1 = Total weight of column (N)
W-Max-column-1 = Maximum weight allowed for each column in ring (N)

W-column-1 = 29,825.3064 N
Fy-c = 241.3165 MPa
E-c = 197,190.0782 MPa
A-actual-1 = 157.0793 cm^2
C-length-1 = 24.6694 m
Radius-Gyr-1 = 139.194 mm

If C-length-1/Radius-Gyr-1 must be less than 180, then

Radius-Gyr-req-1 = C-length-1/180
Radius-Gyr-req-1 = 24.6694/180
Radius-Gyr-req-1 = 137.0526 mm

Per API-650 5.10.3.3

R-c-1 = C-length-1/Radius-Gyr-1
R-c-1 = 24.6694/139.194
R-c-1 = 177.2309

PAGE 111 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Rafter-L-1 = (- R-1 - R-Inner1)/COS(Theta)


Rafter-L-1 = (- 11590 - 0)/COS(3.5763)
Rafter-L-1 = 10846 mm

P-c-1 = W-column-1 + (W-girder-1 * Girder-Length-1)


P-c-1 = 29,825.3064 + (0 * 0)
P-c-1 = 29,825.3064 N

Since R-c-1 > 120, using API-650 Formulas in 5.10.3.4

Fa-1 = (/ (* 12 (EXPT PI 2) E-c) (* 23 (EXPT R-c-1 2)))


Fa-1 = (/ (* 12 (EXPT PI 2) 197,190.0782) (* 23 (EXPT 177.2309 2)))

Per API-650 M.3.5


Fa is not modified Since Design Temp. <= 93.3333 ºC.
(API-650 M.3.5 N.A.)

Fa-1 = 45.285 MPa

A-req-1 = P-c-1/Fa-1
A-req-1 = 29,825.3064/45.285
A-req-1 = 658.6122 mm^2

W-Max-column-1 = (Fa-1 * A-actual-1) - W-column-1


W-Max-column-1 = (45.285 * 157.0793) - 29,825.3064
W-Max-column-1 = 708,293.6652 N

Max-P-column-1 = ((W-Max-column-1/((Rafter-L-1 * N-actual-1)/2)) - Rafter-Weight-1)/(AVERAGE


Average-r-s-inner-1 , Average-r-s-shell-1)
Max-P-column-1 = ((708,293.6652/((10846 * 56)/2)) - 44.6449)/(AVERAGE 0 , 1.3004)
Max-P-column-1 = 0.0033 MPa

Max-T1-column-1 = Max-P-column-1
Max-T1-column-1 = 3.3 kPa

P-ext-3-1 = Max-T1-column-1 - DL - (Fp * MAX(S , Lr))


P-ext-3-1 = 3.3 - 3.3273 - (0.4 * MAX(0 , 1))
P-ext-3-1 = 0.4495 kPa

PAGE 112 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Pa-column-3-1 = P-ext-3-1
Pa-column-3-1 = 0.4495 kPa

Limited by column type

P-max-ext-T = MAX(P-ext-1-1 , P-ext-2-1 , P-ext-3-1)


P-max-ext-T = MAX(-0.8188 , -4.4863 , 0.4495)
P-max-ext-T = 0.4495 kPa

TOP MEMBER DESIGN


CA_roof (Thickness of roof plate) = 0 mm
CA_shell (Thickness of shell plate) = 1.59 mm
D (Shell nominal diameter) = 23.2022 m
ID (Shell inside diameter) = 23.18 m
Theta angle (Angle between the roof and a horizontal plane at the roof-to-shell junction) = 3.5763
deg
tc (Thickness of shell plate) = 6.35 mm
th (Thickness of roof plate) = 5 mm

Shell inside radius


Rc = ID / 2 = 23180.0 / 2 = 11590.0 mm

Shell nominal diameter (D) = 23.2022 m

Length of normal to roof


R2 = Rc / SIN(Theta angle) = 11590.0 / SIN(3.5763) = 185801.8345 mm

Thickness of corroded roof plate


th_corroded = th - CA_roof = 5 - 0 = 5 mm

Thickness of corroded shell plate


tc_corroded = tc - CA_shell = 6.35 - 1.59 = 4.76 mm

Maximum width of participating roof API-650 Figure F-2


Wh = MIN((0.3 * SQRT((R2 * th_corroded))) , 300)
= MIN((0.3 * SQRT((185801.8345 * 5))) , 300)
= 289.1554 mm

PAGE 113 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Maximum width of participating shell API-650 Figure F-2


Wc = 0.6 * SQRT((Rc * tc_corroded)) = 0.6 * SQRT((11590.0 * 4.76)) = 140.9277 mm

Nominal weight of shell plates and framing


DLS = Ws + W_framing = 1.8411021421E6 + 89065.6928 = 1.9301678348E6 N

Nominal weight of roof plates and attached structural


DLR = Wr + W_structural = 162579.5293 + 16564.6733 = 179144.2026 N

Compression Ring Detail a Properties

ID (Shell inside diameter) = 23.18 m


Size (Compression ring size) = l80x80x10
Wc (Length of contributing shell) = 140.9277 mm
Wh (Length of contributing roof) = 289.1554 mm
tc (Thickness of shell plate) = 4.76 mm
th (Thickness of roof plate) = 5 mm

Angle vertical leg size (l_vert) = 80 mm


Angle horizontal leg size (l_horz) = 80 mm
Angle thickness (t_angle) = 10.0 mm
Angle area (A_angle) = 1510.0 mm^2
Angle centroid (c_angle) = 23.4 mm
Angle moment of inertia (I_angle) = 875000.0 mm^4

Contributing shell moment of inertia


I_shell = (Wc * (tc_corroded^3)) / 12
= (140.9277 * (4.76^3)) / 12
= 1266.59 mm^4

Contributing shell area


A_shell = Wc * tc_corroded = 140.9277 * 4.76 = 670.816 mm^2

Contributing roof area


A_roof = Wh * th_corroded = 289.1554 * 5 = 1445.7768 mm^2

Detail total area


A_detail = A_shell + A_roof + A_angle
= 670.816 + 1445.7768 + 1510.0
= 3626.5928 mm^2

PAGE 114 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Find combined moment of inertia about shell inside axis with negative value toward center

Description Variable Equation Value Unit


Shell centroid d_shell tc_corroded / 2 2.3800 mm
Stiffener centroid d_stiff c_angle + tc_corroded 28.1600 mm
moment of inertia of
I_1 I_angle + (A_angle * (d_stiff^2)) 2072408.2560 mm^4
first body
moment of inertia of
I_2 I_shell + (A_shell * (d_shell^2)) 5066.3600 mm^4
second body
Total area A_sum A_angle + A_shell 2180.8160 mm^2
Sum of moments of
I_sum I_1 + I_2 2077474.6160 mm^4
inertia's
((d_stiff * A_angle) + (d_shell *
Combined centroid c_combined 20.2301 mm
A_shell)) / (A_angle + A_shell)
Combined moment of I_sum - (A_sum *
I_combined 1184959.8525 mm^4
inertia (c_combined^2))
Distance from neutral
e1 c_combined 20.2301 mm
axis to edge 1 (inside)
Distance from neutral
e2 (tc_corroded + l_horz) - e1 64.5299 mm
axis to edge 2 (outside)
Combined stiffener
S I_combined / MAX(e1 , e2) 18362.9603 mm^3
shell section modulus

PAGE 115 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Roof Design Requirements

Compression region maximum area for frangible roof API-650 5.10.2.6 a) 5)


Afr = DLS / (2 * pi * Fy * TAN(Theta angle))
= 1.9301678348E6 / (2 * pi * 205 * TAN(3.5763))
= 23976.2538 mm^2

A_actual < Afr ==> Compression region actual cross sectional area is within the limit

Appendix F Requirements

A_actual (Area resisting compressive force) = 3626.5928 mm^2


D (Tank nominal diameter) = 23.2022 m
DLR (Nominal weight of roof plates and attached structural) = 179144.2026 N
DLS (Nominal weight of shell plates and framing) = 1.9301678348E6 N
Fy (Minimum specified yield-strength of the materials in the roof-to-shell junction) = 205 MPa
ID (Tank inside diameter) = 23.18 m
Mw (Wind moment) = 7.0808415238E6 N.m
P (Design pressure) = 0.0 kPa
Theta angle (Angle between the roof and a horizontal plane at the roof-to-shell junction) = 3.5763
deg
W_framing (Weight of framing supported by the shell and roof) = 89065.6928 N
W_structural (Weight of roof attached structural) = 16564.6733 N
Wr (Roof plates weight) = 162579.5293 N
Ws (Shell plates weight) = 1.8411021421E6 N

Uplift due to internal pressure API-650 F.1.2


P_uplift = P * pi * ((ID^2) / 4) = 0.0 * pi * ((23.18^2) / 4) = 0.0 N

Tank design does not have to meet App. F requirements.

Maximum design pressure API 650 F.4.1


P_F41 = ((A_actual * Fy * TAN(Theta angle)) / (200 * (D^2))) + ((0.00127 * DLR) / (D^2))
= ((3626.5928 * 205 * TAN(3.5763)) / (200 * (23.2022^2))) + ((0.00127 * 179144.2026) /
(23.2022^2))
= 0.8542 kPa

Failure pressure for frangible roof API 650 F.6


P_F6 = (1.6 * P_F41) - ((0.000746 * DLR) / (D^2))
= (1.6 * 0.8542) - ((0.000746 * 179144.2026) / (23.2022^2))
= 1.1184 kPa

PAGE 116 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Maximum design pressure API 650 F.4.3


P_F43 = 0.8 * P_F6 = 0.8 * 1.1184 = 0.8948 kPa

Maximum design pressure


P_max = MIN(P_F41 , P_F43) = MIN(0.8542 , 0.8948) = 0.8542 kPa

P <= P_max ==> Design pressure is less than maximum allowable pressure

Maximum allowable internal pressure


P_max_internal = MIN(P_std , P_max) = MIN(18 , 0.8542) = 0.8542 kPa

SUMMARY OF ROOF RESULTS Back

Material = A283M-C
Structural Material = A36M
t-actual = 5 mm
t-required = 5 mm
t-calc = 4.8782 mm
P-Max-Internal = 0.8542 kPa
P-Max-External = 0.4495 kPa
Roof Plates Weight = 162,579.5292 N (16578.49 kg)
Weight of Rafters = 161,529.5828 N (16471.429 kg)
Weight of Girders = 2,201.5556 N (224.49 kg)
Weight of Columns = 29,825.3064 N (3041.33 kg)

SHELL COURSE DESIGN (Bottom course is #1) Back

API-650 ONE FOOT METHOD

D = Tank Nominal diameter (m) per API-650 5.6.1.1 Note 1


H = Max liquid level (m)
I-p = Design internal pressure (kPa)
L = Factor
I-p = 0 kPa
D = 23.18 m
H = 23.88 m
L = (500 * D (t-1 - Ca-1))^0.5
L = (500 * 23.18 (22.225 - 1.59))^0.5 = 489.0395

PAGE 117 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Course # 1

Ca-1 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-1 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-1 = Max pressure at design (kPa)
pmax-int-shell-1 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-1 = Shell actual thickness (mm)
t-calc-1 = Shell thickness design condition td (mm)
t-seismic-1 = See E.6.2.4 table in SEISMIC calculations.
t-test-1 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-1 = 1.59 mm
JE = 1
t-1 = 22.225 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 23.88
H' = 23.88 m

t-calc-1 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-1 (per API-650 5.6.3.2)


t-calc-1 = (4.9 * 23.18 * (23.88 - 0.3) * 1)/137 + 1.59
t-calc-1 = 21.1394 mm

hmax-1 = Sd * (t-1 - CA-1)/(2.6 * D * G) + 1


hmax-1 = 137 * (22.225 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-1 = 25.1885 m

pmax-1 = (hmax-1 - H) * 9.8 * G


pmax-1 = (25.1885 - 23.88) * 9.8 * 1

PAGE 118 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

pmax-1 = 12.8236 kPa

pmax-int-shell-1 = pmax-1
pmax-int-shell-1 = 12.8236 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 23.88
H' = 23.88 m

t-test-1 = (* 4.9 D (H' - 0.3))/St


t-test-1 = (* 4.9 23.18 (23.88 - 0.3))/154
t-test-1 = 17.3913 mm

Course # 2

Ca-2 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-2 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-2 = Max pressure at design (kPa)
pmax-int-shell-2 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-2 = Shell actual thickness (mm)
t-calc-2 = Shell thickness design condition td (mm)
t-seismic-2 = See E.6.2.4 table in SEISMIC calculations.
t-test-2 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-2 = 1.59 mm
JE = 1
t-2 = 22.225 mm
Sd = 137 MPa
St = 154 MPa

PAGE 119 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Design Condition G = 1 (per API-650)

H' = H
H' = 21.4416
H' = 21.4416 m

t-calc-2 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-2 (per API-650 5.6.3.2)


t-calc-2 = (4.9 * 23.18 * (21.4416 - 0.3) * 1)/137 + 1.59
t-calc-2 = 19.1178 mm

hmax-2 = Sd * (t-2 - CA-2)/(2.6 * D * G) + 1


hmax-2 = 137 * (22.225 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-2 = 25.1885 m

pmax-2 = (hmax-2 - H) * 9.8 * G


pmax-2 = (25.1885 - 21.4416) * 9.8 * 1
pmax-2 = 36.7199 kPa

pmax-int-shell-2 = MIN(pmax-int-shell-1 pmax-2)


pmax-int-shell-2 = MIN(12.8236 36.7199)
pmax-int-shell-2 = 12.8236 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 21.4416
H' = 21.4416 m

t-test-2 = (* 4.9 D (H' - 0.3))/St


t-test-2 = (* 4.9 23.18 (21.4416 - 0.3))/154
t-test-2 = 15.5929 mm

Course # 3

Ca-3 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-3 = Max liquid level based on shell thickness (m)
JE = Joint efficiency

PAGE 120 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

pmax-3 = Max pressure at design (kPa)


pmax-int-shell-3 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-3 = Shell actual thickness (mm)
t-calc-3 = Shell thickness design condition td (mm)
t-seismic-3 = See E.6.2.4 table in SEISMIC calculations.
t-test-3 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-3 = 1.59 mm
JE = 1
t-3 = 17.4625 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 19.0032
H' = 19.0032 m

t-calc-3 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-3 (per API-650 5.6.3.2)


t-calc-3 = (4.9 * 23.18 * (19.0032 - 0.3) * 1)/137 + 1.59
t-calc-3 = 17.0962 mm

hmax-3 = Sd * (t-3 - CA-3)/(2.6 * D * G) + 1


hmax-3 = 137 * (17.4625 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-3 = 19.4454 m

pmax-3 = (hmax-3 - H) * 9.8 * G


pmax-3 = (19.4454 - 19.0032) * 9.8 * 1
pmax-3 = 4.3339 kPa

pmax-int-shell-3 = MIN(pmax-int-shell-2 pmax-3)


pmax-int-shell-3 = MIN(12.8236 4.3339)
pmax-int-shell-3 = 4.3339 kPa

PAGE 121 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Hydrostatic Test Condition G = 1

H' = H
H' = 19.0032
H' = 19.0032 m

t-test-3 = (* 4.9 D (H' - 0.3))/St


t-test-3 = (* 4.9 23.18 (19.0032 - 0.3))/154
t-test-3 = 13.7945 mm

Course # 4

Ca-4 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-4 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-4 = Max pressure at design (kPa)
pmax-int-shell-4 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-4 = Shell actual thickness (mm)
t-calc-4 = Shell thickness design condition td (mm)
t-seismic-4 = See E.6.2.4 table in SEISMIC calculations.
t-test-4 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-4 = 1.59 mm
JE = 1
t-4 = 15.875 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 16.5648
H' = 16.5648 m

PAGE 122 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-calc-4 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-4 (per API-650 5.6.3.2)


t-calc-4 = (4.9 * 23.18 * (16.5648 - 0.3) * 1)/137 + 1.59
t-calc-4 = 15.0746 mm

hmax-4 = Sd * (t-4 - CA-4)/(2.6 * D * G) + 1


hmax-4 = 137 * (15.875 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-4 = 17.5311 m

pmax-4 = (hmax-4 - H) * 9.8 * G


pmax-4 = (17.5311 - 16.5648) * 9.8 * 1
pmax-4 = 9.4694 kPa

pmax-int-shell-4 = MIN(pmax-int-shell-3 pmax-4)


pmax-int-shell-4 = MIN(4.3339 9.4694)
pmax-int-shell-4 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 16.5648
H' = 16.5648 m

t-test-4 = (* 4.9 D (H' - 0.3))/St


t-test-4 = (* 4.9 23.18 (16.5648 - 0.3))/154
t-test-4 = 11.996 mm

Course # 5

Ca-5 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-5 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-5 = Max pressure at design (kPa)
pmax-int-shell-5 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-5 = Shell actual thickness (mm)
t-calc-5 = Shell thickness design condition td (mm)
PAGE 123 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-seismic-5 = See E.6.2.4 table in SEISMIC calculations.


t-test-5 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-5 = 1.59 mm
JE = 1
t-5 = 14.2875 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 14.1264
H' = 14.1264 m

t-calc-5 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-5 (per API-650 5.6.3.2)


t-calc-5 = (4.9 * 23.18 * (14.1264 - 0.3) * 1)/137 + 1.59
t-calc-5 = 13.053 mm

hmax-5 = Sd * (t-5 - CA-5)/(2.6 * D * G) + 1


hmax-5 = 137 * (14.2875 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-5 = 15.6167 m

pmax-5 = (hmax-5 - H) * 9.8 * G


pmax-5 = (15.6167 - 14.1264) * 9.8 * 1
pmax-5 = 14.605 kPa

pmax-int-shell-5 = MIN(pmax-int-shell-4 pmax-5)


pmax-int-shell-5 = MIN(4.3339 14.605)
pmax-int-shell-5 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 14.1264
H' = 14.1264 m

PAGE 124 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-test-5 = (* 4.9 D (H' - 0.3))/St


t-test-5 = (* 4.9 23.18 (14.1264 - 0.3))/154
t-test-5 = 10.1976 mm

Course # 6

Ca-6 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-6 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-6 = Max pressure at design (kPa)
pmax-int-shell-6 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-6 = Shell actual thickness (mm)
t-calc-6 = Shell thickness design condition td (mm)
t-seismic-6 = See E.6.2.4 table in SEISMIC calculations.
t-test-6 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-6 = 1.59 mm
JE = 1
t-6 = 12.7 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 11.688
H' = 11.688 m

t-calc-6 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-6 (per API-650 5.6.3.2)


t-calc-6 = (4.9 * 23.18 * (11.688 - 0.3) * 1)/137 + 1.59
t-calc-6 = 11.0314 mm

hmax-6 = Sd * (t-6 - CA-6)/(2.6 * D * G) + 1


hmax-6 = 137 * (12.7 - 1.59)/(2.6 * 23.18 * 1) + 1

PAGE 125 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

hmax-6 = 13.7023 m

pmax-6 = (hmax-6 - H) * 9.8 * G


pmax-6 = (13.7023 - 11.688) * 9.8 * 1
pmax-6 = 19.7405 kPa

pmax-int-shell-6 = MIN(pmax-int-shell-5 pmax-6)


pmax-int-shell-6 = MIN(4.3339 19.7405)
pmax-int-shell-6 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 11.688
H' = 11.688 m

t-test-6 = (* 4.9 D (H' - 0.3))/St


t-test-6 = (* 4.9 23.18 (11.688 - 0.3))/154
t-test-6 = 8.3992 mm

Course # 7

Ca-7 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-7 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-7 = Max pressure at design (kPa)
pmax-int-shell-7 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-7 = Shell actual thickness (mm)
t-calc-7 = Shell thickness design condition td (mm)
t-seismic-7 = See E.6.2.4 table in SEISMIC calculations.
t-test-7 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-7 = 1.59 mm
JE = 1

PAGE 126 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-7 = 9.525 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 9.2496
H' = 9.2496 m

t-calc-7 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-7 (per API-650 5.6.3.2)


t-calc-7 = (4.9 * 23.18 * (9.2496 - 0.3) * 1)/137 + 1.59
t-calc-7 = 9.0098 mm

hmax-7 = Sd * (t-7 - CA-7)/(2.6 * D * G) + 1


hmax-7 = 137 * (9.525 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-7 = 9.8736 m

pmax-7 = (hmax-7 - H) * 9.8 * G


pmax-7 = (9.8736 - 9.2496) * 9.8 * 1
pmax-7 = 6.1153 kPa

pmax-int-shell-7 = MIN(pmax-int-shell-6 pmax-7)


pmax-int-shell-7 = MIN(4.3339 6.1153)
pmax-int-shell-7 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 9.2496
H' = 9.2496 m

t-test-7 = (* 4.9 D (H' - 0.3))/St


t-test-7 = (* 4.9 23.18 (9.2496 - 0.3))/154
t-test-7 = 6.6007 mm

Course # 8

Ca-8 = Corrosion allowance per API-650 5.3.2 (mm)

PAGE 127 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

G = Design specific gravity of the liquid to be stored


H' = Effective liquid head at design pressure (m)
hmax-8 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-8 = Max pressure at design (kPa)
pmax-int-shell-8 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-8 = Shell actual thickness (mm)
t-calc-8 = Shell thickness design condition td (mm)
t-seismic-8 = See E.6.2.4 table in SEISMIC calculations.
t-test-8 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-8 = 1.59 mm
JE = 1
t-8 = 7.93 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 6.8112
H' = 6.8112 m

t-calc-8 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-8 (per API-650 5.6.3.2)


t-calc-8 = (4.9 * 23.18 * (6.8112 - 0.3) * 1)/137 + 1.59
t-calc-8 = 6.9882 mm

hmax-8 = Sd * (t-8 - CA-8)/(2.6 * D * G) + 1


hmax-8 = 137 * (7.93 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-8 = 7.9502 m

pmax-8 = (hmax-8 - H) * 9.8 * G


pmax-8 = (7.9502 - 6.8112) * 9.8 * 1
pmax-8 = 11.1622 kPa

pmax-int-shell-8 = MIN(pmax-int-shell-7 pmax-8)

PAGE 128 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

pmax-int-shell-8 = MIN(4.3339 11.1622)


pmax-int-shell-8 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 6.8112
H' = 6.8112 m

t-test-8 = (* 4.9 D (H' - 0.3))/St


t-test-8 = (* 4.9 23.18 (6.8112 - 0.3))/154
t-test-8 = 4.8023 mm

Course # 9

Ca-9 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-9 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-9 = Max pressure at design (kPa)
pmax-int-shell-9 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
t-9 = Shell actual thickness (mm)
t-calc-9 = Shell thickness design condition td (mm)
t-seismic-9 = See E.6.2.4 table in SEISMIC calculations.
t-test-9 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4384 m
Ca-9 = 1.59 mm
JE = 1
t-9 = 6.35 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H

PAGE 129 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

H' = 4.3728
H' = 4.3728 m

t-calc-9 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-9 (per API-650 5.6.3.2)


t-calc-9 = (4.9 * 23.18 * (4.3728 - 0.3) * 1)/137 + 1.59
t-calc-9 = 4.9666 mm

hmax-9 = Sd * (t-9 - CA-9)/(2.6 * D * G) + 1


hmax-9 = 137 * (6.35 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-9 = 6.0449 m

pmax-9 = (hmax-9 - H) * 9.8 * G


pmax-9 = (6.0449 - 4.3728) * 9.8 * 1
pmax-9 = 16.3864 kPa

pmax-int-shell-9 = MIN(pmax-int-shell-8 pmax-9)


pmax-int-shell-9 = MIN(4.3339 16.3864)
pmax-int-shell-9 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 4.3728
H' = 4.3728 m

t-test-9 = (* 4.9 D (H' - 0.3))/St


t-test-9 = (* 4.9 23.18 (4.3728 - 0.3))/154
t-test-9 = 3.0039 mm

Course # 10

Ca-10 = Corrosion allowance per API-650 5.3.2 (mm)


G = Design specific gravity of the liquid to be stored
H' = Effective liquid head at design pressure (m)
hmax-10 = Max liquid level based on shell thickness (m)
JE = Joint efficiency
pmax-10 = Max pressure at design (kPa)
pmax-int-shell-10 = Max internal pressure at design (kPa)
Sd = Allowable design stress for the design condition per API-650 Table 5-2b (MPa)
St = Allowable stress for the hydrostatic test condition per API-650 5.6.2.2 (MPa)
PAGE 130 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-10 = Shell actual thickness (mm)


t-calc-10 = Shell thickness design condition td (mm)
t-seismic-10 = See E.6.2.4 table in SEISMIC calculations.
t-test-10 = Shell thickness hydrostatic test condition (mm)

Material = A283M-C
Width = 2.4344 m
Ca-10 = 1.59 mm
JE = 1
t-10 = 6.35 mm
Sd = 137 MPa
St = 154 MPa

Design Condition G = 1 (per API-650)

H' = H
H' = 1.9344
H' = 1.9344 m

t-calc-10 = (4.9 * D * (H' - 0.3) * G)/Sd + Ca-10 (per API-650 5.6.3.2)


t-calc-10 = (4.9 * 23.18 * (1.9344 - 0.3) * 1)/137 + 1.59
t-calc-10 = 2.945 mm

hmax-10 = Sd * (t-10 - CA-10)/(2.6 * D * G) + 1


hmax-10 = 137 * (6.35 - 1.59)/(2.6 * 23.18 * 1) + 1
hmax-10 = 6.0449 m

pmax-10 = (hmax-10 - H) * 9.8 * G


pmax-10 = (6.0449 - 1.9344) * 9.8 * 1
pmax-10 = 40.2827 kPa

pmax-int-shell-10 = MIN(pmax-int-shell-9 pmax-10)


pmax-int-shell-10 = MIN(4.3339 40.2827)
pmax-int-shell-10 = 4.3339 kPa

Hydrostatic Test Condition G = 1

H' = H
H' = 1.9344
H' = 1.9344 m
PAGE 131 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-test-10 = (* 4.9 D (H' - 0.3))/St


t-test-10 = (* 4.9 23.18 (1.9344 - 0.3))/154
t-test-10 = 1.2054 mm

SUMMARY OF SHELL RESULTS Back

t-min-Seismic = See API-650 E.6.1.4, table in SEISMIC calculations.


Shell API-650 Summary (Bottom is 1)

t-
Min
Tensile t-min t-min min
Widt CA Yield Sd St Weigh t-
She Materi J Streng Weigh Erecti t-Des t-Test Seism Ext- t-min Statu
h (m Streng (MP (MP t CA Actua
ll # al E th t (N) on (mm) (mm) ic Pe (mm) s
(mm) m) th a) a) (N) l (mm)
(MPa) (mm) (mm) (m
(MPa)
m)
2438. A283M 303,1 281,5 21.13 17.39 15.226 21.13 22.22
1 1.59 1 205 380 137 154 6 NA OK
4 -C 97 25 94 13 3 94 5
2438. A283M 303,1 281,5 19.11 15.59 13.816 19.11 22.22
2 1.59 1 205 380 137 154 6 NA OK
4 -C 97 25 78 29 8 78 5
2438. A283M 238,2 216,5 17.09 13.79 17.09 17.46
3 1.59 1 205 380 137 154 6 12.18 NA OK
4 -C 75 95 62 45 62 25
2438. A283M 216,6 194,9 15.07 11.99 15.07 15.87
4 1.59 1 205 380 137 154 6 10.708 NA OK
4 -C 29 45 46 6 46 5
2438. A283M 194,9 173,2 13.05 10.19 13.05 14.28
5 1.59 1 205 380 137 154 6 9.2459 NA OK
4 -C 79 93 3 76 3 75
2438. A283M 173,3 151,6 11.03 8.399 11.03
6 1.59 1 205 380 137 154 6 7.7975 NA 12.7 OK
4 -C 27 37 14 2 14
2438. A283M 130,0 108,3 9.009 6.600 9.009
7 1.59 1 205 380 137 154 6 6.2359 NA 9.525 OK
4 -C 13 17 8 7 8
2438. A283M 108,2 86,55 6.988 4.802 6.988
8 1.59 1 205 380 137 154 6 4.8338 NA 7.93 OK
4 -C 49 0 2 3 2
2438. A283M 86,68 64,98 4.966 3.003
9 1.59 1 205 380 137 154 6 3.4923 NA 6 6.35 OK
4 -C 7 5 6 9
2434. A283M 86,54 64,87 1.205
10 1.59 1 205 380 137 154 6 2.945 2.3539 NA 6 6.35 OK
4 -C 5 9 4

Total Weight = 1,841,102.142 N (187740.13 kg)

PAGE 132 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

INTERMEDIATE STIFFENER CALCULATIONS PER API-650 Section 5.9.7


D = Nominal diameter of the tank shell (m)
Hu = Vertical Distance Between the Intermediate Stiffener (Per API-650 5.9.7) (m)
L_act = Actual Transform Height Spacing between Stiffeners (m)
L_0 = Uniform Maximum Transform Height Spacing between Stiffineres (m)
V = Design wind speed (km/h)
Wtr = Transposed width of each shell course (m)
Zi = Required Intermediate Stiffener Section Modulus (per API-650 5.9.6.1) (cm^3)
Zi-actual = Actual Top Comp Ring Section Modulus (cm^3)

D = 23.18 m
V = 140.4 km/h
ME = 1

Hu = ME * 9.47 * tsmin * (SQRT (tsmin / D)^3) * (190 / V)^2


Hu = 1 * 9.47 * 6.35 * (SQRT (6.35 / 23.18)^3) * (190 / 140.4)^2
Hu = 15.7902 m (Maximum Height of Unstiffened Shell)

Transforming courses (1) to (10)

Wtr = Course-width * (SQRT (t-uniform / t-course)^5)


Wtr-1 = 2.4384 * (SQRT (6.35 / 22.225)^5) = 0.1064 m
Wtr-2 = 2.4384 * (SQRT (6.35 / 22.225)^5) = 0.1064 m
Wtr-3 = 2.4384 * (SQRT (6.35 / 17.4625)^5) = 0.1944 m
Wtr-4 = 2.4384 * (SQRT (6.35 / 15.875)^5) = 0.2467 m
Wtr-5 = 2.4384 * (SQRT (6.35 / 14.2875)^5) = 0.3211 m
Wtr-6 = 2.4384 * (SQRT (6.35 / 12.7)^5) = 0.4311 m
Wtr-7 = 2.4384 * (SQRT (6.35 / 9.525)^5) = 0.8849 m
Wtr-8 = 2.4384 * (SQRT (6.35 / 7.93)^5) = 1.3991 m
Wtr-9 = 2.4384 * (SQRT (6.35 / 6.35)^5) = 2.4384 m
Wtr-10 = 2.4344 * (SQRT (6.35 / 6.35)^5) = 2.4344 m

Wtr = SUM(Wtr-n)
Wtr = 8.5629 m

PAGE 133 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

For uniformly spaced stiffeners

L_0 = Hts/# of Stiffeners + 1


L_0 = 8.5629/(0 + 1)
L_0 = 8.5629 m

L_act = Wrt
L_act = 8.5629 m

Number of Intermediate Stiffeners Sufficient Since Hu >= L_act

SUMMARY OF SHELL STIFFENING RESULTS


Number of Intermediate stiffeners req'd (NS) = 0

FLAT BOTTOM: ANNULAR PLATE DESIGN Back

Ann-a = Area of annular ring (cm^2)


Ann-d = Density of annular ring (kg/mm3)
Ann-t-actual = Actual annular ring thickness (mm)
Ann-t-min = Minimum annular ring plates thickness per API-650 5.5.3 TABLE 5-1a (mm)
Ann-w-actual = Actual annular ring width (mm)
Ann-w-min = Minimum annular ring width per API-650 5.5.2 (mm)
Ba = Area of bottom (cm^2)
Bottom-OD = Bottom diameter (m)
ca-1 = Bottom (1st) shell course corrosion allowance
ca-Ann = Annular ring corrosion allowance (mm)
Ca-bottom = Bottom corrosion allowance (mm)
D = Nominal diameter per API-650 5.6.1.1 Note 1 (m)
D-bottom = Density of bottom (kg/mm3)
G = Design specific gravity of the liquid to be stored
H = Max liquid level (m)
H' = Effective liquid head at design pressure (m)
R = Nominal radius (m)
S = Maximum Stress in first shell course per API 650 Table 5.1.a
S1 = Product stress in the first shell course per API 650 Table 5.1.a
S2 = Hydrostatic test stress in the first shell course per API 650 Table 5.1.a
Sd = Allowable design stress for the design condition in bottom (1st) shell course (MPa) per API
650 5.6.3.2
St = Allowable stress for the hydrostatic test condition in bottom (1st) shell course (MPa) per API

PAGE 134 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

650 5.6.3.2
t-1 = Bottom (1st) shell course thickness (mm)
t-actual = Actual bottom thickness (mm)
t-calc = Minimum nominal bottom plates thickness per API-650 5.4.1 (mm)
t-min = Minimum nominal bottom plates thickness per API-650 5.4.1 (mm)
t-test-1 = Bottom (1st) shell course test thickness (mm)
td-1 = Bottom (1st) shell course design thickness (mm)

Material = A283M-C
t-actual = 8 mm
Annular Ring Material = A283M-C
Ann-t-actual = 8 mm
Ann-w-actual = 762 mm

Calculation of Hydrostatic Test Stress & Product Stress (per API-650 Section 5.5.1)

Bottom-OD = 21.8785 m
JE = 1
D-bottom = 0.00000784 kg/mm3
t-1 = 22.225 mm
ca-1 = 1.59 mm
G=1
H = 23.88 m
H' = 23.88 m
St = 154 MPa
Sd = 137 MPa
Ca-bottom = 2 mm
ca-Ann = 2 mm
Ann-d = 0.000007 kg/mm3

Product stress in first shell course

S1 = ((td-1 - ca-1) / (t-1 - ca-1)) * Sd


S1 = ((21.1394 - 1.59) / (22.225 - 1.59)) * 137
S1 = 129.7922 MPa

Hydrostatic test stress in first shell course

S2 = (t-test-1 / t-1) * St
S2 = (17.3913 / 22.225) * 154

PAGE 135 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

S2 = 120.5067 MPa

S = Max (S1, S2)


S = Max (129.7922 , 120.5067)
S = 129.7922 MPa

API-650 Table 5.1a required thickness of annular ring excluding corrosion allowance is 6 mm
Annular ring required thickness = 6 + ca-Ann = 6 + 2
Annular ring required thickness = 8 mm

Weight of Bottom plate

BA = PI * ((Bottom-OD / 2) - Ann-w-actual)^2
BA = PI * ((21878 / 2) - 762)^2
BA = 325,393,313.8627 mm^2

Ann-a = PI/4 * Bottom-OD^2 - BA


Ann-a = PI/4 * 21878^2 - 325,393,313.8627
Ann-a = 50,550,534.5527 mm^2

weight = (D-bottom * t-actual * BA) + (Ann-d * Ann-t-actual * Ann-A)


weight = (0.00000784 * 8 * 325,393,313.8627) + (0.000007 * 8 * 50,550,534.5527)
weight = 23,584.3997 kg or 231,283.9541 N

API-650

t-min = 6.0 + Ca-bottom


t-min = 6.0 + 2
t-min = 8 mm

t-calc = t-min
t-calc = 8 mm

API-650 5.5

Ann-t-min = 8 mm

Ann-w-min = (215 * Ann-t-actual)/(H * G)^0.5


PAGE 136 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Ann-w-min = (215 * 8)/(23.88 * 1)^0.5


Ann-w-min = 600 mm Note: API-650 until the inner radius of the shell.
Ann-w-min = 711.225 mm Note: including chime distance, overlap and shell thickness.

SUMMARY OF BOTTOM RESULTS Back

Material = A283M-C
t-actual = 8 mm
t-req = 8 mm
Annular Ring Material = A283M-C
Ann-t-actual = 8 mm
Ann-w-actual = 762 mm
Ann-t-min = 8 mm
Ann-w-min = 711.225 mm

NET UPLIFT DUE TO INTERNAL PRESSURE

Net-Uplift = 0 N, (See roof report for calculations)

WIND MOMENT (Per API-650 SECTION 5.11) Back

A = Area resisting the compressive force, as illustrated in Figure F.1


P-F41 = Design pressure determined in F.4.1
P-v = Internal pressure

Wind Velocity per API-650 ASCE 7-10

V_entered = 180 kph


Vs (Wind Velocity) = 0.78 * V_entered = 140.4 kph

Vf = (Vs / 190)^2
Vf = (140.4 / 190)^2
Vf (Velocity Factor) = 0.546

PWS = 0.86 * Vf
PWS = 0.4695 kPa

PWR = 1.44 * Vf
PWR = 0.7863 kPa
PAGE 137 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

API-650 5.2.1.k Uplift Check

P-F41 = (A * Fy * TAN(Theta))/(200 * D^2) + (0.00127 * DLR)/D^2


P-F41 = (3626.59 * 205 * TAN(3.5763))/(200 * 23.18^2) + ((0.00127 * 179144) / 23.18^2)
P-F41 = 0.8558 kPa

Wind-Uplift = MIN(PWR , (1.6 * P-F41 - Pv))


Wind-Uplift = MIN(0.7863 , 1.3693)
Wind-Uplift = 0.7863 kPa

Ap-Vert (Vertical Projected Area of Roof) = 8.3955 m^2

Horizontal Projected Area of Roof (Per API-650 5.2.1.f)

Xw (Moment Arm of UPLIFT wind force on roof) = 11.59 m


Ap (Projected Area of roof for wind moment) = 422.0042 m^2

M-roof (Moment Due to Wind Force on Roof) = Wind-Uplift * Ap * Xw


M-roof = (786.3022 * 422.0042 * 11.59)
M-roof = 3,845,826 N-m

Xs (Height from bottom to the Shell's center of gravity) = Shell Height/2


Xs = (24.38/2)
Xs = 12.19 m

As (Projected Area of Shell) = Shell Height * (D + 2 * t-ins)


As = 24.38 * (23.18 + 2 * 0)
As = 565.1284 m^2

M-Shell (Moment Due to Wind Force on Shell) = (PWS * As * (Shell Height / 2))
M-Shell = (0.4695 * 565.1284 * (24.38 / 2))
M-Shell = 3,235,015 N-m

Mw (Wind moment) = M-roof + M-shell


Mw = 3,845,826 + 3,235,015
Mw = 7,080,841.5237 N-m

PAGE 138 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RESISTANCE TO OVERTURNING (per API-650 5.11.2)

DLR = Nominal weight of roof plate plus weight of roof plates overlap plus any attached structural.
DLS = Nominal weight of the shell and any framing (but not roof plates) support by the shell and
roof.
F-friction = Maximum of 40% of weight of tank
MDL = Moment about the shell-to-bottom joint from the nominal weight of the shell
MDLR = Moment about the shell-to-bottom joint from the nominal weight of the roof plate plus any
attached structural.
MF = Stabilizing moment due to bottom plate and liquid weight
MPi = Destabilizing moment about the shell-to-bottom joint from design pressure
Mw = Destabilizing wind moment
tb = Bottom plate thickness less C.A.
wl = Circumferential loading of contents along shell-to-bottom joint

An unanchored tank must meet with this criteria:

Mw = 7,080,842 m-N
DLS = 1,930,167.8348 N
DLR = 179,144.2025 N

MPi = P * (Pi * D^2 / 4) * (D / 2)


MPi = 0 * (3.1416 * 23.18^2 / 4) * (23.18 / 2)
MPi = 0 m-N

MDL = DLS * (D/2)


MDL = 1,930,167.8348 * 23.18/2
MDL = 22,370,645 N-m

MDLR = DLR * (D/2)


MDLR = 179,144.2025 * 23.18/2
MDLR = 2,076,281 N-m

tb = 6 mm

wl = (min [59 * tb * SQRT(fy-btm * H-liq)] [140.8 * H-liq * D])


wl = (min [59 * 6 * SQRT(205 * 23.88)] [140.8 * 23.88 * 23.18])
wl = 24,768.3658 N/m

MF = (D/2) * wl * Pi * D

PAGE 139 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

MF = 11.59 * 24,768.3658 * 3.1416 * 23.18


MF = 20,904,707 m-N

Criteria 3

M-shell + Fp * Mpi < MDL /1.5 + MDLR


3,235,015.0351 + 0.4 * 0 < 22,370,645 / 1.5 + 2,076,281
Since 3,235,015 < 16,990,044, Tank is stable

RESISTANCE TO SLIDING (per API-650 5.11.4)

F-wind = Vf * 18 * As
F-wind = 0.546 * 18 * 565.1284
F-wind = 257,421 N

F-friction = 0.4 * [(W-roof-corroded * g) + (W-shell-corroded * g) + (W-btm-corroded * g) + (W-roof-


struct * g)]
F-friction = 0.4 * [(16,578 * 9.8) + (165,628 * 9.8) + (18,481 * 9.8) + (65,539 * 9.8)]
F-friction = 1,044,317 N

No anchorage needed to resist sliding since


F-friction > F-wind

Anchorage Requirement

Tank does not require anchorage


Back

SITE GROUND MOTION CALCULATIONS


Af (Acceleration Coefficient for Sloshing Wave Height) = 0.0029
Anchorage_System (Anchorage System) = mechanically anchored
Av (Vertical Ground Acceleration Coefficient) = 0.0027
D (Nominal Tank Diameter) = 23.18 m
H (Maximum Design Product Level) = 23.88 m
I (Importance Factor) = 1.25
K (Spectral Acceleration Adjustment Coefficient) = 1.5
Q (MCE to Design Level Scale Factor) = 1
Rwc (Convective Force Reduction Factor) = 2

PAGE 140 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Rwi (Impulsive Force Reduction Factor) = 4


Sac (Convective Design Spectral Response Acceleration Parameter at Any Period) = 0.0012
Sai (Impulsive Design Spectral Response Acceleration Parameter at Any Period) = 0.0056
Seismic_Site_Class (Seismic Site Class) = seismic site class c
Seismic_Use_Group (Seismic Use Group) = seismic use group ii
TL (Regional Dependent Transistion Period for Longer Period Ground Motion) = 3 sec

Sloshing Coefficient API 650 Section E.4.5.2


Ks = 0.578 / SQRT(TANH(((3.68 * Liq_max) / D)))
= 0.578 / SQRT(TANH(((3.68 * 23.88) / 23.18)))
= 0.5783

Convective Natural Period API 650 Section E.4.5.2


Tc = 1.8 * Ks * SQRT(D) = 1.8 * 0.5783 * SQRT(23.18) = 5.0116 sec

Impulsive Design Response Spectrum Acceleration Coefficient API 650 Sections E.4.6.2
Ai = Q * (I / Rwi) * Sai = 1 * (1.25 / 4) * 0.0056 = 0.0018

Convective Design Response Spectrum Acceleration Coefficient API 650 Sections E.4.6.2
Ac = Q * K * (I / Rwc) * Sac = 1 * 1.5 * (1.25 / 2) * 0.0012 = 0.0011

Ac = MIN(Ac , Ai) = MIN(0.0011 , 0.0018) = 0.0011

Design Spectral Response Acceleration at Short Period API 650 Sections E.4.6.1
SDS = Ai * (Rwi / I) = 0.0018 * (4 / 1.25) = 0.0058

Design Spectral Response Acceleration at a Period of 1 Second API 650 Sections E.4.6.1
SD1 = (Ac / K) * ((Tc^2) / TL) * (Rwc / I)
= (0.0011 / 1.5) * ((5.0116^2) / 3) * (2 / 1.25)
= 0.0098

Vertical Ground Acceleration Coefficient API 650 Section E.6.1.3 and E.2.2
Av = (2 / 3) * 0.7 * SDS = (2 / 3) * 0.7 * 0.0058 = 0.0027

Vertical Ground Acceleration Coefficient Specified by user (Av) = 0.0027

SEISMIC CALCULATIONS Back

< Mapped ASCE7 Method >


Ac = Convective spectral acceleration parameter
Ai = Impulsive spectral acceleration parameter
Av = Vertical Earthquake Acceleration Coefficient
PAGE 141 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Ci = Coefficient for impulsive period of tank system (Fig. E-1)


D/H = Ratio of Tank Diameter to Design Liquid Level
Density = Density of tank product (SG * 62.42786)
Fc = Allowable longitudinal shell-membrane compressive stress
Fty = Minimum specified yield strength of shell course
Fy = Minimum yield strength of bottom annulus
Ge = Effective specific gravity including vertical seismic effects
I = Importance factor defined by Seismic Use Group
k = Coefficient to adjust spectral acceleration from 5% - 0.5% damping
L = Required Annular Ring Width
Ls = Actual Annular Plate Width
Mrw = Ringwall moment-portion of the total overturning moment that acts at the base of the tank
shell perimeter
Ms = Slab moment (used for slab and pile cap design)
Pa = Anchorage chair design load
Pab = Anchor seismic design load
Q = Scaling factor from the MCE to design level spectral accelerations
RCG = Height from Top of Shell to Roof Center of Gravity
Rwc = Force reduction factor for the convective mode using allowable stress design methods
(Table E-4)
Rwi = Force reduction factor for the impulsive mode using allowable stress design methods (Table
E-4)
S0 = Design Spectral Response Param. (5% damped) for 0-second Periods (T = 0.0 sec)
Sd1 = The design spectral response acceleration param. (5% damped) at 1 second based on
ASCE7 methods per API 650 E.2.2
Sds = The design spectral response acceleration param. (5% damped) at short periods (T = 0.2
sec) based on ASCE7 methods per API 650 E.2.2
SigC = Maximum longitudinal shell compression stress
SigC-anchored = Maximum longitudinal shell compression stress
SUG = Seismic Use Group (Importance factors depends on SUG)
T-L = Regional Dependent Transition Period for Long Period Ground Motion (Per ASCE 7-05, fig.
22-15)
ta = Actual Annular Plate Thickness less C.A.
ts1 = Thickness of bottom Shell course minus C.A.
tu = Equivalent uniform thickness of tank shell
V = Total design base shear
Vc = Design base shear due to convective component from effective sloshing weight
Vi = Design base shear due to impulsive component from effective weight of tank and contents
wa = Force resisting uplift in annular region
Wab = Design uplift load on anchor per unit circumferential length
Wc = Effective Convective (Sloshing) Portion of the Liquid Weight
Weff = Effective Weight Contributing to Seismic Response

PAGE 142 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Wf = Weight of Floor (Incl. Annular Ring)


Wi = Effective Impulsive Portion of the Liquid Weight
wint = Uplift load due to design pressure acting at base of shell
Wp = Total weight of Tank Contents based on S.G.
Wr = Weight Fixed Roof, framing and 10 % of Design Snow Load & Insul.
Wrs = Roof Load Acting on Shell, Including 10% of Snow Load
Ws = Weight of Shell (Incl. Shell Stiffeners & Insul.)
wt = Shell and roof weight acting at base of shell
Xc = Height to center of action of the lateral seismic force related to the convective liquid force for
ringwall moment
Xcs = Height to center of action of the lateral seismic force related to the convective liquid force for
the slab moment
Xi = Height to center of action of the lateral seismic force related to the impulsive liquid force for
ringwall moment
Xis = Height to center of action of the lateral seismic force related to the impulsive liquid force for
the slab moment
Xr = Height from Bottom of Shell to Roof Center of Gravity
Xs = Height from Bottom to the Shell's Center of Gravity
g = 9.8 m/s^2

WEIGHTS

Ws = 188,587 kgf or 1,849,403.0434 N


Wf = 23,584 kgf or 231,283.9541 N
Wr = 16,578 kgf or 162,579.5292 N

EFFECTIVE WEIGHT OF PRODUCT

D/H = 0.9707
Wp = 10,077,460 kgf

Wi = (1 - (0.218 * D/H)) * Wp
Wi = (1 - (0.218 * 0.9707)) * 10,077,460
Wi = 7,944,972 kgf

Wc = 0.23 * D/H * TANH (3.67 * H/D) * Wp


Wc = 0.23 * 0.9707 * TANH (3.67 * 1.0302) * 10,077,460
Wc = 2,247,534 kgf

Weff = Wi + Wc

PAGE 143 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Weff = 7,944,972 + 2,247,534


Weff = 10,192,505.974 kgf

Wrs = 12,434 kgf

DESIGN LOADS

Vi = Ai * (Ws + Wr + Wf + Wi)
Vi = 0.0018 * (188,587 + 16,578 + 23,584 + 7,944,972)
Vi = 14,713 kgf

Vc = Ac * Wc
Vc = 0.0011 * 2,247,534
Vc = 2,472.2879 kgf

V = SQRT (Vi^2 + Vc^2)


V = SQRT (14,713^2 + 2,472.2879^2)
V = 14,918.9707 kgf

CENTER OF ACTION FOR EFFECTIVE LATERAL FORCES

Xs = 11.94 m
RCG = 1/3 * R * (TAND (Theta))
RCG = 1/3 * 11590 * (TAND (3.5763))
RCG = 241.4583 mm or 0.2415 m

Xr = Shell Height + RCG


Xr = 24.38 + 0.2415
Xr = 24.6215 m

CENTER OF ACTION FOR RINGWALL OVERTURNING MOMENT

Xi = (0.5 - (0.094 * D/H)) * H


Xi = (0.5 - (0.094 * 0.9707)) * 23.88
Xi = 9.7611 m

Xc = (1 - (COSH (3.67 * H/D) - 1) / ((3.67 * H/D) * SINH (3.67 * H/D))) * H


Xc = (1 - (COSH (3.67 * 1.0302) - 1) / ((3.67 * 1.0302) * SINH (3.67 * 1.0302))) * 23.88
Xc = 17.8456 m

PAGE 144 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

CENTER OF ACTION FOR SLAB OVERTURNING MOMENT

Xis = (0.5 + (0.06 * D/H)) * H)


Xis = (0.5 + (0.06 * 0.9707)) * 23.88)
Xis = 13.3308 m

Xcs = (1 - (COSH (3.67 * H/D) - 1.937) / ((3.67 * H/D) * SINH(3.67 * H/D))) * H


Xcs = (1 - (COSH (3.67 * 1.0302) - 1.937) / ((3.67 * 1.0302) * SINH(3.67 * 1.0302))) * 23.88
Xcs = 18.1156 m

Dynamic Liquid Hoop Forces

Width
SHELL Y (m) Ni (N/mm) Nc (N/mm) Nh (N/mm) SigT+ (MPa) SigT- (MPa)
(m)
= 1.85 * Ac * G * D^2 * = (+ Nh (SQRT (Ni^2 = (- Nh (SQRT (Ni^2
= 2.6 * Ai * = 4.9011293 *
SUMMARY (COSH (3.68 * (H - Y)) / + Nc^2 + (Av * Nh / + Nc^2 + (Av * Nh /
G * D^2 Y*D*G
D) / (COSH (3.68 * H / D)) 2.5)^2))) / t-n 2.5)^2))) / t-n
Shell 1 2.4384 23.5752 2.5146 0.0493 2,678.3354 120.6825 120.3375
Shell 2 2.4384 21.1368 2.5146 0.054 2,401.3133 108.2081 107.883
Shell 3 2.4384 18.6984 2.5146 0.0669 2,124.2911 121.8437 121.4537
Shell 4 2.4384 16.26 2.5137 0.09 1,847.2689 116.5656 116.1611
Shell 5 2.4384 13.8216 2.4182 0.1267 1,570.2467 110.1104 109.6966
Shell 6 2.4384 11.3832 2.2234 0.1827 1,293.2246 102.0359 101.6214
Shell 7 2.4384 8.9448 1.9293 0.2664 1,016.2024 106.9226 106.4532
Shell 8 2.4384 6.5064 1.5358 0.3905 739.1802 93.4369 92.9893
Shell 9 2.4384 4.068 1.0431 0.5739 462.158 72.9841 72.5774
Shell 10 2.4344 1.6296 0.451 0.8444 185.1358 29.3092 29.0012

Overturning Moment

Mrw = ((Ai * [(Wi * g) * Xi + (Ws * g) * Xs + (Wr * g) * Xr])^2 + [Ac * (Wc * g) * Xc]^2)^0.5


Mrw = ((0.0018 * [(7,944,972 * 9.8) * 9.7611 + (188,587 * 9.8) * 11.94 + (16,578 * 9.8) * 24.6215])^2
+ [0.0011 * (2,247,534 * 9.8) * 17.8456]^2)^0.5
Mrw = 1,480,520.3284 N-m

Ms = ((Ai * [(Wi * g) * Xis + (Ws * g) * Xs + (Wr * g) * Xr])^2 + [Ac * (Wc * g) * Xcs]^2)^0.5


Ms = ((0.0018 * [(7,944,972 * 9.8) * 13.3308 + (188,587 * 9.8) * 11.94 + (16,578 * 9.8) * 24.6215])^2
+ [0.0011 * (2,247,534 * 9.8) * 18.1156]^2)^0.5
Ms = 1,966,205.8044 N-m

PAGE 145 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

RESISTANCE TO DESIGN LOADS

Fy = 205 MPa

Ge = S.G. * (1- 0.4 * Av)


Ge = 1 * (1- 0.4 * 0.0027)
Ge = 0.9989

wa = MIN (99 * ta * (Fy * H * Ge)^0.5 , 201.1 * H * D * Ge)


wa = MIN (99 * 6 * (205 * 23.88 * 0.9989)^0.5) , 201.1 * 23.88 * 23.18 * 0.9989)
wa = MIN ( 41,538.0295 , 111,196.3503)
wa = 41,538.0295 N/m

wt = (Wrs + Ws) / (Pi * D)


wt = (12,434 + 188,587) / (3.1416 * 23.18)
wt = 27,070.5899 N/m

wint = P * (Pi * D^2 / 4) / (Pi * D)


wint = 0 * (3.1416 * 23.18^2 / 4) / (3.1416 * 23.18)
wint = 0 N/m

Annular Ring Requirements

L = MIN (0.035 * D , MAX (0.45 , 0.01723 * ta * (Fy / (H * Ge))^0.5))


L = MIN (0.035 * 23.18 , MAX (0.45 , 0.01723 * 6 * (205 / (23.88 * 0.9989))^0.5))
L = MIN (0.8113 , MAX (0.45 , 0.3031))
L = 0.45 m

Ls = 0.762 m
Since Ls > L.

Anchorage Ratio

J = Mrw / (D^2 * [wt * (1 - 0.4 * Av)] + wa - 0.4 * wint


J = 1,480,520.3284 / (23.18^2 * [27,070.5899 * (1 - 0.4 * 0.0027)] + 41,538.0295 - 0.4 * 0
J = 0.0402

Since J <= 0.785, The tank is self-anchored, per API 650 Table E-6

PAGE 146 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Maximum Longitudinal Shell-Membrane Compressive Stress

ts1 = 20.635 mm
SigC = [wt * (1 + (0.4 * Av)) + (1.273 * Mrw) / D^2] * (1 / (1,000 * ts))
SigC = [27,070.5899 * (1 + (0.4 * 0.0027)) + (1.273 * 1,480,520.3284) / 23.18^2] * (1 / (1,000 *
20.635))
SigC = 1.4832 MPa

Allowable Longitudinal Shell-Membrane Compression Stress

Fty = 205 MPa

Criteria for Fc

Since [G * H * D^2 / ts1^2] < 44


Since [1 * 23.88 * 23.18^2 / 20.635^2] < 44
Since 30.1337 < 44 Then Fc = (83 * ts) / (2.5 * D) + (7.5 * SQRT(G * H))

Fc = (83 * ts) / (2.5 * D) + (7.5 * SQRT(SG * H))


Fc = (83 * 20.635) / (2.5 * 23.18) + (7.5 * SQRT(1 * 23.88))
Fc = 66.2052 MPa

Hoop Stresses

SHELL SUMMARY SigT+ Sd * 1.333 Fy * 0.9 * E Allowable Membrane t-Min Shell Ok


Shell 1 120.6825 182.621 184.5 182.621 15.2263 OK
Shell 2 108.2081 182.621 184.5 182.621 13.8168 OK
Shell 3 121.8437 182.621 184.5 182.621 12.18 OK
Shell 4 116.5656 182.621 184.5 182.621 10.708 OK
Shell 5 110.1104 182.621 184.5 182.621 9.2458 OK
Shell 6 102.0359 182.621 184.5 182.621 7.7974 OK
Shell 7 106.9226 182.621 184.5 182.621 6.2358 OK
Shell 8 93.4369 182.621 184.5 182.621 4.8338 OK
Shell 9 72.9841 182.621 184.5 182.621 3.4923 OK
Shell 10 29.3092 182.621 184.5 182.621 2.3539 OK

PAGE 147 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Mechanically Anchored

Number of anchor = 25
Max spacing = 3 m
Actual spacing = 2.9441 m
Minimum # anchor = 25

Wab = (1.273 * Mrw) / D^2 - wt * (1 - 0.4 * Av) + wint


Wab = (1.273 * 1,480,520.3284) / 23.18^2 - 27,070.5899 * (1 - 0.4 * 0.0027) + 0
Wab = -23,533.7065 N/m

Pab = Wab * Pi * D / Na
Pab = -23,533.7065 * 3.1416 * 23.18 / 25
Pab = -68,550.97370304844 N

Pa = 3 * Pab
Pa = 3 * -68,550.97370304844
Pa = -205,652.92110914533 N

Shell Compression in Mechanically-Anchored Tanks

SigC-anchored = [Wt * (1 + (0.4 * Av)) + (1.273 * Mrw) / D^2] * (1 / (1,000 * ts))


SigC-anchored = [27,070.5899 * (1 + (0.4 * 0.0027)) + (1.273 * 1,480,520.3284) / 23.18^2] * (1 /
(1,000 * 20.635))
SigC-anchored = 1.4832 MPa

Fc = 66.2052 MPa

SigC-anchored <= Fc Then the design is acceptable.

Detailing Requirements (Anchorage)

SUG = II
Sds = 0.0058 g or 0.58 %g

PAGE 148 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Freeboard - Sloshing

TL-sloshing = 4 sec
I-sloshing = 1.25
Tc = 5.0116
k = 1.5
Sd1 = 0.0098 g or 0.98 %g
Af = 0.0029 g per API 650 E.7.2

Delta-s = 0.42 * D * Af
Delta-s = 0.42 * 23.18 * 0.0029
Delta-s = 0.0282 m

0.7 * Delta-s = 0.0198 m

Since Sds < 0.33g and SUG = II per API 650 Table E-7.
a. A freeboard of O.7*Delta-s is recommended for economic considerations but not required.

Sliding Resistance

mu = 0.4 (friction coefficient)


V = 14,918.9707 kgf

Vs = mu * (Ws + Wr + Wf + Wp) * (1 - 0.4 * Av)


Vs = 0.4 * (188,587 + 16,578 + 23,584 + 10,077,460) * (1 - 0.4 * 0.0027)
Vs = 4,118,031.5273 kgf

Since V <= Vs Then the tank will not experience major sliding and does not require additional lateral
anchorage, per API 650 E.7.6.

Local Shear Transfer

Vmax = 2 * V / (Pi * D)
Vmax = 2 * 14,918.9707 / (3.1416 * 23.18)
Vmax = 409.7373 kgf/m

PAGE 149 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

ANCHOR BOLT DESIGN Back

Bolt Material : A36M


Sy = 250 MPa

UPLIFT LOAD CASES, PER API-650 TABLE 5-21b

A-s-r = Bolt Root Area Req'd


bt = Uplift load per bolt
D = Tank D (m)
Fp = Pressure Combination Factor
Mrw = Seismic Ringwall Moment (Nm)
N = Anchor bolt quantity
P = Design pressure (pa)
Pf = Failure pressure per F.6 (KPa)
Pt = Test pressure per F.7.6 = 1.25 * P = 0 (pa)
sd = Allowable Anchor Bolt Stress (MPa)
Shell-sd-at-anchor = Allowable Shell Stress at Anchor Attachment (MPa)
t-actual = Actual Roof plate thickness (mm)
t-h = Roof plate thickness less CA (mm)
Vf = Velocity factor (kph)
W1 = Dead Load of Shell minus C.A. and Any Dead Load minus C.A. other than Roof Plate Acting
on Shell
W2 = Dead Load of Shell minus C.A. and Any Dead Load minus C.A. including Roof Plate minus
C.A. Acting on Shell
W3 = Dead Load of New Shell and Any Dead Load other than Roof Plate Acting on Shell

For Tank with Structural Supported Roof

W1 = W-shell-corroded + Shell Insulation


W1 = 1,624,256.5761 + 0
W1 = 1,624,256.5761 N

W2 = W-shell-corroded + Shell Insulation + Corroded Roof Plates Supported by Shell + Roof Dead
Load Supported by Shell
W2 = 1,624,256.5761 + 0 + 162,579.5292 + 0
W2 = 1,786,836.1054 N

W3 = New Shell + Shell Insulation


W3 = 1,841,102.142 + 0

PAGE 150 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

W3 = 1,841,102.142 N

Uplift Case 1: Design Pressure Only

U = [(P - 0.08 * t-h) * D^2 * 785] - W1


U = [(0 - 0.08 * 5) * 23.18^2 * 785] - 1,624,256.5761
U = -1,792,972.6697676748 N

bt = U/N
bt = -71,718.90679070698 N

sd = 104.1666 MPa
Shell-sd-at-anchor = 136.6666 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 2: Test Pressure Only

U = [(Pt - 0.08 * t-h) * D^2 * 785] - W1


U = [(0 - 0.08 * 5) * 23.18^2 * 785] - 1,624,256.5761
U = -1,792,972.6697676748 N

bt = U/N
bt = -71,718.90679070698 N

sd = 138.8888 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 3: Failure Pressure Only

Pf (failure pressure per F.6) = 1.1179 KPa

Uplift Case 4: Wind Load Only

PWR = Wind-Uplift per API 650 Table 5-21a, 5-21b


PWS = Wind-Pressure per API 650 Table 5-21a, 5-21b

PAGE 151 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

PWR = 0.7863 KPa


PWS = 469.5971 N/m^2
MWH = PWS * D * (H^2 / 2) per API 650 Table 5-21a, 5-21b
MWH = 469.5971 * 23.18 * (24.38^2 / 2)
MWH = 3,235,015.0351 Nm

U = PWR * D^2 * 785 + (4 * MWH / D) - W2


U = 0.7863 * 23.18^2 * 785 + (4 * 3,235,015.0351 / 23.18) - 1,786,836.1054
U = -896,939.0485905409 N

bt = U/N
bt = -35,877.56194362164 N

sd = 200 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 5: Seismic Load Only

U = [4 * Mrw / D] - W2 * (1 - 0.4 * Av)


U = [4 * 1,480,520 / 23.18] - 1,786,836.1054 * (1 - 0.4 * 0.0027)
U = -1,529,423.9534217454 N

bt = U/N
bt = -61,176.95813686982 N

sd = 200 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 6: Design Pressure + Wind Load

U = [(Fp * P + PWR - 0.08 * t-h) * D^2 * 785] + [4 * MWH / D] - W1


U = [(0.4 * 0 + 0.7863 - 0.08 * 5) * 23.18^2 * 785] + [4 * 3,235,015.0351 / 23.18] - 1,624,256.5761
U = -903,075.6129247858 N

bt = U/N

PAGE 152 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

bt = -36,123.024516991434 N

sd = 138.8888 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 7: Design Pressure + Seismic Load

U = [(Fp * P - 0.08 * t-h) * D^2 * 785] + [4 * Mrw / D] - W1 * (1 - 0.4 * Av)


U = [(0.4 * 0 - 0.08 * 5) * 23.18^2 * 785] + [4 * 1,480,520 / 23.18] - 1,624,256.5761 * (1 - 0.4 *
0.0027)
U = -1,535,736.1036475971 N

bt = U/N
bt = -61,429.444145903886 N

sd = 200 MPa
Shell-sd-at-anchor = 170.8333 MPa

A-s-r = N.A., since Load per Bolt is zero

Uplift Case 8: Frangibility Pressure

U = [(3 * Pf - 0.08 * t-actual) * D^2 * 785] - W3


U = [(3 * -0.2487 - 0.08 * 5) * 23.18^2 * 785] - 1,841,102.142
U = -2,324,544.145072672 N

bt = U/N
bt = -92,981.76580290688 N

sd = 250 MPa
Shell-sd-at-anchor = 205 MPa

A-s-r = N.A., since Load per Bolt is zero

PAGE 153 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

ANCHOR BOLT SUMMARY Back

Bolt Root Area Req'd = 0 mm^2


Bolt Diameter (d) = 30 mm (M30)
Threads per centimeters (n) = 0.2857

A-s = Actual Bolt Root Area


A-s = (pi / 4) * (d - 33.02 / n)^2
A-s = 0.7854 * (30 - 33.02 / 0.2857)^2
A-s = 508.7055 mm^2

Exclusive of Corrosion
Bolt Diameter Req'd = 4.294 mm (per ANSI B1.1)
Actual Bolt Diameter = 30 mm (M30)
Bolt Diameter Meets Requirements

ANCHORAGE REQUIREMENTS

Wind or Uplift calculations require anchorage


Minimum # Anchor Bolts = 25
per API-650 5.12.3
Actual # Anchor Bolts = 25
Anchorage Meets Spacing Requirements

ANCHOR CHAIR DESIGN

(from AISI 'Steel Plate Engr Data' Dec. 92, Vol. 2, Part VII)

Entered Parameters

Chair Material : A36M


Top Plate Type : DISCRETE
Chair Style : VERT. TAPERED
Top Plate Width (a) : 254 mm
Top Plate Length (b) : 204 mm
Vertical Plate Width (k) : 127 mm
Top Plate Thickness (c) : 26 mm
Bolt Eccentricity (e) : 102 mm

PAGE 154 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Outside of Top Plate to Hole Edge (f) : 80 mm


Distance Between Vertical Plates (g) : 108 mm
Chair Height (h) : 712 mm
Vertical Plates Thickness (j) : 28 mm
Bottom Plate thickness (m) : 8 mm
Shell Course + Repad Thickness (t) : 22.225 mm
Nominal Radius to Tank Centerline (r) : 11601 mm
Design Load per Bolt (P) : 0 N
Bolt Diameter (d) = 30 mm (M30)
Threads per unit length (n) = 0.2857

Bolt Yield Load = A-s * Sy


Bolt Yield Load = 508.7055 * 250
Bolt Yield Load = 127,176.3859 N

Seismic Design Bolt Load (Pa) = -205,652.92110914533 N


Anchor Chairs will be designed to withstand
Design Load per Bolt
Anchor Chair Design Load, (P) : 0 N

For anchor Chair Material: A36M


(per API-650 Table 5-2b, Sd-Chair = 160 MPa

Since bottom t > 10 mm, and Seismic anchorage required (J) <= 1.45,
or Wind Speed is < 160.9344 kph,
h-min is 153 mm.

For Discrete Top Plate,


Max. Chair Height Recommended : h <= 3 * a

h-max = 3 * a
h-max = 3 * 254 = 762 mm.

h-actual = 712 mm.

e-min = 0.886 * d + 15
e-min = 0.886 * 30 + 15 = 41.58 mm.

e-actual = 102 mm.

PAGE 155 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

g-min = d + 26
g-min = 30 + 26 = 56 mm.

g-actual = 108 mm.

f-min = d/2 + 4
f-min = 30/2 + 4 = 19 mm.

c-min = SQRT[P / Sd-Chair / f * (0.375 * g - 0.22 * d)]


c-min = SQRT[0 / 160 / 80 * (0.375 * 108 - 0.22 * 30)] = 0 mm.

c-actual = 26 mm.

j-min = MAX(13, [0.04 * (h - c)])


j-min = MAX(13, [0.04 * (712 - 26)]) = 27.44 mm.

j-actual = 28 mm.

b-min = e-min + d + 7
b-min = 41.58 + 30 + 7 = 78.58 mm.

Stress due to Top Plate Thickness


S-actual-Top-Plate = P / (f * c^2) * (0.375 * g - 0.22 * d)
S-actual-Top-Plate = 0 / (80 * 26^2) * (0.375 * 108 - 0.22 * 30) = 0 MPa

Shell Stress due to Chair Height (For discrete Top Plate)


S-actual-ChairHeight = P * e / t^2 * F3
Where F3 = F1 + F2

now F1 = (1.32 * z) / (F6 + F7)


where F6 = (1.43 * a * h^2) / (r * t)
and F7 = (4 * a * h^2)^(1/3)
and z = 26 / (F4 * F5 + 26)
where F4 = (0.177 * a * m) / SQRT(r * t)
and F5 = (m / t)^2

yields F5 = (8 / 22.225)^2
F5 = 0.1295

PAGE 156 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

yields F4 = (0.177 * 254 * 8) / SQRT(11,590 * 22.225)


F4 = 0.7086
yields z = 26 / (0.7086 * 0.1295 + 26)
z = 0.9964
yields F7 = (4 * 254 * 712^2)^(1/3)
F7 = 801.588
yields F6 = (1.43 * 254 * 712^2) / (11,590 * 22.225)
F6 = 714.8329
yields F1 = (1.32 * 0.9964) / (714.8329 + 801.588)
F1 = 0.0008
now F2 = 0.031 / SQRT(r * t)
yields F2 = 0.031 / SQRT(11,590 * 22.225)
F2 = 0.0019
yields F3 = 0.0008 + 0.0019
F3 = 0.0028
yields S-actual-ChairHeight = 0 * 102 / 22.225^2 * 0.0028
yields S-actual-ChairHeight = 0 MPa

Maximum Recommended Stress is 170 MPa for the Shell


(per API-650 E.6.2.1.2)
Sd-ChairHeight = 170 MPa

ANCHOR CHAIR SUMMARY

S-actual-Top-Plate Meets Design Calculations


(within 105% of Sd-Chair)
S-actual-Top-Plate/Sd-Chair
0/160 = 0%
S-actual-ChairHeight Meets Design Calculations
(within 105% of Sd-ChairHeight)
S-actual-ChairHeight/Sd-ChairHeight
0/170 = 0%

NORMAL AND EMERGENCY VENTING (API-2000 6th EDITION) Back

NORMAL VENTING

T_boil (Product boiling point) = 70.0 degc


T_flash (Product flash point) = 0.0 degc
Vpe (Maximum emptying rate) = 590.46 m^3/hr

PAGE 157 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Vpf (Maximum filling rate) = 1362.6 m^3/hr


Vtk (Tank capacity) = 10375.8964 m^3

In-breathing

Required in-breathing flow rate due to liquid movement API-2000 A.3.4.1.1


Vip = 0.94 * Vpe = 0.94 * 590.46 = 555.0324 m^3/hr

As per API-2000 A.3.4.1.2 Table A.3 Column 2, Required in-breathing flow rate due to thermal
effects (VIT) = 1235.373 m^3/hr

Total required in-breathing volumetric flow rate


Vi = Vip + VIT = 555.0324 + 1235.373 = 1790.4054 m^3/hr

Out-breathing

(T_flash < 37.8) OR (T_boil < 148.9) ==> Use API-2000 section A.3.4.2.2

Required out-breathing flow rate due to liquid movement API-2000 A.3.4.2.2


Vop = 2.02 * Vpf = 2.02 * 1362.6 = 2752.452 m^3/hr

As per API-2000 A.3.4.2.2 Table A.3 Column 4, Required out-breathing flow rate due to thermal
effects (VOT) = 1235.373 m^3/hr

Total required out-breathing volumetric flow rate


Vo = Vop + VOT = 2752.452 + 1235.373 = 3987.825 m^3/hr

EMERGENCY VENTING

As per API-2000 4.3.3.2, Since roof is frangible, it is not necessary to consider additional
requirements for emergency venting

PAGE 158 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

PLAN VIEW APPURTENANCE

OUTSIDE INSIDE
CUST. RADIUS REF
MARK DESCRIPTION PROJ PROJ ORIENT REMARKS
MARK (mm) DWG
(mm) (mm)
ULTRAVENT II
SEE
CV01 BY -- -- 11114mm CV01
TABLE
ULTRAFLOTE
24" ROOF
RM01 281mm 0mm 0' 0mm
MANWAY
8" ROOF
RN01 203mm 0mm 0' 0mm
NOZZLE
8" ROOF
RN01 203mm 0mm 0' 0mm
NOZZLE
2" ROOF
RN02 152mm 0mm 0' 0mm
NOZZLE
2" ROOF
RN02 152mm 0mm 0' 0mm
NOZZLE
6" ROOF
RN03 203mm 0mm 0' 0mm
NOZZLE
6" ROOF
RN03 203mm 0mm 0' 0mm
NOZZLE
RV01 24" FREEVENT 178mm 0mm 0' 0mm RN97
WR01A WINGRAIL -- -- 0' 11513mm

PAGE 159 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

ELEVATION VIEW APPURTENANCE


OUTSIDE INSIDE
CUST. ELEVATION REF
MARK DESCRIPTION PROJ PROJ ORIENT REMARKS
MARK (mm) DWG
(mm) (mm)
ANCHOR SEE
AC01A -- -- --
CHAIRS TABLE
NP01A STD API -- -- 0' 1016mm
ROOF
RPA01A -- -- 0' --
PLATFORM
30" SHELL
SM01 260mm 0mm 0' 900mm
MANWAY
30" SHELL
SM01 260mm 0mm 0' 900mm
MANWAY
16" SHELL
SN01 250mm 0mm 0' 531mm
NOZZLE
12" SHELL
SN02 225mm 0mm 0' 449mm
NOZZLE
2" SHELL
SN03 150mm 0mm 0' 175mm
NOZZLE
2" SHELL
SN03 150mm 0mm 0' 175mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
4" SHELL
SN04 175mm 0mm 0' 259mm
NOZZLE
6" SHELL
SN05 200mm 0mm 0' 306mm
NOZZLE

PAGE 160 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Nozzle R-4 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 8 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14,
or API-650 FIG 5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 219.075
Required Area = 1095.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 219.075
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 5] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 678.7763 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 1095.375 - 0 - 678.7763
A-rpr = 416.5987 mm^2

PAGE 161 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (416.5987 / 219.075) + 0
t_rpr = 1.9016 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 8 in
Repad Size (OD) Must be 450 mm

Nozzle R-5 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 2 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14,
or API-650 FIG 5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 60.325
Required Area = 301.625 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 60.325
Available Roof Area = 0 mm^2

PAGE 162 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.5372 - 0) + 5] * (5.5372 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 176.1835 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 301.625 - 0 - 176.1835
A-rpr = 125.4415 mm^2

Since Nozzle size <= NPS 2 (per API-650 5.7.2), t_rpr = 0

No Reinforcement Pad required.

Nozzle R-6 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 6 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14,
or API-650 FIG 5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 168.275
Required Area = 841.375 mm^2

PAGE 163 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 168.275
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (10.9728 - 0) + 5] * (10.9728 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 529.2346 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 841.375 - 0 - 529.2346
A-rpr = 312.1404 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (312.1404 / 168.275) + 0
t_rpr = 1.8549 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 6 in
Repad Size (OD) Must be 375 mm

Nozzle R-7 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 2 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

PAGE 164 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14,
or API-650 FIG 5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 60.325
Required Area = 301.625 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 60.325
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.5372 - 0) + 5] * (5.5372 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 176.1835 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 301.625 - 0 - 176.1835
A-rpr = 125.4415 mm^2

Since Nozzle size <= NPS 2 (per API-650 5.7.2), t_rpr = 0

No Reinforcement Pad required.

Nozzle R-10 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 6 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
PAGE 165 OF 187
CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14,
or API-650 FIG 5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 168.275
Required Area = 841.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 168.275
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (10.9728 - 0) + 5] * (10.9728 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 529.2346 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 841.375 - 0 - 529.2346
A-rpr = 312.1404 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (312.1404 / 168.275) + 0
t_rpr = 1.8549 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 6 in
Repad Size (OD) Must be 375 mm

Nozzle R-8 Reinforcement Requirements

(Per API-650 and other references below)

NOZZLE Description : 8 in SCH 80 TYPE RFSO

t_rpr = (Re Pad Required Thickness)

PAGE 166 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_n = (Thickness of Neck)


Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Roof Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF NOZZLE,REF. API-650 FIG 5-19, TABLE 5-14 AND FOOTNOTE A OF TABLE 5-14,
or API-650 FIG 5-20, TABLE 5-15 AND FOOTNOTE A OF TABLE 5-15)

Required Area = t_Basis * D


Required Area = 5 * 219.075
Required Area = 1095.375 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 219.075
Available Roof Area = 0 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 5] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 678.7763 mm^2

A-rpr = (Required Area - Available Roof Area - Available Nozzle Neck Area)
A-rpr = 1095.375 - 0 - 678.7763
A-rpr = 416.5987 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (416.5987 / 219.075) + 0
t_rpr = 1.9016 mm

Reinforcement Pad is required.


Based on Roof Nozzle Size of 8 in
Repad Size (OD) Must be 450 mm

PAGE 167 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Nozzle S-2 Reinforcement Requirements

NOZZLE Description : 16 in SCH 40 TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.531 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 406.4
Required Area = 7944.8636 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 406.4
Available Shell Area = 441.2004 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 20.635] * (12.7 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 1278.3621 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 7944.8636 - 441.2004 - 1278.3621
A-rpr = 6225.3011 mm^2

PAGE 168 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (6225.3011 / 406.4) + 0
t_rpr = 15.3182 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 16 in
Repad Size (L x W) Must be 850 x 1035 mm

Nozzle S-3 Reinforcement Requirements

NOZZLE Description : 12 in SCH XS TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.449 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 323.85
Required Area = 6331.0632 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 323.85
Available Shell Area = 351.5816 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (12.7 - 0) + 20.635] * (12.7 - 0) * MIN((103.4213/137) 1)

PAGE 169 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Nozzle Neck Area = 1278.3621 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 6331.0632 - 351.5816 - 1278.3621
A-rpr = 4701.1195 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (4701.1195 / 323.85) + 0
t_rpr = 14.5163 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 12 in
Repad Size (L x W) Must be 685 x 840 mm

Nozzle S-5 Reinforcement Requirements

NOZZLE Description : 2 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.175 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 60.325
Required Area = 1179.3157 mm^2

PAGE 170 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 60.325
Available Shell Area = 65.4907 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.54 - 0) + 20.635] * (5.54 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 437.871 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 1179.3157 - 65.4907 - 437.871
A-rpr = 675.954 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (675.954 / 60.325) + 0
t_rpr = 11.2052 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 2 in
Repad Size (L x W) Must be 203 x 203 mm

Nozzle S-8A Reinforcement Requirements

NOZZLE Description : 2 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.175 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

PAGE 171 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 60.325
Required Area = 1179.3157 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 60.325
Available Shell Area = 65.4907 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (5.54 - 0) + 20.635] * (5.54 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 437.871 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 1179.3157 - 65.4907 - 437.871
A-rpr = 675.954 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (675.954 / 60.325) + 0
t_rpr = 11.2052 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 2 in
Repad Size (L x W) Must be 203 x 203 mm

Nozzle S-9A Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

PAGE 172 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 114.3
Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1355.7789 / 114.3) + 0
t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-9B Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)

PAGE 173 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sd_n = (Stress of Neck Material)


Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 114.3
Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1355.7789 / 114.3) + 0
t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

PAGE 174 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Nozzle S-9C Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 114.3
Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA

PAGE 175 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (1355.7789 / 114.3) + 0


t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-9D Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 114.3
Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

PAGE 176 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1355.7789 / 114.3) + 0
t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-7 Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D

PAGE 177 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Shell Area = (20.635 - 19.5494) * 114.3


Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1355.7789 / 114.3) + 0
t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-10 Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

PAGE 178 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 114.3
Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1355.7789 / 114.3) + 0
t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-11 Reinforcement Requirements

NOZZLE Description : 4 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.259 ft

COURSE PARAMETERS:

PAGE 179 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 114.3
Required Area = 2234.4929 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 114.3
Available Shell Area = 124.0876 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (8.56 - 0) + 20.635] * (8.56 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 754.6263 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 2234.4929 - 124.0876 - 754.6263
A-rpr = 1355.7789 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (1355.7789 / 114.3) + 0
t_rpr = 11.8616 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 4 in
Repad Size (L x W) Must be 305 x 385 mm

Nozzle S-12 Reinforcement Requirements

NOZZLE Description : 6 in SCH STD TYPE RFSO

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)

PAGE 180 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Sd_s = (Stress of Shell Course Material)


CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.306 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL NOZZLE REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 168.275
Required Area = 3289.6701 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 168.275
Available Shell Area = 182.6845 mm^2

Available Nozzle Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Nozzle Neck Area = [4 * (10.97 - 0) + 20.635] * (10.97 - 0) * MIN((103.4213/137) 1)
Available Nozzle Neck Area = 1046.9167 mm^2

A-rpr = (Required Area - Available Shell Area - Available Nozzle Neck Area)
A-rpr = 3289.6701 - 182.6845 - 1046.9167
A-rpr = 2060.0688 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (2060.0688 / 168.275) + 0
t_rpr = 12.2423 mm

Reinforcement Pad is required.


Based on Shell Nozzle Size of 6 in
Repad Size (L x W) Must be 400 x 495 mm

PAGE 181 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Manway S1-A Reinforcement Requirements

MANWAY Description : 30 in SCH --

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.9 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL MANWAY REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 793.75
Required Area = 15517 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 793.75
Available Shell Area = 861.7196 mm^2

Available Manway Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Manway Neck Area = [4 * (15.875 - 0) + 20.635] * (15.875 - 0) * MIN((137/137) 1)
Available Manway Neck Area = 2318.385 mm^2

A-rpr = (Required Area - Available Shell Area - Available Manway Neck Area)
A-rpr = 15517 - 861.7196 - 2318.385
A-rpr = 12337 mm^2

t_rpr = (A_rpr / D) + repad_CA

PAGE 182 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

t_rpr = (12337 / 793.75) + 0


t_rpr = 15.5429 mm

Reinforcement Pad is required.


Based on Shell Manway Size of 30 in
Repad Size (L x W) Must be 1543.05 x 1866.9 mm

Manway S1-2 Reinforcement Requirements

MANWAY Description : 30 in SCH --

t_rpr = (Re Pad Required Thickness)


t_n = (Thickness of Neck)
Sd_n = (Stress of Neck Material)
Sd_s = (Stress of Shell Course Material)
CA = (Corrosion Allowance of Neck)

MOUNTED ON SHELL 1 : Elevation = 0.9 ft

COURSE PARAMETERS:
t-calc = 21.1394 mm
t_cr = 19.5494 mm (Course t-calc less C.A)
t_c = 20.635 mm (Course t less C.A.)
t_Basis = 19.5494 mm

(SHELL MANWAY REF. API-650 TABLE 5-6, TABLE 3-6 AND FOOTNOTE A OF TABLE 5-7)

Required Area = t_Basis * D


Required Area = 19.5494 * 793.75
Required Area = 15517 mm^2

Available Shell Area = (t_c - t_Basis) * D


Available Shell Area = (20.635 - 19.5494) * 793.75
Available Shell Area = 861.7196 mm^2

Available Manway Neck Area = [4 * (t_n - CA) + t_c] * (t_n - CA) * MIN((Sd_n/Sd_s) 1)
Available Manway Neck Area = [4 * (15.875 - 0) + 20.635] * (15.875 - 0) * MIN((137/137) 1)
Available Manway Neck Area = 2318.385 mm^2

PAGE 183 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

A-rpr = (Required Area - Available Shell Area - Available Manway Neck Area)
A-rpr = 15517 - 861.7196 - 2318.385
A-rpr = 12337 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (12337 / 793.75) + 0
t_rpr = 15.5429 mm

Reinforcement Pad is required.


Based on Shell Manway Size of 30 in
Repad Size (L x W) Must be 1543.05 x 1866.9 mm

Manway R-1 Reinforcement Requirements

(Per API-650 Section 5.8.4 and other references below)


MANWAY Description : 24 in SCH -- TYPE
t_rpr = (Re Pad Required Thickness)
MOUNTED ON ROOF: Elevation = 25.1094 ft

ROOF PARAMETERS:
t-calc = 5 mm
t_cr = 5 mm (Roof t-calc less C.A)
t_c = 5 mm
t_Basis = 5 mm

(FOR ROOF MANWAY,REF. API-650 FIG 5-16, TABLE 5-13)

Required Area = t_Basis * D


Required Area = 5 * 623.6
Required Area = 3118 mm^2

Available Roof Area = (t_c - t_Basis) * D


Available Roof Area = (5 - 5) * 623.6
Available Roof Area = 0 mm^2

Available Manway Neck Area = [4 * (t_n - CA) + t_c] * (t_n - ca) * MIN((Sd_n/Sd_s) 1)
Available Manway Neck Area = [4 * (7 - 0) + 5] * (7 - 0) * MIN((137/137) 1)

PAGE 184 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Available Manway Neck Area = 288.29 mm^2

A-rpr = (Required Area - Available Roof Area - Available Manway Neck Area)
A-rpr = 3118 - 0 - 288.29
A-rpr = 2829.71 mm^2

t_rpr = (A_rpr / D) + repad_CA


t_rpr = (2829.71 / 623.6) + 0
t_rpr = 4.5377 mm

Reinforcement Pad is required.


Based on Roof Manway Size of 24 in
Repad Size (OD) Must be 1150 mm

PAGE 185 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

CAPACITIES and WEIGHTS Back

Maximum Capacity (to Max Liq Level) : 10,063 M^3


Capacity to Top of Shell (to Tank Height) : 10,274 M^3
Working Capacity (to Normal Working Level) : 9,577 M^3
Net working Capacity (Working Capacity - Min Capacity) : 9,094 M^3
Minimum Capacity (to Min Liq Level) : 483 M^3

Component New Condition (N) New Condition (Kg) Corroded (N) Corroded (Kg)
SHELL 1,841,103 187,741 1,624,257 165,629
ROOF 162,580 16,579 162,580 16,579
RAFTERS 161,530 16,472 265,920 27,117
GIRDERS 0 0 0 0
FRAMING 0 0 0 0
COLUMNS 29,826 3,042 29,826 3,042
BOTTOM 231,284 23,585 181,238 18,482
STAIRWAYS 17,172 1,751 17,172 1,751
STIFFENERS 8,488 866 8,488 866
WIND GIRDERS 0 0 0 0
ANCHOR CHAIRS 14,710 1,500 14,710 1,500
INSULATION 0 0 0 0
TOTAL 2,466,693 251,536 2,304,191 234,966

Weight of Tank, Empty : 2,466,693 N (251536 kg)


Weight of Tank, Full of Product (SG = 1) : 101,292,816.109 N(10328990.52 kg)
Weight of Tank, Full of Water : 101,292,812.4852 N (10328990.16 kg)
Net Working Weight, Full of Product : 96,409,444.7719 N (9831025.338 kg)
Net Working Weight Full of Water : 96,409,444.7719 N (9831025.338 kg)

Foundation Area Req'd : 325.3933 m^2


Foundation Loading, Empty : 7,580.6505 N/m^2
Foundation Loading, Full of Product : 303,712.8265 N/m^2
Foundation Loading, Full of Water : 303,712.8154 N/m^2

SURFACE AREAS

PAGE 186 OF 187


CALCULATION STORAGE TANKS

CLIENT: VOPAK TERMINAL VERACRUZ. REVISION: A


PROJECT NO. 20182020 PROJECT: VERACRUZ CPPs PHASE 2 - NEW TANKS, ME&I AND CIVIL DATE: 01-08-2018
LOCATION: MEXICO DOCUMENT NUMBER: 1045-BB1-ME-CAL-001 PROJECT NO. 1042

Roof : 422.8275 m^2


Shell : 1,775.4032 m^2
Bottom : 325.3933 m^2

Wind Moment : 7,080,841.5237 N-m


Seismic Moment : 1,966,205.8044 N-m

MISCELLANEOUS ATTACHED ROOF ITEMS


MISCELLANEOUS ATTACHED SHELL ITEMS

MAWP & MAWV SUMMARY Back

MAWP = Maximum calculated internal pressure


MAWV = Maximum calculated external pressure

MAXIMUM CALCULATED INTERNAL PRESSURE

MAWP = 18 kPa or 1,835.658 mmh2o (per API-650 App. F.1.3 & F.7)
MAWP = 12.8236 kPa or 1,307.7636 mmh2o (due to shell)
MAWP = 0.8558 kPa or 87.2753 mmh2o (due to roof)
TANK MAWP = 0.8558 kPa or 87.2772 mmh2o

MAXIMUM CALCULATED EXTERNAL PRESSURE

MAWV = -6.9 kPa or -703.6689 mmh2o (per API-650 V.1)


MAWV = N/A (due to shell) (API-650 App.V not applicable)
MAWV = 0.4495 kPa or 45.8405 mmh2o (due to roof)
TANK MAWV = 0.4495 kPa or 45.8409 mmh2o

PAGE 187 OF 187