You are on page 1of 6

PROJECT

Project-1

Project-2
Project-3

Project-4
Weekly progress
03Aug20 -07Aug20

1. AQC conveyor -1 Drvie platfrom strucutural drawings reviewed and


give clearance for fabrication.

1. Hyquip RAV, Slide gate, Diverting gate GA drawings reviewe and


commented.
2. AQC Inlet duct refractory detailing and PH inlet and outlet, cooler
vent duct and cyclone inlet duct insulation specification released for
client procuremen.
3. PH & AQC Chutes detail fabrication work started.
4. Chute expansion joints GA drawings reviewed and approved.
5.AQC BOILER DUCT SUPPORTING STEEL DRAWINGS
reviewed and commented.
6.PH Operating Floor 12.15M Revised RCC Floor plan reviewed and
send for site clearance.
PH Boiler Chain conveyor 1 & 2 Structure stadd model submitted for
client approval.
Planning for next week
10Aug20 -14Aug20

1. Civil and structural drawings to be reviewed.


2. TG Building 15.0M ,18.70M & Roof drawings to be checked.

1. Civil and structural drawings to be reviewed.


2. Chutes detail fabrication
1. Civil drawings to be reviewed.
2. Once PH Boiler Layout approved , Specification of Boiler Discharge
equipments to be released.
3.AQC Boiler Inlet and outlet duct GA drawings will be submitted for client
aproval.after PH Boiler layout approval.
4. PH boiler outlet duct G.A & fabrication drawing internal review.
5. once comments recieved from client on PH Boiler Chain conveyor 1 & 2
structural Loads to be submitted along with footings.

You might also like