ERECTION PROGRESS REPORT for steel factory


Date :23-08-2012
Job No. QA-0271 Bldg. Size : 39,841,935 m² TYPE: PEB

Project Name : factory for production of reinforced steel ROOF CLADDING :


Customer Name : wall cladding :
Project Info

Location : MIC SPECIAL MATERIALS:


No. of Buildings : 1 SUPPLIER : By ATC
Erection by : ATC : Mabani Steel BSI
EBS LOCAL :
KIRBY OTHERS:
A.B. Shipment Date : RECEIVED NO
ANCHOR BOLT

A.B. Installation Date : YES NO


A.B. Setting / Checking Date : YES NO
Concrete casted /A.B. Final Checking Date: YES NO
PEB Date of 1st Delivery / Last Delivery Date : ١٢-‫فبراير‬-١٤
PPA Date of 1st Shipment / Last Shipment Date :
PEB Date Erection Started / Expected Completion Date: ١٢-‫فبراير‬-٢٠
PEB Erection - ACTUAL Completion Date: roof monitor for phase one 10/08/2012
PPA Date Erection Started / Completion Date: roof sheet & monitor phase 1 29-7-2012 start 28-8-2012 complete
DURATION

PPA Installation - ACTUAL Completion Date:


Erection Duration (as per the Contract) N/A
Time Elapsed N/A
No. of Weeks Remaining for Completion (as per the contract) N/A
Actual No. of Weeks Remaining for Completion N/A
Current Status ACTIVE ON HOLD
Erection Team Leader

MANPOWER
Foreman Shafeequl isalm & Noufal A & mito mia
Group Leader
Average No. of Erectors /day 17
No. of Crane/s on Site 1 -35 ton

EQPTS.
No. of Boom loader on Site N/A
No. of Man lifts / Sissorlift 4 man lift-28m
No. of Forklifts 1
From : Supplier ATC Office
PENDING ISSUES

From : Customer Consultant


From : Main Cont Others
From : erection team
Claims Issued to Date

Bldg no. PEB STEEL PPA SHEETING ACCESSORIES


1 50.00% 40.00% 0.00%

Date : Description of Work Progress REMARKS


23-Aug-12 erection of roof monitors @ grid line Y1:Y21/x3:x2(phase one erection of roof monitors 100% done) see below pictures
23-Aug-12 erection of roof monitors @ grid line Y17:Y19/x2:x1(phase one erection of roof monitors100% done) see below pictures
23-Aug-12 sag rod fixing & purlins joint bolt fixing @ grid line 01:9/X4:X3-roof monitor see below pictures
23-Aug-12 installation of valley gutters & cunter roof cladding @ grid line x4:x2/Y9:Y16 mito mia team
23-Aug-12 installation of roof monitor @ grid line x4:x3/Y1:Y3 Shafeequl isalm team
23-Aug-12 installation of valley gutters & cunter roof cladding @ grid line x4:x3/Y1:Y9-done Shafeequl isalm team
SITE COMMENTS
1 the installation of roof cladding has stopped due to the site generator break down

PHOTOS
roof cladding progress
erection of roof monitors @ grid line Y17:Y21/x2:x1
installation of roof monitor@ grid line installation of valley gutters & cunter roof
installation of valley gutters & cunter roof cladding
x4:x3/Y1:Y2 cladding @ grid line x4:x3/Y1:Y9-done
@ grid line x4:x2/Y9:Y16 -mito mia team

S.NO NAME ID NO. JOB. NO.


1 Dulal Bojendra 39 441
2 Mhd. Akram 43 441
3 Mhd. Mito Mia 46 441
4 Sohel Mhd. Islam 71 441
5 Meghal Kalu Ram 293 441
6 Tatkaka Naresh 299 441
7 Md Shohidul Islam Late Yosub Ali 850 441
8 Azahar Uddin Md Raiq 944 441
9 Md Masum Abdul Halim 945 441
10 Alamin Islam shah Jahan shikder 949 441
11 Sivagnanam Poomalai 955 441
12 Elangovan Chinnathambi 960 441
13 Farhad Kayum Sheikh 987 441
14 Shafeequl isalm 990 441
15 Golam Mustafa Ahthar Ali 991 441
16 Shohag Palk Sowkat Palk 992 441
17 Tajul Islam Mansur Ali 993 441
18 Taher Omar 994 441
19 Noufal A 995 441
20 Nasir 1010 441