CONSTRUCTION FORM PHILIPPINE ASSOCIATED SMELTING AND

REFINING CORP
ISABEL, LEYTE
DAILY WORK ACTIVITY REPORT

Project Name: Date Start: 28-Sep-21 Report Date: DS 29-Sep-21


ONSITE SERVICING REPAIR MINOR SHUTDOWN
Total Days: 2 Report Number: 2
Weather Condition: Type: Strength:
Project Location: Dawn (12MN-6AM): FS - Fair / Sunny L - Light
PRIMARY SMELTER
Morning (6AM-12NN): FS L C - Cloudy M - Moderate
Project Number: Afternoon (12NN-6PM): FS L R - Rainy H - Heavy

Project Duration: 3 Working Day #: 2 Evening (6PM-12MN): W - Windy

Contractor: EMAI Note: kindly state "NA" if no work during that particular range of time

Manpower loading: Equipment loading:

No of manpower Description Plan Actual Utilized B/down Remarks


Designation Remarks
Actual Actual Absent /
Plan (direct) (indirect) Lacking Extension wire 4 3 3
Supervisor 1 1 Cutting outfit 3 2 2

Safety Officer 1 1 Combination wrench 6 4 4

Foreman 1 1

Mechanic 15 15

Permit Holder 2 3
Millwright 1 1

Fire Watcher 2 TOTAL 13 9 9

Material delivery at site:


Inspection Inspection
Description Qty Status Description Qty Status

TOTAL 21 22 2 24 Note: For Inspection Status, it would be "not inspected", "approved" or "rejected"

Activities executed during the day:

Preparation of tools and materials


Removal of snob pulley
Removal of gear box

Significant issues encountered during the day:

Field Engineers Notes:

CONTRACTOR REPRESENTATIVE: PASAR REPRESENTATIVE:

Prepared by: ELMER A. BALARES Checked by: JC CATALUÑA


Field/Project Engineer PASAR Team Leader

Noted by: DENNIS BOHOLST


EMAI-Supervisor
CONSTRUCTION FORM PHILIPPINE ASSOCIATED SMELTING
AND REFINING CORP
ISABEL, LEYTE
DAILY WORK ACTIVITY REPORT

Project Name: ONSITE SERVICING REPAIR MINOR SHUTDOWN Project Number:

Date: 29-Sep-21 Day: WEDNESDAY

Project Location: Project Duration: 3 Working Day #: 2


EMAI SHOP BILWANG ISABEL LEYTE
Contractor: EMAI

Site Photo References:

Prepared by:

ELMER A. BALARES

QC/Field Engineer