PLUMBING+FF DAILY REPORT

DATE:12/04/2023 Weather:
Ref:
No. of days elapsed: No. of remaining days: Visitors:
Staff & Labour Plant & Equipment
Title
MEP Plant MEP
Indirect/Staff
Project Manager 1
Electrical Engineer
plumbing Engineer 1
plumbing Forman 1
FF Forman 1
PLUMBERS 22
Mechnical Labour
MEP QA/QC 1 +

TOTAL
Subcontractors Fire Fighting

VISION SAFET 5

Total 5

Summary of Work for the Day


PLUMBING Work Summary:
1) STORE KEEPER (1 NOS )
2) CHARGE HAND (1)
3) 1ST FLOOR DRAINAGE SUPPORT ( 3 NOS)
4) 10TH FLOOR AC DRAIN (2 NOS)
5) MANHOLE WORK GROUND FLOOR (2 NOS )
6) UPPER GROUND DRAINAGE INSULATION (2 NOS)
7) 9TH FLOOR PPR TESTING (2 NOS)
8) 4TH FLOOR WATER METER ROOM (2 NOS)
9) SHIFTING ALL MATERIAL FROM ALL FLOORS (1 NOS )
10) 1ST BASEMENT WATER TANK ( 2 NOS)
11) ABSENT (3 NOS)
FF WORK SUMMARY:
1) 8TH FLOOR PRESSURE TESTING (2 NOS)
2) 9TH FLOOR PINDING (2 NOS)