TABLE OF CONTENTS
TABLE OF CONTENTS
1.0 Purpose ..................................................................................................................... 1
1.0 PURPOSE
Generally, the purpose of the Procurement Management Plan is to define what items
will be procured for the project and how vendors will be identified, selected, and
managed. Additionally, the plan should outline roles and responsibilities relating to
procurement as well as any contract requirements which must be met. This
Procurement Management Plan has been created to provide a framework in which all
procurement actions will be managed across all of the organizations involved.
Role Responsibilities
Name of Subcon/
Required on Ordering
Ref Item Supplier Price
Site Responsibility
Used In Tender
1 Plumbing Installation 15/05/2011 QS IPS
2 Electrical Installation 15/05/2011 QS TMR
2a Electrical Panels 15/05/2011 QS/ PM EW
2b Cables 15/05/2011 QS/ PM EW
2c Lights 15/05/2011 QS/ PM Gables
2d Data 15/06/2011 QS/ PM Claj
3 Aluminium Windows 03/07/2011 QS P's Security
4 Aluminium Doors 03/07/2011 QS Oran
5 Doors (Prov Sum) 03/07/2011 QS Carters
6 Roof Drains & Rainwater Goods 02/10/2011 PM Carters
7 Hardware 20/08/2011 QS Vincent Elliott
8 Wall & Floor Tiles 07/08/2011 QS ACP associates
9 Roofing Membrane 01/06/2011 QS Rooftec
10 Internal Doors 03/08/2012 PM Caters
11 Bathroom Fittings/ Accessories 10/09/2011 QS Vincent Elliott
12 Sanitary Ware 10/09/2011 QS Brydens
13 Joinery 11/04/2011 TBA J.P Woodworks
14 Fire Hose Reels 11/12/2011 QS Safety Supply
15 Pinboards 09/08/2012 PM J.P Woodworks
16 Chalkboards 09/08/2011 PM J.P Woodworks
17 Mirrors 09/08/2011 QS Glassesco
18 Decoran 09/08/2011 QS One Stop
19 Handrails 07/08/2011 QS MetalcraftWorks
20 Structural steelwork/ Quiklok 07/08/2011 QS Metaluxuries
21 Road Paving 07/08/2011 PM C.O Williams
Pearsons Pest
22 Termite Treatment 07/08/2011 PM Control
23 Vinyl Tiles 07/08/2011 QS ACP
24 Vinyl Tiles - pc Sum 07/09/2011 QS ACP Associates
25 Suspended Ceilings 07/09/2011 QS DCR ($33.75/ sy)
26 Permaclad Roofing 07/09/2011 QS BRC
The Project Manager and team will select the best suitable vendor proposals by utilising
the above criteria. Once all contracts are complete, the Project Manager will begin the
vendor management phase of the procurement process.
Vendor
#1
Vendor
#2
In addition to rating each vendor, actual values will be noted in order to build a past-
performance data base for selecting vendors for future procurement activities.