Professional Documents
Culture Documents
BARRAGE
CHAPTER # 09
SANTOSH KUMAR GARG
INTRODUCTION
Direct Irrigation scheme has various parts like permanent canals which take off from
diversion weir or barrage.
To ensure the continuous supply of water to canals distinct arrangements at specific
heads are made even at low flow.
The work, which are constructed at the head of canal:
To divert river water
Ensuring continuous supply
Regulated silt free supply
At certain Minimum Head
known as Diversion Headwork.
WEIR & BARRAGE
To accomplish the purpose of Diverting River Water by construction a Barrier
across the river.
Raise the water at upstream of the Obstruction
Feeding the main canals either from one or two sides
Ponding can be achieved through Permanent Pucca Raised Crest or Raised by
Supplemented falling Gates.
If Major part of ponding is achieved by Raised Crest as compared to gates or
shutter, then Barrier is known as WEIR.
If most of the ponding is done by Gates and smaller portion by raised Crest, then
Barrier is known as Barrage.
Afflux: Barrages generate controlled floods as compared to Weirs. Through gates
manipulation of controlling mechanism is too easy.
Gravity and Non-Gravity Weirs
Gravity Weirs:
When the weight of weir (floor + body) balances the uplift pressure
caused by Head of water seeping below the weir.
Non-Gravity Weirs:
Ifthe weir floor is continuous and divided by reinforced piers. The weight of
concrete slab together with weight of divided piers, keep the structure safe
against uplift.
LAYOUT OF
DIVERSION
HEADWORK
COMPONENTS:
1. WEIR
2. UNDER SLUICES
3. DIVIDE WALL:
Dividing the river in Two-portions. One is Weir and Second is Canal take off.
Note: If there are Two canals taking off from flanks. Then there will be Two Divide Walls
and under sluices weirs.
4. RIVER TRAINING WORK:
Marginal Bund, Guide Banks and Groynes
5. FISH LADDER
6. CANAL HEAD REGULATOR
7. WEIR’S ANCILLATORY WORK (GATE OR SHUTTER)
8. SILT REGULATOR WORK
DIVERSION WEIR & TYPES
Height of weir may be 9.0 meters
Height of Gate or Shutter over the weir crest may be 1.2 meters or so
Entire length of river is divided into number of bays by means of piers to
avoid the cross-flow in floods.
Weir should be aligned at Right Angle to Main river current
Lesser Length of Weir, Better Discharging Capacity and Lesser Cost
Right Angle Alignment is better especially for Silty and Sandy riverbed
An Oblique Angle alignment sometimes can be used for safe and better
foundation
For Gravel and Shingle riverbed to avoid blockage of canal head regulators.
TYPES: