Professional Documents
Culture Documents
DAILY SITE RECORD Monday, September 21, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS
SITE VIEW
Architectural
work
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% AT LIFT CORE WALL APPLICATION OF DAVCO WATERPROOFING
MEMBRANEINSTALLED WITH HARD POLYFOAM PROTECTION PRIOR TO
11 Pile caps more to complete at lower Deck Level , GREEN SHADES
BACKFILLING WORKS
@ Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL
SUBSTATION AREA, AT LIFT PIT PREPARATION TO RECEIVE DAVCO
WATERPROOFING MEMBRANE, ON GOIMG EXCAVATION WORKS FOR
PILE CAPS AT GRIDLINE A 1 1 to 4.
Weather G Worker 10
TC OPERATOR 1
LB D HAC K TEAM 3
EXCAV. OPTR 1 IC WORKS IC#4 5
FAIR
EXC AV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 34 TOTAL : 0 TOTAL : 5 57 KEY PLAN SHOWING DETENTION DRAIN @88% COMPLETE, DETENTION LEANCONCRETE ON THIS AREA TO CONTINUE SLAB REBAR WORKS
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF
WORKS
Housekeeping work inprogress,
AT Lower Deck Level REMAINS @ 60.71% 11 Pile caps more to complete at lower Deck Level , GREEN SHADES @ Upper Deck Level PILE CAP @
100% Completed , AT ELECTRICAL SUBSTATION AREA, AT LIFT PIT PREPARATION TO RECEIVE DAVCO WATERPROOFING MEMBRANE, ON
8 PILE
GOIMG EXCAVATION WORKS FOR PILE CAPS AT GRIDLINE A 1 1 to 4.
CAPS RC SUMPS AND PIPE
HAUNCHING @43.00%
3 PILE
COMPLETE
CAPS
DETENTION DRAIN @88% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF WORKS
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 43.00% COMPLETE KEY PLAN SHOWING 11 MORE PILE CAPS TO CAST AT LOWER DECK KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
LEVEL, STAIRCASE #1 PILE CAP TO CAST ON 23 SEPTEMBER 43.00% COMPLETE
SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS AND TOP REINFORCING BARS
DONEUNTIL GRIDLINE 12-9F-G 70% COMPLETED FIRST SEGMENT OF SLAB 01B TARGET TO CAST ON 29 SEPTEMBER GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
ESS
AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS WEEK. SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS
REINFORCING BARS AND TOP REINFORCING BARS DONEUNTIL GRIDLINE 12- WEEK.
SEPTEMBER
LIFT COREWALL: APPLICATION WITH DAVCO WATERPROOFING MEMBRANE COVERED WITH HARD POLYFOAM PROTECTION TO
NEWLY INSTALLED WATERPROOFING MEMBRANE PRIOR TO BACKFILLING WORKS
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE
INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL WALLS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT COREWALL: APPLICATION WITH DAVCO WATERPROOFING MEMBRANE
APPLIED WITH DAVCO WATERPROOFING MEMBRANE COVERED WITH HARD POLYFOAM PROTECTION TO NEWLY INSTALLED
22 WORKERS +8 LCT +2 LBD +2CL 4 WATERPROOFING WORKS AND DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER 22 WORKERS +8 LCT +2 LBD +2CL 4 WATERPROOFING WORKS AND
INSTALLED 10 DROP PANELS SLAB SPLIT LEVEL BEAM APPLIED
DECK DEEP BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT DISMANTLE FORMWORKS=4 WORKERSESS FORMWORKS=4
BOTTOM REINFORCING BARS AND 3 DAVCO WATERPROOF DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP
WORKERS UPSTAND BEAMSFORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR
ROWS OF GROUND BEAMS MEMBRANE
WORKERS 8 DEPLOYED WORKERS TO DO WATERPROOFING PREPARATION GRINDING TOUCH UP, ASSIST TOWER CRANE, BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT DISMANTLE
INSTALLED AT GRID LINE 12 T0 9 D E F
SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS G FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS UPSTAND