BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Monday, September 21, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS

LOWER DECK: PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 17 nos.
total Number OF Pile Caps@ Lower Deck 28 nos. 60.71%
UPPER DECK: PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 29 nos.
total Number OF Pile Caps 29 nos. 100.00%
Structural work

MSCP PILES 100.00%

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES 100.00%

TOWER CRANE PILE CAP CAST 100.00%

CAPPING BEAMS CAST TO DATE 82.00%

1ST STOREY WALL- COLUMN STUMP CAST TO DATE 45.00%


DETENTION DRAIN CAST TO DATE 88.00%
INTERNAL DRAINAGE UPDATE 42.86%

SITE VIEW
Architectural
work

@ LIFT CORE WALL APPLICATION OF DAVCO


WATERPROOFING MEMBRANEINSTALLED WITH
HARD POLYFOAM PROTECTION PRIOR TO
BACKFILLING WORKS
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% AT LIFT CORE WALL APPLICATION OF DAVCO WATERPROOFING
MEMBRANEINSTALLED WITH HARD POLYFOAM PROTECTION PRIOR TO
11 Pile caps more to complete at lower Deck Level , GREEN SHADES
BACKFILLING WORKS
@ Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL
SUBSTATION AREA, AT LIFT PIT PREPARATION TO RECEIVE DAVCO
WATERPROOFING MEMBRANE, ON GOIMG EXCAVATION WORKS FOR
PILE CAPS AT GRIDLINE A 1 1 to 4.

MAIN C ON STRUC TURAL ARC HITEC TURAL M&E MAC HINERY


ATTENDANCE
P Manager 1 Supervisor 1 Generator 2

Site Supervisor 1 Safety Supervisor 1 Excavator CL 1


@ DETENTION @ IC WORKS #4 TO SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and 2
Safety officer LOWER DECK DEEP BEAM
IC#3: INSTALL 150MM WORKERS INSTALLED DAVCO WATERPROOF
DISMANTLE - FORMWORK DRAIN: UPDATED MEMBRANE MATERIALS, WALL BESIDES INSTALLED
08:30 17:30 1 2 DETENTION
AT 88% COMPLETE DRAIN
DIAMETER DUCTILE SUBSOIL PERFORATED PIPES
IRON PIPE
Site engineer LIFT PIT FORMWORK OPEN BAR BENDER MACHINE
1 4 1

RTO BIG BREAKER


ESS REBAR- FORMWORKS
1 4 1
@ REMAINING
AREA OF
STAIRCASE#1 REBAR 1 TONNE ROLLER- COMPACTOR
Administrator
FORMWORKS DETENTION DRAIN
REMARKS 1 2 1
TO COMPLETE
UPPER /LOWER AIR RECEIVER
@12%
DECKSLAB/DROP PANEL/ 24
Coordinator 1 10 1
INSTALLATION

WATERPROOFING WALL TC INSTALLED


ECO 1 4 1

Weather G Worker 10
TC OPERATOR 1
LB D HAC K TEAM 3
EXCAV. OPTR 1 IC WORKS IC#4 5
FAIR
EXC AV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 34 TOTAL : 0 TOTAL : 5 57 KEY PLAN SHOWING DETENTION DRAIN @88% COMPLETE, DETENTION LEANCONCRETE ON THIS AREA TO CONTINUE SLAB REBAR WORKS
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF
WORKS
Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 60.71% 11 Pile caps more to complete at lower Deck Level , GREEN SHADES @ Upper Deck Level PILE CAP @
100% Completed , AT ELECTRICAL SUBSTATION AREA, AT LIFT PIT PREPARATION TO RECEIVE DAVCO WATERPROOFING MEMBRANE, ON
8 PILE
GOIMG EXCAVATION WORKS FOR PILE CAPS AT GRIDLINE A 1 1 to 4.
CAPS RC SUMPS AND PIPE
HAUNCHING @43.00%
3 PILE
COMPLETE
CAPS
DETENTION DRAIN @88% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGES OF WORKS

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 43.00% COMPLETE KEY PLAN SHOWING 11 MORE PILE CAPS TO CAST AT LOWER DECK KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
LEVEL, STAIRCASE #1 PILE CAP TO CAST ON 23 SEPTEMBER 43.00% COMPLETE

SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS AND TOP REINFORCING BARS
DONEUNTIL GRIDLINE 12-9F-G 70% COMPLETED FIRST SEGMENT OF SLAB 01B TARGET TO CAST ON 29 SEPTEMBER GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G

ESS

AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS WEEK. SLAB REBAR IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM AT ESS BELOW TRANSFORMER ROOM TO CAST UPSTAND BEAMS WITHIN THIS

REINFORCING BARS AND TOP REINFORCING BARS DONEUNTIL GRIDLINE 12- WEEK.

9F-G 70% COMPLETED FIRST SEGMENT OF SLAB 01B TARGET TO CAST ON 29

SEPTEMBER

LIFT COREWALL: APPLICATION WITH DAVCO WATERPROOFING MEMBRANE COVERED WITH HARD POLYFOAM PROTECTION TO
NEWLY INSTALLED WATERPROOFING MEMBRANE PRIOR TO BACKFILLING WORKS
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL WALLS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT COREWALL: APPLICATION WITH DAVCO WATERPROOFING MEMBRANE
APPLIED WITH DAVCO WATERPROOFING MEMBRANE COVERED WITH HARD POLYFOAM PROTECTION TO NEWLY INSTALLED

WATERPROOFING MEMBRANE PRIOR TO BACKFILLING WORKS

22 WORKERS +8 LCT +2 LBD +2CL 4 WATERPROOFING WORKS AND DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER 22 WORKERS +8 LCT +2 LBD +2CL 4 WATERPROOFING WORKS AND
INSTALLED 10 DROP PANELS SLAB SPLIT LEVEL BEAM APPLIED
DECK DEEP BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT DISMANTLE FORMWORKS=4 WORKERSESS FORMWORKS=4
BOTTOM REINFORCING BARS AND 3 DAVCO WATERPROOF DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP
WORKERS UPSTAND BEAMSFORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR
ROWS OF GROUND BEAMS MEMBRANE
WORKERS 8 DEPLOYED WORKERS TO DO WATERPROOFING PREPARATION GRINDING TOUCH UP, ASSIST TOWER CRANE, BEAM FORMWORK INSTALL / 6 WORKERS LIFT PIT DISMANTLE
INSTALLED AT GRID LINE 12 T0 9 D E F
SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS G FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS UPSTAND

BEAMSFORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL


@ELECTRICAL SUBSTATION REBAR INSTALL=6 REBAR WORKERS 8 DEPLOYED WORKERS TO DO
BELOW TRANSFORMER
WATERPROOFING PREPARATION GRINDING TOUCH UP, ASSIST TOWER
ROOM : INSTALLING
REBARS FOR UPSTAND CRANE, SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND
BEAMS TO CAST WITHIN OTHER SITE WORKS
THIS WEEK

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed


OTHER PERTINENT ACTIVITIES

RC LIFT PIT WALL WALL INSTALLING DAVCO


WATERPROFING MATERIALS COVERED WITH HARD
POLYFOAM PROTECTION PRIOR TO BACKFILLING WORKS

AT ELECTRICAL SUBSTATION BELOW TRANSFORMER ROOM ,


INSTALLING UPSTAND BEAM REBARS, TO CAST THIS WEEK

ON GOING EXCAVATION AT GRIDLINE A 1 TO 4