BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Monday, March 23, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks

PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 4 nos.
total Number OF Pile Caps 57 nos. 7.02%

MSCP PILES 100.00%


Structural work

CONTIGUOUS Bored Pile ( CBP ) 100.00%


GROUT PILES 100.00%

SITE VIEW
Architectural
work
M & E Work

TOWER CRANE CAPPING BEAM REBAR EXCAVATION WORKS TO PLATFORM LEVEL AT


INSTALLATION IN PROGRESS PILE CAP GROUP P 56 AND AT P57 NEAR ERSS
GRID LINE 12/G

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 BIG BREAKER 1
Site engineer 1 Safety office 1 New excavator 1
RTO 1 REBAR WORK 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 2 vibro hammer 1
Coordinator 1 gen Worker 4 NEW crawler crane 1
G Worker 7 FORMWORK 2 grout machine 1

Weather

DRIZZLING

Manpower
16:00 17:00 TOTAL : 16 TOTAL : 14 TOTAL : 0 TOTAL : 0 30 MANUAL TRIMMING HACKING OF CBP PILES ON GOING INSTALLATION OF CAPPING BEAM
TO CUT OFF LEVEL IN PROGRESS REBARS TO CAST ON TUESDAY AFTERNOON

Housekeeping work inprogress,

TOWER CRANE CAPPING BEAM REBAR INSTALLATION IN PROGRESS

EXCAVATION WORKS TO PLATFORM LEVEL AT PILE CAP GROUP P 56 AND AT P57 NEAR
ERSS GRID LINE 12/G

MANUAL TRIMMING HACKING OF CBP PILES TO CUT OFF LEVEL IN PROGRESS

REMARKS :
ON GOING INSTALLATION OF CAPPING BEAM REBARS TO CAST ON TUESDAY
AFTERNOON

BACKFILLING WORKS AT NEWLY CAST PILE CAPS, COLUMN STUMPS TO FOLLOW


CASTING

BACKFILLING WORKS AT NEWLY CAST PILE CAPS, COLUMN STUMPS TO FOLLOW


CASTING

BACKFILLING WORKS AT NEWLY CAST PILE BACKFILLING WORKS AT NEWLY CAST PILE
CAPS, COLUMN STUMPS TO FOLLOW CAPS, COLUMN STUMPS TO FOLLOW CASTING
CASTING

noise level reading: No record of Noise Exceeded