You are on page 1of 1

BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Wednesday, September 02, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks


PILE CAP STATUS

Lower DECk PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 13 nos.
total Number OF Pile Caps@ Lower Deck 27 nos. 48.15%
Upper DECk PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 28 nos.
total Number OF Pile Caps 30 nos. 93.33%
Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 66.45%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 42.10%
DETENTION DRAIN CAST TO DATE 62.66%
INTERNAL DRAINAGE :32 18.75%

SITE VIEW
Architectural
work
M & E Work

cast 2 Pile Caps today PILE CAP P31and P30 at Upper Pile Cap Construction AT LOWER DECK PILE CAPS is at 48.15%
Deck Level. STATUS: at Lower Deck Level is at COMPLETE, At Upper Deck is at 93.33% Complete LCT STARTED
48.15% Complete, Upper Deck Level PILE CAP INSTALLING reinforcing bars BELOW ELECTRICAL SUBSTATION
TRANSFORMER ROOM AREA SUCH AS DEEP BEAM for UPSTAND
IS AT 93.33% Complete , 13 Pile caps more to
BEAM & BEAM Wall Preparation AT Electrical Substation TO
complete at lower Deck Level
FORM UP THE UPPER DECK SLAB LEVEL BEHIND ELECTRICAL
SUBSTATION Area ( YELLOW CLOUD )

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor 1 Generator 2
Site Supervisor Safety Supervisor 1 Excavator CL
1 1
DETENTION DRAIN:
Safety officer REBAR
1 WORK/FRMWRK RC 3 UPDATED AT 62.66%
08:30 17:30
SUMP WALL COMPLETE RC SUMPS AND PIPE
Site engineer
1
FORMWORK D DRAIN
WALL/CAST 3
BAR BENDER MACHINE
1
DETENTION DRAIN HAUNCHING PROGRESS
RTO BIG BREAKER
@18.75%
1 INTERNAL DRAIN 3 1

REBAR WORK D DRAIN 1 TONNE ROLLER-


REMARKS Administrator 1 TOP SLAB 6 COMPACTOR 1

Coordinator 1 CAPPING BEAM - AIR RECEIVER 1


PILE CAP P23 TC INSTALLED
ECO 1 7 1

Weather G Worker 6
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
5
INTERNAL DRAINAGE
DRIZZLE
EXCAV SUPVSR 1
Manpower
2:00 14:30 TOTAL : 14 TOTAL : 30 TOTAL : 0 TOTAL : 5 49 DETENTION DRAIN @62.66% COMPLETE RC SUMPS AND PIPE HAUNCHING AT 18.75% COMPLETE

Housekeeping work inprogress,

Pile Cap Construction AT LOWER DECK PILE CAPS is at 48.15% COMPLETE, At Upper Deck is at 93.33%
Complete LCT STARTED INSTALLING reinforcing bars BELOW ELECTRICAL SUBSTATION
TRANSFORMER ROOM AREA SUCH AS DEEP BEAM for UPSTAND BEAM & BEAM Wall Preparation AT
Electrical Substation TO FORM UP THE UPPER DECK SLAB LEVEL BEHIND ELECTRICAL SUBSTATION
Area ( YELLOW CLOUD )

DETENTION DRAIN @62.66% COMPLETE

DETENTION DRAIN @62.66% COMPLETE EXCAVATION TO LAY M&E PIPE TO IC #3 CAST 450MM DIA PIPE HAUNCHING FOR INTERNAL DRAINAGE AT
18.75% ACCOMPLISHED

INSTALLING DEEP BEAM REINFORCING BARS BELOW ELECTRICAL-SUBSTATION TRANSFORMER


ROOM AREA

CAST PILE CAP P31 AND PILE CAP P30 INSTALLING DEEP BEAM REINFORCING BARS BELOW CAST PILE CAP P31 AND PILE CAP P30
ELECTRICAL-SUBSTATION TRANSFORMER ROOM AREA

24 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @DETENTION 24 WORKERS +8 LCT +2 LBD +2CL SUPERVISOR 1,
DRAIN CONSTRUCTION: 6 REBAR workers &SLAB FORMWORKS INSTALLATION pILE CAPS:6 workers SAFETY 1, PILE
DOING SITEWORKS: BEAKDOWN OF
REBAR+ FORMWORK INSTALLATION, INTERNAL DRAINAGE: 6REBAR+FORMWORKS, BELOW ESS: CAPS : 6WORKERS
DEEP BEAMS INSTALLING3 REBAWORKERS, 2 WORKERS SAFETY & HOUSEKEEPING, SHIFTING MANPOWER @DETENTION DRAIN
HOISTING MARTERIALS FROM LC&T Laydown Area, 3 LBD HACKING OF MSCP PILES+ 4 WORKERS CONSTRUCTION: 6 REBAR workers
IC WORKS @HDB BLOCK 231 FMWRK+6 REBAR
&SLAB FORMWORKS INSTALLATION WORKERS , INTERNAL
pILE CAPS:6 workers REBAR+ DRAINAGE 6 WRKS/
FORMWORK INSTALLATION, FORMWORKS/REBARS,

INTERNAL DRAINAGE: TOWER CRANE


OPERATOR 1 LBD
6REBAR+FORMWORKS, BELOW ESS:
HACK TEAM 3
DEEP BEAMS INSTALLING3
EXCAV OPRTR 1
REBAWORKERS, 2 WORKERS SAFETY & EXCAV SUPVSR 1,
HOUSEKEEPING, SHIFTING HOISTING IC#4SEWER 4
MARTERIALS FROM LC&T Laydown WORKERS
Area, 3 LBD HACKING OF MSCP PILES+
4 WORKERS IC WORKS @HDB BLOCK
231

Today Noise Meter does not exceed

You might also like