DAILY SITE RECORD Wednesday, September 02, 2020 DAILY SITE PHOTO
SITE VIEW
Architectural
work
M & E Work
cast 2 Pile Caps today PILE CAP P31and P30 at Upper Pile Cap Construction AT LOWER DECK PILE CAPS is at 48.15%
Deck Level. STATUS: at Lower Deck Level is at COMPLETE, At Upper Deck is at 93.33% Complete LCT STARTED
48.15% Complete, Upper Deck Level PILE CAP INSTALLING reinforcing bars BELOW ELECTRICAL SUBSTATION
TRANSFORMER ROOM AREA SUCH AS DEEP BEAM for UPSTAND
IS AT 93.33% Complete , 13 Pile caps more to
BEAM & BEAM Wall Preparation AT Electrical Substation TO
complete at lower Deck Level
FORM UP THE UPPER DECK SLAB LEVEL BEHIND ELECTRICAL
SUBSTATION Area ( YELLOW CLOUD )
Weather G Worker 6
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
5
INTERNAL DRAINAGE
DRIZZLE
EXCAV SUPVSR 1
Manpower
2:00 14:30 TOTAL : 14 TOTAL : 30 TOTAL : 0 TOTAL : 5 49 DETENTION DRAIN @62.66% COMPLETE RC SUMPS AND PIPE HAUNCHING AT 18.75% COMPLETE
Pile Cap Construction AT LOWER DECK PILE CAPS is at 48.15% COMPLETE, At Upper Deck is at 93.33%
Complete LCT STARTED INSTALLING reinforcing bars BELOW ELECTRICAL SUBSTATION
TRANSFORMER ROOM AREA SUCH AS DEEP BEAM for UPSTAND BEAM & BEAM Wall Preparation AT
Electrical Substation TO FORM UP THE UPPER DECK SLAB LEVEL BEHIND ELECTRICAL SUBSTATION
Area ( YELLOW CLOUD )
DETENTION DRAIN @62.66% COMPLETE EXCAVATION TO LAY M&E PIPE TO IC #3 CAST 450MM DIA PIPE HAUNCHING FOR INTERNAL DRAINAGE AT
18.75% ACCOMPLISHED
CAST PILE CAP P31 AND PILE CAP P30 INSTALLING DEEP BEAM REINFORCING BARS BELOW CAST PILE CAP P31 AND PILE CAP P30
ELECTRICAL-SUBSTATION TRANSFORMER ROOM AREA
24 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @DETENTION 24 WORKERS +8 LCT +2 LBD +2CL SUPERVISOR 1,
DRAIN CONSTRUCTION: 6 REBAR workers &SLAB FORMWORKS INSTALLATION pILE CAPS:6 workers SAFETY 1, PILE
DOING SITEWORKS: BEAKDOWN OF
REBAR+ FORMWORK INSTALLATION, INTERNAL DRAINAGE: 6REBAR+FORMWORKS, BELOW ESS: CAPS : 6WORKERS
DEEP BEAMS INSTALLING3 REBAWORKERS, 2 WORKERS SAFETY & HOUSEKEEPING, SHIFTING MANPOWER @DETENTION DRAIN
HOISTING MARTERIALS FROM LC&T Laydown Area, 3 LBD HACKING OF MSCP PILES+ 4 WORKERS CONSTRUCTION: 6 REBAR workers
IC WORKS @HDB BLOCK 231 FMWRK+6 REBAR
&SLAB FORMWORKS INSTALLATION WORKERS , INTERNAL
pILE CAPS:6 workers REBAR+ DRAINAGE 6 WRKS/
FORMWORK INSTALLATION, FORMWORKS/REBARS,