TIMES SCHEDULE PROYEK DOCKING REPAIR

NAMA PROYEK : BG. TAMA 2502 STATUS DOCKING : DOCKING REPAIR


PT. DUTABAHARI MENARA LINE
DOCKYARD KODE PEKERJAAN : R - 8.142 /DR KLASIFIKASI : BKI / IS
Jl. Ir.H.P.M Noor, Kuin Cerucuk Banjarmasin - : 18 Hari : 76.20/75.15 x 21.94 x 4.87 Meter
ESTIMASI WAKTU REPAIR DOCK DIMENSI
70129
Telp. +62 511 4413364 Fax. +62 511 4413365 NO. PENAWARAN : PEMILIK KAPAL : PT. HABCO PRIMATAMA

1 2 3 4 5 6 7 8 9
Bobot Progress
NO DESCRIPTION OF WORKS Lama pekerjaan Alat /Gun Progress % Actual Progress %
%

10 11 12 13 14 15 16 17 18
HULL CONSTRUCTION 100.00% 51.90% 51.90%
Side shell Sb
Replating Sideshell Fr. 3/4 - 4/5 (Sb) 8 Hari 99.81% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48%
Rewelding 1 Hari 0.19% 0.19%

Total 100.00% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 0.19%
24.95% 37.43% 49.91% 62.38% 74.86% 87.34% 99.81% 100.00%

Demikian yang dapat kami sampaikan, atas perhatian dan kerjasamannya saya ucapkan terima kasih.

Direncanakan oleh, Diketahui Disetujui


Keterangan :
= Estimasi
= Re schedule
= Actual
Huruf warna hijau pekerjaan tambahan
Masudi Guszazif Titah P. Hadi Soetrisno = Tidak ada kerja
Pimpro Manager Produksi General Manager = Selesai