Professional Documents
Culture Documents
I PEKERJAAN STRUKTUR
A PEKERJAAN PERSIAPAN 2.2591% 28 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 0.081% 2.259%
B PEKERJAAN GALIAN, URUGAN DAN LANTAI KERJA 8.0028% 7 1.143% 1.143% 1.143% 1.143% 1.143% 1.143% 1.143% 8.003%
C PEKERJAAN STRUKTUR
C.1 LANTAI BASEMENT 3 4.7896% 10 0.479% 0.479% 0.479% 0.479% 0.479% 0.479% 0.479% 0.479% 0.479% 0.479% 4.790%
C.2 LANTAI BASEMENT 2 3.5426% 10 0.354% 0.354% 0.354% 0.354% 0.354% 0.354% 0.354% 0.354% 0.354% 0.354% 3.543%
C.3 LANTAI BASEMENT 1 3.5426% 11 0.322% 0.322% 0.322% 0.322% 0.322% 0.322% 0.322% 0.322% 0.322% 0.322% 0.322% 3.543%
C.4 LANTAI 1 4.1256% 9 0.458% 0.458% 0.458% 0.458% 0.458% 0.458% 0.458% 0.458% 0.458% 4.126%
C.5 LANTAI 2 4.0382% 8 0.505% 0.505% 0.505% 0.505% 0.505% 0.505% 0.505% 0.505% 4.038%
C.6 LANTAI 3 3.7394% 6 0.623% 0.623% 0.623% 0.623% 0.623% 0.623% 3.739%
C.7 LANTAI ATAP 1.0665% 2 0.533% 0.533% 1.066%
C.8 STRUKTUR LAIN - LAIN 1.6664% 3 0.555% 0.555% 0.555% 1.666%
II PEKERJAAN ARSITEKTUR
A PEKERJAAN PERSIAPAN 1.4684% 13 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 1.468%
B LANTAI BASEMENT 3 1.0784% 5 0.216% 0.216% 0.216% 0.216% 0.216% 1.078%
C LANTAI BASEMENT 2 1.5342% 5 0.307% 0.307% 0.307% 0.307% 0.307% 1.534%
D LANTAI BASEMENT 1 5.2946% 5 1.059% 1.059% 1.059% 1.059% 1.059% 5.295%
E LANTAI 1 4.1191% 5 0.824% 0.824% 0.824% 0.824% 0.824% 4.119%
F LANTAI 2 3.8550% 6 0.643% 0.643% 0.643% 0.643% 0.643% 0.643% 3.855%
G LANTAI 3 3.8170% 5 0.763% 0.763% 0.763% 0.763% 0.763% 3.817%
H LANTAI ATAP 1.8431% 4 0.461% 0.461% 0.461% 0.461% 1.843%
I PEKERJAAN KULIT BANGUNAN 0.8895% 4 0.222% 0.222% 0.222% 0.222% 0.890%
J PEKERJAAN FASOS DAN FASUM 3.3935% 4 0.848% 0.848% 0.848% 0.848% 3.394%
BOBOT PROGRES BULANAN 100.00% 0.081% 0.081% 0.081% 0.081% 1.224% 1.703% 1.703% 2.057% 1.236% 1.215% 1.720% 1.366% 1.064% 1.419% 0.914% 0.914% 0.757% 0.861% 1.479% 2.318% 3.361% 3.554% 5.979% 6.341% 7.717% 6.092% 7.682% 8.253% 8.452% 7.158% 6.488% 2.950% 2.335% 1.366% 100.00%
KUMULATIF PROGRES RENCANA BULANAN 0.081% 0.161% 0.242% 0.323% 1.547% 3.250% 4.952% 7.010% 8.246% 9.461% 11.181% 12.547% 13.612% 15.030% 15.944% 16.858% 17.615% 18.476% 19.955% 22.273% 25.634% 29.188% 35.167% 41.508% 49.225% 55.317% 62.999% 71.252% 79.704% 86.862% 93.350% 96.300% 98.634% 100.000%
BOBOT PROGRES AKTUAL BULANAN
KUMULATIF PROGRES AKTUAL BULANAN
DEVIASI
Disetujui Oleh :
Keterangan Diajukan Oleh : Diperiksa Oleh :
Pemilik Proyek/Owner
Catatan : PT. Java Indoku PT. Padang Garbha Utama PT. Adhi Garba Sakti
( Firman Pratikno ) (Dr.Ir.IBP Adnyana , ST, MT,IPM) ( dr. Kadek Sugiharta, SpOG (k) )
Project Manager Konsultant Direktur
A PEKERJAAN PERSIAPAN
1 Mob Demob Pekerja 1.00 ls 50,000,000.00 50,000,000.00
2 Keamanan Proyek (Mulai dari Bulan November 2016) 17.00 bln 12,000,000.00 204,000,000.00
3 Pengukuran kembali site 2,588.00 m2 3,100.00 8,022,800.00
4 Pembersihan Lahan 2,588.00 m2 8,900.00 23,033,200.00
5 Akses Jalan Proyek :
- Jembatan masuk ke proyek ( beton bertutalang ) 9.00 m2 1,000,000.00 9,000,000.00
- Perataan + Pemadatan Tanah + Urugan Limestone 50.00 m 3
150,000.00 7,500,000.00
6 Pagar Proyek 220.00 m' 337,000.00 74,140,000.00
7 Papan nama Proyek & Papan IMB 2.00 unit 636,000.00 1,272,000.00
8 Pos Jaga 1.00 unit 1,236,000.00 1,236,000.00
9 Kantor Direksi 36.00 m2 629,600.00 22,665,600.00
10 Toilet Karyawan, Dapur + Mushola 24.00 m2 508,800.00 12,211,200.00
11 Bedeng/Barak Pekerja, Uk 15x5m 75.00 m2 508,800.00 38,160,000.00
12 MCK Pekerja ( Include Septictank, torn air dan instalasi pipa ) 24.00 m2 508,800.00 12,211,200.00
13 Gudang Material 18.00 m 2
508,800.00 9,158,400.00
14 Rumah Genset 4.00 m2 508,800.00 2,035,200.00
15 Rumah Bar Bender & Bar Cuter 4.00 m 2
508,800.00 2,035,200.00
16 Pengadaan Listrik kerja Token/prabayar ( 1300 Watt ) 1.00 ls 4,200,000.00 4,200,000.00
17 Pengadaan Listrik kerja ( 41,5KVA ) 41.50 kva 2,500,000.00 103,750,000.00
18 Biaya bulanan listrik (Mulai dari Bulan Februari 2017) 14.00 bln 3,000,000.00 42,000,000.00
19 Pengadaan Air kerja sementara 1.00 ls 9,240,000.00 9,240,000.00
20 Pengadaan Air kerja Permanent ( Sumur Bor + Perijinan ) 1.00 ls 178,000,000.00 178,000,000.00
2 LANTAI BASEMENT
a Galian Basement 11,972.00 m3 40,700.00 487,260,400.00
b Galian GWT & STP 1,929.18 m3 40,700.00 78,517,626.00
c Pembersihan sisa tanah di dinding Soldier Pile 657.10 m 2
15,000.00 9,856,500.00
- Beton K300, Ready Mix, (Incl. alat bantu) 54.26 m3 1,101,600.00 59,771,934.72
- Besi :
D16mm 3,192.00 kg 12,000.00 38,304,000.00
D10mm 1,366.28 kg 12,000.00 16,395,321.60
2 TIE BEAM
a TB 4 ( 30x60cm ) 609.00 m'
- Galian tanah manual ( cadas ) 152.25 m3 143,200.00 21,802,200.00
- Urugan Pasir 10cm 18.27 m3 245,600.00 4,487,112.00
- Lantai Kerja Beton Tumbuk, Ad. 1Pc : 3Ps : 5Kr tebal 5 cm 9.14 m 3
823,200.00 7,519,932.00
- Bekisting batako 609.00 m2 85,000.00 51,765,000.00
- Beton K300, Ready Mix, (Incl. alat bantu) 109.62 m 3
1,101,600.00 120,757,392.00
- Besi :
D19mm 9,473.97 kg 12,000.00 113,687,654.98
D16mm 625.07 kg 12,000.00 7,500,880.80
D13mm 1,433.25 kg 12,000.00 17,199,000.00
D10mm 6,085.37 kg 12,000.00 73,024,449.12
3 PLAT LANTAI BASEMENT - 3
a LANTAI TEBAL 25CM 1,600.00 m2
- Perataan & Pemadatan Tanah 1,600.00 m2 25,500.00 40,800,000.00
- Urugan Pasir 10cm 160.00 m 3
245,600.00 39,296,000.00
- Lantai Kerja Beton Tumbuk, Ad. 1Pc : 3Ps : 5Kr tebal 5 cm 80.00 m 3
823,200.00 65,856,000.00
- Floor Hardeener tabur ex fosroc 1,600.00 m2 60,000.00 96,000,000.00
7 TANGGA
a TANGGA UTAMA
1) TB 4 ( 30x60cm ) 9.35 m'
- Galian tanah manual ( cadas ) 2.34 m3 143,200.00 334,730.00
- Urugan Pasir 10cm 0.28 m3 245,600.00 68,890.80
- Lantai Kerja Beton Tumbuk, Ad. 1Pc : 3Ps : 5Kr tebal 5 cm 0.14 m 3
823,200.00 115,453.80
- Bekisting batako 9.35 m2 85,000.00 794,750.00
- Beton K300, Ready Mix, (Incl. alat bantu) 0.98 m 3
1,101,600.00 1,081,495.80
- Water Proofing Integral, Aquapel Ex' Cementaid 0.98 m3 618,000.00 606,721.50
- Besi :
D19mm 153.25 kg 12,000.00 1,839,014.10
D16mm 15.54 kg 12,000.00 186,532.50
PT. JAVA INDOKU 10
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
- Besi :
D13mm 110.60 kg 12,000.00 1,327,233.60
d8mm 41.81 kg 12,000.00 501,681.60
8 RAMP MOBIL B2 - B3
1 KOLOM TYPE KRM ( 40x40cm ) 1.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 4.40 m2 248,900.00 1,095,160.00
- Beton K350, Ready Mix, (Incl. alat bantu) 0.44 m 3
1,240,500.00 545,820.00
- Besi :
D16mm 119.70 kg 12,000.00 1,436,400.00
D10mm 20.85 kg 12,000.00 250,194.00
5 PARAPET BETON RAMP MOBIL, (TEBAL 15CM x TINNGI 120CM) 25.40 m'
- Bekisting Multipleks 12mm, rangka kayu 60.96 m2 278,100.00 16,952,976.00
- Beton K300, Ready Mix, (Incl. alat bantu) 4.57 m 3
1,101,600.00 5,036,515.20
- Besi :
D10mm 1,105.20 kg 12,000.00 13,262,457.60
9 SUMP - PIT
a TYPE - 1 ( 80x120x150cm) TEBAL 25CM 4.00 Unit
- Galian tanah manual ( cadas ) 19.95 m3 143,200.00 2,856,840.00
- Urugan Pasir 10cm 0.38 m 3
245,600.00 94,310.40
- Lantai Kerja Beton Tumbuk, Ad. 1Pc : 3Ps : 5Kr tebal 5 cm 0.19 m3 823,200.00 158,054.40
- Bekisting batako 30.80 m2 85,000.00 2,618,000.00
- Bekisting Multipleks 12mm, rangka kayu 24.00 m 2
352,800.00 8,467,200.00
- Beton K300, Ready Mix, (Incl. alat bantu) 6.00 m3 1,101,600.00 6,609,600.00
- Water Proofing Integral, Aquapel Ex' Cementaid 6.00 m 3
618,000.00 3,708,000.00
- Besi :
D13mm 946.27 kg 12,000.00 11,355,220.80
- Beton K300, Ready Mix, (Incl. alat bantu) 2.63 m3 1,101,600.00 2,891,700.00
- Water Proofing Integral, Aquapel Ex' Cementaid 2.63 m 3
618,000.00 1,622,250.00
- Besi :
D13mm 376.36 kg 12,000.00 4,516,281.00
- Besi :
D19mm 206.52 kg 12,000.00 2,478,243.60
D16mm 20.95 kg 12,000.00 251,370.00
D13mm 27.65 kg 12,000.00 331,808.40
D10mm 79.95 kg 12,000.00 959,439.60
5 TANGGA
a TANGGA UTAMA
1) KOLOM KT (150x300mm) 4.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 9.18 m2 248,900.00 2,284,902.00
- Beton K350, Ready Mix, (Incl. alat bantu) 0.46 m 3
1,240,500.00 569,389.50
- Besi :
D13mm 102.70 kg 12,000.00 1,232,431.20
D10mm 45.58 kg 12,000.00 547,008.00
- Beton K300, Ready Mix, (Incl. alat bantu) 0.54 m3 1,101,600.00 594,864.00
- Besi :
D13mm 82.95 kg 12,000.00 995,425.20
D10mm 54.39 kg 12,000.00 652,680.00
5 TANGGA
a TANGGA UTAMA
1) KOLOM KT (150x300mm) 4.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 11.34 m2 248,900.00 2,822,526.00
- Beton K350, Ready Mix, (Incl. alat bantu) 0.57 m3 1,240,500.00 703,363.50
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
- Besi :
D13mm 110.60 kg 12,000.00 1,327,233.60
d8mm 41.81 kg 12,000.00 501,681.60
b TANGGA DARURAT
1) KOLOM KT (150x300mm) 1.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 2.84 m2 248,900.00 705,631.50
- Beton K350, Ready Mix, (Incl. alat bantu) 0.14 m 3
1,240,500.00 175,840.88
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
4 TANGGA
a TANGGA UTAMA
1) KOLOM KT (150x300mm) 4.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 11.34 m2 248,900.00 2,822,526.00
- Beton K350, Ready Mix, (Incl. alat bantu) 0.57 m 3
1,240,500.00 703,363.50
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
b TANGGA DARURAT
1) KOLOM KT (150x300mm) 1.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 2.84 m2 248,900.00 705,631.50
- Beton K350, Ready Mix, (Incl. alat bantu) 0.14 m 3
1,240,500.00 175,840.88
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
- Beton K300, Ready Mix, (Incl. alat bantu) 0.36 m3 1,101,600.00 399,330.00
- Besi :
D13mm 38.18 kg 12,000.00 458,211.60
D10mm 28.92 kg 12,000.00 347,008.20
- Besi :
D19mm 99.75 kg 12,000.00 1,197,000.00
D13mm 99.75 kg 12,000.00 1,197,000.00
D10mm 79.32 kg 12,000.00 951,825.00
7 DROP OFF
a Jalan beton tebal = 20cm 270.60 m2
- Perataan & Pemadatan Tanah 270.60 m2 25,500.00 6,900,300.00
- Urugan Pasir 10cm 270.60 m2 245,600.00 66,459,360.00
- Lantai Kerja Beton Tumbuk, Ad. 1Pc : 3Ps : 5Kr tebal 5 cm 13.53 m 3
823,200.00 11,137,896.00
- Beton K300, Ready Mix, (Incl. alat bantu) 54.12 m 3
1,101,600.00 59,618,592.00
- Besi :
Wiremesh M8 - 150mm, uk. 2,1x5,4m ( 2 lapis ) 541.20 m2 67,910.05 36,752,920.63
- Besi :
D16mm 66.50 kg 12,000.00 798,000.00
D10mm 45.33 kg 12,000.00 543,900.00
- Besi :
D19mm 4,018.77 kg 12,000.00 48,225,253.20
D16mm 220.00 kg 12,000.00 2,640,000.00
D13mm 671.96 kg 12,000.00 8,063,470.80
D10mm 2,220.56 kg 12,000.00 26,646,748.80
- Besi :
D19mm 7,863.98 kg 12,000.00 94,367,788.80
D10mm 1,500.00 kg 12,000.00 18,000,000.00
4 TANGGA
a TANGGA UTAMA
1) KOLOM KT (150x300mm) 4.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 12.78 m2 248,900.00 3,180,942.00
- Beton K350, Ready Mix, (Incl. alat bantu) 0.64 m3 1,240,500.00 792,679.50
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
b TANGGA DARURAT
1) KOLOM KT (150x300mm) 1.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 3.20 m2 248,900.00 795,235.50
- Beton K350, Ready Mix, (Incl. alat bantu) 0.16 m3 1,240,500.00 198,169.88
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
- Besi :
D13mm 115.21 kg 12,000.00 1,382,535.00
- Beton K300, Ready Mix, (Incl. alat bantu) 63.36 m3 1,101,600.00 69,797,376.00
- Besi :
D19mm 5,638.62 kg 12,000.00 67,663,449.60
D16mm 589.19 kg 12,000.00 7,070,280.00
D13mm 777.73 kg 12,000.00 9,332,769.60
D10mm 1,570.11 kg 12,000.00 18,841,305.60
4 TANGGA
a TANGGA UTAMA
1) KOLOM KT (150x300mm) 4.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 11.34 m2 248,900.00 2,822,526.00
- Beton K350, Ready Mix, (Incl. alat bantu) 0.57 m 3
1,240,500.00 703,363.50
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
b TANGGA DARURAT
1) KOLOM KT (150x300mm) 1.00 ttk
- Bekisting Multipleks 12mm, rangka kayu 2.84 m2 248,900.00 705,631.50
- Beton K350, Ready Mix, (Incl. alat bantu) 0.14 m3 1,240,500.00 175,840.88
- Besi :
D13mm 119.82 kg 12,000.00 1,437,836.40
D10mm 55.94 kg 12,000.00 671,328.00
1 BALOK
a B1 (40x60cm) 215.00 m'
- Bekisting Multipleks 12mm, rangka kayu 344.00 m2 248,900.00 85,621,600.00
- Beton K300, Ready Mix, (Incl. alat bantu) 51.60 m 3
1,101,600.00 56,842,560.00
- Besi :
D19mm 3,320.07 kg 12,000.00 39,840,810.00
D13mm 449.87 kg 12,000.00 5,398,470.00
D10mm 1,672.49 kg 12,000.00 20,069,910.00
b KD-2 2.00 bh
- WF. 250x125x6x9mm 745.92 kg 21,500.00 16,037,280.00
- Stiffner Plate 8mm, Uk. 325x400mm 32.66 kg 21,500.00 702,104.00
- Stiffner Plate 8mm, Uk. 59x232mm 10.32 kg 21,500.00 221,778.45
- Joint Plate 10mm, Uk. 145x510mm 11.61 kg 21,500.00 249,618.23
- Bolt Ø16mm 20.00 pcs 10,000.00 200,000.00
Dudukan Gording
- G1 Plate 8mm, Uk. 100x150mm 20.72 kg 21,500.00 445,566.00
- G1 Plate 8mm, Uk. 100x125mm 17.27 kg 21,500.00 371,305.00
c KD-3 4.00 bh
- WF. 250x125x6x9mm ( Inc. Cat Zincromate ) 1,594.40 kg 21,500.00 34,279,600.00
- Stiffner Plate 8mm, Uk. 325x400mm 65.31 kg 21,500.00 1,404,208.00
- Stiffner Plate 8mm, Uk. 59x232mm 20.63 kg 21,500.00 443,556.90
- Joint Plate 10mm, Uk. 145x510mm 23.22 kg 21,500.00 499,236.45
- Bolt Ø16mm 40.00 pcs 10,000.00 400,000.00
PT. JAVA INDOKU 48
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
Dudukan Gording
- G1 Plate 8mm, Uk. 100x150mm 41.45 kg 21,500.00 891,132.00
- G1 Plate 8mm, Uk. 100x125mm 34.54 kg 21,500.00 742,610.00
d KD-4 8.00 bh
- WF. 250x125x6x9mm ( Inc. Cat Zincromate ) 1,539.20 kg 21,500.00 33,092,800.00
- Stiffner Plate 8mm, Uk. 325x400mm 130.62 kg 21,500.00 2,808,416.00
- Stiffner Plate 8mm, Uk. 59x232mm 27.51 kg 21,500.00 591,409.20
- Joint Plate 10mm, Uk. 145x510mm 46.44 kg 21,500.00 998,472.90
- Bolt Ø16mm 80.00 pcs 10,000.00 800,000.00
Dudukan Gording
- G1 Plate 8mm, Uk. 100x150mm 45.22 kg 21,500.00 972,144.00
- G1 Plate 8mm, Uk. 100x125mm 37.68 kg 21,500.00 810,120.00
4 LAIN - LAIN
- Penutup Atap 576.00 m2 100,000.00 57,600,000.00
- WF. 200x100x5,5x8mm ( Inc. Cat Zincromate ) 1,075.20 kg 21,500.00 23,116,800.00
- Gording Cnp. 200x75x20x3,2mm @6m ( Inc. Cat Zincromate ) 13,070.70 kg 21,500.00 281,020,050.00
- Trekstang Ø12mm, panjang 1,25m (Incl. Mur + baut) 468.00 m' 35,000.00 16,380,000.00
- Ikatan angin Ø19mm, panjang 12m (Incl. Turnbuckle) 382.00 kg 12,000.00 4,584,000.00
A PEKERJAAN PERSIAPAN
1 Pengadaan air/Listrik kerja 12 bln 10,000,000 120,000,000
2 Keamanan Proyek 12 bln 15,000,000 180,000,000
3 Mob/Demob Pekerja 1 ls 75,000,000 75,000,000
4 Pengukuran 1 ls 100,000,000 100,000,000
5 Pembersihan Lahan 1 ls 50,000,000 50,000,000
6 Pagar Proyek 1 ls 150,000,000 150,000,000
7 Bedeng pekerja 1 ls 50,000,000 50,000,000
8 Asuransi Jamsostek 1 ls 75,000,000 75,000,000
9 K3 ( Keselamatan & Kesehatan kerja ) 1 ls 200,000,000 200,000,000
10 Pemadam Kebakaran 1 ls 20,000,000 20,000,000
PT. JAVA INDOKU 49
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
B PEKERJAAN ARSITEKTUR
I LANTAI BASEMENT 3
I.a PEKERJAAN DINDING
1 Pasangan dinding bata ringan tebal 7.5 cm (tanpa finish) "Celcon"
pemasangan dgn dry mortar lengkap berikut dgn kolom & balok praktis
3 Skimcoat
- Dinding Beton 235.2 m2 117,000 27,518,400
- Kolom 294 m2 117,000 34,398,000
- Tangga 26.55 m2 117,000 3,106,350
3
Pengadaan dan pemasangan Keramik 300 x 300 mm ex Roman berikut
dengan mortar dan juga perlengkapan pemasangan
3 Skimcoat
- Pada plat dan balok beton Area Parkir Basement 1547.1875 m2 117,000 181,020,938
3 Pengadaan dan pemasangan Kusen & pintu Alum. Ex ' Alexindo fin.
coating ( Incl. kaca ) berikut dengan aksesories dan perlengkapan
pemasangannya.
- Ruang tangga 1 nos 7,500,000 7,500,000
PT. JAVA INDOKU 52
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
1 Pengadaan dan pemasangan Car stopper berikut dengan finish cat dan
perlengkapan pemasangannya.
- Parkir mobil 90 pcs 250,000 22,500,000
II LANTAI BASEMENT 2
II.a PEKERJAAN DINDING
1 Pasangan dinding bata ringan tebal 7.5 cm (tanpa finish) "Celcon"
pemasangan dgn dry mortar lengkap berikut dgn kolom & balok praktis
3 Skimcoat
- Dinding Beton 235.2 m2 117,000 27,518,400
- Kolom 294 m2 117,000 34,398,000
- Tangga 26.55 m2 117,000 3,106,350
3
Pengadaan dan pemasangan Keramik 300 x 300 mm ex Roman berikut
dengan mortar dan juga perlengkapan pemasangan
5
Pengadaan dan pemasangan Keramik 300 x 300 mm ex Roman berikut
dengan mortar dan juga perlengkapan pemasangan
4 Skimcoat
- Pada plat dan balok beton Area Parkir Basement 1,216 m2 117,000 142,225,200
3 Pengadaan dan pemasangan Kusen & pintu Alum. Ex ' Alexindo fin.
coating ( Incl. kaca ) berikut dengan aksesories dan perlengkapan
pemasangannya.
- Lobby tangga ( Kusen pintu dan jendala kaca ) 1 nos 7,500,000 7,500,000
- Toilet laki-laki ( kusen pintu ) 3 nos 4,000,000 12,000,000
- Toilet wanita ( kusen pintu ) 3 nos 4,000,000 12,000,000
1 Pengadaan dan pemasangan Car stopper berikut dengan finish cat dan
perlengkapan pemasangannya.
- Parkir mobil 36 pcs 250,000 9,000,000
3 Skimcoat
- Ramp Pasien 143.75 m2 117,000 16,818,750
- Tangga 26.55 m2 117,000 3,106,350
2
Pengadaan dan pemasangan Keramik 300 x 300 mm ex Roman berikut
dengan mortar dan juga perlengkapan pemasangan
4 Skimcoat
- Ramp pasien 135 m2 90,000 12,150,000
- Tangga + Stepnosing 24.5 m 2
90,000 2,205,000
3 Pengadaan dan pemasangan Kusen & pintu Alum. Ex ' Alexindo fin.
coating ( Incl. kaca ) berikut dengan aksesories dan perlengkapan
pemasangannya.
- Kamar Rawat Inap ( Kusen dan jendala kaca ) 30 nos 4,563,000 136,890,000
- Ramp pasien ( Kusen dan pintu kaca ) 1 nos 5,265,000 5,265,000
III.f PEKERJAAN LAIN - LAIN
IV LANTAI 1
IV.a PEKERJAAN DINDING
1 Pasangan dinding bata ringan tebal 7.5 cm (tanpa finish) "Celcon"
pemasangan dgn dry mortar lengkap berikut dgn kolom & balok praktis
3 Skimcoat
- Ramp Pasien 143.75 m2 117,000 16,818,750
- Tangga 26.55 m2 117,000 3,106,350
2
Pengadaan dan pemasangan Keramik 300 x 300 mm ex Roman berikut
dengan mortar dan juga perlengkapan pemasangan
4 Skimcoat
- Ramp pasien 135 m2 90,000 12,150,000
- Tangga 24.5 m2 90,000 2,205,000
3 Pengadaan dan pemasangan Kusen & pintu Alum. Ex ' Alexindo fin.
coating ( Incl. kaca ) berikut dengan aksesories dan perlengkapan
pemasangannya.
- Lobby, Ruang tunggu, Koridor 2 nos 5,265,000 10,530,000
- UGD 2 nos 5,265,000 10,530,000
- Ruang Dokter 2 nos 5,265,000 10,530,000
- Ruang Laboratorium 2 nos 5,265,000 10,530,000
- Ruang Rekam Medis 2 nos 5,265,000 10,530,000
- Farmasi + Ruang Apotik 2 nos 5,265,000 10,530,000
- Ruang CT Scan 2 nos 5,265,000 10,530,000
- Ruang Operator 2 nos 5,265,000 10,530,000
- Ruang Dokter + R. Xray 2 nos 5,265,000 10,530,000
- Ruang USG 2 nos 5,265,000 10,530,000
- Ruang Poli Saraf 2 nos 5,265,000 10,530,000
- Ruang Poli THT 2 nos 5,265,000 10,530,000
- Ruang Poli Kulit 2 nos 5,265,000 10,530,000
- Ruang Poli SP Anak 9 2 nos 5,265,000 10,530,000
- Ruang Ply Ground 2 nos 5,265,000 10,530,000
- Ruang Poli Obgyn 2 nos 5,265,000 10,530,000
PT. JAVA INDOKU 75
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
V LANTAI 2
V.a PEKERJAAN DINDING
1 Pasangan dinding bata ringan tebal 7.5 cm (tanpa finish) "Celcon"
pemasangan dgn dry mortar lengkap berikut dgn kolom & balok praktis
3 Skimcoat
- Ramp Pasien 143.75 m2 117,000 16,818,750
- Tangga 26.55 m2 117,000 3,106,350
3 Pengadaan dan pemasangan Kusen & pintu Alum. Ex ' Alexindo fin.
coating ( Incl. kaca ) berikut dengan aksesories dan perlengkapan
pemasangannya.
- Lobby, Ruang tunggu, Koridor 2 nos 5,265,000 10,530,000
- UGD 2 nos 5,265,000 10,530,000
- Ruang Dokter 2 nos 5,265,000 10,530,000
- Ruang Laboratorium 2 nos 5,265,000 10,530,000
- Ruang Rekam Medis 2 nos 5,265,000 10,530,000
- Farmasi + Ruang Apotik 2 nos 5,265,000 10,530,000
- Ruang CT Scan 2 nos 5,265,000 10,530,000
- Ruang Operator 2 nos 5,265,000 10,530,000
- Ruang Dokter + R. Xray 2 nos 5,265,000 10,530,000
- Ruang USG 2 nos 5,265,000 10,530,000
- Ruang Poli Saraf 2 nos 5,265,000 10,530,000
- Ruang Poli THT 2 nos 5,265,000 10,530,000
- Ruang Poli Kulit 2 nos 5,265,000 10,530,000
- Ruang Poli SP Anak 9 2 nos 5,265,000 10,530,000
- Ruang Ply Ground 2 nos 5,265,000 10,530,000
- Ruang Poli Obgyn 2 nos 5,265,000 10,530,000
- Ruang Rehab Medik 2 nos 5,265,000 10,530,000
- Ruang Poli Mata 2 nos 5,265,000 10,530,000
- Ruang Poli Gigi 2 nos 5,265,000 10,530,000
- Ruang Poli lain - lain 2 nos 5,265,000 10,530,000
- Tangga + Stepnosing 2 nos 5,265,000 10,530,000
- Supermarket 2 nos 5,265,000 10,530,000
- Toilet umum laki-laki 2 nos 936,000 1,872,000
- Toilet umum wanita 2 nos 936,000 1,872,000
- Toilet UGD 2 nos 936,000 1,872,000
- Toilet CT Scan 2 nos 936,000 1,872,000
- Toilet Xray 2 nos 936,000 1,872,000
- Toilet Poli Obgin 2 nos 936,000 1,872,000
- Janitor 2 nos 936,000 1,872,000
PT. JAVA INDOKU 88
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
VI LANTAI 3
VI.a PEKERJAAN DINDING
1 Pasangan dinding bata ringan tebal 7.5 cm (tanpa finish) "Celcon"
pemasangan dgn dry mortar lengkap berikut dgn kolom & balok praktis
3 Pengadaan dan pemasangan Kusen & pintu Alum. Ex ' Alexindo fin.
coating ( Incl. kaca ) berikut dengan aksesories dan perlengkapan
pemasangannya.
- Ramp Pasien 1 nos
2,677,500
- Pintu kaca Double Polos Tempered 12mm (Incl. sticker sandblast) 4.50 m2 595,000
- Koridor
Jendela type jungkit + Kaca Mati 6mm, L = 260cm 2 nos
- kusen Alumunium 3'', Ex'Alexindo powder coating putih 22.40 m' 154,000 3,449,600
- Frame jendela Alum. 18.80 m' 154,000 2,895,200
- kaca Polos 6mm 7.80 m2 181,500 1,415,700
PT. JAVA INDOKU 97
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
- Janitor + Gudang
Bouvenlight Alum. + Kaca Mati 6mm, Uk : 200 x 60CM
- kusen Alumunium 3'', Ex'Alexindo powder coating putih 6.40 m' 154,000 985,600
- kaca Polos 6mm 1.20 m2 181,500 217,800
- Sealant 7.00 m' 27,500 192,500
- Jasa Pasang 1.20 m2 121,000 145,200
PEKERJAAN MEP
PT. JAVA INDOKU 100
Jl. Anggrek Neli Murni Blok C No. 109 Jakarta 11480, Indonesia
NO. URAIAN PEKERJAAN VOL SAT HARGA JML HARGA
( Firman Pratikno ) (Dr.Ir.IBP Adnyana , ST, MT,IPM) ( dr. Kadek Sugiharta, SpOG (k) )
Project Manager Konsultant Direktur
PERINCIAN PEMBAYARAN :
1 PRESTASI PEKERJAAN :
JUMLAH :
PPN 10% :
JUMLAH YANG HARUS DIBAYARKAN :
TOTAL PEMBULATAN YANG HARUS DIBAYARKAN :
TERBILANG :
## DUA PULUH EMPAT MILYAR TUJUH RATUS SEBELAS JUTA ENAM RATUS
PULUH RIBU RUPIAH##
CATATAN :
Demikian Berita Pembayaran ini dibuat dan ditanda tangani dengan sesungguhnya untuk dipergunakan sebagaimana
Pemilik Proyek
Diajukan Oleh : Diperiksa Oleh :
Disetujui Oleh :
PT. JAVA INDOKU PT. PADANG GARBHA UTAMA PT. ADHI GARBA SAK
Firman Pratikno Dr. I.B Putu Adnyana, S.T., M.T. ( dr. Kadek Sugiharta SPO
Project Manager Project Management Direktur Utama
Keterangan :
BULANAN
R
n Kaja Badung Bali - Kuta Utara
Rp. 22,465,155,674.99
Rp. 22,465,155,674.99
Rp. 2,246,515,567.50
Rp. 24,711,671,242.49
Rp. 24,711,670,000.00
Pemilik Proyek
Disetujui Oleh :
PT. ADHI GARBA SAKTI
( dr. Kadek Sugiharta SPOG (K) )
Direktur Utama