MASTER SCHEDULE PELAKSANAAN FINSHING FAÇADE

PROYEK GEDUNG REKTORAT UIB


PERIODE 2023-2024

Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Keterangan


NO JENIS PEKERJAAN Bobot
04-10 11-17 18-24 25-31 01-07 08-14 15-21 22-28 29-04 05-11 12-18 19-25 26-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-02 03-09 10-16 17-29 24-30

1 PEKERJAAN LANTAI 1
a PEMASANGAN KACA CURTAIN WALL 3.60% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36%

b PEMASANGAN PLAFOND 1.41% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

c PEMASANGAN PLAFOND TOILET 0.03% 0.01% 0.01% 0.01% 0.01% 0.01%

2 PEKERJAAN LANTAI 2 6.4%

a PEMASANGAN PLAFOND 1.55% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 6.3% 6.3%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01%


6.2% 0.01%
6.2% 0.01% 0.01%
6.1%
c PEMASANGAN KUSEN INTERIOR 0.82% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10%

3 PEKERJAAN LANTAI 3
a PEMASANGAN PLAFOND 1.55% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
5.8%
b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

c PEMASANGAN KUSEN INTERIOR 1.13% 5.6% 5.6% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%

4 PEKERJAAN LANTAI 4
a PEMASANGAN PLAFOND 1.55% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
5.3% 5.3%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

c PEMASANGAN KUSEN INTERIOR 0.93% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%

5 PEKERJAAN LANTAI 5
a PEMASANGAN PLAFOND 1.55% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

c PEMASANGAN KUSEN INTERIOR 0.93% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%

6 PEKERJAAN LANTAI 6
a PEMASANGAN PLAFOND 1.33% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17%

b PEMASANGAN PLAFOND TOILET 0.05% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22%

c PEMASANGAN KUSEN INTERIOR 0.70% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%

7 PEKERJAAN LANTAI 7
a PEMASANGAN PLAFOND 1.33% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17%

3.8% 3.8%
b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

c PEMASANGAN KUSEN INTERIOR 0.70% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%

8 PEKERJAAN LANTAI 8
a PEMASANGAN PLAFOND 1.29% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

3.1%
c PEMASANGAN KUSEN INTERIOR 0.51% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%

9 PEKERJAAN LANTAI 9
a PEMASANGAN PLAFOND 1.20% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
2.8%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

2.6%
c PEMASANGAN KUSEN INTERIOR 0.47% 2.6% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%

10 PEKERJAAN LANTAI 10
a PEMASANGAN PLAFOND 1.20% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

2.1%
c PEMASANGAN KUSEN INTERIOR 0.54% 2.1% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%

11 PEKERJAAN LANTAI 11
a PEMASANGAN PLAFOND 1.20% 1.9% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
1.8%

b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
1.7%

c PEMASANGAN KUSEN INTERIOR 0.51% 0.10% 0.10% 0.10% 0.10% 0.10%

12 PEKERJAAN LANTAI 12
a PEMASANGAN PLAFOND 1.20% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%

1.3% 1.3%
1.3%
b PEMASANGAN PLAFOND TOILET 0.05% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
1.2%
1.1%
c PEMASANGAN KUSEN INTERIOR 0.27% 0.05% 0.05% 0.05% 0.05% 0.05%

13 PEKERJAAN FAÇADE
PEMASANGAN KACA CURTAIN WALL FAÇADE 46.38% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57% 3.57%

14 PEKERJAAN ALUMINIUM COMPOSITE PANEL ( ACP )


a PEKERJAAN LIST COVER ACP CURTAIN WALL 12.59% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.84% 0.7%

TAMPAK DEPAN. SAMPING DAN BELAKANG 0.6%

b PEKERJAAN LIST ACP ORNAMEN BALOK SAMPING 0.85% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%

c PEKERJAAN LIST PLANK KANOPI ROOF TOP 5.39% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.3%

15 PEKERJAAN HOLLOW KISI-KISI ALUMINIUM


a TAMPAK DEPAN 6.79% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52% 0.52%

TOTAL 100.00% 3.8% 3.8% 5.3% 5.3% 5.6% 5.6% 5.8% 6.1% 6.2% 6.2% 6.3% 6.3% 6.4% 2.8% 3.1% 2.6% 2.6% 2.1% 1.9% 2.1% 1.7% 1.8% 1.3% 1.3% 1.1% 1.3% 1.2% 0.7% 0.6% 0.3%
RENCANA
AKTUAL
DEVIASI