TIMES SCHEDULE PROYEK DOCKING REPAIR

NAMA PROYEK : BG. TAMA 2502 STATUS DOCKING : DOCKING REPAIR


PT. DUTABAHARI MENARA LINE
DOCKYARD KODE PEKERJAAN : R - 8.142 /DR KLASIFIKASI : BKI / IS
Jl. Ir.H.P.M Noor, Kuin Cerucuk Banjarmasin - : 18 Hari : 76.20/75.15 x 21.94 x 4.87 Meter
ESTIMASI WAKTU REPAIR DOCK DIMENSI
70129
Telp. +62 511 4413364 Fax. +62 511 4413365 NO. PENAWARAN : PEMILIK KAPAL : PT. HABCO PRIMATAMA

1 2 3 4 5 6 7 8 9 10 11 12 13
Bobot Progress
NO DESCRIPTION OF WORKS Lama pekerjaan Alat /Gun
%
Progress % Actual Progress % SEPTEMBER 2018
6 7 8 9 10 11 12 13 14 15 16 17 18
Docking Preparation 5.00% 60.00% 3.00%
Kapal datang & tambat 1 0.50% 0.50%
Hari
Pemasangan kupingan tarik 1 0.50% 0.50%
Hari
Proses Docking 1 Hari 2.00% 2.00%
Proses Undocking 1 Hari 2.00% 2.00%

HULL CONSTRUCTION 20.00% 93.10% 18.62%


Pelurusan Bulwark Ps
Plate 7 Hari 7.88% 1.13% 1.13% 1.13% 1.13% 1.13% 1.13% 1.13%
Plate 7 Hari 2.39% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34%
Top bulwark 7 Hari 2.83% 0.40% 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
Stanchion 7 Hari 2.01% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29% 0.29%
Top stanchion 7 Hari 0.50% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
Ganti siku bulwark haluan
Top bulwark 4 Hari 2.89% 0.72% 0.72% 0.72% 0.72%
Stanchion 4 Hari 1.26% 0.31% 0.31% 0.31% 0.31%
Top stanchion 4 Hari 0.25% 0.06% 0.06% 0.06% 0.06%

OTHER 15.00% 50.50% 7.58%


Bongkar dan Pasang Anti Karat 4 Hari 6.75% 1.69% 1.69% 1.69% 1.69%
Bongkar dan Semen Kembali Decksell Manhole 2 Hari 2.25% 1.13% 1.13%
Buka dan Tutup Kembali Decksell Manhole 2 Hari 2.25% 1.13% 1.13%
Cleaning Batu Bara Haluan 2 Hari 2.25% 1.13% 1.13%
Rewelding skeg Ps 1 Hari 1.50% 1.50%

SANDBLASTING DAN PAINTING 10 Hari 60.00% 69.11% 41.47% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00%

Total 100.00% 3.00% 3.94% 11.04% 10.45% 11.02% 11.02% 9.33% 8.23% 8.23% 7.50% 6.00% 8.25% 2.00%
6.94% 17.98% 28.43% 39.45% 50.46% 59.79% 68.02% 76.25% 83.75% 89.75% 98.00% 100.00%

Demikian yang dapat kami sampaikan, atas perhatian dan kerjasamannya saya ucapkan terima kasih.

Direncanakan oleh, Diketahui Disetujui


Keterangan :
= Estimasi
= Re schedule
= Actual
Huruf warna hijau pekerjaan tambahan
Masudi Guszazif Titah P. Hadi Soetrisno = Tidak ada kerja
Pimpro Manager Produksi General Manager = Selesai