BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Tuesday, September 15, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS

Lower DECk PILE CAP STATUS


Pil e CAP works in progress.

total completed to date: 17 nos.


total Number OF Pile Caps@ Lower Deck 27 nos. 62.96%
Upper DECk PILE CAP STATUS
Pil e CAP works in progress.

total completed to date: 29 nos.

total Number OF Pile Caps 30 nos. 96.67%


Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 82.00%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 42.10%
DETENTION DRAIN CAST TO DATE 70.22%
INTERNAL DRAINAGE UPDATE 34.30%

SITE VIEW
Architectural

INSTALL REINFORCING BARS @LIFT PIT AREA


work
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS

10 Pile caps more to complete at lower Deck Level , GREEN SHADES


@Upper Deck Level PILE CAP @ 96.67% Complete YELLOW CLOUDS
AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT
REINFORCING BARS INSTALLATION IN PROGRESS

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor 1 Generator 2

Site Supervisor Safety Supervisor Excavator CL


1 1 1
@ DETENTION DRAIN:
Safety officer LOWER DECK DEEP BEAM
REBAR INSTALL
UPDATED AT 70% COMPLETE
08:30 17:30 1 4 DETENTION DRAIN@ IC WORKS #4 TO
IC#3: INSTALL 150MM
DIAMETER DUCTILE IRON WALL WB4a WB4 WB5, AND
Site engineer
1
PILE CAP REBAR AT LIFT
6
BAR BENDER MACHINE @1 REMAINING PIPE GH11b GH11c REINFORCING
PIT AREA BARS ALREADY CHECKED TO
RTO BIG BREAKER
AREA OF
CAST AT 1 PM TOMORROW
1 ESS 2
DETENTION
1
DRAIN
TO COMPLETE
FORMWORK/ WALL ON 1 TONNE ROLLER- COMPACTOR @30%
TOP OF CAPPING BEAM
REMARKS Administrator 1 2 1

UPPER /LOWER AIR RECEIVER


DECKSLADROP PANEL/
Coordinator 1 6 1
WALL BEAM REBAR
INSTALL
TC INSTALLED
ECO 1 1

Weather G Worker 10

TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR IC WORKS IC#4
1 5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION WALL WB4a WB4 WB5, AND GH11b GH11c REINFORCING BARS ALREADY
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE CHECKED TO CAST AT 1 PM ON 16 SEPTEMBER 2020

Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 55.56% 13 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT FOUNDATION AREA casting RC SUMPS AND PIPE HAUNCHING
done remains @34.30% COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 34.30 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
34.30 % COMPLETE

GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, INSTALLING BOTTOM REINFORCING BARS AT
GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL
REBARS INSTALLATION IN
PROGRESS AT AREAS OF UPPER
DECK SLAB GRIDLINE 12 TO 7 D TO
G
@ELECTRICAL
SUBSTATION BELOW
TRANSFORMER ROOM :
INSTALLING DEEP BEAMS

UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION IN PROGRESS. GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION

INSTALLING BOTTOM REINFORCING BARS AT GRIDLINE 12 TO 7 / G TO D IN PROGRESS.

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE

REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS, PARTIAL BOTTOM SLAB REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE
REBARS ARRIVED LCT TO QUICKLY SETTLE RWDP ISSUES,WALL WB4a WB4 WB5, AND GH11b GH11c REINFORCING BARS
ALREADY CHECKED TO CAST AT 1 PM ON 16 SEPTEMBER 2020

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
6 REBAR WORKERS @ UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT FOUNDATION 4 + 4 workers INSTALLED 10 DROP PANELS WALL WB4a WB4 WB5,
BOTTOM REINFORCING BARS AND 3 MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 6 REBAR WORKERS @
AT PARAPET WALL FORMWORKS/ CAST 2 WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2 WORKERS SAFETY AND GH11b GH11c
ROWS OF GROUND BEAMS, PARTIAL
& HOUSEKEEPING, SHIFTING HOISTING MARTERIALS TO UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES REINFORCING BARS UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT
BOTTOM SLAB REBARS ARRIVED LCT
ALREADY CHECKED TO
TO QUICKLY SETTLE RWDP ISSUES FOUNDATION 4 + 4 workers AT PARAPET WALL FORMWORKS/ CAST 2
CAST AT 1 PM ON 16
SEPTEMBER 2020 WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2

WORKERS SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS TO


@ELECTRICAL
SUBSTATION BELOW UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES

TRANSFORMER ROOM :
INSTALLING DEEP BEAMS,
upstand beams

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed