Location: Cabuyao, Laguna Owner: Mr. Webster Manuel
SUMMARY OF PROJECT COST
DESCRIPTION PERCENTAGE TOTAL AMOUNT
1 GENERAL REQUIREMENTS 7.35% 481,623.74
2 STRUCTURAL / CIVIL WORKS 37.53% 2,458,688.05
A EARTHWORKS 46,643.65 B CONCRETE WORKS 333,902.74 C FORMWORKS & FALSEWORKS 575,011.58 D REINFORCEMENT BARS (STRUCTURAL) 707,327.92 E MASONRY WORKS (excluding Perimeter Fence) 612,354.09 F ROOFING FRAMING and ROOFING WORKS 183,448.07
3 ARCHITECTURAL WORKS 45.59% 2,986,704.02
A BOARD-UP WORKS 334,610.73 B PAINTING WORKS 385,721.09 C TILING WORKS 416,934.11 D FABRICATED MATERIALS 492,114.50 E DOORS AND WINDOWS 749,643.59 F CABINETRIES 607,680.00
4 ELECTRICAL & PLUMBING WORKS 3.09% 202,536.89
A ELECTRICAL WORKS - B PLUMBING WORKS 202,536.89
5 PERIMETER FENCE & MAIN GATE WORKS 6.44% 422,040.45
TOTAL PERCENTAGE 100.00% TOTAL PROJECT COST, Php ₱ 6,551,593.15
Prepared by: ________________________
Jan Lawrence Alberto, RCE. RMP. Prequal Construction, Quantity Engineer
Approved by: ________________________
Kim Prince Payumo, RCE Prequal Construction, General Manager