BILL OF QUANTITY

PROJECT : VILLA SANGGAH


UNIT : BLOCK A
WORK : STRUCTURE
LOCATION : Jl. Batu Belig Gg. Daksina No.4, Kerobokan Kelod, Kec. Kuta Utara, Kabupaten Badung, Bali 80361
OWNER : Mr.ANTHONI ELAM

RECAPITULATION BILL OF QUANTITY


JOB DESCRIPTION PRICE ( Rp ) TOTAL PRICE ( Rp )
NO MATERIAL + MATERIAL + NOTE
INDONESIA ENGLISH MATERIAL WAGES MATERIAL WAGES
WAGES WAGES

I PEKERJAAN STRUKTUR STRUCTURE WORK


A PEKERJAAN BOWPLANK BOWPLANK WORK - 6.187.500 6.187.500
B PEKERJAAN TANAH LAND WORK 26.464.321 30.819.879 57.284.200
C PEKERJAAN PONDASI FOUNDATION WORK 133.253.248 58.275.803 191.529.051
D PEKERJAAN STRUKTUR BETON DAN BAJA CONCRETE AND STEEL STRUCTURE WORK 866.991.564 382.997.187 1.249.988.751
D-1 PEKERJAAN BETON LANTAI 1 1St FLOOR CONCRETE WORK 184.248.750 60.430.569 244.679.319
D-2 PEKERJAAN BETON LANTAI 2 2Nd FLOOR CONCRETE WORK 201.223.464 53.426.026 254.649.490
D-3 PEKERJAAN STRUKTUR BAJA STEEL STRUCTURE WORK 381.308.350 227.390.592 608.698.942
D-4 PEKERJAAN STRUKTUR BAJA ATAP ROOF STEEL STRUCTURE WORK 100.211.000 41.750.000 141.961.000
E PEKERJAAN DINDING WALLS WORK 111.704.297 54.345.998 166.050.295
E-1 PEKERJAAN DINDING LANTAI 1 1St FLOOR WALL WORK 72.240.000 35.841.038 108.081.038
E-2 PEKERJAAN DINDING LANTAI 2 2Nd FLOOR WALL WORK 39.464.297 18.504.960 57.969.257
F INSTALASI PLUMBING PLUMBING INSTALLATION 55.093.660 23.599.433 78.693.093
G PEKERJAAN BIOSEPTICTANK BIOSEPTICTANK WORK 6.741.556 2.405.588 9.147.143
H PERESAPAN SEPTIC TANK, DIA.100 D.200 CM SEPTIC TANK IMPRECIATION, DIA.100 D.200 CM 2.205.000 1.214.707 3.419.707

SUB TOTAL PRICE 1.202.453.646 553.658.596 1.756.112.241


CONTRACTOR FEE 10% 120.245.365 55.365.860 175.611.224
GRAND TOTAL 1.322.699.010 609.024.455 1.931.723.466
ROUNDED 1.322.690.000 609.020.000 1.931.720.000

Catatan / Note:
1 Tidak termasuk beban pajak dan pungutan retribusi desa // Does not include the burden of village taxes and levies
2 Item pekerjaan yang belum masuk dalam Boq di hitung sebagai pekerjaan tambahan // Work items that have not been included in the Boq are counted as additional work

Denpasar, 15 Agustus 2023


Leonardus Indra Cahyana

Villa Sanggah_Unit A
Boq_Struture work 15 Agustus 2023 1
BILL OF QUANTITY
JOB DESCRIPTION UNIT PRICE ( Rp ) PRICE ( Rp )
NO UNIT QTY. MATERIAL + MATERIAL + NOTE
INDONESIA ENGLISH MATERIAL WAGES MATERIAL WAGES
WAGES WAGES
a b c d e f g h=( f + g ) i=( e x f ) j=( e x g ) k=( i + j ) l

I PEKERJAAN STRUKTUR STRUCTURE WORK


A PEKERJAAN BOWPLANK BOWPLANK WORK
Pekerjaan bowplank , material kayu menggunakan bekas Bowplank work, wood materials using demolition scraps from
1 bongkaran dari pemilik, Untuk material: paku, benang, cat the owner, For materials: nails, threads, pilox paint etc. from M¹ 75,00 - 82.500 82.500 - 6.187.500 6.187.500
pilox dll dari kontraktor the contractor
TOTAL A - 6.187.500 6.187.500

B PEKERJAAN TANAH LAND WORK


1 Pekerjaan galian tanah menerus Excavation work for continues foundation M³ 43,56 168.000 168.000 - 7.318.080 7.318.080
2 Pekerjaan galian tanah setempat Local excavation work M³ 48,32 168.000 168.000 - 8.116.970 8.116.970
3 Pekerjaan urugan kembali Work of fill back the land M³ 22,97 88.000 88.000 - 2.021.257 2.021.257
4 Pekerjaan urugan pasir Sandfill work - - - -
- Urugan pasir di bawah pondasi, t=10 cm - Fill sand under the foundation, t=10 cm M³ 17,42 264.600 120.000 384.600 4.610.390 2.090.880 6.701.270
- Urugan pasir dibawah lantai kerja - footplate ,t=5cm - Sand filling under work floor - footplate, t=5cm M³ 1,46 264.600 120.000 384.600 387.401 175.692 563.093
- Urugan pasir, dibawah lantai kerja slab floor - Sand fill, under the work floor slab floor M³ 10,28 264.600 120.000 384.600 2.718.765 1.233.000 3.951.765
5 Pekerjaan urugan limestone, t=20 cm Limestone filling work, t=20 cm M³ 61,65 206.100 120.000 326.100 12.706.065 7.398.000 20.104.065
6 Pekerjaan plastik dasar beton slab floor Slab floor concrete base plastic work M² 205,50 29.400 12.000 41.400 6.041.700 2.466.000 8.507.700
TOTAL B 26.464.321 30.819.879 57.284.200
C PEKERJAAN PONDASI FOUNDATION WORK
1 Pekerjaan pondasi batu kali River stone foundation work
- Pekerjaan anstampeng batu kali, t= 20 cm - Install loose river stone, t= 20 cm M³ 29,13 471.700 228.000 699.700 13.739.678 6.641.184 20.380.862
- Pekerjaaan pondasi batu kali, 30/70 x 100 cm - Work of stone foundation, 30/70 x 100 cm M³ 63,72 892.300 420.000 1.312.300 56.855.125 26.761.350 83.616.475
2 Pekerjaan beton lantai kerja, t=5cm Work floor concrete work, t=5cm M³ 1,46 996.700 378.000 1.374.700 1.459.268 553.430 2.012.698
3 Pekerjaan pondasi footplate Footplate foundation work - - - -
- Beton pondasi footplate - Concrete footplate foundation M³ 7,32 4.977.000 2.143.000 7.120.000 36.434.129 15.687.832 52.121.960
- Beton kolom pedestal, 30x30 cm - Pedestal column concrete, 30x30 cm M³ 4,16 5.956.000 2.076.000 8.032.000 24.765.048 8.632.008 33.397.056
TOTAL C 133.253.248 58.275.803 191.529.051

D PEKERJAAN STRUKTUR BETON DAN BAJA CONCRETE AND STEEL STRUCTURE WORK
D-1 PEKERJAAN BETON LANTAI 1 1St FLOOR CONCRETE WORK
1 Pekerjaan beton sloof Sloof concrete work
- Beton sloof, S1: 20 x 30 cm - Sloof concrete, S1 20 x 30 cm M³ 12,01 5.612.000 2.415.000 8.027.000 67.411.344 29.008.980 96.420.324
- Beton sloof, S2: 20 x 20 cm - Sloof concrete, S1 20 x 20 cm M³ 0,79 5.612.000 2.415.000 8.027.000 4.444.704 1.912.680 6.357.384
- Beton sloof, S3: 15 x 30 cm - Sloof concrete, S2 15 x 30 cm M³ 0,71 5.027.000 2.038.000 7.065.000 3.566.657 1.445.961 5.012.618
2 Pekerjaan beton lantai indoor, ground floor t= 10 cm Indoor floor concrete work, ground floor t = 10 cm thick - - -
- Tv room, bathroom, kitchen, staging, laundry - Tv room, bathroom, kitchen, staging, laundry, toilet M³ 7,43 3.038.000 785.000 3.823.000 22.557.150 5.828.625 28.385.775
- Stair area - Stair area M³ 1,76 3.038.000 785.000 3.823.000 5.346.880 1.381.600 6.728.480
- Garage, storage - Garage, storage M³ 7,12 3.038.000 785.000 3.823.000 21.638.155 5.591.163 27.229.318
3 Pekerjaan beton lantai outdoor, ground floor t= 10 cm Outdoor floor concrete work, ground floor t = 10 cm thick - - -
- Teracce - Teracce M³ 4,23 3.038.000 785.000 3.823.000 12.849.221 3.320.158 16.169.379
- Teracce staging area - Teracce staging area M³ 1,93 3.038.000 785.000 3.823.000 5.848.150 1.511.125 7.359.275
4 Pekerjaan beton tangga, t= 12 cm Ladder concrete work, t= 12 cm M³ 2,65 6.472.000 1.687.000 8.159.000 17.179.277 4.477.973 21.657.250
5 Pekerjaan beton kanopi Canopy concrete work M³ 1,30 8.904.000 1.907.000 10.811.000 11.576.981 2.479.481 14.056.462
6 Pekerjaan Beton komposit struktur baja expose Exposed steel structure composite concrete work - - -
- Beton komposit kolom HB 200 = 1pcs - Composite concrete column HB 200= 1pcs M³ 0,38 4.391.000 1.289.000 5.680.000 1.651.894 484.922 2.136.816
- Beton komposit kolom IWF 250= 4pcs - Composite concrete column IWF 250= 4pcs M³ 1,37 4.391.000 1.289.000 5.680.000 6.006.888 1.763.352 7.770.240
- Beton komposit Lisplang kastela IWF 200= 9,50 M¹ - Composite concrete kastela beam IWF 200= 9,50 M¹ M³ 0,95 4.391.000 1.289.000 5.680.000 4.171.450 1.224.550 5.396.000
TOTAL D-1 184.248.750 60.430.569 244.679.319
D-2 PEKERJAAN BETON LANTAI 2 2Nd FLOOR CONCRETE WORK
1 Pekerjaan beton lantai, t=12 cm Floor concrete work, t=12 cm

Villa Sanggah_Unit A
Boq_Struture work 15 Agustus 2023 2
BILL OF QUANTITY
JOB DESCRIPTION UNIT PRICE ( Rp ) PRICE ( Rp )
NO UNIT QTY. MATERIAL + MATERIAL + NOTE
INDONESIA ENGLISH MATERIAL WAGES MATERIAL WAGES
WAGES WAGES
a b c d e f g h=( f + g ) i=( e x f ) j=( e x g ) k=( i + j ) l

- Lantai indoor ( Bedroom, bathroom, Wardrobe ) - Indoor floor ( Bedroom, bathroom, Wardrobe ) M³ 9,84 6.472.000 1.687.000 8.159.000 63.662.734 16.594.412 80.257.146
- Lantai outdoor ( Teras, Garden ) - Outdoor floor(Teracce, garden ) M³ 7,27 6.472.000 1.687.000 8.159.000 47.072.150 12.269.888 59.342.039
- Atap area garase - Roof garage area M³ 9,40 6.472.000 1.687.000 8.159.000 60.852.074 15.861.781 76.713.855
2 Pekerjaan Beton komposit struktur baja expose Exposed steel structure composite concrete work - - -
- Beton komposit kolom HB 150= 5pcs - Composite concrete column HB 150= 5pcs M³ 0,76 4.391.000 1.289.000 5.680.000 3.337.160 979.640 4.316.800
- Beton komposit Balok IWF 200= 33,60 M¹ - Composite concrete beam IWF 200= 33.60 M¹ M³ 1,68 4.391.000 1.289.000 5.680.000 7.376.880 2.165.520 9.542.400
- Beton komposit Balok IWF 150= 8,00 M¹ - Composite concrete beam IWF 150= 8,00 M¹ M³ 0,40 4.391.000 1.289.000 5.680.000 1.756.400 515.600 2.272.000
- Beton komposit Balok IWF 100= 24,35 M¹ - Composite concrete beam IWF 100= 24,35 M¹ M³ 0,55 4.391.000 1.289.000 5.680.000 2.405.719 706.211 3.111.930
- Beton komposit Lisplang kastela IWF 150= 37,35 M¹ - Composite concrete kastela beam IWF 150= 37,35 M¹ M³ 3,36 4.391.000 1.289.000 5.680.000 14.760.347 4.332.974 19.093.320
TOTAL D-2 201.223.464 53.426.026 254.649.490
D-3 PEKERJAAN STRUKTUR BAJA STEEL STRUCTURE WORK
1 Material utama baja The main material is steel
- Kolom HB 200, HB 150, IWF 250, IWF 200, IWF 150 - Column HB 200, HB 150, IWF 250, IWF 200, IWF 150 Unit 1,00 91.820.925 91.820.925 91.820.925 - 91.820.925
- Balok lantai IWF 250, IWF 200, IWF 150 - Floor beams IWF 250, IWF 200, IWF 150 Unit 1,00 180.780.863 180.780.863 180.780.863 - 180.780.863
- Balok ring IWF 200, IWF 150, IWF 100 - Ring beams IWF 200, IWF 150, IWF 100 Unit 1,00 39.071.813 39.071.813 39.071.813 - 39.071.813
- Balok kanopi IWF 100 - Canopy beam, IWF 100 Unit 1,00 6.945.750 6.945.750 6.945.750 - 6.945.750
2 Material penyambung ( Plat eser, mur, baut, ring) Connecting material (Eser plate, nuts, bolts, washers) Unit 1,00 32.094.700 32.094.700 32.094.700 - 32.094.700
3 Material pendukung ( kawat las, resibon, amplas ) Supporting materials, welding wire, resibon, sandpaper Unit 1,00 11.129.800 11.129.800 11.129.800 - 11.129.800
4 Material cat ( zingkromate, tinner, kuas, Rool cat Dll) Paint material (zingrmate, thinner, brush, paint roller, etc.) Unit 1,00 19.464.500 19.464.500 19.464.500 - 19.464.500
5 Biaya tenaga kerja + alat kerja Labour cost+ work tools Kg 17.491,58 13.000 13.000 - 227.390.592 227.390.592
TOTAL D-3 381.308.350 227.390.592 608.698.942

D-4 PEKERJAAN STRUKTUR BAJA ATAP ROOF STEEL STRUCTURE WORK


Material utama baja: Balok struktur atap, besi hollow 5x10 The main material is steel: roof structural beams, 5x10 cm
1 Unit 1,00 78.782.000 78.782.000 78.782.000 - 78.782.000
cm, Balok gording, besi hollow 5x10 cm hollow iron, curtain rods, 5x10 cm hollow iron
Material penyambung ( Plat eser, besi siku, mur, baut, Connecting material (Eser plate, angle iron, nuts, bolts,
2 Unit 1,00 10.584.000 10.584.000 10.584.000 - 10.584.000
ring) washers)
3 Material pendukung ( kawat las, resibon, amplas ) Supporting materials, welding wire, resibon, sandpaper Unit 1,00 1.869.000 1.869.000 1.869.000 - 1.869.000
4 Material cat ( zingkromate, tinner, kuas, Rool cat Dll) Paint material (zingrmate, thinner, brush, paint roller, etc.) Unit 1,00 8.976.000 8.976.000 8.976.000 - 8.976.000
5 Biaya tenaga kerja + alat kerja Labour cost+ work tools M² 167,00 250.000 250.000 - 41.750.000 41.750.000
TOTAL D-4 100.211.000 41.750.000 141.961.000
TOTAL D 866.991.564 382.997.187 1.249.988.751

E PEKERJAAN DINDING WALLS WORK


Catatan: estimasi dalam pekerjaan dinding batako untuk
Note: estimation in brick wall work to support structural work
mendukung pekerjaan struktur
E-1 PEKERJAAN DINDING LANTAI 1 1St FLOOR WALL WORK
1 Pekerjaan dinding batako Batako wall work
- Pekerjaan dinding batako single - Single batako wall work M² 259,22 125.600 72.000 197.600 32.557.404 18.663.480 51.220.884
- Pekerjaan dinding batako Double - Double batako wall work M² 35,38 251.200 144.000 395.200 8.886.451 5.094.144 13.980.595
- Pekerjaan dinding batako penebalan - Thickening batako wall work M³ 5,81 1.256.000 720.000 1.976.000 7.294.848 4.181.760 11.476.608
2 Pekerjaan beton kolom praktis, 15x15 cm Practical column concrete work, 15x15 cm M³ 2,82 5.811.000 2.088.000 7.899.000 16.380.047 5.885.654 22.265.701
3 Pekerjaan ring balok latiu, 10x15 cm Latiu beam ring work, 10x15 cm M³ 0,75 6.330.000 1.792.000 8.122.000 4.747.500 1.344.000 6.091.500
4 Pekerjaan ring balok, 10x15 cm Beam ring work, 10x15 cm M³ 0,38 6.330.000 1.792.000 8.122.000 2.373.750 672.000 3.045.750
TOTAL E-1 72.240.000 35.841.038 108.081.038

E-2 PEKERJAAN DINDING LANTAI 2 2Nd FLOOR WALL WORK


1 Pekerjaan dinding batako Batako wall work
- Pekerjaan dinding batako single - Single batako wall work M² 123,20 125.600 72.000 197.600 15.473.920 8.870.400 24.344.320
- Pekerjaan dinding batako Double - Double batako wall work M² 12,87 251.200 144.000 395.200 3.232.944 1.853.280 5.086.224
- Pekerjaan dinding batako border taman - Garden border brick wall work M² 28,64 125.600 72.000 197.600 3.597.686 2.062.368 5.660.054
2 Pekerjaan beton kolom praktis, 15x15 cm Practical column concrete work, 15x15 cm M³ 1,94 5.811.000 2.088.000 7.899.000 11.296.584 4.059.072 15.355.656

Villa Sanggah_Unit A
Boq_Struture work 15 Agustus 2023 3
BILL OF QUANTITY
JOB DESCRIPTION UNIT PRICE ( Rp ) PRICE ( Rp )
NO UNIT QTY. MATERIAL + MATERIAL + NOTE
INDONESIA ENGLISH MATERIAL WAGES MATERIAL WAGES
WAGES WAGES
a b c d e f g h=( f + g ) i=( e x f ) j=( e x g ) k=( i + j ) l

3 Pekerjaan ring balok latiu, 10x15 cm Latiu beam ring work, 10x15 cm M³ 0,30 6.330.000 1.792.000 8.122.000 1.899.000 537.600 2.436.600
4 Pekerjaan ring balok, 10x15 cm Beam ring work, 10x15 cm M³ 0,63 6.330.000 1.792.000 8.122.000 3.964.163 1.122.240 5.086.403
TOTAL E-2 39.464.297 18.504.960 57.969.257
TOTAL E 111.704.297 54.345.998 166.050.295

F INSTALASI PLUMBING PLUMBING INSTALLATION


Catatan: estimasi dalam pekerjaan pipa ini untuk Note: the estimate for this pipe work is to support structural
mendukung pekerjaan struktur, untuk pekerjaan instalasi work, for clean water and hot water pipe installation work not
pipa air bersih dan air panas belum masuk dalam boq ini yet included in this boq
Pekerjaan drainase air hujan dengan lebar 60 cm, depan Rainwater drainage work with a width of 60 cm, in front of the
1 garase dengan setruktur beton plat dan tutup plat beton, garage with a concrete plate structure and a concrete slab
panjang tahap 1=11,80 cm cover, the length of stage 1 = 11.80 cm
- Pekerjaan galian tanah menerus dan urugan kembali - Continuous excavation work and backfill M³ 5,91 168.000 168.000 - 992.191 992.191
- Pekerjaan dinding beton t:10 cm - Concrete wall work t: 10 cm M³ 2,36 6.472.000 1.687.000 8.159.000 15.273.920 3.981.320 19.255.240
- Pekerjaan tutup beton dengan lubang, tebal 8 cm - Concrete cover work with holes, 8 cm thick M³ 0,57 6.472.000 1.687.000 8.159.000 3.665.741 955.517 4.621.258
- Pekerjaan plesteran sisi dalam dan toping - Plastering work on the inside and topping M² 21,24 52.500 66.000 118.500 1.115.100 1.401.840 2.516.940
- - -
2 Pekerjaan drainase air hujan, buis beton dia.40 cm Rainwater drainage work, concrete foam dia.40 cm - - -
- Pekerjaan galian tanah menerus, 36,72 Meter - Continuous excavation work, 36.72 meters M³ 18,18 168.000 168.000 - 3.053.635 3.053.635
- Pekerjaan urugan kembali - Work of fill back the land M³ 4,54 88.000 88.000 - 399.881 399.881
- Pekerjaan urugan pasir di bawah buis beton, t=10 cm - Sand filling work under concrete block, t=10 cm M³ 2,02 264.600 120.000 384.600 534.386 242.352 776.738
- Pekerjaan pasang buis beton Ø 40 cm - Concrete bus installation work Ø 40 cm M¹ 36,72 405.300 88.500 493.800 14.882.616 3.249.720 18.132.336
- - -
Pekerjaan instalasi pipa air kotor dan air sabun Installation of dirty water and soapy water pipes using
3 - - -
menggunakan pipa wavin/ setara wavin/equivalent pipes
- Instalasi pipa ventilasi PVC AW dia 1 inch - Installing the PVC AW ventilation pipe dia 1 inch M¹ 5,00 20.200 33.000 53.200 101.000 165.000 266.000
- Instalasi pipa drain wastafel PVC AW dia. 1,5 inch - Installing a PVC AW sink drain pipe dia. 1.5 inch M¹ 7,20 31.700 33.000 64.700 228.240 237.600 465.840
- Instalasi pipa air sabun PVC AW dia. 3 inch - Installation of AW dia PVC soap water pipes. 3 inches M¹ 52,60 77.700 44.000 121.700 4.087.020 2.314.400 6.401.420
- Instalasi pipa air kotor PVC AW dia. 4 inch - Installation of AW dia PVC dirty water pipes. 4 inches M¹ 29,46 125.300 49.500 174.800 3.691.338 1.458.270 5.149.608
- Fitting (Elbow, sock, Tee Dll) - Fittings (Elbow, sock, Tee Etc.) Ls 1,00 1.216.140 417.527 1.633.667 1.216.140 417.527 1.633.667
- - -
Pekerjaan instalasi pipa air hujan menggunakan pipa
4 Rainwater pipe installation work using wavin/equivalent pipes - - - -
wavin/ setara
- Instalasi pipa horisontal lantai 1, PVC AW dia. 4 inch - 1st floor horizontal pipe installation, PVC AW dia. 4 inches M¹ 35,93 125.300 49.500 174.800 4.501.778 1.778.436 6.280.214
- Instalasi pipa vertikal lantai 1, PVC AW dia. 3 inch - 1st floor vertical pipe installation, PVC AW dia. 3 inches M¹ 33,60 77.700 44.000 121.700 2.610.720 1.478.400 4.089.120
- Instalasi pipa horisontal lantai 2, PVC AW dia. 3 inch - 2nd floor horizontal pipe installation, PVC AW dia. 3 inches M¹ 23,71 77.700 44.000 121.700 1.842.422 1.043.328 2.885.750
- Fitting (Elbow, sock Dll) - Fitting (Elbow, sock etc) Ls 1,00 1.343.238 430.016 1.773.255 1.343.238 430.016 1.773.255
TOTAL F 55.093.660 23.599.433 78.693.093

G PEKERJAAN BIOSEPTICTANK BIOSEPTICTANK WORK


1 Pekerjaan galian tanah setempat Excavation work M³ 3,96 168.000 168.000 - 665.973 665.973
2 Pekerjaan urugan kembali Work of fill back the land M³ 0,99 88.000 88.000 - 87.211 87.211
3 Pekerjaan urugan pasir lantai kerja,t=5cm Sand fill for working floor, t=5cm thick M³ 0,12 264.600 120.000 384.600 31.785 14.415 46.200
4 Beton lantai kerja t=5 cm Concrete work floor t=5 cm thick M³ 0,12 996.700 378.000 1.374.700 119.729 45.407 165.136
5 Pekerjaan dinding batako Batako wall work M² 8,99 125.600 72.000 197.600 1.129.144 647.280 1.776.424
6 Pekerjaan beton plat tutup, t= 10 cm Top Slab, t= 10 cm M³ 0,24 6.472.000 1.687.000 8.159.000 1.554.898 405.302 1.960.200
7 Bio Septictank kapasitas 1000 liter Bio Septictank Capasity 1000 liter Unit 1,00 3.906.000 540.000 4.446.000 3.906.000 540.000 4.446.000
TOTAL G 6.741.556 2.405.588 9.147.143

H PERESAPAN SEPTIC TANK, DIA.100 D.200 CM SEPTIC TANK IMPRECIATION, DIA.100 D.200 CM
1 Pekerjaan galian tanah setempat Excavation work M³ 3,31 168.000 168.000 - 556.416 556.416

Villa Sanggah_Unit A
Boq_Struture work 15 Agustus 2023 4
BILL OF QUANTITY
JOB DESCRIPTION UNIT PRICE ( Rp ) PRICE ( Rp )
NO UNIT QTY. MATERIAL + MATERIAL + NOTE
INDONESIA ENGLISH MATERIAL WAGES MATERIAL WAGES
WAGES WAGES
a b c d e f g h=( f + g ) i=( e x f ) j=( e x g ) k=( i + j ) l

2 Pekerjaan urugan kembali Work of fill back the land M³ 0,66 - 88.000 88.000 - 58.291 58.291
3 Pekerjaan buis beton + tutup Concrete buis work + closing Unit 1,00 2.205.000 600.000 2.805.000 2.205.000 600.000 2.805.000
TOTAL H 2.205.000 1.214.707 3.419.707

TOTAL 1.202.453.646 559.846.096 1.762.299.741