Professional Documents
Culture Documents
Contract Location : San Fernando Airport, Mayor Lorenzo L. Dacanay Avenue, Canaoay, 2500 City of San Fernando, La Union, Philippines
Contractor : JJJ-A Construction and Supplies
Contract Cost @ Completion : PHP 6,793,406.94
II PIPE LAYING WORKS 55.04 3,744,134.10 62.00 2,321,363.14 34.17 38.00 1,417,478.96 20.87 100.00 3,738,842.10 55.03
III CONCRETE WORKS 2.97 201,718.20 58.00 116,996.56 1.72 42.00 84,721.64 1.25 100.00 201,718.20 2.97
IV REBARS / STEEL WORKS 26.19 1,778,923.44 100.00 1,778,923.44 26.19 100.00 1,778,923.44 26.19
V FORMWORKS AND SCAFFOLDS 2.91 197,862.00 100.00 197,862.00 2.91 100.00 197,862.00 2.91
TOTAL 100.01 PHP 6,798,698.94 PHP 5,133,515.32 75.57 PHP 1,659,891.62 24.44 PHP 6,793,406.94 100.00