DAILY WORK REPORT 9/2/2022


Project P4-1F MODIFICATION OF RAILINGS AT BREAK AREA NEAR MLCC BATCH
Location P4 - 1F Actual Completion Rate 73.33%
Contractor DUAL AIR INC. Required Completion Rate 50.00%
Target Date 9/10/2022 Category B
PICTURES / PHOTOS

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

INSTALLATION WORKS

FABRICATION WORKS (RAILINGS) 10.50 7.70 2.80 SQ M 73.33%

73.33%
146.67%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 2
CIVIL Welder 1
Helper 2
Pipe Fitter 0
TOTAL 5

Melvin Sarcia

Engr. Raymart Dela Cruz


Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 9/8/2022


Project P4-1F MODIFICATION OF RAILINGS AT BREAK AREA NEAR MLCC BATCH
Location P4 - 1F Actual Completion Rate 100.00%
Contractor DUAL AIR INC. Required Completion Rate 100.00%
Target Date 9/10/2022 Category B
PICTURES / PHOTOS

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

INSTALLATION WORKS

FABRICATION WORKS (RAILINGS) 10.50 10.50 0.00 SQ M 100.00%

100.00%
200.00%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 2
CIVIL Welder 1
Helper 2
Pipe Fitter 0
TOTAL 5

Melvin Sarcia

Engr. Raymart Dela Cruz


Project In Charge