DAILY WORK REPORT 7/12/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 57.14%
Contractor DUAL AIR INC. Required Completion Rate 50.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 SQ M 0.00%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
57.14%
457.14%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/22/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 58.82%
Contractor DUAL AIR INC. Required Completion Rate 55.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 3.01 SQ M 11.73%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
58.82%
470.54%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/23/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 61.04%
Contractor DUAL AIR INC. Required Completion Rate 55.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 7.01 SQ M 27.31%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
61.04%
488.35%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/24/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 64.41%
Contractor DUAL AIR INC. Required Completion Rate 60.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 13.06 SQ M 50.88%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
64.41%
515.29%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/27/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 67.79%
Contractor DUAL AIR INC. Required Completion Rate 65.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 CU M 0.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
67.79%
542.36%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 6/28/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 82.08%
Contractor DUAL AIR INC. Required Completion Rate 80.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 SQ M 0.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
82.08%
656.64%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/2/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 85.36%
Contractor DUAL AIR INC. Required Completion Rate 65.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 3.29 SQ M 22.93%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
85.36%
682.84%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/5/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 88.62%
Contractor DUAL AIR INC. Required Completion Rate 65.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 6.57 SQ M 45.78%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
88.62%
708.97%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/6/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 92.18%
Contractor DUAL AIR INC. Required Completion Rate 80.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 10.15 SQ M 70.73%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
92.18%
737.48%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/6/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 96.37%
Contractor DUAL AIR INC. Required Completion Rate 85.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 19.14 SQ M 74.56%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 14.35 SQ M 100.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
96.37%
770.93%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/6/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 93.26%
Contractor DUAL AIR INC. Required Completion Rate 90.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 21.07 SQ M 82.08%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 10.15 SQ M 70.73%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
93.26%
746.07%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 7/15/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 100.00%
Contractor DUAL AIR INC. Required Completion Rate 83.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

DEMOLITION WORKS

CONCRETE CHIPPING 25.67 25.67 SQ M 100.00%


CONCRETE POURING
CONCRETE PAD 3.72 3.72 CU M 100.00%
EPOXY PAINT 14.35 14.35 SQ M 100.00%

SUPPLIED MATERIALS
12 MM CORRUGATED REBAR 6M 49.00 49.00 EA 100.00%
WHITE SAND 4.32 4.32 EA 100.00%
GRAVEL3/4'' 4.00 4.00 EA 100.00%
PORTLAND CEMENT 46.00 46.00 EA 100.00%
100.00%
800.00%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 0
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 2

Rose Andrei Francisco

ARVY SILANG
Project In Charge
Room 204 Cabrera Building II, No. 64 Timog Avenue Diliman, Quezon City 1103
Tel. No.(632) 931-4533; Fax No.(632) 412-4401
E-mail: dualair_inc@yahoo.com / dualairinc.ph@gmail.com

DAILY WORK REPORT 8/22/2022


Project P4 - BASEMENT CONSTRUCTIION OF CONCRETE PAD FOR HPDA COMPRESSOR
Location P4 - BASEMENT Actual Completion Rate 100.00%
Contractor DUAL AIR INC. Required Completion Rate 100.00%
Target Date 6/30/2022 Category B
PICTURES / PHOTOS

BEFORE

AFTER

SCOPE OF WORK SPECIFICATION TOTAL COMPLETED REMAINING UNIT COMPLETION

MASONRY WORKS
CONCRETE POURING 1.92 1.92 0.00 CU M 100.00%
EPOXY PAINT 12.01 12.01 0.00 SQ M 100.00%

100.00%
300.00%
PART POSITION MANPOWER PROJECT REMARKS (ISSUES, CONCERNS & COMMENTS)
Project Engineer 1
Safety Officer 1
GENERAL Supervisor 1
Foreman 1
Safety Watchman 1
TOTAL
Mason 0 NOTE:

Painter 2
CIVIL Welder 0
Helper 2
Pipe Fitter 0
TOTAL 4

Melvin Sarcia

Engr. Raymart Dela Cruz


Project In Charge