Professional Documents
Culture Documents
1ST MONTH LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER 1ST WEEKLY PROGRESS 2nd WEEKLY PROGRESS 3rd WEEKLY PROGRESS 4th WEEKLY PROGRESS
1 Mobilization & Demob. 4,02% 1 Landfill 0,03% 1 Smoothing and Compaction 0,21% 1 Sand Fill 50 mm 0,25%
SKILL W-1 W-2 W-3 W-4 TOTAL
2 Temporary Shelter 4,87% 5,68%
2 Sloof of Reinforced Concrete 20X20 2 Sand Fill 50 mm 0,10% 2 Plastering + Glaring 1,73%
3 Temporary Warehouse 3,78% 3 Concrete Column 25X25 5,52% 3 Ringbalk 15x20 5,49% 3 Septic Tank Work 0,15%
1 Head Builder 7 10 8 3 28 man 4 Soil Excavation 0,28% 4 Hebel Brick Wall 5,99% 4 Lightweight Steel Roof Truss Canal5,75%
C 4
2 Bricklayer 4 4 7 4 19 man 5 Sand Fill 50 mm 0,01% 5 Installation of Harmonica Ram 1,59% 5 Zincalume spandex Roof, 0.5 mm 3,69% 5
3 Blacksmith 4 8 7 2 21 man 6 Working Floor 50 mm 0,03% 6 6 Gutter 0,14% 6
4 Carpenter - - - - - man 7 Concrete Pile Cap & Columns 12,12% 7 7 Flashing zincalume 2,11% 7
5 Painter - - - - - man 8 Land Disposal 0,06% 8 8 Plastering + Glaring 1,52% 8
6 Worker 10 7 6 2 25 man 9 9 9 Septic Tank Work 0,45% 9
7 Foreman/Superintendent 3 6 7 2 18 man 10 10 10 Rolling Door 0,57% 10
8 etc. - - - - - man 11 11 11 11
12 12 12 12
13 13 13 13
14 14 14 14
TOTAL 25,16% TOTAL 18,81% TOTAL 20,01% TOTAL 2,14%
PLAN 25,19% PLAN 5,68% PLAN 12,29% PLAN 4,33%
WORK BEGINS : 07:00 WORK ENDS : 17:00
ACTUAL 25,16% ACTUAL 18,81% ACTUAL 20,01% ACTUAL 2,14%
WHEATHER W-1 W-2 W-3 W-4 TOTAL DEVIATION PROGRESS CHART (PLAN VS ACTUAL)
30,87%
25,19%
25,16%
SONY SYAFARI EEP HERRY K AGUS WARYONO W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8
Project Manager Site Manager Field Supervisor JICA PROJECT TEAM
WEEKLY REPORT JICA PROJECT TEAM, SANYU CONSULTANS INC. CONTRACTOR :
THE EAST TOWER 17TH FLOOR, JAKARTA, JL. DR. IDE ANAK. AGUNG GDE AGUNG KAR,. E1.2 NO.1, CV. ANUGRAH KARYA BERSAMA
PERIOD : NOVEMBER 9 - NOVEMBER 14 JAKARTA SELATAN 12950
JL. KARASAK BARU NO.32 RT.006 RW.002
BANDUNG
YEAR : 2021
PROJECT : CONSTRUCTION OF A NEW WAREHOUSE FOR THE SINAR MUKTI FARMER GROUP
1ST WEEK LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED WEEKLY PROGRESS
1 Sands 6 M3 PREPARATORY WORK WEIGHT (%)
SKILL D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL
2 Split Stone 7 M3 1 Mobilization & Demob. P 4,02%
3 Column Iron Ø 12 Full 2 Temporary Shelter P 4,87%
1 Head Builder - 2 2 1 2 - - 7 man 4 Ring Iron Ø 8 Full 3 Temporary Warehouse P 3,78%
2 Bricklayer - - - - - 2 2 4 man 5 Nail size 5 cm 12,67%
3 Blacksmith - - - - - 2 2 4 man 6 Nail size 7 cm FOUNDATION WORK
4 Carpenter - - - - - - - - man 7 Steel Wire 1 Soil Excavation P 0,28%
5 Painter - - - - - - - - man 8 Rafers 2 Sand Fill 50 mm P 0,01%
6 Worker - 2 2 2 2 1 1 10 man 9 Pile Cap 80 Ø 10 3 Working Floor 50 mm P 0,03%
7 Foreman/Superintendent - - 1 1 1 - - 3 man 10 Cement Pc 13 Bag Volume 50 Kg 4 Concrete Pile Cap & Columns P 12,12%
8 etc. - - - - - - - - man 11 Hebel Bricks 1 M3 5 Landfill 0,00%
12 6 Land Disposal P 0,06%
13 12,49%
14
TOTAL WEEKLY PROGRESS 25,16%
15
H 0 2 6 2 3 2 1
P RAIN
M 0 30 25 26 0 24 0
17,75 H
H 0 0 0 0 0 0 0
BRIGHT 0,00 H
M 0 0 0 0 0 0 0
H 0 0 0 0 0 0 0
OVERCAST 0,00 H
M 0 0 0 0 0 0 0
2ND WEEK LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED WEEKLY PROGRESS
1 A. FOUNDATION WORK WEIGHT (%)
SKILL D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL
2 5 Landfill P 0,03%
3 0,03%
1 Head Builder - 1 1 4 2 2 - 10 man 4 C. STRUCTURE WORK
2 Bricklayer 2 - 2 - - - - 4 man 5 1 Sloof of Reinforced Concrete 20X20
P 5,68%
3 Blacksmith 2 - 2 - 2 2 - 8 man 6 2 Concrete Column 25X25 P 5,52%
4 Carpenter - - - - - - - - man 7 3 Ringbalk 15x20 P
5 Painter - - - - - - - - man 8 11,19%
6 Worker 1 2 1 1 1 1 - 7 man 9 B. WALL WORK
7 Foreman/Superintendent 1 1 1 1 1 1 - 6 man 10 1 Hebel Brick Wall P 5,99%
8 etc. - - - - - - - - man 11 - - 2 Installation of Harmonica Ram P 1,59%
12 7,58%
13
14
THIS WEEK PROGRESS 18,81%
15
3RD WEEK LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED WEEKLY PROGRESS
1 Hebel WORK ITEMS WEIGHT (%)
SKILL D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL
2 Cement 1 Smoothing and Compaction P 0,21%
3 Sand 2 Sand Fill 50 mm P 0,10%
1 Head Builder 2 2 2 - - 2 - 8 man 4 Steel Roof Truss Canal C 3 Ringbalk 15x20 P 5,49%
2 Bricklayer 2 - - 2 2 1 - 7 man 5 4 Plastering + Glaring P 1,52%
3 Blacksmith - 2 2 - 1 - 2 7 man 6 5 Lightweight Steel Roof Truss CanalPC 5,75%
4 Carpenter - - - - - - - - man 7 6 Zincalume spandex Roof, 0.5 mm P 3,69%
5 Painter - - - - - - - - man 8 7 Gutter P 0,14%
6 Worker 1 1 1 1 1 1 - 6 man 9 8 Flashing zincalume P 2,11%
7 Foreman/Superintendent 1 1 1 1 1 1 1 7 man 10 9 Septic Tank Work P 0,45%
8 etc. - - - - - - - - man 11 - 10 Rolling Door P 0,57%
12
13
14
THIS WEEK PROGRESS 20,01%
15
4TH WEEK LOCATION : TUGUMUKTI VILLAGE, CISARUA DISTRICT, WEST BANDUNG REGENCY
MAN POWER MATERIALS BROUGHT IN TOTAL ACCEPTED TOTAL REJECTED WEEKLY PROGRESS
1 - WORK ITEMS WEIGHT (%)
SKILL D-1 D-2 D-3 D-4 D-5 D-6 D-7 TOTAL
2 - 1 Sand Fill 50 mm P 0,25%
3 - 2 Plastering + Glaring P 1,73%
1 Head Builder 2 1 - - - - - 3 man 4 - 3 Septic Tank Work P 0,15%
2 Bricklayer 2 2 - - - - - 4 man 5 4 P
3 Blacksmith 2 - - - - - - 2 man 6 5 P
4 Carpenter - - - - - - - - man 7 6 P
5 Painter - - - - - - - - man 8 7 P
6 Worker 1 1 - - - - - 2 man 9 8 P
7 Foreman/Superintendent 1 1 - - - - - 2 man 10 9 P
8 etc. - - - - - - - - man 11 - 10 P
12
13
14
THIS WEEK PROGRESS 2,14%
15
H 0 0 0 0 0 0 0
OVERCAST 0,00 H
M 0 0 0 0 0 0 0
1 Lightweight Steel Roof Truss Canal C 98,64 m2 5,75% 1,15% 1,15% 1,15% 1,15% 1,15%
2 Zincalume spandex Roof, 0.5 mm 118,37 m2 7,38% 0,74% 0,74%53,69%
0,74% 0,74% 0,74% 1,85% 1,85%
3 Gutter 9,00 m1 0,28% 0,03% 0,03% 0,03% 0,03% 0,03% 0,07% 0,07%
4 Flashing zincalume 118,37 m2 4,21% 0,42%50,25%
0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42% 0,42%
WEEKLY WEIGHT PROGRESS (ACTUAL) 100,00% 0,00% 12,81% 2,62% 2,45% 2,42% 2,42% 2,42% 2,90% 2,86% 2,86% 2,86% 3,66% 3,66% 0,00% 1,53% 1,32% 3,44% 3,44% 3,94% 2,84% 3,51% 0,99% 1,14% 3,41% 3,30% 1,37% 4,18% 6,20% 2,95% 2,95% 0,72% 0,72% 0,72% 0,72% 4,55% 1,04% 1,04% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
CUMULATIVE WEEKLY WEIGHT PROGRESS (ACTUAL) 0,00% 12,81% 15,43% 17,89% 20,31% 22,74% 25,16% 28,06% 30,92% 33,79% 36,65% 40,31% 43,97% 43,97% 45,50% 46,82% 50,25% 53,69% 57,63% 60,47% 63,98% 64,97% 66,12% 69,53% 72,82% 74,19% 78,37% 84,58% 87,52% 90,47% 91,19% 91,91% 92,64% 93,36% 97,91% 98,96% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
WEEKLY WEIGHT PROGRESS (PLAN) 100,00% 0,00% 12,76% 2,53% 2,57% 2,44% 2,42% 2,46% 0,81% 0,81% 0,81% 0,81% 0,81% 0,81% 0,81% 1,76% 1,76% 1,76% 1,76% 1,76% 1,76% 1,76% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 1,84% 1,84% 1,84% 1,84% 1,84% 1,84% 1,84% 1,61% 1,61% 1,61% 1,61% 1,61% 1,61% 1,61% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 2,17% 0,52% 0,52% 0,52% 0,20% 0,20% 0,20% 0,20%
CUMULATIVE WEEKLY WEIGHT PROGRESS (PLAN) 0,00% 12,76% 15,30% 17,87% 20,31% 22,74% 25,19% 26,00% 26,81% 27,62% 28,44% 29,25% 30,06% 30,87% 32,62% 34,38% 36,14% 37,89% 39,65% 41,40% 43,16% 45,33% 47,49% 49,66% 51,83% 53,99% 56,16% 58,33% 60,16% 62,00% 63,83% 65,67% 67,50% 69,34% 71,17% 72,78% 74,39% 76,00% 77,61% 79,22% 80,83% 82,44% 84,61% 86,78% 88,95% 91,11% 93,28% 95,45% 97,62% 98,14% 98,67% 99,19% 99,39% 100% 100% 100%