AIRCURTAIN AND DOCK EXTENTION

JTI – LIMA TECHNOLOGY CENTER


AUGUST 31,2022

PREVIOUS ACCOMPLISHMENT :
PRESENT ACCOMPLISHMENT :
ACCOMPLISHED ACTIVITIES AIR CURTAIN AND FLAP DOCK EXTENSION

 ACCOMPLISHED ACTIVITIES
 Installation of bracket – 100%
 Installation of air curtain – 50%
 Installation of Flap dock extension – 20%
%ACCOMPLISHMENT REPORT AIR CURTAIN AND FLAP DOCK EXTENSION

LOAD FACTOR PERCENT ACCOMPLISHMENT WT. IN % ACCOMPLISHMENT


ITEM NO. DESCRIPTION
% PREVIOUS THIS PERIOD (9- TO DATE PREVIOUS THIS PERIOD TO DATE
02-22)
I. PRELIMINARIES / GEN REQTS
2.00 2.00
1.0 PPE's -Safety/ Workers Uniform 100% 100% - 2.00
5.33 5.33
2.0 Mobilization 100% 100% - 5.33
2.00 2.00
3.0 Temfacil Construction 100% 100% - 2.00
4.00 4.00
4.0 Site Transportation / Delivery Cost 100% 100% - 4.00
1.33 1.33
5.0 Badging / Workers Access / Orinetation 100% 100% - 1.33
6.0 Supervision 6.67 0% - - -

II. AIR CURTAIN AND LOADING DOCK FLAP


A. AIR CURTAIN
38.20 38.20
1.0 Air Curtain 36" Width 100% 100% - 38.20
2.0 Electrical ( CO available at Doorway) - 0% - - -
2.02 2.02
3.0 Testing and Adjustment 100% 100% - 2.02
B. STEEL FLAP FOR LOADING DOCK
17.64 5.29
1.0 Checkered Plate 1/4" x 4' x 8' A-36 30% 30% - 5.29
2.0 Concrete Spacers 13.10 0% - - -
C. OTHERs
1.0 Garbage Hauling 1.87 0% - - -
2.0 Safety Barrier / Protection 5.83 0% - - -

100.00 0.00 60.18 60.18


ACTIVITIES FOR NEXT WEEK AIR CURTAIN AND FLAP DOCK EXTENSION

 ACTIVITIES FOR NEXT WEEK


 Installation of Flap dock extension
 Painting
 Installation of concrete spacer
EHS REPORT AIR CURTAIN AND FLAP DOCK EXTENSION

 ENVIRONMENTAL, HEALTH AND SAFETY REPORT

SAFETY RECORD AS OF AUGUST 25, 2022

DESCRIPTION PREVOIUS THIS PERIOD

SAFETY VIOLATION 0 0 0

FIRST AID TREATMENT CASE 0 0 0

MEDICAL TREATMENT CASE 0 0 0

HIGHEST MANPOWER PERIOD


6
AUGUST 25, 2022

ACCUMULATED SAFE MAN HOURS


192
AUGUST 31 , 2022
MANPOWER/EQUIPMENT LOADING AIR CURTAIN AND FLAP DOCK EXTENSION

 MANPOWER LOADING – AUGUST 31, 2022 (CLEANAIR CONSTRUCTION AND SUPPLY )


• Supervisor – 1
• Safety Officer – 1
• Foreman – 1
• Skilled Workers - 2
• Labor – 1
• TOTAL –6