Professional Documents
Culture Documents
ON
Submitted by
DRISHYA D NAMBIAR
18 NOVEMBER 2022
MISSION
To Provide Qualitative value added Training for enhancing talent of young minds
VISION
The Training opportunity that CMTI provided enabled me to gain vast amount of
knowledge on various practical aspects of construction sectors and individually
develop professionalism. I consider myself very lucky to be a part of this
programme.
I am very grateful to the entire team of Shriram Properties Limited and
FOUNDER AND CEO of CMTI, Er. Ashok Kumar, for providing this
Training opportunity. I am very thankful for these people for guiding me in each
and every aspect which enabled my professional development. I also convey my
gratitude to all the trainers who trained me every day in spite of their busy
schedules. These trainers provided me with a great guidance and deep knowledge
which enabled me to learn many things theoretically and practically. I believe this
opportunity will be a greatest milestone in my career and through this training i
will be successful in achieving my goals and assure to continue to learn much
more knowledge in this construction sector with the cooperation of CMTI.
i
CONTENTS
Contents Page No.
ACKNOWLEDGEMENT i
LIST OF TABLES iv
LIST OF FIGURES v
Chapter 1. ABOUT THE COMPANY 1
1.1 Vision 1
1.2 Mission 1
Chapter 2. ABOUT WYT FIELD YUVA 3
Chapter 3. PROJECT DATA 4
3.1 Project Location 4
Chapter 4. SAFETY 5
Chapter 5. MIVAN FORMWORK 7
5.1 Wall Components 8
5.1.1 Wall Panel 8
5.1.2 Rocker 8
5.1.3 Kicker 8
5.1.4 Stub Pin 9
5.2 Beam Components 9
5.2.1 Beam Side Panel 9
5.2.2 Prop Head for Soffit Beam 9
5.2.3 Beam Soffit Panel 10
5.2.4Beam Soffit Bulkhead 10
5.3 Deck Component 10
5.3.1 Deck Panel 10
5.3.2 Deck Prop 11
5.3.3 Deck Mid - Beam 11
5.3.4 Soffit Length 12
5.3.5 Deck Beam Bar 12
5.4 Other Components 12
5.4.1nternal Soffit Corner 12
5.4.2 External Soffit Corner 13
5.4.3 External Corner 13
5.4.4 Internal Corner 13
5.5 Pin and Wedge System 14
Chapter 6. CONSTRUCTION ACTIVITIES WITH MIVAN AS FORMWORK 15
6.1 Pre-concrete Activities 15
6.2 On concrete Activities 16
6.3 Post-concrete Activities 16
Chapter 7. CONVENTIONAL FORMWORK (PLYWOOD, WOODEN RUNNERS,
STAGING) 19
ii
Chapter 8. GRID LINE MARKING ON THE SLAB BY SURVEYOR FOR WALL
PANELS ERECTIONS AS PER LAYOUT 21
8.1 Procedure 21
Chapter 9. CONCRETE 22
9.1 Ready mix concrete (RMC) 22
9.2 Self Dynamic Concrete (SDC) 22
9.3 Grade of Concrete 23
9.4 Quality Tests for the Concrete 24
9.4.1 Flow Test of Smart Dynamic Concrete (SDC) 24
9.4.2 Compressive Strength of Concrete 24
9.4.3. Casting of concrete moulds for determination of compressive strength as
per IS516. 25
Chapter 10. CONSTRUCTION MACHINERY USED IN SITE 26
10.1 Mixer 26
10.2 Vibrator 26
10.3 Bar Cutter 26
10.4 Meters 26
10.5 Truck 26
10.6 Masons Square 27
10.7 Plumb Bob 27
10.8 Sprit Level 27
10.9 Pan 27
10.10 Dumpy Level 27
10.11 JCB 28
10.12 Mobile Crane 28
10.13 Total Station 29
. 10.14 Tower Crane 29
Chapter 11. CHECKLIST 30
Chapter 12. COLUMN FORMWORK 34
Chapter 13. PRESSURE GROUTING 36
Chapter 14. WATER PROOFING 38
Chapter 15. TILING WORK 40
Chapter 16. WINDOW FRAME AND BALCONY FRAME FIXING 42
16.1 ACRYLIC SEALANT 43
16.2 SILICONE SEALANT 44
Chapter 17. WALL FINISHES 45
17.1 Putty Work 45
17.2 Painting Work 46
Chapter 18. TRAINING OUTCOMES 47
18.1 Technical Outcomes 47
18.2 Non-technical Outcomes 48
Chapter 19. CONCLUSION 50
iii
iv
LIST OF TABLES
No Title Page No.
1. Project data 4
2. Conventional formwork 23
3. Mivan formwork 23
4. SDC design mix details 23
5. Normal design mix details 24
v
LIST OF FIGURES
No Title Page No.
1 Project location 4
2 Safety measures in site 6
3 Mivan formwork 7
4 Wall panel 8
5 Rocker 8
6 Kicker 9
7 Stub pin 9
8 Beam side panel 9
9 Prop head for soffit beam 10
10 Beam soffit-panel 10
11 Beam soffit bulkhead 10
12 Deck panel 11
13 Deck prop 11
14 Deck mid-beam 11
15 Soffit length 12
16 Deck beam bar 12
17 Internal soffit corner 13
18 External soffit corner 13
19 External corner 13
21 Wall assembly details 14
22 Beam assembly details 14
23 Reinforcement work in progress of walls and beams 17
24 Fixing the kicker 17
25 Strike bottom level shutter to erect above level 17
26 Wall panels placing 18
27 Preparation of wall tie to be place 18
28 Conventional formwork 19
29 Structural line marking by surveyor 21
30 Compressive Strength Test Machine and Cube Testing 25
31 RMC truck 26
32 Plumb bob 27
33 Sprit level 27
34 Dumpy level 28
35 JCB 28
36 Mobile crane 29
37 Total station 29
38 Tower crane 29
39 Column formwork fixing 34
40 Materials required for pressure grouting 36
41 Pressure grouting application 36
42 Waterpond in mother slab 38
43 Haunching 38
44 Brushbond with chemicals 38
45 Skin coat application 39
46 Tiling in bathroom 41
47 Checking the window openings 42
vi
48 Fixing balcony frames 43
49 Acrylic sealant 44
50 1st coat putty application mixing 20kg putty powder with 5-6litre of water 46
vii
CHAPTER 1
ABOUT THE COMPANY
Shriram properties limited is one of the leading residential real estate development companies
in South India, primarily focused on the mid-market and affordable housing categories. It is
among the five largest residential real estate companies in South India, including specifically
in Bengaluru and Chennai, in terms of number of aggregate units launched in the calendar years
2012 to 2017 and the six months ended June 30, 2018. They also present in the mid-market
premium and luxury housing categories, commercial and office space category as well as
Shriram properties limited is part of the Shriram Group, which is a prominent business group
with four decades of operating history in India and a well-recognized brand in the retail
Since inception in 1995, Shriram Properties have been relentless in their pursuit to deliver the
highest standards of living. They design innovative living spaces which make optimal use of
space, to provide you the best in comfort. The builder is in Kolkata, Vishakhapatnam, Chennai,
Coimbatore, Bengaluru and has been actively developing projects all around the locality.
1.1 VISION
"Be ever respected as the most trusted, honest and progressive corporate in the real estate
industry"
1.2 MISSION
To build quality properties across India with high standards, conforming to relevant building
1
To stand committed to their communities in all spheres of our activities including addressing
the environmental concerns such as energy efficiencies, optimum use of water resources &
To stand committed to working in partnership with all their stake holders including joint
venture partners, contractors and suppliers giving due consideration to their needs and
2
CHAPTER 2
ABOUT WYT FIELD YUVA
by Shriram Properties in Whitefield, Bangalore. Whitefield has become one of the most
developed residential areas of Bangalore city. This world-class residential property offers
plenty of advanced living facilities that include strategic location, comfortable and lavish
This residential complex offers multiple luxury apartments in 2 BHK and 3 BHK format. We
can find 78% open spaces and greenery to ensure an eco-friendly lifestyle.
The modern living facilities offered by this residential property are really top-notch. It comes
with a large swimming pool where people can chill anytime. These premium-quality homes
are future ready with electric car parks and cycle docking stations. There will be two lavishly
designed clubhouses for a youthful living experience with 40+ lifestyle amenities. The
beautiful landscaped garden is a perfect place for hanging out with friends and family. Some
other key features of this complex are sports facility, intercom facility, well-equipped
gymnasium, multipurpose hall, and many more. With 24-hour CCTV surveillance,
This residential property by Shriram Properties comes with many location benefits. Situated at
residential property. Also, this popular IT hub of Bangalore enjoys close proximity to
Bengaluru International Airport. That is why Whitefield is considered as one of the best
3
CHAPTER 3
PROJECT DATA
Project Data
4
CHAPTER 4
SAFETY
Every developer should ensure that his employees are exposed to a safe work environment. It
is mandatory for a developer with more than 50 workers, to issue a policy statement with
respect to the safety and health of his workers and ensure that the said policies are followed.
Usually, it is the Building and Other Constructions Workers (BOCW) Act that regulates and
provides assistance to workers engaged in construction activities. The BOCW Act lays down
• Ensuring safe means of access to any construction site, by providing suitable and
sufficient protective equipment like helmets, eyewear, footwear, gloves, ladders, etc.,
to workers.
• Ensuring suitable and adequate lighting, when lifting and lowering loads.
5
Fig 2 Safety Measures in Site
6
CHAPTER 5
MIVAN FORMWORK
A fast-track construction, One of the Latest technology for successful completion of mass
housing Reinforced Concrete Structures. Mivan formwork is the advanced formwork system
made of strong and sturdy aluminum components that has great strength, durability, simple to
install, adaptable and is used in the construction of residential units and mass housing projects.
Here the Columns, Walls, Slabs and Beams poured together – a Monolithic pouring. It provides
The basic element of the formwork is the panel, which is an extruded aluminium rail section,
welded to an aluminium sheet. This produces a lightweight panel with an excellent stiffness to
weight ratio, yielding minimal deflection under concrete loading. Panels are manufactured in
the size and shape to suit the requirements of specific projects. The panels are made from high
strength aluminium alloy with a 4 mm thick skin plate and 6mm thick ribbing behind to stiffen
the panels.
7
5.1 WALL COMPONENTS
It forms the face of the wall. It is an Aluminium sheet properly cut to fit the exact size of the
wall.
5.1.2 Rocker
It is a supporting component of wall. It is Lshaped panel having allotment holes for stub pin.
Fig 5 Rocker
5.1.3 Kicker
It forms the wall face at the top of the panels and acts as a ledge to support
8
Fig 6 Kicker
5.1.4 Stub Pin
It forms the side of the beams. It is a rectangular structure and is cut according to the size of
the beam.
It forms the soffit beam. It is a V-shaped head for easy dislodging of the formwork.
9
Fig 9 Prop head for soffit beam
It forms the horizontal surface for casting of slabs. It is built for proper safety of workers.
10
Fig 12 Deck panel
It forms a V-shaped prop head. It supports the deck and bears the load coming on the deck
panel.
11
5.3.4 Soffit Length
It provides support to the edge of the deck panels at their perimeter of the room.
It is the deck for the beam. This component supports the deck and beam.
It forms the vertical internal corner between the walls and the beams, slabs, and the horizontal
internal cornice between the walls and the beam slabs and the beam soffit.
12
Fig 17 Internal soffit corner
13
5.5 PIN AND WEDGE SYSTEM
The panels are held in position by a simple pin and wedge system that passes through holes in
the outside rib of each panel. The panels fit precisely, simply and securely and require no
bracing. Buildings can be constructed quickly and easily by unskilled labour with hammer
being the only tool required. Once the panels have been numbered, measuring is not necessary.
As the erection process is manually, tower cranes are not required. The result is a typical 4 to
14
CHAPTER 6
CONSTRUCTION ACTIVITIES WITH MIVAN FORMWORK
The construction activities are divided as pre –concrete activities, during concreting and post
– concrete activities.
b) Level Surveys – Level checking are made to maintain horizontal level check.
After the above activities have been completed it is necessary to check the following.
1. All formwork should be cleaned and coated with approved realize agent.
4. Check all horizontal formwork (deck soffit, and beam soffit etc.) in level.
5. Ensure deck and beam props are vertical and there is vertical movement in the prop lengths.
6. Check wall ties, pins and wedges are all in position and secure.
15
7. Any surplus material or items to be cleared from the area to be cast.
ON CONCRETE ACTIVITIES:-
At least two operatives should be on standby during concreting for checking pins, wedges and
wall ties as the pour is in progress. Pins, wedges or wall ties missing could lead to a movement
of the formwork and possibility of the formwork being damaged. This affected area will then
5. Strike wall – Mounted on a Working Platform the wall are fitted on next floor.
16
Fig 23 Reinforcement work in progress of walls and beams
17
Fig 26 Wall panels placing
18
CHAPTER 7
CONVENTIONAL FORMWORK (PLYWOOD, WOODEN
RUNNERS, STAGING)
Formwork and centering is a temporary structure that is erected to support and contain concrete
to the required dimensions and shape, till it attains enough strength to become self supporting.
The formwork is designed to safely support the combined loads(dead and live loads)
• staging -cup-lock system, is a supporting system required to keep the form work in
1. Base jack
5. Primary waler
6. Secondary waler
19
• Ply wood
• Wooden runner
Runners are used to strengthen the plywood and to prevent the plywood from bending,
warping and bulging. Spacing and size of runners depends on loads that will be imposed
on the formwork.
20
CHAPTER 8
GRID LINE MARKING ON THE SLAB BY SURVEYOR FOR
WALL PANELS ERECTIONS AS PER LAYOUT
8.1 PROCEDURE
Structural line is drawn on the slab at offset distance of 300mm from internal side of wall with
help of points given by the surveyor at every right angle of walls (at every corner of walls).
Surveyor locates these points with aid of total station equipment. The application of total station
that is used by surveyor is stake out/ setting out process(Stake out means process of finding the
FFL SSL
Terrace level 931.7
14th floor 928.8 928.75
13th floor 925.85 925.8
12th floor 922.9 922.85
11th floor 919.95 919.9
10th floor 917 916.95
9th floor 914.05 914
8th floor 911.1 911.05
7th floor 908.15 908.1
6th floor 905.2 905.15
5th floor 902.25 902.2
4th floor 899.3 899.25
3rd floor 896.35 896.3
2nd floor 893.4 893.35
1st floor 890.45 890.4
Ground floor 887.5 887.45
21
CHAPTER 9
CONCRETE
Mostly RMC is used for all concrete casting in site “Concrete that is manufactured for delivery
4926:2003 defines RMC as: “Concrete mixed in a stationary mixer in a central batching and
mixing plant or in a truck-mixer and supplied in fresh condition to the purchaser either at the
RC Wall of mivan formwork are cast by using SDC concrete mix design in working site.
SDC is a special concrete which is highly flow able, non-segregating and by its own weight
spread into place and completely fill the formwork even in the presence of dense reinforcement.
SDC offers several economical and technical benefits. SDC requires minimal to no vibration
due to its self-compacting properties, thereby resulting in lower energy and manpower
utilization. Demoulding can be done in 16 hours and faster rotation of the formwork or in other
words, shorter cycle times resulted in overall cost savings and more importantly, earlier
completion times. Excellent surface finish with no honeycombing and voids can be achieved
with SDC, Hence, the repair costs of concrete members cast with SDC can be maintained at a
low level. SDC is an attractive proposition for designers, contractors, and owners because it is
22
9.3 GRADE OF CONCRETE
Conventional Formwork
1 PCC M10
2 Footing and RW Raft M30WPC
3 Retaining Wall M30WPC
4 Column and SW M40
5 LB slab (Capital drops) M40
6 LB slab M30
7 UB slab M40
Mivan Formwork
23
Normal Design Mix Details
Sl descript Ceme Cem GG MSa 20m 12.5 Wat Admixt w/c Slum
N ion nt ent BS nd m mm er ure kgs p(mm
o brand kgs kgs kgs kgs )
1 Final ACC 250 80 759 695 463 155 1.65 0.47 130
mix 53 76% 24% 60% 40% CACH3
design GRA
330 1158
M25 DE
OPC
2 Final ACC 280 90 787 658 439 163 1.85 0.44 130
mix 53 76% 24% 60% 40% CACH3
design GRA
370 1097
M30 DE
OPC
3 Final ACC 360 90 732 649 436 162 2.25 0.36 120
mix 53 80% 20% 60% 40% CACH3
design GRA
450 1085
M40 DE
OPC
The flow test is used to measure the workability of high or very high workable concrete,
which eventually would exhibit the collapse of slump. It gives an idea about the quality
of the concrete with respect to the consistency and cohesiveness. This workability test is
quite simple to perform and is the best for the concrete which has a nominal maximum
to carry the loads on it without any crack or deflection. The compressive strength of concrete
24
can be calculated by dividing the load applied to the concrete cube at the point of failure by
the cross-section area of the cube (15x15x15 cm) on which the load was applied.
516
• Finish the top surface by thapi/trowel after compaction of the last layer
For every 50cubic meter of concrete, 9cubes are casted ie 3 cubes are tested for compressive
strength at 3days and 3cubes at 7days and 3cubes at 28days. In 3days it should be 45% of
Marking on cubes contains the date of casting, grade and type of concrete, tower number.
25
CHAPTER 10
CONSTRUCTION MACHINERY USED IN SITE
10.1 MIXER
It is a mechanical material used for mixing the concrete ingredients (water, cement and
aggregate). In site they use truck mixer from RMC plant, a concrete mixer mounted on the
10.2 VIBRATOR
Having secured the necessary supply, the concrete needs to be placed and compacted. These
two activities are carried out simultaneously. Placing and compaction of concrete should be
done without causing any segregation of its ingredients. For of compaction the concrete, on
Bar cutter is used to cut the reinforcement bar to accelerate the work, also called set-to In
Site.
10.4 METERS
10.5 TRUCK
26
Truck is used to transport materials to different location in sites.
Masons square is used to get right angle, also called squadra in site.
Sprit level is used with straight edge, for getting a horizontal surface. The levelling tube is
10.9 PAN
Pan is used to carry mortar, concrete etc. To other place in the construction.
Dumpy level is a Levelling instrument used to locate the points in same horizontal plane.
27
Fig 34 Dumpy level
10.11 JCB
The function of the JCB machine is excavation of the land which is categorized as earth
Fig 35 JCB
propelled models. They are designed to easily transport to a site and use with different types
28
Fig 36 Mobile crane
A total station can measure angles and distances electronically and process trigonometrically
29
CHAPTER 11
CHECKLIST
A construction checklist is a set of items or activities that a site in-charge must verify, check,
and inspect to ensure the systematic progress of a project. It is a great tool that can help
optimize and organize a project in many ways. It helps to overcome the errors that arise due
to human carelessness.
2. Equipment checklists
3. Tools checklists
5. Pre-work checklists
3. Reinforced checked
8. Check plumb
30
• Cement consumption in kgs Actual / Theoretical
Vehicle no
Invoice no
Concrete qty
Batching time
Slump test
Location
Identification mark
Remark
31
• CHECKLIST: Quality Inspection Report - Wall Tie Hole Packing
After
1. Steel Reinforcement
2. Shuttering work
3. Concrete work
4. Wall grinding
5. T holes packing
6. Touchup work
7. Plastering work
9. Windows/door james
11. Toilets
12. Handover
32
14. Foor Cleaning
33
CHAPTER 12
COLUMN FORMWORK
1. Column starter: before casting column a special type of concrete arrangement is made
It is given
2. The column box or shuttering for columns is formed of plyboard sheets made up of
adequate stiffeners.
3. A thin film of oil or grease ought to be applied to the inner surface of the shuttering to
5. Formwork should be totally supported with props size before running the concrete in
34
6. The gaps close to the shuttered joints ought to be sealed with plaster or a bit of wood to
7. An appropriate area is to be provided within the inner face of the shutter and
9. The removal of shutters should be done gently while not jerking in order that the edges
10. Care ought to be taken relating to fixing and supporting column shuttering to avoid
35
CHAPTER 13
PRESSURE GROUTING
In existing RCC surface weak area and honey combs should be thoroughly checked to fix
Nozzles, Drilling with 18mm bit by drilling machine up to length 36mm, fix nozzles of 18mm
dia and seal around the pipe with Rapid setting Renderoc plug and allow to dry minimum 4
hours.
water to be added up to flow able consistency. Thorough mixing and grout with pressure
grouting machine upto honey combs get filled, seal the nozzle with FOSROC RENDEROC
36
Allow 4 hours to dry and cutting the projected nozzles and seal it with FOSROC CONPEXTRA
37
CHAPTER 14
WATER PROOFING
2. Check crack is present or not, if crack is there means do treatment like Pressure grouting
3. After completing this procedure we have to check mother slab by keeping water for
48hr
Fig 43 Haunching
4. After 48hr no leakage means we can start haunching (a process of making the sharp
corners into smooth curve in areas like floor and wall junctions
38
5. Waterproofing Coating Brushbond method is applied, first coat horizontally then after
24hrs second coat vertically applied. Chemical used is Sikatop seal 107 IN comp A
6. Next is skin coat, 1:4 mortar ratio with 200ml conplast WL.
39
CHAPTER 15
TILING WORK
1. Cleaning of completed floor slab and rc wall prior for start survey marking and layout
2. Do not begin tiling work until all concealed conduits, pipes, electrical cables, electrical
boxes, etc that penetrate the tiling have been fixed securely in position and making good
is completed
3. Also ensure that waterproofing for wet areas is already done including leak test before
tile work
4. Before laying tiles, floor need to be wet and cement mortar bed of 1:8 mix proportion
5. Cement slurry shall be applied over cement mortar and back of tile with 2mm spacer
joint
The bathroom tiles used in site are Kajaria Digital Nabhraska brown 300 x 300mm, Nabhraska
crema 300 x 450mm, Malaga gris 300 x 450mm, Dona beige 300 x 300. The floor tile is AGL
40
Fig 46 Tiling in bathroom
41
CHAPTER 16
WINDOW FRAME AND BALCONY FRAME FIXING
1. Hoist the frame into the wall opening and check its level.
2. The wall thickness is 160mm, frame is fixed like outside offset 32mm and inside 45mm
3. Measure and drill fixing holes into the sides of the frame
4. Drill the fixing screws through the frame and into the wall.
6. Apply a line of silicone sealant/ Acrylic sealant around the frame’s external surface
42
Fig 48 Fixing balcony frames
Acrylic sealant is a sealing material, mainly obtained from water based acrylic resins. It is not
suitable for use in locations subject to direct water exposure. As it is a paintable material,
acrylic sealant is an ideal material for interior and exterior decoration. It cures after drying. It
is an environmentally friendly material. It provides protection from dust and pests from various
surface cavities.
Generally, it is used in construction covering all kinds of cracks and gaps, expansion joints
between prefabricated building elements and assembly of wood, pvc, iron and aluminum
joinery, plastering of joinery, sealing of joints, combination of eternit, aluminum roof and
43
Fig 49 Acrylic sealant
One of the most necessary yet underrated tools in the industrial world is Adhesives. Adhesives
are used in every level of work right from the minor repairs at home to big fixtures in industries.
One such water-resistant glue is a Silicone Sealant that can be used for any fixation. It makes
These are gel-like substances in liquid form. Its chemical components are different from any
other polymer-based organic adhesives. Silicone is known to have properties that can sustain
stability and elasticity in extreme temperatures, making it one of the best options to use in
repairing and building objects.One of the things that need to be taken care of while using it is
that curing is essential. Curing is meant by letting it dry, although it can take as little as 24
hours. The curing’s ideal temperature is between 40◦F and 100◦F, and humidity is between 5%
and 95%. Sometimes it can take a few days to cure depending on the thickness.
Before applying sealant, it is important to ensure that the exterior or interior area is free of wet
surfaces, frost, dirt, and dust in order to achieve a strong bonding and clean and long-lasting
results. It is also important to follow the manufacturer’s instructions to make sure that all the
44
CHAPTER 17
WALL FINISHES
The building finishes requires very less maintenance since the formwork used will provide a
smooth finish surface since no need to provide an extra coating of plastering with cement
mortar. The finished internal surface of the house is coated with 3 coat of putty and one coat
3 coat putty on wall, ceiling and lobby area. The material used are Berger paints BISON
professional putty.
• Grinding the concrete joints and wall ties, removal of dust, grease etc
• Take the required quantity of wall putty and 35-40% of water by volumn
This process will bring smooth surface to the walls. To test the smoothness take a light and
45
Fig 50 1st coat putty application mixing 20kg putty powder with 5-6litre of water
After putty apply 1coat berger primer then 2 coat berger paint.
46
CHAPTER 18
TRAINING OUTCOMES
This training has enhanced my knowledge about the environment which is present in a
company. The entire period of two months proved to be a good source of practical exposure.
At the end of these two months now I feel myself better equipped to face the problems in field
of construction. I came to know that what environment prevails in office and site. The friendly
welcome from all the seniors is appreciating, sharing their experience and giving their peace
of wisdom which they have gained in long journey of work. Working at this site helped me to
know all the major and minor aspects of construction management. I got to know new
techniques. I also learnt to tackle with the general problems faced on site. I came to know the
Furthermore I have learnt many things by identifying different types of construction materials
and their uses, and also learning a lot about construction process and methods that are used in
WYT Field Yuva construction site, plus by talking and asking questions from the construction
In the end, I feel myself to be more confident and independent. I also feel that this training has
given many valuable things which would help me throughout my professional life.
• After undergoing my internship, I came across the various departments that prevail at
• I came to know about various materials that were used at the site
• I came to know about the process and specification of different activities starting from
47
• Study and understanding of architectural and structural drawings.
• I came to know finishing works that is gypsum plastering, tiling and door and window
fixings.
• One main thing that I have learned through this internship is time management and
patience
• I feel much confident to deal with the problems occurring in the site.
• I now fully understand the importance of being a good team player while working in
The objective of the internship is to address more practical knowledge and to develop
construction skills for the students. So I have learnt some of the construction skills at site as
much possible within two months. The skills and practical knowledge that have learnt at the
site is of totally different from the actual knowledge gained from the classes.
Some of the practical knowledge and skills that I have learnt from the industrial training was:
48
• Various departments that is present in construction industry and their functions, roles
• Surveying skills-column and footing markings using total station equipments. The
• Concrete sequence arrangement of concrete pump and pipes, pouring, compacting and
finishing activities.
• I have learnt various construction works and their standard methodologies followed at
the starting from excavation to finishing stage that are required to complete the entire
building.
49
CHAPTER 19
CONCLUSION
On the whole, this internship was a useful experience. I have gained new practical knowledge,
skills and met many new people. I got insight into professional practices currently advocated
in the industry. I got a chance to improve both my theoretical and practical knowledge when I
stay in the site. I was learned how to communicate with the site workers. The senior engineers
provided me with a great guidance and deep knowledge which enabled me to learn many things
practically, It taught me a lot about how to handle a variety of situations. The internship
program connects me to the real construction works and made me to hold a vital confidence.
50