(CPM)
By
Drishya D Nambiar
Civil Trainer
EduCADD
INTRODUCTION
Critical path is a sequence of activity between a project’s start and finish that takes the longest
time to complete.
Critical path method is based on mathematical calculations and it is used for scheduling project
activities.
Critical path is the sequential activities from stat to the end of a project. Although many projects
have only one critical path, some projects may have more than one critical paths depending on
the flow logic used in the project
The essential technique for using CPM is to construct
a model of the project that includes the following
ABDEF:7+2+4+4+3=20
ACDEG:7+4+4+4+5=24