Professional Documents
Culture Documents
Lecture # 5
1
Learning Objectives
By the end of this lecture, you will be able to;
• Know the processes required to manage the time.
• Understand the project schedule management techniques.
– Critical Path Method (CPM)
– Program Evaluation & Review Technique (PERT)
• Demonstrate the project schedule compression techniques.
– Crashing
– Fast tracking
• Understand the Project Network diagram / network analysis.
– Arrow diagraming method (Activities-on-Arrow (AOA))
– Precedence diagraming method (Activities-on-Nodes (AON))
• Understand Project Schedule & their types.
– Preliminary schedule, detailed schedule, baseline schedule & updated
schedule (also Gantt Chart)
Project Time Management includes the processes required to
manage the timely completion of the project.
Plan Schedule Management: Plan Schedule Management
is the process of establishing the policies, procedures, and
documentation for planning, developing, managing,
executing, and controlling the project schedule.
Define Activities: The process of identifying and
documenting the specific actions to be performed to
produce the project deliverables.
Sequence Activities: The process of identifying and
documenting relationships among the project activities.
(Precedence Diagraming Method (PDM))
Estimate Activity Resources: The process of estimating
the type and quantities of material, human resources,
equipment, or supplies required to perform each activity.
Estimate Activity durations: The process of estimating the
number of work periods needed to complete individual
activities with estimated resources.
Develop Schedule: The process of analyzing activity
sequences, durations, resource requirements, and
schedule constraints to create the project schedule
model.
Control Schedule: The process of monitoring the status of
project activities to update project progress and manage
changes to the schedule baseline to achieve the plan.
Introduction
Critical Path Analysis and PERT are powerful tools that
help you to schedule and manage complex projects.
Both rely on a logical sequence of tasks.
As with Gantt Charts, Critical Path Analysis (CPA) or the
Critical Path Method (CPM) helps you to plan all tasks
that must be completed as part of a project.
They act as the basis both for preparation of a
schedule, and of resource planning. During
management of a project, they allow you to monitor
achievement of project goals.
They help you to see where remedial action needs to
be taken to get a project back on course.
5
Significance
CMP/PERT can answer the following important questions:
How long will the entire project take to be completed?
Which are the critical activities or tasks in the project which could delay
the entire project if they were not completed on time?
Is the project on schedule, behind schedule or ahead of schedule?
If the project has to be finished earlier than planned, what is the best way
to do this at the least cost?
CPM Calculate
The longest path of planned activities to the end of the
project & it estimate the minimum project duration.
The earliest and latest that each activity can start and finish
without making the project longer by performing forward
pass & backward pass analysis
Determines “critical” activities (on the longest path).
Prioritize activities for the effective management and to
shorten the planned critical path of a project by:
“Fast tracking" (performing more activities in parallel)
“Crashing the critical path" (shortening the durations of
critical path activities by adding resources) 9
Critical Path Method (Cont.)
EF = ES+D-1
EF = 6+5-1 = 10
EF = ES+D-1
LS = LF-D+1
TFactivity = Project Dur. – Path Lengthactivity
or TFactivity = LS-ES or LF-EF LS = LF-D+1
FFactivity = ESsuccessor – 1 - EFactivity LS = 15-10+11 = 10
10
PMBOK Guide 6th Ed.
Program Evaluation & Review Technique
12
Three Time Estimate Example
Time estimates Expected
Activity Predecessor
Opt. (o) Normal (m) Pess. (p) time
A — 2 4 6 4.00
B — 3 5 9 5.33
C A 4 5 7 5.17
D A 4 6 10 6.33
E B, C 4 5 7 5.17
F D 3 4 8 4.50
G E 3 5 8 5.17
13
Difference
BASIS FOR
PERT CPM
COMPARISON
PERT is a project management CPM is a technique of project
Meaning technique, used to manage uncertain management that manages well defined
activities of a project. activities of a project.
14
Arrow & Precedence Diagraming Method
B D F
C 16
Activity On Arrow (AOA) (cont.)
17
Activity On Node (AON)
Activity on Node / Precedence Diagraming Method
In this type of project network diagram, nodes are tasks, and the
arrows are merely connectors.
18
Precedence Diagramming Method (PDM)
The Precedence Diagramming Method (PDM) is a technique
used for constructing a schedule model in which activities are
represented by nodes and are graphically linked by one or more
logical relationships to show the sequence in which the activities
are to be performed.
PDM includes four types of dependencies or logical
relationships.
A Predecessor activity is an activity that logically comes before a
dependent activity in a schedule.
A Successor activity is a dependent activity that logically comes
after another activity in a schedule.
22
AON Example
23
AON Example (cont.)
24
AON Example (cont.)
Forward Pass/Path: For Calculating Early Start (ES) & Early Finish (EF)
Consider maximum EF
of the predecessor
for finding ES (if connected
with multiple predecessor)
EF = ES+D-1
ES EF LS = LF-D+1
D TFactivity = Project Dur. – Path Lengthactivity
or TFactivity = LS-ES or LF-EF
FFactivity = ESsuccessor – 1 - EFactivity
LS LF 25
AON Example (cont.)
Calculating Free Float
EF = ES+D-1
LS = LF-D+1
TFactivity = Project Dur. – Path Lengthactivity
or TFactivity = LS-ES or LF-EF
FFactivity = ESsuccessor – 1 - EFactivity
26
AON Example (cont.)
Backward Pass/Path: For Calculating Late Start(LS) & Late Finish(LF)
ES EF
D
LS LF
Consider min LS EF = ES+D-1
of the successor LS = LF-D+1
for finding LF (if TFactivity = Project Dur. – Path Lengthactivity
connected with 4 9 or TFactivity = LS-ES or LF-EF
multiple successors) FFactivity = ESsuccessor – 1 - EFactivity
27
Class Exercise
A C G
Start H
B D E
32
Graphical Example
• Milestone charts or Master schedule: These charts are similar to bar charts, but
only identify the scheduled start or completion of major deliverables and key
external interfaces.
• Bar charts: Also known as Gantt charts, represent schedule information where
activities are listed on the vertical axis, dates are shown on the horizontal axis, and
activity durations are shown as horizontal bars placed according to start and finish
dates.
Graphical Example Cont.
Project schedule network diagrams: These diagrams are commonly presented in
the activity-on-node diagram format showing activities and relationships without a
time scale, sometimes referred to as a pure logic diagram or presented in a time-
scaled schedule network diagram format that is sometimes called a logic bar chart.
36
Schedule Compression (Cont.)
38
PMBOK Guide 6th Ed.
Gantt Chart Example
Summary
• Processes required to manage the time.
• Project scheduling techniques i.e. Critical Path Method (CPM),
Program Evaluation & Review Technique (PERT)
• Schedule compression techniques, i.e. Crashing & Fast tracking
• Arrow diagraming method (Activities-on-Arrow (AOA))
• Precedence diagraming method (Activities-on-Nodes (AON))
• Project Schedule & their types i.e. Preliminary schedule, detailed
schedule, baseline schedule & updated schedule.
Reference
• PMBOK Guide 6th Edition.
• www.wikipedia.com
• www.westbrookstevens.com
THANK YOU!
42