Professional Documents
Culture Documents
A project is an interrelated set of activities that has a definite starting and ending point and
those results in a unique product. That means projects are not repetitive.
6. Construction of a ship.
Characteristics of Project
1.Uniqueness
2.Complexity
3.Life cycle
6.Non recurring
8.Completion deadline
9.Involves resources
10.Performance measurement
Basic steps in project management
Managing a project, regardless of its size and complexity, requires identifying every activity
to be undertaken and planning when each activity must begin and end in order to complete
6. Periodically assess the progress of the project and repeat steps 2-6 as needed.
three constraints cost, scope and time leads to a quality final deliverable. These constraints
interconnect and must continually be balanced. When a change is made to one constraint,
adjustments are required to one or both of the other constraints to maintain quality. This
model is also called the iron triangle, golden triangle, project triangle and triple constraint.
NETWORK
2. Event: An event is a specific instant of time marks the start and end of an activity.
3. Critical path: It is the sequence of activities which decides the total project duration.
4. Duration (d): Duration is the estimated or actual time required to complete a task or an
activity.
5. Total project time: Time to complete the project. In other words, it is the duration of
critical path.
6. Earliest start time (E): It is the earliest possible time at which an activity can start. It is
7. Latest start time (Li): It is the latest possible time by which an activity can start.
8. Earliest finish time (Ej): It is the last event time of the head event. It is calculated by
9. Latest finish time (Lj): It is the last event time of the head event. It is calculated by
11. Free float: (Latest Finish Time – Earliest Start Time) – Activity duration.
Network scheduling
Both are based on the use of a network/graphical model to depict the work tasks being
scheduled.
The popularity of network based scheduling can be attributed to its many benefits, especially
1. It provides a visual display of needed task and their temporal ordering, which makes it easy
to see how tasks should be sequenced as shown below. This assists communication and co-
operation among task teams because each team can see how its work affects other team.
2. It provides a relatively accurate estimate of the time required to complete the project at the
3. It identified and highlights the tasks that are critical to keep the project on schedule.
4. It provides a method for evaluating the time-cost tradeoffs resulting from reallocating
5. It provides a method for monitoring the project throughout its life cycle. As the project
progresses, PERT/CPM easily identifies change in which tasks are critical and how the
6. It provides a convenient method for incorporating uncertainty regarding task times into the
schedule and it helps to evaluate the effect of this uncertainty on project completion time.
Difference between PERT and CPM
PERT CPM
PERT is a probabilistic model with uncertainty CPM is a deterministic model with well-
PERT terminology uses word like network CPM terminology employs word like
PERT terminology uses word like network CPM terminology employs word like
PERT basically does not demarcate between CPM marks the critical activities.
PERT is applied in projects where resources are CPM is applied to projects where
importance.
PERT is suitable in Defence project and R&D Suitable for plant maintenance, civil
where activity time can’t be readily predicted. construction projects etc. where activity
duration is known.
CRITICAL PATH METHOD FOR CONSTRUCTION
The critical path method (CPM) is a popular scheduling technique in the construction
industry due to its simplicity and effectiveness. The CPM approach to project scheduling
includes splitting a project into multiple job tasks, displaying them in a flow chart, and
calculating the duration for each task and the overall project duration based on the individual
functions.
foundation of that project schedule should typically be made up of the essential tasks to keep
the project moving. That brings us to the Critical Path Method, which is widely used in the
construction industry.
While smaller construction jobs allow for spontaneous planning, more significant projects
require construction project management. The construction critical path method (CPM) is a
tool that many project managers use, often with their construction management software, to
help figure out the best steps to take to finish a job efficiently. This critical path method,
otherwise known as critical path scheduling, is one of the most frequently used construction
planning techniques.
CPM for project management uses a network diagram to graphically illustrate a construction
project’s significant activities and show the links between activities. CPM assigns each
List of Activities. They need to have a list of all activities required to complete the
project. Managers typically use a work-breakdown structure to list all activities and
first.
The project managers or superintendents must have the duration of each activity. This
is important in determining the overall schedule. While using PERT, they should be
able to get a reasonably accurate estimate for the total length of each part.
activities. In construction, there are specific tasks that MUST happen before other
functions because it would be impossible to start them without them. These are
Milestones and Deliverables. To know when a task or activity is complete, the project
manager must know when the project should end and what the end looks like. Also,
many subcontractors are paid based on their deliverables, so knowing what the
Oracle Primavera P6 is a project, program and portfolio management tool that is used for
planning, managing and executing your project work. It is designed to handle large and small
projects in many diverse industries. Such as construction, manufacturing, energy and IT. It is
been doing so for more than 30years in projects across the globe.
Primavera P6 can trace its origins to 1983 when it was first established under the name
Primavera Systems. In the next 15years, it rapidly gained popularity. By the late 90s,
advancements in server technology drove the company to split primavera systems into two
In 2008, Primavera systems was bought out by oracle, which then developed the tool into the
Primavera software that’s used today. It can be used to schedule, monitor and planning of
projects. Primavera can handle complex projects due to its capacity of organizing 100000
activities and assigning unlimited resources. It can handle more than one project at a time.
Moreover, it allows users to arrange activities and allot resources in number of ways. It can
also be used to control and manage the delays in project during execution of work.
Primavera P6 Features
Risk management: Identify, track and resolve risks before they become issues.
Calendar & activity views: View project tasks set over a calendar view.
Scheduling alerts: Keep the project on track by always knowing what’s due when.
Project network view: Project network diagrams allow users to visualize their project
Work breakdown structure: P6 allows users to create a work breakdown structure that lets
Critical path method (CPM): Oracle primavera lets users find the critical path of their
projects. The critical path method is an important project scheduling technique that allows
project managers to estimate the total duration of a project and determine which project tasks
responsible for the projects in enterprise. The OBS usually reflects the management structure
of the organization from top level personal down through the various levels constituting in
business
Enterprise Project Structure (EPS) forms the hierarchy structure of database of the projects.
Each EPS can be sub – divided into multiple levels to presents the work that needs to be done
in the organization. You can use the EPS to perform top-down budgeting & resource and
Cost Analysis. Manage multiple projects from the highest level of the organization to the
in a project that defines the total scope of the project • It is a foundation document in project
management because it provides the basis for planning and managing project schedules,
All necessary data including drawing and bill of quantities, resources available and other
Methods
Based on data available activities involved were identified and listed down.
Make EPS
Enterprise project structure is made first it is basically structure of company with its all
Create OBS
Organization break down structure is created for every section it is the hierarchical structure
A project is a sum of different activities that create a deliverable and plan to execute these
activities to achieve desired goal. In primavera a project can be created for relevant branch of
EPS and allot the person responsible from OBS. For creating new project the project menu
bar in main menu bar is used. Allocation of calendar, start and finish dates allocation was
Work breakdown structure (WBS) is main part of schedule it is hierarchical structure of work.
WBS is different for every project. It mainly defines duration and constraints of activities. It
Add activities
Activity is basic unit of project. All activities sum up to create a deliverable. An activity have
its identification (ID), codes, name, constraints, calendar, start and ending dates, relationship
Company
name
Branch 1 Branch 2
Construction IT Construction IT
software
Building Building Road
development
Project 1
CEO
Director 1 Director2
Senior
Construction Structural Project Planning
QA/QC planning Site engineer
manager engineer Engineer engineer
engineer
3.Work breakdown structure example
Construction
of G+2
Residential
Building
Project
Preliminary
Construction Closing
work
Preliminary works
Start of project
Contract agreement
Initial survey
Site clearance
Final survey
Foundation- Earthworks
start of earthwork
excavation layout
termite proofing
backfilling
finish of earthwork
Foundation structure works
Column footings
Wall footings
Plinth beams
Horizontal DPC