Exercise
Given the following formula, data, and
diagram, determine the critical path and
the expected time of the project.
Time is represented in days
ET = 4(M) + 1(B) + 1(W) / 6
A = 2, B = 3, C = 1, D = 4, E = 3, F = 2, G = 2, H = 1,
and I = 3
Exercise (cont.)
A D G
C F I
B E H
Begin the Analysis
Remember your steps Find the earliest start
for PERT diagrams: time
Using the given Find the latest start
diagram, list all the time
steps
Determine task times Determine slack and
the critical path
Determine
relationships
between the tasks
Summary
Review the exercise
Advantages of PERT
Disadvantages of PERT
Odds and Ends
Review the Exercise