Professional Documents
Culture Documents
Reading Materials for
IC Training Modules
Construction
Workshop
IC PROFESSIONAL TRAINING SERIES
Construction Workshop
Objectives:
A. Builder’s Practices
B. Plumbing works
Page 1
IC Professional Training
Construction Workshop
Introduction
This practical training is primarily designed for first year students from
Throughout the training, considerable emphasis is placed on the types and uses,
methods. Also it is expected that the trainees will gain from the training
experiences an “appreciation” of good standards of workmanship. The safe use
and care of hand and power machine tools forms an integral part of all activities,
and the importance of good preparation work, as well as inspection and test
After the material and process introductory stage the trainees are given “real”
work construction projects to do, many of an “on-site” nature. These projects are
usually placed in the summer term of first year and will last for about five weeks
in which trainees play key roles as in a building contractor. They allow the
trainees to get managerial, group and supervisory work experience, and they
enable trainees to get a sound appreciation of the techniques and skills
necessary to achieve professional construction works. The site work training
includes site planning and site office procedures; project design and costing; raw
material ordering and control; site organisation; site work and site work
Page 2
IC Professional Training
Construction Workshop
Contents
Topics Page
Construction Workshop Safety Instructions 6-9
1.1 Introduction 10
1.2 Materials 10
1.2.1 Cement
1.2.2 Aggregates
1.2.3 Water
1.3 Production of Concrete 11 - 14
1.3.1 Batching
1.3.2 Mixing
1.3.3 Transport
1.3.4 Placing & Compacting
1.3.5 Compaction
1.3.6 Make Good Surface
1.3.7 Curing
1.4 Quality Control 14 - 16
1.4.1 Workability
1.4.2 Concrete Test Cubes
1.4.3 Temperature Control
1.5 Finishes 16 - 17
1.5.1 General Class of Finishes Hong Kong
1.5.2 Finishes Classified by Method of Forming
1.6 Construction Joint 18
1.7 Discussion & Exercises in Concreting 18 - 19
1.8 Type of Reinforcing Steel Bars 19 - 21
1.9 Cutting 21
1.10 Bending 21
1.11 Fixing Reinforcement & Cover to Reinforcements 21 - 22
1.12 Bar Bending Schedules 22
1.13 Discussion & Exercises in Steel Reinforcement 23 - 25
Page 3
IC Professional Training
Construction Workshop
2.5 Falsework 30
2.6 Formwork 30 - 35
2.6.1 Precast Concrete Forms
2.6.2 Formwork for Cast-in-situ
2.6.3 Notes for Design Forms
2.6.4 Materials
2.6.5 Other Formwork Materials
2.6.6 Parts of Forms
2.6.7 Striking of Formwork
2.6.8 Investigative Method for Formwork
2.6.9 Practical Design Notes
2.7 Discussion & Exercises 35 - 37
Page 4
IC Professional Training
Construction Workshop
5.1 Introduction 72
5.2 Learning Outcomes 72
5.3 Brief Syllabus Content 72 – 73
5.4 Learning Approach 73
5.5 Assessment 73 - 74
REFERENCES 75 – 78
BIBLIGRAPHY 79
RECOMMENDED READINGS 80
Page 5
IC Professional Training
Construction Workshop
performing tasks,
2. You should wear long trousers to reduce the risk of contact with sharp object
with power driven or hand tools (e.g. abrasive wheels, cartridge operated
fixing tools, drilling tools, screw drivers, hammers and chisels etc.),
8. You should be alert of the safety notices and posters in the workshops. Do
not rush through an operation; you should not proceed on any task if you
are uncertain of the safety procedures,
9. You must know where to assemble in case of fire. Be familiar with the fire
escape route.
2. You must wear earmuffs and a face shield when using any machines,
3. Before using any machines, make sure all guards are correctly positioned and
all hands are away from machines,
4. You must use push-sticks when using the electrical saw machines,
5. Students are not permitted to clean the dangerous parts of the machines
Page 6
IC Professional Training
Construction Workshop
hand tools (e.g. saws, sanding machine, drilling machine, hammer and chisels
etc.).
2. When erecting metal scaffold, you must follow the supervisor’s instructions,
3. Proper access and egress provided should be used and no climbing along
the standards/ledgers of the scaffold should be allowed,
supervisor.
6. Always knock the protruding nails into the wood immediately after
dismantling formwork,
7. When batching concrete, you must wear protective mask, spectacles and
gloves,
8. Always turn off the concrete mixer/cement mortar mixer, before loading and
unloading the materials.
2. Always wear safety mask and spectacles when mixing cement mortar,
3. You must wear safety goggles, mask and ear-muffs when polishing
bricks/stones with grinders,
Page 7
IC Professional Training
Construction Workshop
2. You must wear safety goggles, mask and ear-muffs when performing cutting
and grinding on steel members using steel cutting and grinding machines,
4. Use fume extractor to extract fumes outside the workshop during welding
process. The welding area should be well surrounded, kept dry and free of
combustible materials; special precautions should be made to protect
3. When using fire-gun, you must follow manufactures instructions and also
ensure liquefied petroleum gas (LPG) is firmly connected to the fire gun and
other person nearby when using hand tools (e.g. stained spanner, wrench,
Page 8
IC Professional Training
Construction Workshop
3. You must wear suitable protective gloves, dust mask, goggles and earmuffs
when drilling holes for anchor bolts and mixing chemical mixtures for
adhesive anchoring system,
4. You must use the proprietary hammering shield for protection of hand
3. You must wear suitable protective gloves and goggles when carrying
carbonation test using Phenolphthalein solution.
----------------------------------------------------------------------------------------
Note: For safety management purpose, students working in this workshop are
required to sign the student record sheet to ensure they have read and understood
the above safety instructions.
----------------------------------------------------------------------------------------
Page 9
IC Professional Training
Construction Workshop
1.1 Introduction
1.2 Materials
1.2.1 Cement
are required. It develops strength quickly enough for the general run of
concrete works. Other types of cement such as Rapid hardening Portland
Cement, white Portland cement, etc. are used for special purposes. Cement
must be kept dry in silos, or in 3-ply paper bags, it should be kept under
cover and off the ground.
1.2.2 Aggregates
Sands and crushed stone, such as granite are in common use as aggregates.
The essential requirements of aggregates are durability and cleanness. In
Hong Kong fine crushed stone is generally used rather than sand.
Aggregates of size >5mm is classified as coarse aggregates, size ≤5mm is
contamination.
1.2.3 Water
Water has always to be present in fresh concrete, not only to hydrate the
cement but also to convert it into a paste and thus make the concrete
Page 10
IC Professional Training
Construction Workshop
1.3.1 Batching
weight, but with light-weight aggregates and with small batches, volume
batching may be desirable. If sand is batched by volume, allowance must
be made for 'bulking', an increase in volume which occurs when the sand is
moist.
1.3.2 Mixing
b. Non-tilting drum
c. Reversing drum
Most mixers are fitted with power-operated loading hoppers and automatic
or semi-automatic water-measuring devices. Some mixers also have
admixture dispensers fitted. It is normally best to add the water at the same
When the concrete is mixed the complete contents of the drum should be
is not possible to remove all the contents from the area of the mixer
immediately. If this is not done, there is a risk that the larger aggregate
may separate from the mix, so that different container loads will have
different proportions. At the start of the day the batches will be harsh and
stonily because some mortar will stick to the inside of the drum and around
Page 11
IC Professional Training
Construction Workshop
After use, the mixer should be thoroughly washed out and the blades
cleaned to prevent hardened concrete building up around the drum and
blades. The inside of the drum should be inspected regularly and any
blades which are worn or broken should be replaced. Inspection and
1.3.3 Transport
size and complexity of the site and such factors as whether or not a crane is
available. In all cases the concrete must be transported so that it does not
is the cheapest means of transport, but it must be borne in mind that there
is still a danger of segregation.
Before the concrete is placed in its final position, the formwork has to be
checked for its stability, dimension and alignment according to the design
Rubbish such as sawdust, timber and cans, should be removed or blown out
by compressed air.
1.3.5 Compaction
Poker vibrator
Page 12
IC Professional Training
Construction Workshop
that it contains the minimum amount of unwanted air. This is easy with a
wet, workable mix, but the excess water will form unabsorbed bubbles in
the concrete, reducing its strength. Thus vibrators, which enable a drier
mix to be completely compacted to achieve the production of better
quality concrete.
The most common type of vibrator is the internal vibrator or poker. This is a
vibrating tube at the end of a flexible drive. Pokers vary in size, usually from
25 to 75 mm in diameters. It should be placed vertically in the concrete,
held in position until air bubbles cease to come to the surface. This should
External vibrators are occasionally used, but they are often used particularly
in heavily reinforced walls and the webs of deep beams, where it is difficult
or impossible to insert an internal vibrator.
Slabs are best compacted by vibrating tamping beams. These combine the
action of a screed and a vibrator, but they are only effective for a limited
depth. In general, a slab more than 150 mm thick should be compacted
1.3.7 Curing
Drying out, if allowed to take place too soon, results in low strength and a
porous concrete. To prevent evaporation of moisture and the consequent
formation of cracks in the surface, the curing must begin immediately
after the concrete has been placed and finished. One method is to cover
the concrete surface with impervious plastic sheets or to spray the surface
Page 13
IC Professional Training
Construction Workshop
1.4.1 Workability
Slump Test
For most concrete, the slump test is a practical means of measuring the
Page 14
IC Professional Training
Construction Workshop
The most common test for hardened concrete involves taking a sample of
fresh concrete and putting it into special cube moulds (150mm cube
concrete cubes are used mainly to check that the strength of the concrete is
above the minimum strength which had been specified; the results can be
used to access to control which has been exercised over the production of
concrete.
Page 15
IC Professional Training
Construction Workshop
temperature. The control method is to mix the concrete with ice water or
add suitable retarder.
1.5. Finishes
Treated finishes ( T1 to T6 )
Page 16
IC Professional Training
Construction Workshop
b. Indirect Method
The action of the bush hammer is to cut and spall away the
c. Indirect Method
Page 17
IC Professional Training
Construction Workshop
Suggested procedures:
• Take a formwork prefabricated in the Formwork workshop, estimate
total quantity of concrete required
• With the mix proportion given, calculate materials required for
• Prepare apparatus for slump test and cube test, tools for transportation
and equipment for compaction of concrete
o Mix concrete with a drum mixer
o Carry out slump test and take record of workability of concrete
strength tests
o Strike the formwork of the concrete and carry out cube strength
Page 18
IC Professional Training
Construction Workshop
Reinforcing bars are available in various sizes and grades. The grade
designates the yield strength of the material used in the manufacture of the
bars.
to BS4449. Ordinary round bars have a minimum yield stress of 250 N/mm2
(grade 250) and deformed high tensile bar shall have a minimum tensile
stress of 460 N/mm2 (grade 460).
The use of Y50 re-bar is not permitted by B.O.O. and because of its weight,
it is not commonly used in HK.
Page 19
IC Professional Training
Construction Workshop
or fracture the material. All bars should preferably be bent cold. Bending of
high yield steel bars to complicated shape should be avoided.
b. Abbreviations
Page 20
IC Professional Training
Construction Workshop
1.9 Cutting
Length of steel reinforcement are normally 12m long, they will be cut into
1.10 Bending
Steel bar bending machine either of
Unless the bars are rigidly fixed in the correct position, the reinforcements
Page 21
IC Professional Training
Construction Workshop
At all intersections, the bars or links should be securely tied together with
∅1.6mm soft iron wire. The ends of the wire ties must not point towards
the face of the concrete, and all ends should be cut off. As soon as steel
fixing has been completed, off cut of binding wire must be removed from
However, all welding should be carried out with low temperature welding
rods. Before concreting, the reinforcement should be free from mud, oil,
paint, loose rust and scale. Release agents should not be allowed to come
The normal concrete cover - the distance from the outside of the
reinforcements to the concrete surface - should be as given on the working
drawings. Small, precast concrete blocks or proprietary plastic spacers may
Spacer blocks
Bar bending schedules are very important parts of detailing. The method of
showing the bar bends in the schedule should be as given in BS8666:2000,
Page 22
IC Professional Training
Construction Workshop
reinforcement details of slab, beam and column; trainees have to select one
of the structural elements for their team to practice.
Suggested procedures:
• Read and identify the bars in the R.C. drawing,
column,
• Prepare the hand tools and spacer blocks for steel bar fixing,
• Fix the reinforcements as shown in the R.C. details,
• Inspect and comment on the steel bars fixed by other groups with
reference to the designed R.C. details,
• Discuss the implication of arrangement of bars against the placing of
Page 23
IC Professional Training
Construction Workshop
3600
1800
400
1B/A/1-2
(300X400)
400
A
120 120
1B/1-2/A-B (300X300)
3000
1B/1/A-B (300X300)
1B/2/A-B (300X300)
1S1 1S2
400
B
1B/B/1-2 (300X400)
1 2
GENERAL ARRANGEMENT OF
TYPICAL BUILDING FLOOR
10T10-3-250 B1 10T10-2-250 T1
4T10-4-250 T1 10T10-3-250 B1
10T10-1-250 T1 4T10-4-250 T1
10T10-1-250 T1
A
1290 1290
320
320
1290 1290
A A
2340
2340
2340
2340
2340
1290 1290
10T10-5-300 T2
320
320
1 2
1 2 1
7 7
6 6
3 3
A-A
Page 24
IC Professional Training
Construction Workshop
1 2
850 850
1
250
400 3T10-13
1
1200 1200
5T10-15-300 LINK 5T10-15-300 LINK
2T10-14 2T10-14
1B/A/1-2
12 12
10 10
418. 5225
13 13 13
1-1
B A
800 800
2T10-17
2
2350
9T10-18-300 LINK
16 16
18
17 17
2-2
Page 25
IC Professional Training
Construction Workshop
Hand tools should ALWAYS be kept in good condition and good working
order.
Use them correctly, carry them carefully, and store them safely.
Circular Saw
Disc Sander
Band Saw
Page 26
IC Professional Training
Construction Workshop
i. Always ask permission from the person in charge, before using any
machine.
ii. Avoid wearing loose clothing, button or roll up your sleeves. Remove
your necktie as well.
iii. Lay out and carefully plan your work before using the machine.
vii. Always use push stick when using circular saw and surface planing
machine.
viii. Don't forget to use every safety guard provided by the machine.
ix. When demonstration goes on, don't keep too close to the machine.
x. Try to check everything clear away from the moving parts of the
machine before witching on it.
scaffolding:
away from the wall at a distance which will accommodate the required
width of the working platform. The standards are joined together with
horizontal members called ledgers and are tied to the building with cross
members called putlogs. The scaffold is erected as the building rises and is
Page 27
IC Professional Training
Construction Workshop
An independent scaffold has two rows of standards, which are tied by cross
members called transoms. This form of scaffold does not rely upon the
building for support and is therefore suitable for use in conjunction with
cross members connected to it; alternatively a tube with a reveal pin in the
opening can provide a connection point for the cross members. If suitable
openings are not available then the scaffold should be strutted from the
2.4.3 Framework
Framework is used for the support and the protection of workmen engaged
in building. It comprises horizontal, vertical, and diagonal members up on
which scaffolding planks are laid. Since a man cannot work satisfactorily at
a height greater than 2 m above where he stands, scaffolding must be
erected as the building increases in height.
2.4.4 MATERIALS
i) Tubular steel,
iii) Bamboo.
scaffolds.
Page 28
IC Professional Training
Construction Workshop
b) Scaffold Fittings
scaffolding are:
Base plate - the support for the foot of standard in metal scaffolding.
Ledger - the horizontal member that ties and secures the standard.
rest.
Toe board - the horizontal board placed against the outer edge of the
working platform to prevent articles falling from the platform.
Guard rail - the horizontal member placed about 900mm above the
Page 29
IC Professional Training
Construction Workshop
iii. Ladder should be project 1050mm min above the working platform
working platform.
vi. Inner standards should not fix more than 300 mm away from the wall.
2.5 Falsework
Falsework Details
2.6 FORMWORK
Precast concrete usually has to be made within fine limits of accuracy and to
Page 30
IC Professional Training
Construction Workshop
strike a mould when the concrete is in a very green state, both to permit
early re-use of the forms and to enable the finished article to be cleaned
down when in a workable state. A panel or unit should come square away
from the concrete face and not side off it.
reassembled,
• Forms should be strong enough to withstand the tamping of
concrete.
2.6.4 Materials
Timber most commonly used is Douglas fir or British Colombian pine and
When the finished concrete is not covered in any way Fare Face it is
necessary to select timber fairly free from knots and coarse grain. May be
Green or freshly stuff should not be used for formwork. Timber for
Page 31
IC Professional Training
Construction Workshop
Untreated - 1 to 10 uses
Resin-coated - 5 to 20 uses
Holes can be filled with epoxy fillers or repaired with a simple plug driven
into the hole.
Screws, nails, staples etc can usually be used but a minimum edge distance
of 9 mm is recommended.
Where possible, standard size sheets (1200 x 2400 mm) should be used. In
addition curved formwork with sufficiently rigid framework, can be used.
Rubber - Rubber materials are generally used as form liners when complex
Plastic sheet - Plastic sheets are used as form liners to produce an almost
endless variety of low relief patterns.
Kicker – a small concrete upstand cast above floor level to position wall or
column forms for the next lift and to assist the prevention of grout loss.
Page 32
IC Professional Training
Construction Workshop
members and lacing them together (may be used to carry a beam soffit).
The period, which should elapse before the formwork is struck, will vary from
job to job and will depend on the concrete used. Formwork must not be
able to carry imposed loads. The time of striking should be related to the
strength of the concrete and, obviously, soffit forms to beams and slabs
must be left in place longer than is necessary for the side form.
Striking must be carried out with care to avoid damage to arise and
damage immediately after removing the forms. Before soffit forms and
Page 33
IC Professional Training
Construction Workshop
All formwork must be easy to strike after concreting. Care is needed to see
that no piece is keyed into the concrete, particularly end grain of timber. As
few nails as possible should be used and those that are used should be left
with heads standing so that they can be easily removed, unless they are in
the form face. Nails must not be driven both ways in an internal angle.
Dovetailing helps to give added holding power against direct withdrawal.
Adequate supports should be provided both vertically and laterally by
Wall sheeting
Concrete paste maybe squeezed out from joints between form panels when
the concrete is under tamping or vibrating. In order to minimize these
Page 34
IC Professional Training
Construction Workshop
defects to line the surfaces with waterproof paper, or use plywood or sheet
metal.
Great care must be taken in the method framing and allowance for
stripping. For column allow CLEAN-OUT TRAP at the floor level. The
air or water can be used to clean out the formwork. A most essential item in
column and beam work is the corner fillet. Sharp corner in concrete is easily
Slabs
The formwork panels are usually placed 600 to 900 mm side by side.
Paneling might be used with a great amount of repetitive work.
Suggested procedures:
i. Position the adjustable base-plates, spaced according to the lengths
of the ledger and transom horizontal members.
ii. Fit the basic standards or standards into the adjustable base-plates; fit
the horizontal members; check the structure is level.
iii. Fit the first working platform to ease the erection.; fit the complete
working platform in the access bay
iv. Build the first lift; fit the ledger and the transom horizontal members.
v. Fit the access working platform in the access bay; lower the ladder;
Page 35
IC Professional Training
Construction Workshop
vii. On the working platform at the lower level, fit the guardrails and toe
boards.
viii. The erector moves to the first stage which is already protected by the
erected working guardrails and toe boards.
ix. Tie the structure once every 20 square meters of surface (or use the
raker); continue erection as for the previous lifts; fit accessories as
1280
200
1960 1830
700
50
1000
150
LONGITUDINA L BRACE
R D RD
BOA BOA
T OE TOE
RAIL
RD
GUA LADDER
975
100
350
JACKPLATE
Suggested procedures:
ii. Design the formwork and associated supports; and sketch the
working drawings for the
iii. Calculate the quantities of timber plywood for the formwork
iv. Prepare the adequate amount of plywood and cut to the required
shapes
v. Erect the column forms first and provide adequate lateral supports
Page 36
IC Professional Training
Construction Workshop
vi. Erect the forms for the simple supported and cantilevered beam and
viii. Check the tightness of every adjacent plywood boards and check
stability of the whole form.
200
500
2400
ELEVATION
600
400
PLAN
Page 37
IC Professional Training
Construction Workshop
Page 38
IC Professional Training
Construction Workshop
3.2 Materials
bricks in the building of walls. The types of the materials and the mixing
have a considerable effect to the strength, durability, and the appearance of
Page 39
IC Professional Training
Construction Workshop
works.
3.2.3 Bricks
x 65 mm thick. Clay bricks are fired earth or shale. They are formed by
3.2.4 Blocks
Concrete blocks are walling units, for the heights must not exceed the
length or six times the thickness.
It made from dense aggregates (BS 882, 1983), suitable for general use
in load bearing external walls including works below ground level.
Page 40
IC Professional Training
Construction Workshop
140mm x 90mm.
3.3 Brickwork
3.3.1 Bonds
Bond is set out length of wall working from each end to ensure no vertical
joints are above one another is consecutive courses. Walls, which are not
in exact bond length, can be set in Broken Bond or Reversed Bond. A
quarter bond is obtained by placing closer next tooth end header or
Page 41
IC Professional Training
Construction Workshop
aesthetically superior uses less facing bricks (79 facing bricks / m²).
iv. Dry laying the designed pattern to check the correct spacing,
v. Prepare mortar into good consistency,
vi. Spread mortar bed (approx. 10 mm thick.),
vii. Build up the corner bricks as reference with guided thread attached on
top of the material,
viii. Place the bricks into correct position with true alignment includes
Page 42
IC Professional Training
Construction Workshop
a. Erosion: due to the action of wind laden with dust and driving rain.
3.4 Plastering
The undercoat is designed to even out any irregularity on the wall surface of
the internal and external wall. The undercoat is a mix based on cement and
sand called cement mortar, usually 10-20 mm thick.
Page 43
IC Professional Training
Construction Workshop
The finish coat of external wall is a mixed based on a cement and sand called
cement mortar, most are usually 10mm thick, that is to prevent the
penetration of water into the wall.
The finish coat of internal wall is a mix based on cement and lime called
putty coat or smooth coat, finish coat of plaster applied with trowel to give
a smooth finish.
v. Pitch the spaces between the screeds and rule off with a straight
edge,
vi. Use the wood float to work the surface to a sandy gritty finish,
vii. Roughen the coating with a metal comb to provide good keys for
further coating,
Page 44
IC Professional Training
Construction Workshop
viii. For external corners, metal cramps with straight edge may be used in
Bond failure: A wall surface of smooth dense blocks may not offer enough
mechanical key. The porosity and suction of the background
affect adhesion. Spray the background with water before
application is essential.
Hair cracks: The use of clean cement in powder or slurry form to daub the
surface of a finishing coat. Single coat rendering increase the
possibility of crazing.
Page 45
IC Professional Training
Construction Workshop
6431.
The unglazed back of the tiles are porous and absorb moisture very fast,
therefore advisable to soak tiles in water before fixing.
Wall Finish
Procedures:
iii. Set out the work, start from a corner and at the base of the wall,
iv. Bed a horizontal temporary support against the wall, (not greater
Page 46
IC Professional Training
Construction Workshop
vii. Start with the layer just above the temporary support, lay the first two
tiles beside the center line, then spread out to the left and right (in
most cases),
viii. Press the tile against the wall with a gentle force and ensure it is
ix. Allow a small joint as possible due to the quality control of tiles,
ensure plumb and flatness by using a spirit level and a straight edge,
x. By moving the trowel or the fingers over the edges of newly fixed
tiles, one can easily tell if the edges are flat to each other or not,
xi. Proceed on with another tile, leaving a space of 1-2 mm between two
tiles for adjustment for irregularity of tiles,
xii. After completing one layer of tiles, proceed on other layer upwards.
xiii. Carefully cut the tiles with tile cutter,
xiv. When finishing lying to desired level, remove the support and
Page 47
IC Professional Training
Construction Workshop
Tile cutter
Mosaic tiles are another kind of good protective coating, due to its good
durability on appearance and good resistance to weather, usually applied to
external or internal surfaces and floors.
Following procedures:
i. Apply the cement paste on the surface and float it evenly with the
iii. Attach these tiles to position with correct alignment that correctly set
up before,
iv. Lightly tapping on the backing paper with a plastering trowel to its
alignment,
Page 48
IC Professional Training
Construction Workshop
vi. grouting all open joints with cement slurry and wet up all the backing
paper,
vii. Wait for suitable duration until the backing paper has thoroughly
absorbed with the moisture,
viii. Detach the paper from the tiles carefully, any damage should make
good on the tiles,
surface.
a) monolithic method
b) separate method
Page 49
IC Professional Training
Construction Workshop
a) Monolithic method
Laying the topping within 3 hours on the concrete slab. The mix should
At about 2 hours after the topping is laid and fully compacted trowel it
to a smooth finish.
b) Separate method
the surface well then, removing any surplus water before grouting. The
grout should be composed of cement mode into stiff slurry with water.
This will provide a bond between the topping and the base. The surface
is then trowelled and cured.
The concrete floor may be topped with 25-mm thick cement and sand
screed trowelled to a smooth finish. The usual mix is 1:3 and a coloring
agent may be added.
3.6.3 Terrazzo
Page 50
IC Professional Training
Construction Workshop
Clean the sub floor thoroughly and brush the bay to be laid with cement
Procedures:
level.
iii. Flour "fresh" dry cement powder over the screed and spray with
water.
iv. Fix the sheet of mosaic tiles on the cement paste according to the
trademarks if applicable. (or follow the arrowheads)
v. Press the tiles downwards evenly and gently.
vi. Proceed on the other sheets, leave a uniform space between adjacent
tiles.
vii. Spray water over the tiles and wait for some time (say 1/2 hour).
viii. Also brushing over the back of tiles with water in order to maintain
the best absorption.
ix. Peel off the paper carefully after the paper absorbed adequate water
and become soft.
x. Fill up the joints by brushing or rubbing against the tiles with cement
Page 51
IC Professional Training
Construction Workshop
3.7 Paving
Page 52
IC Professional Training
Construction Workshop
• Richer mixes should not be used, as this will increase the difficulty in
future repair works.
and bed and blocks, it is necessary to ensure that all kerbs and other
edge restraints are erected. Ensure that all are ready for the paving
operations. Ensure that there is an adequate supply of sand of
ii. Commence lying as soon as the sand bed is laid and place the blocks
butt-jointed in a manner that does not disturb the sand.
iv. Use edge blocks at perimeters or cut blocks to provide clean edges.
Page 53
IC Professional Training
Construction Workshop
vi. Do not compact near the edge of blocks unless they are restrained.
vii. After initial compaction, brush sand over the finished paving and
vibrate into spaces between the blocks. Sweep surplus sand away,
On the external wall, the general design technique is to contrast with large
cladding system.
Page 54
IC Professional Training
Construction Workshop
with discs and polishing compound. There is also special machinery to cut,
grind or polish different marble and granite stores into various shapes.
themselves to carry out real work practices on brickwork, plastering and tiling
as described below:
Suggested procedures:
Page 55
IC Professional Training
Construction Workshop
(1:3),
vii. Plastering: to apply coats of cement / gauged mortar to internal faces
of wall (1:1:6),
viii. Damp the background, transfer mortar with trowel / wood float, apply
by dots & screeds method,
xi. Remove in diagonal way after plastering, wire scrapped on if extra keys
required.
Tiling: (ceramic/glazing)
Page 56
IC Professional Training
Construction Workshop
a. Direct System - in this system all sanitary fittings are supplied with
cold water direct from the main, and a stop valve or non-return
valve is required to install before water meter.
It is generally the pipework system for collecting rainwater onto the roof
of building and discharging it away to the underground drainage system
outside the building.
It includes generally the soil, waste, and ventilation pipework and fittings
in the building. It functions to convey discharges from appliance to
underground drains and can be arranged in three different ways: two-
pipes, one-pipe and single-stack systems.
Page 57
IC Professional Training
Construction Workshop
In Hong Kong, pipes for plumbing work are generally made of the
following materials: Cast iron, Ductile iron, Stainless Steel, Mild Steel
(galvanised), Copper, and Plastics. Choice of materials for different piping
systems depends on the properties of and the suitability of the materials.
The common types of pipes used in local plumbing work are summarised
as below:
4.2.2 Valves
The term 'cocks', 'valves' and 'taps' are used to name fittings required to control the
flow of fluids in a pipeline. Cocks and valves are usually used to control the flow
along a pipeline, whilst taps are usually used at the end of a pipeline for draw-off
purposes.
Page 58
IC Professional Training
Construction Workshop
C opper
DI
G I PV C
Lining
Stainless
Steel
CI
MS
U PV C
M D PE
PB
a. Types of Fittings
Page 59
IC Professional Training
Construction Workshop
Page 60
IC Professional Training
Construction Workshop
Pipe Types
Pipe Brackets CI DI MS CU PVC
Cast Iron
Galvanised
M alleable Iron
Steel
Plastic Coated
Copper Alloy
Pipe Brackets:
a. Pipe Wrenches
Page 61
IC Professional Training
Construction Workshop
b. Pipe Cutters
c. Threading Tools
Page 62
IC Professional Training
Construction Workshop
d. Plumbing Benders
4.3.1 In this section practical training is arranged for students to appreciate the
local practices in plumbing trades which include understanding of
Vertical Pipe Line Diagrams, preparation of materials and associated
installation methods.
Page 63
IC Professional Training
Construction Workshop
Thread Joint
Page 64
IC Professional Training
Construction Workshop
4.3.4 Bending
Metal and plastic pipes can be bent to minimise the need for expensive
connectors and so as to reduce the cost of installing pipe systems.
Bending of copper and G.I. pipes of diameters up to 75mm may be done
by hand compression or hydraulic bending machine. Bending of plastic
pipes are generally by heat treatment processes.
lever arm
oil pressure
former valve
hydraulic press-bender
4.3.5 Jointing
There are many types of jointing for water pipe. Steel Threaded Joints,
Flange Joints, Compression Joints, Weld Joints, Cold Weld Joints and etc.
However, they can be classified into two nature of jointing: Rigid Joint
and Flexible Joint.
4.3.5.1 Steel Threaded Joints (Stainless Steel and G.I. pipe) - for threaded
joint, all pipe fitting are tapped with internal pipe thread, the
plumber needs only make the external pipe thread. The jointing
process is as below:
Page 65
IC Professional Training
Construction Workshop
b. Compression Joints
- Cut the tube to the required length;
- Ream the cut end and remove the burrs of the tubing;
- A swaged end formed on the tube and the nut is put on the
tube before forming a swaged end;
- Insert tube end into fitting;
- Tighten cap nut with a spanner.
tightening
soft copper nut
ring
Page 66
IC Professional Training
Construction Workshop
4.4.1 The use of water in building and other purposes is made possible and
convenient by the provision of sanitary appliances which are of
appropriate form and have water supply either from the main, or from
hot or cold water storage vessels. It is essential that the supply water is
not contaminated by foul water and for this reason in most cases the taps
Page 67
IC Professional Training
Construction Workshop
prevent the risk of back siphonage of foul water into the supply pipe.
Glazed Earthenware
- for sinks and w.c. pans
Glazed Fireclay
- relatively weak
- non-absorbent even when it is unglazed
- various colours may be obtained
Mild Steel
- galvanised or enamelled
- used for toughs and sinks
- relatively cheap
Stainless Steel
Acrylic Plastic
- various colours, and excellent appearance
- light in weight
- relatively cheap
- hot water tends to soften the material
Page 68
IC Professional Training
Construction Workshop
G.R. Polyester
Cast Iron
- mainly for large appliance such as baths
- sinks
b. Waste Fittings:
- wash basins
- sinks
- baths
c. Flushing Cisterns:
atomspheric overflow
pressure
flow
s trap
sink mixer
single trap
water closet basin section
Page 69
IC Professional Training
Construction Workshop
Suggested procedures:
Part A - Working procedure of steel pipe installation (20mm, 15mm
GI/Stainless Steel)
Page 70
IC Professional Training
Construction Workshop
pipe)
Page 71
IC Professional Training
Construction Workshop
5.1 Introduction
Page 72
IC Professional Training
Construction Workshop
The work integrated construction project will be a real site project administered
and constructed by the students under the supervision of IC staff. The scope of
work will in general involve miscellaneous renovation works and minor structures
construction in school campus improvement projects. Students are required to
formulate themselves their own site organization structure and will team-play
different roles as in a contractor, the IC staff as the site supervisors and mentors
will co-ordinate the student contractor teams to complete the assigned tasks in
the construction project.
5.5 Assessment
Page 73
IC Professional Training
Construction Workshop
Oral presentation 5%
Page 74
IC Professional Training
Construction Workshop
REFERENCES
• ASD (2007). “General Specification for Building (2007) Vol. 1 & 2”. ASD,
HKSAR,
Bureau, HKSAR,
concrete”,
• BS5975:1996. “Code of Practice for Falsework”. BSI,
• BS 8110:1985. “The Structural Use of Concrete”. BSI,
Page 75
IC Professional Training
Construction Workshop
Concrete Society,
• Construction industry research and information association (1995).
NOTICE 2007,
Page 76
IC Professional Training
Construction Workshop
London,
• William P. Spence & L. Duance Griffiths (1995). “Woodworking Basics –
The Essential Benchtop Reference”. Sterling Pub. Co., New York.
Butterworth-Heinemann.
• Lilley A.A. & Clark A.J. (1981). “Concrete block paving for lightly trafficked
roads & paved areas”. Cement and Concrete Association.
Part IV – Plumbing
• Building Development Department, 1984, General Specification for
Building Architectural Office, Hong Kong
• Charles N. McConnell (1989). “Plumbers and Pipe Fitters Library: Materials,
Technical,
• Miller James (1993). “Basic Plumbing Techniques”. Ortho Books,
• Oravetz Jules, Sr. (1967). “Plumbers and Pipe Fitters Library: Materials,
Page 77
IC Professional Training
Construction Workshop
Page 78
IC Professional Training
Construction Workshop
BIBLIGRAPHY
Page 79
IC Professional Training
Construction Workshop
RECOMMENDED READINGS
• BS 7973 Part 1 & 2:2001. “Spacers and chairs for steel reinforcement and
BS EN 206-1”. BSI,
• BS EN 197 Part 1:2000. “Cement – Composition, specifications and
BSI.
Ltd..
Page 80
IC Professional Training