PROGRAM OF WORKS
DIRECT COST
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT TOTAL AMOUNT
TOTAL UNIT COST
I. Site Clearing and Leveing 96.00 sq.m. 1,650.00 17.19 1,650.00
II. Excavation and Backfilling 60.67 cu.m 9,300.00 153.29 9,300.00
III. Concrete Works 17.68 cu.m 161,210.00 9,118.21 161,210.00
IV. Masonry works/Plastering 9.69 sq.m 65,900.00 6,800.83 65,900.00
V. Painting works 20.00 sq.m 14,460.00 723.00 14,460.00
VI. Steel works 108.16 sq.m 180,054.45 1,664.70 180,054.45
VII. Electrical works 1.00 l.s. 74,340.00 74,340.00 74,340.00
TOTAL 506,914.45
A. Cost (Direct and Indirect) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
B. Engineering and Administrative Overhead _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
C. Total Cost _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 506,914.45
D. Survey and Preparation of Plan _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
E. Quality Control _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
F. Overhead Expenses _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
G. Row/Site Acquisition, Soil Exploration _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
TOTAL ESTIMATED COST (A-C) 506,914.45
CHECKED BY:
0.00
B. Labor
1 Foreman @ 500.00 /day x 1 days 500.00
1 Mason @ 450.00 /day x 1 days 450.00
2 Laborer @ 350.00 /day x 1 days 700.00
1,650.00
SUMMARY
I. Materials 0.00
II. Equipment -
III. Labor 1,650.00
IV. ESTIMATED DIRECT COST 1,650.00
TOTAL 1,650.00
UNIT COST 17.19
TOTAL ITEM COST 1,650.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY
I. Materials 6,000.00
II. Equipment -
III. Labor 3,300.00
IV. ESTIMATED DIRECT COST 9,300.00
TOTAL 9,300.00
UNIT COST 153.29
TOTAL ITEM COST 9,300.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY
I. Materials 123,260.00
II. Equipment -
III. Labor 37,950.00
IV. ESTIMATED DIRECT COST 161,210.00
TOTAL 161,210.00
UNIT COST 9,118.21
TOTAL ITEM COST 161,210.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY
I. Materials 52,700.00
II. Equipment -
III. Labor 13,200.00
IV. ESTIMATED DIRECT COST 65,900.00
TOTAL 65,900.00
UNIT COST 6,800.83
TOTAL ITEM COST 65,900.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY
I. Materials 10,560.00
II. Equipment -
III. Labor 3,900.00
IV. ESTIMATED DIRECT COST 14,460.00
TOTAL 14,460.00
UNIT COST 723.00
TOTAL ITEM COST 14,460.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY
I. Materials 145,405.00
II. Equipment -
III. Labor 33,000.00
IV. ESTIMATED DIRECT COST 178,405.00
TOTAL 178,405.00
UNIT COST 1,649.45
TOTAL ITEM COST 180,054.45
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY
I. Materials 30,670.00
II. Equipment -
III. Labor 6,500.00
IV. ESTIMATED DIRECT COST 37,170.00
TOTAL 37,170.00
UNIT COST 37,170.00
TOTAL ITEM COST 74,340.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY OF MATERIALS:
A. Materials UNIT QTY. U-COST AMOUNT
I. Site clearing
II. Excavation and backfilling
Gravel cu.m. 10.00 600.00 6,000.00
6,000.00
III. Concrete works
Portland cement bags 137.00 260.00 35,620.00
12mm RSB pcs. 144.00 260.00 37,440.00
10mm RSB pcs. 210.00 180.00 37,800.00
#16 G.I. Tie wire kgs. 20.00 80.00 1,600.00
Sand cu.m. 8.00 600.00 4,800.00
Gravel cu.m. 10.00 600.00 6,000.00
123,260.00
IV. Masonry works
Cement bags 83.00 260.00 21,580.00
Sand cu.m. 8.00 600.00 4,800.00
CHB 4" pcs. 1,260.00 12.00 15,120.00
10mm x 6m RSB pcs. 60.00 180.00 10,800.00
#16 G.I. Tie Wire kls 5.00 80.00 400.00
52,700.00
VI. Painting works
Semi-gloss Latex white pail 2.00 2,400.00 4,800.00
Shophie Shirt gray gal 1.00 750.00 750.00
Roller brush with pan pcs. 3.00 110.00 330.00
Paint brush 2" pcs. 5.00 55.00 275.00
Skim coat bags 5.00 250.00 1,250.00
RawSiena lit. 2.00 185.00 370.00
#80 sand paper pcs. 25.00 25.00 625.00
Paleta pcs. 6.00 35.00 210.00
8,610.00
VIII. Steel works
4mm x 63mm x 63mm angle bar pcs. 51.00 950.00 48,450.00
Welding rod(5kls/box) box 4.00 850.00 3,400.00
.40mmthk roofing sheets (pre painted) 8.52m pcs. 18.00 480.00 8,640.00
C-purlins 2x3 pcs. 32.00 850.00 27,200.00
Wall Flashing pcs. 18.00 450.00 8,100.00
Gray primer gal 2.00 600.00 1,200.00
Paint Brush 2'' pcs. 3.00 65.00 195.00
2-1/2'' Tekscrew pcs. 2,000.00 2.50 5,000.00
102,185.00
IX. Electrical works
Led Tubular Lamp 18 watt daylight
with aluminum Reflective Surface type, firefly set 1.00 1,100.00 1,100.00
1 gang Switch wide s set/s 1.00 110.00 110.00
Junction box PVC pcs. 4.00 30.00 120.00
Utilitybox, metal deep type 8mm pcs. 1.00 40.00 40.00
20mm PVC pipe, orange (atlanta) pcs. 3.00 100.00 300.00
2.0mm sq. THW copper wire Columbia/Sycwin mtrs. 20.00 60.00 1,200.00
2,870.00
TOTAL= 295,625.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY OF MATERIALS:
A. Materials UNIT QTY. U-COST AMOUNT
I. Site clearing
II. Excavation and backfilling
Gravel cu.m. 10.00 600.00 6,000.00
6,000.00
III. Concrete works
Portland cement bags 137.00 260.00 35,620.00
12mm RSB pcs. 144.00 260.00 37,440.00
10mm RSB pcs. 210.00 180.00 37,800.00
#16 G.I. Tie wire kgs. 20.00 80.00 1,600.00
Sand cu.m. 8.00 600.00 4,800.00
Gravel cu.m. 10.00 600.00 6,000.00
123,260.00
IV. Masonry works
Cement bags 83.00 260.00 21,580.00
Sand cu.m. 8.00 600.00 4,800.00
CHB 4" pcs. 1,260.00 12.00 15,120.00
10mm x 6m RSB pcs. 60.00 180.00 10,800.00
#16 G.I. Tie Wire kls 5.00 80.00 400.00
52,700.00
V. Tile works
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF!
VI. Painting works
Semi-gloss Latex white pail 2.00 2,400.00 4,800.00
Shophie Shirt gray gal 1.00 750.00 750.00
Roller brush with pan pcs. 3.00 110.00 330.00
Paint brush 2" pcs. 5.00 55.00 275.00
Skim coat bags 5.00 250.00 1,250.00
RawSiena lit. 2.00 185.00 370.00
#80 sand paper pcs. 25.00 25.00 625.00
Paleta pcs. 6.00 35.00 210.00
8,610.00
VII. Plumbing works
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF!
VIII. Steel works
4mm x 63mm x 63mm angle bar pcs. 51.00 950.00 48,450.00
Welding rod(5kls/box) box 4.00 850.00 3,400.00
.40mmthk roofing sheets (pre painted) 8.52m pcs. 18.00 480.00 8,640.00
C-purlins 2x3 pcs. 32.00 850.00 27,200.00
Wall Flashing pcs. 18.00 450.00 8,100.00
Gray primer gal 2.00 600.00 1,200.00
Paint Brush 2'' pcs. 3.00 65.00 195.00
2-1/2'' Tekscrew pcs. 2,000.00 2.50 5,000.00
102,185.00
IX. Electrical works
Led Tubular Lamp 18 watt daylight
with aluminum Reflective Surface type, firefly set 1.00 1,100.00 1,100.00
1 gang Switch wide s set/s 1.00 110.00 110.00
Junction box PVC pcs. 4.00 30.00 120.00
Utilitybox, metal deep type 8mm pcs. 1.00 40.00 40.00
20mm PVC pipe, orange (atlanta) pcs. 3.00 100.00 300.00
2.0mm sq. THW copper wire Columbia/Sycwin mtrs. 20.00 60.00 1,200.00
2,870.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
TOTAL= #REF!
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY OF LABOR:
A. Materials UNIT COST DAYS AMOUNT
I. Site clearing
Foreman 1 500.00 1.00 500.00
Mason 1 450.00 1.00 450.00
Laborer 2 350.00 1.00 700.00
1,650.00
II. Excavation and backfilling
Foreman 1 500.00 2.00 1,000.00
Mason 1 450.00 2.00 900.00
Laborer 2 350.00 2.00 1,400.00
3,300.00
III. Concrete works
Foreman 1 500.00 23.00 11,500.00
Mason 1 450.00 23.00 10,350.00
Laborer 2 350.00 23.00 16,100.00
37,950.00
IV. Masonry works
Foreman 1 500.00 8.00 4,000.00
Mason 1 450.00 8.00 3,600.00
Laborer 2 350.00 8.00 5,600.00
13,200.00
VI. Painting works
Foreman 1 500.00 3.00 1500.00
Painter 1 450.00 3.00 1350.00
Laborer 1 350.00 3.00 1050.00
3,900.00
VIII. Steel works
Foreman 1 500.00 20.00 10,000.00
Welder 1 450.00 20.00 9,000.00
Laborer 2 350.00 20.00 14,000.00
33,000.00
IX. Electrical works
Foreman 1 500.00 5.00 2,500.00
electrician 1 450.00 5.00 2,250.00
Laborer 1 350.00 5.00 1,750.00
6,500.00
no. of days= 62.00
TOTAL= 99,500.00
DETAILED ESTIMATE
Name of Project: PROPOSED SUPPLY WAREHOUSE
SUMMARY OF LABOR:
A. Materials UNIT COST DAYS AMOUNT
I. Site clearing
Foreman 1 500.00 1.00 500.00
Mason 1 450.00 1.00 450.00
Laborer 2 350.00 1.00 700.00
1,650.00
II. Excavation and backfilling
Foreman 1 500.00 2.00 1,000.00
Mason 1 450.00 2.00 900.00
Laborer 2 350.00 2.00 1,400.00
3,300.00
III. Concrete works
Foreman 1 500.00 23.00 11,500.00
Mason 1 450.00 23.00 10,350.00
Laborer 2 350.00 23.00 16,100.00
37,950.00
IV. Masonry works
Foreman 1 500.00 8.00 4,000.00
Mason 1 450.00 8.00 3,600.00
Laborer 2 350.00 8.00 5,600.00
13,200.00
V. Tile works
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF!
VI. Painting works
Foreman 1 500.00 3.00 1500.00
Painter 1 450.00 3.00 1350.00
Laborer 1 350.00 3.00 1050.00
3,900.00
VII. Plumbing works
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF!
VIII. Steel works
Foreman 1 500.00 20.00 10,000.00
Welder 1 450.00 20.00 9,000.00
Laborer 2 350.00 20.00 14,000.00
33,000.00
IX. Electrical works
Foreman 1 500.00 5.00 2,500.00
electrician 1 450.00 5.00 2,250.00
Laborer 1 350.00 5.00 1,750.00
6,500.00
no. of days= #REF!
TOTAL= #REF!