Professional Documents
Culture Documents
FOR CIVIL
[ J V/iTi'-jHSScD
VPr.J
I IWITOESSaP"
REVIEWED
REV
VPCI A—
Proposed by: Approved by: JV'^
(Subcon QA/QC Mngr) (VPCI Dept Mngr)|
tM"'
'■ . -U/ i
#'t„
, ' if , '•
■}.■ ■ ■ MS-f'
;>«?■' ' ■,»v
)SCO ENC CONFIDENTIAL OIBilHdeeminjae) 2020-02-21 17;01-.14 01 S/Hfe S^SS^Sj SI^SIOI HHSil 4= SsU
eflh JG SUMMIT
a P PETROCHEMICALS
JJigP GROUP FLUOR.
JG Summit Petrochemical Technical Query (TQ) Form
Stage 1 Expansion Project Page 1 of 2
Technical Query (TQ) No.: A4-JGS1EP-GTI-TQ-0043 [ Rev O ] bate: 25" Feb. 202"0
Contractor / Vendor: VPCI
Subject I Bored piling work without casing due to the geographical condition J Discipline j Civil
Specification / Drawings / Document Referenced or Impacted
With regard to the Bored piling work forGTG foundation, CONTRACT documents describe as follovirs.
• Adding grout to raise the pile cut-off elevation after the pile has reached its
initial set shall not be permitted.
• Sleeves or casings shall tie placed around the pile top If the pile cut-off
elevation Is above the surrounding groirod surface elevallon.
• Reinforcing steel cages or central bar sftall t>e supported to prevent settling
below the planned elevation.
c) After concreting up to the lop of the temporary steei casing in the firs! ooncrele
pouring stags, the temporary steei casing shall be pulled out about two meters.
And then, the concrete shall be refilled into the temporary steel casing up to
top of the temporary steel casing.
d) The temporary steel casing shall be pulled out very slowly
Status
The piling work is facing infeasibility to bore the remaining 20-300 with casing due to the solid geographical condition, and the casing
keeps getting stuck while the work sequence is. around 770-7900to be bored by the auger bit in advance, then the casing attached
with diamond ring bit bores the remaining 20-300 VPCI figured out during the boring that surrounding actual geography is Guadalupe
condition consisted of high density limestone & coral, dornick that is not feasible to tie bored by casing ring bit
Technically casing is not required for the solid geographical condition and also not using casing could maximize the adhesive strength
between the concrete and surface of borehole. The attached T4 air hammer is compressing the borehole surface and the compressed
surface is too solid to additionally absorb the size of casing, unlike the previous H-0305 with typical auger bit which require the casing to
preserve the borehole against potential collapse with loosen soil
VPCI decided to pour concrete in the 1" borehole after observing 4 days since bored, without collapse and any particular change with
loose soil from the bottom without fully covered casing to the bottom due to the geographical condition that eventually stuck the Casing.
Less quantity of soil was emerged than expected volume of borehole after boring which could mean the borehole itself is compressed
and compacted by the function of T4 air hammer bit.
Proposal
VPCI proposes to bore the hole than inspect that the hole is solid enough without any potential collapse and sufficiently bored according
to the tolerable design as per speafication before pouring concrete without casing, in order to flexibly adapt the geographical condition.
Depth and width of borehole shall be measured with a weighted tape by all parties' loint inspection and witness while loose soil shall be
cleaned up in advance if required. Integnty test shall be carried out upon the entire bored piles then insufficient construction shall be
reinforced by engineering analysis or even additional pile according to the project ITP
As the borehole surface is with soil tensile force itself, it could withstand before the concrete is poured within 1.5 hours as minimum even
with extremely soft geographical condition.
NOTE: Owner s response to this TQ does not constitute authorization to perform a change to the Contract. Contractor may proceed in
accordance with the response only on the basis that Contractor agrees that it is not a change If Contractor believes that the response
does constitute a change, Contractor shall notify Owner in accordance with Article 15.0 of Part 111, Section 15 2 and shall not proceed until
authorized in accordance with 15 3 or 15 4
JG SUMMIT
o PETROCHEMICALS
GROUP FLUOR.
Technical Query (TQ)Form
JG Summit Petrochemical
Stage 1 Expansion Project Page 2 of 2
Engineer's opinion
1 There is no such pile casing requirement for the bored piling worir as per our Project specifications And If the collapse of the wall does
not occur, casing is not necessary Purpose of using casing is to prevent collapse of the inner wall
2 Since there is no specification. Engineering deviation could not be issued by TQ but only could support the constructional TQ
3. It is Constructional responsibility to check the actual condition of tjorehole and determine whether to proceed pouring concrete or not.
In addition, visual inspection of the bore hole is one of the most reliable tests
4. Integrity test shall be carried out by Construction's responsibility to check the shape of concreting is satisfactory as per the design
If construction faces difficulties to fully satisfy the integrity test PEC will try to find solution
YOUNGfvCfcVvOO / Civil Engineer
Originator's Name Sung Kwang, Kwak Originator's Organization Civil Manager \J
Date 25'" February, 2020
Requesting Organization Approver Position Approval Signature and Date
Project Manager
SECTION 2: RESPONSE
Response:
' The Contractor's proposal is acceptable for the reasons they have provided
Are the question and response adequate for closure of this TQ? Is there a cost impact due to this TOT
fi^fVes □ No □ Yes □ If YES, MOC required
j^No
Is there a schedule impact due to this TQ? Is it a change in scope?
□ Yes □ If YES. MOC required □ Yes □ If YES, MOC required
^No ^ No
Distribution:
NOTE: Owner's response to this TQ does not constitute authorization to perform a change to the Contract Contractor may proceed in
accordance with the response only on the basis ttiat Contractor agrees that it is not a change If Contractor believes that the response
does constitute a change, Contractor shall notify Owner in accordance with Article 15.0 of Part III, Section 15 2 and shall not proceed until
authorized in accordance with 15.3 or 15.4
CAa JG SUMMIT
O JP PETROCHEMICALS
CyP GROUP METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
METHOD STATEMENT
FOR
JGSUMMfT □ Witnessed
Witnes
[^Reviewed
Reviewed
iwo
A / i
B
26 FEBRUARY
2020
Issued for Review I^H^
15 JANUARY /
A Issued for Review CHL
2020 ACC YHC
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 2 of46
TABLE OF CONTENTS
1.0 GENERAL
1.1 PURPOSE 3
1.2 SCOPE OF WORK 3
1.3 DEFINITIONS AND ABBREVIATIONS 4
1.4 ROLES AND RESPONSIBILITIES 4
1.5 REFERENCES 6
1.6 ORGANIZATIONAL CHART 6
1.7 LOCATION OF WORK 8
1.8 SCHEDULE FOR PILE & FOUNDATION 8
1.9 TEMPORARY SHELTER LOCATION 9
1.10 EQUIPMENT ROUTE PLAN 10
1.11 PILE MACHINE ASSEMBLY AREA 11
TURBINE
JG Summit Stage 1
Rev. B Page 3 of46
Expansion Project
1.0 GENERAL
1.1 PURPOSE
The works to be performed under this section shall include but not limited to the
following activities:
TURBINE
JG Summit Stage 1 Page 5 of46
Rev. B
Expansion Project
1.4.6 Surveyor
1.5 REFERENCES
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 6 of46
r>
. iBI S
j:
i
'■I
I
»^ccwMerTMNaerM.
' i
■gcncfc / * >
/
. 7
• i
poeoo
rwc^ac =cf>
-syitajL^aaa^aFanrHKHucEaagigTEgt^
w -Mtao ^
i I ! ' i ' i I « I 1 ! • 1 • 1 • r~
NOTES
C CONCRETE STPENGTi-
2 DES GN CAPAC-TV OF P LE
A woe pile
a A/AL COMPRESSOR 200 C TON
b HORIZONTAi. 2T 0 TON
C AX At. TENSION 20 0 TON
JG SUMMIT
a P PETROCHEMICALS
CyP GROUP
3*.ni€i 4-'fe IhfOi-g^ I.tnov.nia''
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
Asof09Decembef 2019
JIlJSPHIICORP.
JlyJ!
SITE ORGANIZATION
JGSPG Package 1 Naphtha Crackmg Ejpansiou and Second Stage ofPygas Hydrogenation Project - Batangas
gk CACffJ^fW 1 P 1 p
K H ^JAEVtlKCHa A
tvv aJl~'.<t.VA.£iaUcMS ASPAAHeiV
M M
■n fock730324®rspWcom
msn-ss^ts
?f$46*ca;i6JEk?ee$*o-
11
\l
' ssarjM
1
f
3:>si:-s93
ynei.i92^«iae.c3ir.
UMm ik 1 r^-ii
A ur:F^ce { p 1 P 1p
A i
fl1
EBAO.SBH ^tsesz 5€.U^
1 PC^7S!0, ^AVCft
11
' 03158«0223 Q83-^-aa5
i ebxtn^grnaicom
A -kfapnhKtki^Tito6.cf
jH 'portrs^vtfoLS'r
.*L. i-SeMl
■i 2-W3f-J
IP SttExrwr
moxm
09381213118
^isaho27$g(Tuilcorn :x'%
XdF-13 ^>4.^-19
I p"
ffiKEWi«fEO,=BEFaM«K
TvaAmfK a3£WSC^355
tessasB
Dm
0^
A imry j p
Vete*
8 sc«tiAAU^
1 »S!Z!3S;:3t
rwpcrt.^^ff^s.s3r
i2-4ir-i5
cAa JG SUMMIT
ff jP petrochemicals
QqP group
. N:. 0».'Ougn i.u-iovar.o-;
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
1
la ,ai □ □ 0 D □ □ B \
□
^ O ^1
□ D n □
O ^ "1 i
□ □ □ 0 □ □
□ □ □ 0 □ n' i
U □ D a □
□
n □ □ 0 n □
THIS AREA T T T
a □ o □ □ □
1 A ,..^1 1
cf U
Th ®
o
CIS
j} m
-ji rri pn
EEJ
T] £D
E
°1 HlEZir ii] S 0 0
3 □ !° °| 0 0 0 HQ jE □
CD
E E
3Q a q a al a o o
GO 0 3 ' ' a B a„ oc
a o
- O CZ3 9 J *0 o ra a a
CD Q Q a
' aa a
c=3 O 3 E ^Q 0 T C=1
+ □ CD
<=3 O □'t t'0 Q
k
rrr:
222'Q
. J
H ■ m.nj
1205 o@3300=19800 1205
E 33 752 '
I J
10 I i
U"
Lj lj
~_r "LT ">0" r-J
L. i -
r1;
TIEU N 1,006.497
E 322.552
I r-| fETl
uJ_l^ I
J
cPq jg summit
a P PETROCHEMICALS
Qffi GROUP METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s
VPCI
TURBINE
JG Summit Stage 1 Page 9 of 46
Rev. B
Expansion Project
PILE SCHEDULE
PILE PILE PILE
PILE NO, QTY CUT-OFF EL. TIP EL LENGTH REMARKS
(M) (M) (M)
« OF P»>LE
"rSYMM :
& 3
30TTC*i! RE-SAR
OF PflLf CAP
CX'T-CFF El_
1- LEJW< CCHC.
- D12 rT>T» [
CP
4
f
• •
f
• T T
C9- a B B a
GENERATOR &
GAS TURBINE
REaARL.A.'iTIOUN m t(»
-t — i (it Jjhk
'^S
I , *
\ - ■
/
; 14 -
^ SHvAi
6,..VwaMV
TURBINE
JG Summit Stage 1
Rev. B Page 11 of46
Expansion Project
t h^f
■*krM
•i ~ :*5ih
B ■
GATE
BnflLri^
%'M
U tihf t.'-i r-rt♦ TT-i-t-H
ttr-rt f T
9:9 9
s
flPa JG SUMMIT
a O PETROCHEMICALS
group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
VPCI
-i-' ■ .1 ;■ Xi"'
FOR GENERATOR AND GAS
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 12 of 46
iMUllMt t Ji2000
: ^
lCMP comp
© © © «
© © ©' ,
© « $
WG LUTE 32i»C
cAd jg summit
C jp PETROCHEMICALS METHOD STATEMENT FOR BORED
group
PILING WORK & FOUNDATION WORK
VPCI
FOR GENERATOR AND GAS
TURBINE
JG Summit Stage 1
Rev. B Page 13 of46
Expansion Project
3890 3740
o o 4^j
O Q
vD O
rvj >—1
3700
mm
TURBINE
JG Summit Stage 1
Rev. B Page 14 of46
Expansion Project
o»
o
fOt
PLAN (BARRICADE(
SCAFFOLDING PIPE
scaffolding Clamp
300mmx300mm PRE-FAB
CONCRETE
Q'
'O.
..g: '■i'W'. ,..^1
J
SeCTKON (BARRICAOE)
VAR -S
I
ISOMETRIC VIEW
(BARRICAOE)
I SCAFFOLDING PIPE
+
I t- SCAFFOLDING CLAMP
300mmx300mrn PRE-FAB
CONCRETE
i.r .-Lafcssoji.L." ■ f.
ELEVATION (BARRICAOE)
TURBINE
JG Summit Stage 1 Rev. B Page 15 of46
Expansion Project
Inspection
Rebar cage
fabrication
Inspection
Rebar Cage
inspection installation
Inspection
1®' Concreting
Casing removal
Final Concreting
Inspection
Site clearing
Next Pile
JG SUMMIT
a a PETROCHEMICALS
CqP group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
sVPCI
TURBINE
JG Summit Stage 1
Rev. B Page 16 of46
Expansion Project
a) The platform elevation shall be decided on the basis of the pile cut off level
and ground condition.
b) The ground shall be leveled and made firm for balance of the equipment
and support of working weight.
a) The piling rigs mounted with a crane and shall be set up accurately on the
marked piling position.
b) The piles shall be installed by using a specially developed rotary system
which ensures a minimum disturbance of original soil conditions and
negligible influence to piles already casted.
TURBINE
JG Summit Stage 1
Rev. B Page 17 of46
Expansion Project
c) Full length casing shall only be used when boring in typical soil conditions
without hard stratum (solid geographical condition). In relation full length of
casing is not always necessary even in typical soil conditions when borehole
can retain its shape and this can be visually check on site.
d) In case the screw bit struggles to advance due to the stratum layer, a special
pneumatic jack hammer bit can be equipped, which can be break through
stratum layer.
e) When jack hammer is equipped and being used, the soil is being
simultaneously being compacted into the ground and only the loose soil will
be ejected upward through the auger blade and air pressure.
f) When boring such stratum soil conditions only minimal casing length may be
used to secure the borehole top shape diameter only enough to cover the pile
cut-off EL (+63.03m), but if top portion up to pile cut-off EL drilled w/o minimum
casing and still maintains its cylindrical shape then even minimal casing may not
be used. This is so that refrain from happening of usage of longer/full casing in
non-applicable soil conditions then getting casing eventually stuck up.
Cylindrical shapes are one of the most structurally sound, and strongest,
geometrical shapes it is good at resisting uniform interior or exterior
pressure.
g) During boring in-case some portion of borehole wall has collapsed and
widen due to the force of impact and air pressure through jack hammer.
This is not a concerning issue as the loose soil will be cleaned up prior to
insertion of rebar cage and concrete pouring and for the some widen
portions of borehole it is additionally beneficial over the design, while the
ifio JG SUMMIT
a D PETROCHEMICALS
VgP GROUP METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
sVPCI
TURBINE
JG Summit Stage 1
Rev. B Page 18 of46
Expansion Project
h) The depth of borehole shall be measured with a weighted tape after all loose
soil is cleaned up in the borehole.
i) Once loose soil and design depth elevation is met, rebar cage shall be
inserted.
j) The bored pile shall have verticality of 3% and maximum position tolerance
of 150mm.
m) In-case of due to some conditions and reasons where complete boring and
pouring cannot be performed, Pre-drilling may be performed to expedite the
boring process in advance, borehole shall be pre-drilled of depth and
backfilled again, so that borehole soil is disturbed in advance.
t ,
aPq jg summit
ff jp PETROCHEMICALS
CqP group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
sVPCI
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 19 of46
To ensure total removal of sediments and loose soil particles at the bottom of
each pile, the following steps are taken.
a) When the drilling depth reaches the bearing layer which is defined in the
pile installation criteria, the bottom of the borehole should be leveled.
b) The cuttings, sediments and loose soil particles shall be removed by a high-
air pressure through an air nozzle equipped at the bottom of the auger
shaft. Before pulling out the drilling rig from the borehole, the excavated
materials at the bottom of the hole shall be removed completely by the high
air pressure.
c) The bottom of the hole shall be cleaned by several blows of the high air
pressure to ensure that the excavated debris piled at the bottom of the hole
is removed completely.
d) After cleaning up the hole, a weighted tape is lowered down the bottom of
the hole to measure the drilling depth. A joint inspection by the contractor
and owner's engineer is required to be performed to verify the depth and
diameter of the hole, and the verticality of the hole.
e) The excavated materials from the borehole should be disposed properly at
the designated area.
i-# -sr
■■
TURBINE
JG Summit Stage 1
Rev. B Page 20 of46
Expansion Project
a) Rebar cage shall be fabricated at designated area within the site boundary.
Rebar cage may also be transported by crane to site with limited space to
allocate fabrication yard. The fabrication shall be in accordance to
approved drawings for construction.
b) The rebar cages shall be rigid enough to prevent deformation during lifting
by placing stiffeners within the cage. Lifting point of sling belt shall be
reinforced with additional tie rods prior to installation of shackle. This shall
identify by the rigger on where to put/hook the sling for lifting. Additional
binding string installation if required.
e) Always keep clean at rebar cage fabrication area. Rebar cages shall be lifted by
crane of sufficient capacity with the use of appropriate lifting gears. The lifting
points shall be reinforced with additional tie rods prior to installation of shackle.
f) Movable Scaffolding to be install around the Bore Hole pile prior to proceed
the inserting of rebar cage. The rebar cage shall be inserted slowly into the
borehole in order to avoid damage to the spacers and lowered down until
the design elevation of top rebar is met, if necessary chain block to casing
top shall be used to secure the correct rebar cage elevation. Inspection of
inserted rebar cage to be conducted as per ITP plan.
In case the rebar cage is divided into two segments due to the extensive
length. The bottom segment of the rebar cage shall be left to extended out
of the casing and suspended by crossing two re-bars across the reinforced
section then the top segment shall be inserted on to the bottom segment to
be joint together by reinforcing with splicing the main bars with tie rod, once
the two segments are securely joint together then the rebar cage set shall
be lowered down to its design elevation into the borehole.
cAa JG SUMMIT
C P PETROCHEMICALS
CqP group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 21 of46
i\
vump*em m
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 22 of46
e
Trtl tfinq M Cfyipin^ iO(*(ion
kxjbon iOufvtf*- • Iniid*)
and tfutkJ* ttmomi
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 23 of46
0
lift up * Wtl*
Fnong thng M
by (tM< pm
Mntov* StMf
0
biMit tfM r*6*r tmft
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 24 of46
b) The concrete is poured through pump car under the water concreting
method that the water inside the borehole is displaced by concrete.
c) The pump car may be supported by the boom truck for the assistance to
the concrete piping for pouring activity.
d) After concreting up to the top of the temporary steel casing in the first
concrete pouring stage, the temporary steel casing shall be slowly pulled
out from the borehole. And then, after removal of the steel casing and for
the final stage concreting, depending on the pile cutoff elevation in
relative to the EGL the concrete shall be poured and topped up with the
excess concrete volume up to 1m~1.5m above the pile head cut-off
elevation or incase EGL may be reached within the 1m~1.5m level the
equivalent volume of the excess concrete for pouring, then it shall be
poured to let it to overflow such volume to ensure quality of the pile, and
it shall be witnessed by the QC engineer.
® *M !ing by auotr :*k«> mum) <S> instaHiflo' (?) pour ing ooncrsta in stsp
by stap
<3^ ifiMrtino casing by ciroulatlon
m4 piah <ktf ing txc
-H IS
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 26 of46
a) When extraction of casing failed due to the inadequate length was used in
relation to the soil conditions, cutting of casing shall be perform by grinder
or oxy/gas cutting enough to expose initially the GL as soon as it is
needed, then during pile hacking up to the pile cut-off EL.
1. When the pile installation has satisfied the Specification requirements, the
concrete of the head of the pile shall be cut off to the level specified.
3. Surroundings of a pile shall be ground in 10 ~ 15mm depth along withthe cut off
level if necessary.
4. The pile shall be broken down to the ground line by breaking machines & concrete
cutter / grinder (7").
7. Care shall be taken to avoid shattering or otherwise damaging the rest of the
pile. Any cracked or defective concrete shall be cut away and the pile repaired
to provide a full and sound section to be cut-off level.
8. Removal of concrete and expose reinforcing steel Bar with specification drilling fluid or
soil is exceeded and that the pile is neither in section nor contaminated.
9. The concrete level within a temporary casing shall be topped up where necessary during
oPq jg summit
a JP PETROCHEMICALS
CqP group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
VPCI
FOR GENERATOR AND GAS
JG Summit Stage 1 TURBINE
the course of casing extraction in such a way that the base of the casing is always below
the concrete surface until the casing of the pile has been completed.
10.Adequate precautions shall be taken in all cases where excess heads of water drilling
fluid could occur as the casing is withdrawn because of the displacement of water or
fluid by the concrete as it flows into its final position against the walls of the pile bore.
TURBINE
JG Summit Stage 1
Rev. B Page 28 of46
Expansion Project
Records for the installation and length of each pile shall be kept and the details
to be recorded.
1 Cargo Truck 1 EA
2 Crane 50 tons 1 EA
5 T4 Hammer D800 1 EA
6 Compressor 25bar 2 EA
8 Water Truck 1 EA
9 Backhoe 1 EA
10 Pump car 1 EA
11 Mixer truck 3 EA
TURBINE
JG Summit Stage 1
Rev. B Page 29 of46
Expansion Project
17 Chipping Gun 4 EA
18 Jackhammer 4EA
■* : 1
i ' •
_...EQUlJ?MEfeHdLIOOLS . , ,_.I3TY.a!
1 Backhoe 1 EA
4 Welding Machine 2 EA
7 Pump car 1 EA
9 Viixer truck 2 EA
! ITEM QTY J
1 Construction Manager 1
2 Site Engineer 1
3 Surveyor 1
4 QA/QC Engineer 1
6 Equipment Operators 4
7 Foreman 2
8 Riggers 4
9 Watchman 4
10 Survey Aide 3
11 Skilled worker 15
1 Construction Manager 1
2 Site Engineer 1
3 Surveyor 1
4 QA/QC Engineer 1
6 Equipment Operators 4
7 -oreman 3
8 fdiggers
4
cPd jg summit
a JP PETROCHEMICALS METHOD STATEMENT FOR BORED
GROUP
PILING WORK & FOUNDATION WORK
3- \ ! iiiOvJl;on VPCI
FOR GENERATOR AND GAS
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 31 of46
9 Watchman / Flagman 3
10 Survey Aide 3
11 Steeiman 8
12 Mason 5
13 Carpenter 5
14 Scaffolder 10
15 Welder 4
16 Electrician 2
17 Helper 15
1.1 INTRODUCTION
This section presents the general statement of the methodology and procedures to be
implemented in the execution of the pile Integrity test for the project in conformation
with the technical specifications requirements. This section describes the principles of
the work, details of work sequence, equipment, and materials.
5.1 INTRODUCTION
This section presents the general statement of the methodology and procedures to be
implemented in the execution of the pile integrity test for the project in conformation
with the technical specifications requirements. This section describes the principles of
the work, details of work sequence, equipment, and materials.
flPa JG SUMMIT
Cl D petrochemicals
CqQ group
dercvi .. .ti.' fr.oujf. . ' u.ir.i:-,'
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s
VPCI
TURBINE
JG Summit Stage 1
Rev. B Page 32 of46
Expansion Project
5.2 MATERIALS
5.2.1 Water
Water used for the concrete will be clean, free from quantities of soil, and
organic matter and shall comply with the technical specification.
5.2.2 Concrete
A steel casing is used to stabilize the excavated hole, and it support whenever
necessary depending on the ground condition or if required will be used and
shall be in accordance with the technical specification.
5.2.5 Spacers
Rebar spacers will be used as centralizers. This will be installed on the spiral
reinforcement of the cage during fabrication.
CAa JG SUMMIT
ff jP petrochemicals
QqP group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
TURBINE
JG Summit Stage 1
Rev. B Page 33 of46
Expansion Project
Quantities
Type of Test ASTM Protocol
Production
Test Piles
Piles
Low Strain Test(PIT) -
14 ASTM D 5882
CAa JG SUMMIT
tt jp PETROCHEMICALS
PgP GROUP
3eU'C'r ..:T' ■ • 'jf 1 M 'ovat'..
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
sVPCI
TURBINE
JG Summit Stage 1
Rev. B Page 34 of46
Expansion Project
A. Introduction
This method of testing covers the procedure of testing the integrity of the piles
against cracks, voids, portion of low quality of concrete, bulging and necking. The
TDR-2 pile Integrity tester has a dual purpose: To estimate the length and general
dimensions of the pile using an echo testing technique complying with ASTMD 5882-
96(1). (Pile Integrity Test shall be performed in all 14 Bore Pile).
a) To check for the presence of defects within the pile by assessing its
characteristic mobility changes in mobility within the body of the pile are
identified by observation of resonating peaks (standing waves). These
peaks are determined by the natural vibrational frequency of the pile.
b) Increases/ decrease in pile cross section (bulging or necking)
c) Cracking
d) Voids
e) Zones of weak, low density or otherwise poor quality concrete.
B. Test Apparatus
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 35 of46
C. Test Procedure
The pile head should be thoroughly cleaned and all loose debris removed by
blowing compressed air across its surface. Two flat areas of surface (scab bled
flat if necessary) are selected; one towards the outer edge of the pile head to
locate the geophone; the other close to the central axis of the pile to receive
impact from the instrumented hammer. The surface area selected for impact
should be located so that the hammer travel is at least 600 mm before contact
with the concrete. Contact between geophone and concrete surface is ensured
using heavy grease or other suitable transmission medium for the input and
reflected signals.
cAq jg summit
a jp PETROCHEMICALS
GROUP
TURBINE
JG Summit Stage 1
Expansion Project Rev. B Page 36 of46
b. Testing Procedure
TURBINE
JG Summit Stage 1
Rev. B Page 37 of 46
Expansion Project
Viewing the mobility trace in the data assessment of mobility data: This
may be the mobility/frequency spectrum for individual hammer blows
or the mean performance derived from four blows. Examination of the
peaks present on the mobility trace enables the experienced operator
to make an initial interpretation of pile characteristics. Where potential
anomalies are detected, the tests are repeated and referenced as
suspect and subject to further analysis:
Viewing the velocity trace in the data acquisition unit allows preliminary
field assessment of pile length.
AccetefOTefe-
i.'
^ 1
op
A load test report on Pile will be submitted after the completion of test in accordance
with Specification. The observations and analysis of all tests are analyzed and
interpreted in the final report to be submitted to the Contractor.
cPq jg summit
a JP PETROCHEMICALS
QgP GROUP
^ ' » lAj! 1 .•iovat;c?
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
v3
VPCI
TURBINE
JG Summit Stage 1
Rev. A Page 38 of 46
Expansion Project
START
(SAFETY MEASURES)
I
PRELIMINARIES
1. Pre-con Survey Works
2. Site Measures
3. Clearing & Grubbing
4. Stripping of top soil
5. Soil Improvement
Work
1 Permit
Inspection before
Survey
Execution
Works
Excavation Works
(Leveling of soil)
Lean Concrete
Form
"Rebar Works
works/Shorino
Anchor Bolt
Setting
Concreting
Concrete Test ^ 4.
Works
Curing Protection
Stripping of Forms
Works
Backfilling of
Structures
FDT
Finish
GENERAL WORK
rwikt
cAb JG summit
tt jP petrochemicals
Xllfff GROUP
teller 'ii-ougn Lmovdnon
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s
VPCI
TURBINE
JG Summit Stage 1
Rev. A Page 39 of 46
Expansion Project
6.1 Preliminaries
Methods Statement for the cited preliminary activities and/or pre-requisites as itemized in
the General Procedures is discussed in each separately submitted method statement.
Once preliminary activities has set, accomplished, and accepted by the Engineer and/or
owner's representative, inspection prior to undertaking the major activity commences.
Excavation works for the Generator and Gas Turbine foundation shall be undertaken using
a backhoe. Manual trimming & leveling is required so that cast in place piles will not be
damaged. Survey and lay-out must be finalized the elevation required prior to inspection.
The concrete works for the Foundation comprises of the Leveling Concrete, Mat
Foundation and Pedestal.
The required concrete compressive strength is 24 MPa in 28 days using cement C150
type-1. Design mix proposals and approval is part of the preliminary works.
TURBINE
JG Summit Stage 1
Rev. A Page 40 of46
Expansion Project
Before concrete works, subgrade visual inspection shall be conducted to verify the
subgrade meets design requirements.
Concrete Pump Car, Backhoe or Chute shall be used for the pouring. The compressive
strength of lean concrete as specified in the design criteria would be 10MPa @ 28days,
using type 1 cement.
Mixer triick:
Concrete deiivery
from batcNng
piant
Concrete Pi*np
truckrTransf^ring
concrete by pumping.
-Si
Prior to formworks installation, Contractor shall establish survey points on top of lean
concrete. For checking of pedestal location, establish survey point on top of footing.
Pre-fabricated forms shall be used for the formworks, which shall be fixed on position
with vertical and horizontal supports (shoring), ensuring the joints shall be free of
leakages of grout. In cases, the design requirements calls chamfer, the fillets shall be cut
to provide even lines.
Form works and supports are to be cleaned and coated with an approved release agent.
The release agent must not have contact with placed concrete and reinforcement.
Material approval for the release agent is under the preliminary works.
cPd jg summit
ff jP petrochemicals
GqQ group METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
TURBINE
JG Summit Stage 1
Rev. A Page 41 of46
Expansion Project
wm
FORM WORKS
Formwork &
Scaffolding
works.
staging work.
Crane; Loading
& unloading of
k 'Ji
I Rebar installation.
\\
A \
TURBINE
JG Summit Stage 1
Rev. A Page 42 of46
Expansion Project
6.3.5 Reinforcement
Reinforcing steel bars as called for in the drawings for construction/ reference is
deformed and in accordance with ASTM A706 Grade 60 or equivalent. Rebar cutting and
bending schedule is a supplemental submission under the preliminary works.
Rebar installation and fixing in position of the entire reinforcement requirement shall
adhere to ASTM standards.
Mixer truck:
Concrete delivery
from batching
plant
CorKrete Pump
truclcTransferrir^
concrete by pumpir^.
/ l-A
Concrete Area
TURBINE
JG Summit Stage 1
Rev. A Page 43 of46
Expansion Project
Prior to placing concrete, reinforcement and embedded items needs assurance of proper
fixings and approval to proceed to concrete pouring is secured.
As shown in Figure 5, the concrete sequence shall be cast into 3 stages including lean
concrete.
Anchor bolts shall be installed within the acceptance criteria. Location and elevation of
bolts shall be within ±3mm. Plumbness shall be within a maximum tolerance of 2°.
All materials shall be inspected by VPCI & JG SUMMIT OLEFINS CORPORATION before
using @ site. This material shall pass according to the specification specified in the
drawing. All materials must also free from rust, the thread must be well protected against
corrosion & properly store using wood as a support.
All materials to be used must place near the area to be installed. If not install the
same day of the delivery to site, cover the materials to protect against rain &
damage. Materials must be supported by wood during lifting to the area.
Lay-out must be done by the surveyor using total station as per approved drawing. Mark
the exact location & orientation of anchor bolts to be installed.
JG SUMMIT
tt D PETROCHEMICALS
QqP group
;5t* ii?f 'h<Ough innovdtioi.
METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s
VPCI
TURBINE
JG Summit Stage 1
Rev. A Page 44 of46
Expansion Project
Set the anchor bolt supported by rebar bracing. Install the plate, ring & nut as specified in
the drawing. Welded re-bars as a support for the bolts so that it will not move while
concreting. Make sure that the location of anchor bolt is correct before fixing (welding).
Survey checking must done after installation of anchor bolt to make sure that it complies
the specified elevation & alignment of anchor bolt in the approved drawing.
Provisions for standby of critical equipment are necessary to ensure continuous and
smooth pouring operation in the event of equipment breakdown.
Adequate lightings are necessary during night time where mixing, transporting, and
placing is in progress.
• Never throw stripped material to the ground from a work platform. Always lower it by
passing it to a co-worker or by another controlled method.
• Ensure that stripping area is clean to avoid slips & trips.
• Inspect footing, pedestal and remove any loose concrete or debris.
cAq jg summit
a D PETROCHEMICALS
Vhgff GROUP METHOD STATEMENT FOR BORED
PILING WORK & FOUNDATION WORK
FOR GENERATOR AND GAS
s VPCI
TURBINE
JG Summit Stage 1
Rev. A Page 45 of46
Expansion Project
• When stripping, always wear gloves and safety eye wear to protect against cuts, pinches,
scrapes & injuries from debris.
• Never strip forms unless you have verified that the concrete strength is sufficient.
Concrete shall be protected immediately after placing and texturing from sunshine and
drying winds by shading and windbreaks, and from cold, rain or running water after placing,
for a curing period of at least seven (7) days after placing.
Water used during curing operations shall be fresh water. The concrete surface shall be
covered with moist hessian (burlap) or any approved curing material. The material shall
be periodically moistened with water misting or spraying making sure it is always damp
during the curing period.
Maintain all existing site access, roads, foot path and reinstate any damaged caused by any
reason whatsoever during the construction work.
Ensure that ingress and egress to the site are kept free from obstruction brought about by the
construction of shoreline protection and in no way cause hindrance to any traffic or ancillary
works.
Any damage to existing utilities and/or adjacent structure shall be repaired as original.
TURBINE
JG Summit Stage 1
Rev. A Page 46 of 46
Expansion Project
Subcontractor will install waste trash bins for different type of wastes at a designated area
approved by JG SUMMIT OLEFINS CORPORATION. The location will be discussed later.
Shelter will be erected beside the working area