PROJECT: TAPIS EOR BROWNFIELD MODIFICATIONS & RETROFITS

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D

WEEKLY ENGINEERING PROGRESS REPORT NO #06 WEEK ENDING: 9th NOVEMBER 2012

CLIENT: SHAPADU ENERGY & ENGINEERING SDN BHD

0 R

9 D

ISSUE FOR APPROVAL PREPRE APPROVED BY ED BY ULTES APPROVED BY IEV

DESCRIPTION

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

1.0 MANHOURS PREVIOUS CUMULATIVE NIL

MAN-HOURS WORKED ULTes

THIS WEEK 9th NOVEMBER 2012

TOTAL CUMULATIVE

2.0 PROGRESS ACHIEVED FOR THE WEEK a. Process List down the redundant equipment for Tapis-A base on master equipment list

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

Locate all the redundant equipment for Tapis-A listed in master equipment list with the equipment layout. Finding: some of the equipments cannot be find in the equipment layout Need conformation from SEEN Finding: Some of the process drawings related to redundant equipment not provided. SEEN to provide the remaining drawings.

Compare the redundant equipment for Tapis-A listed in master equipment list against process drawings.

b. c.

Structural Literature Review for Structural Mothballing Pipeline Preparing Make Safe and Mothballing of Redundant Pipeline report

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

d.

Electrical Drawing review and information interpretation. (continue) Discussion with engineering team leader for the data findings. (continue weekly basis) Identify and listed of equipment/facilities to be preserved/mothball. (continue) Finalized for the report format (draft) for E&I and other discipline.

e.

Instrument Drawing review and information interpretation. (continue) Discussion with engineering team leader for the data findings. (continue weekly basis) Identify and listed of equipment/facilities to be preserved/mothball. (continue) Finalized for the report format (draft) for E&I and other discipline.

f.

Mechanical

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

g.

Preparing Make Safe and Mothballing of Redundant Equipment report

Piping

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

3.0 WORK PLANNED FOR NEXT WEEK Process Finalize the list of redundant equipment for Tapis-A List down the redundant equipment for Tapis-C Locate all the redundant equipment for Tapis-C listed in master equipment list with the equipment layout. Compare the redundant equipment for Tapis-C listed in master equipment list against process drawings.

Structural Preparing structural mothballing and demolition report.

Pipeline

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

Awaiting for requested documents

Electrical Discussion with team leader regarding the SOW in details. (continue) Information review and study for further understanding (continue) Finalized and preparation on the draft format report for E&I.

Instrument Discussion with team leader regarding the SOW in details. (continue) Information review and study for further understanding (continue) Finalized and preparation on the draft format report for E&I.

Mechanical Continue working on report

DEMOLITION STUDY FOR TAPIS EOR PROJECT TAPIS A, B, C AND D WEEKLY PROGRESS REPORT NO #06 WEEK ENDING : 9th NOVEMBER 2012

Piping

4.0 INFORMATION REQUIRED

5.0 ATTACHMENT