TECHNICAL TENDER
Table of Contents
1. MOBILISATION
2. CONSTRUCTION MANAGEMENT
3. CONSTRUCTION SCOPE
4. PRE-MOBILIZATION
5. SECURITY
6. MOBILZATION
7. LOGISTIC
8. WORK METHOD STATEMENTS
9. PRE-COMMISSIONING AND COMMISSIONING
10. Mechanical Completion
11. Commissioning Team
12. Pre-commissioning Audit
13. Commissioning
14. Demobilization
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
1.2 Objective
The objective of this Execution Plan is to detail the method to be implored by MICRENCH
GLOBAL RESOURCES LTD in the execution and construction phase of this Project that will
ensure a safe, quality and timely delivery of the project within estimated budget.
1.4.1 Objectives
MICRENCH Project objectives for the LOCATION PREPARATION AND ACCESS ROAD CALL-
OFF CONTRACT are as follows:
To successfully deliver safe, cost effective and sustainable project.
To ensure Design, Technical and Operational integrity of the project.
Safeguard reputation as a safe and professional Oil, Gas and Energy Contractor.
Execute the project, safely on schedule and within contract value.
HSE
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
No harm to people.
Zero LTI.
No harm to the environment.
No damage to assets
Integrity
To provide safe, available and reliable facilities that will provide effective and
desired performance within the operating life.
Reliability
Achieve operational reliability and availability target of 99%.
Cost
Complete project within the agreed costs
Schedule
Completion of work scope within planned execution period.
Quality
Conform to Seplat and all the project envelopes, standards, specifications
and guidelines.
Successful commissioning
Reputation
Enhance reputation as a top quartile, indigenous oil, gas and energy contractor.
All matters related to the general supervision and management of the project,
Liaison with Clients in respect of all matters associated with the works,
All matters related to Engineering, Procurement, Fabrication, Construction and
installation
All matters related to cost control,
Controlling the project schedule to ensure timely and economical completion,
Ensuring construction, operations and materials are in compliance with project
requirements, the quality assurance requirements and the detailed procedures and
instructions,
Ensuring that the prescribed project requirement are properly implemented,
controlled and effectively documented,
Ensuring that effective corrective actions are taken on identified problems,
Stopping work any time the quality of work is in question,
Issuance of weekly and monthly report
Ensuring that managers and supervisors are aware of their HSE responsibilities
Carrying out regular inspections of site and work places to determine whether work
is being carried out in accordance with health and safety procedures.
Carrying out quantified safety audits in accordance with procedures.
Carrying out accident/incident investigations in accordance with the
Accident/Incident reporting procedures and analyzing all data, making
recommendations to the Construction manager to avoid any recurrences,
Carrying out induction training and identifying any additional training requirements
Ensure that all statutory inspections/examinations are carried out as required.
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
Mobilisation
New Well site Location preparation for drilling
Rehabilitation of existing Well site Locations
Location access road construction and rehabilitation
Campsite construction and rehabilitation
Piling works
Bridge works
Marine structures
Jetty, sheet piling, shore protection construction
Equipment Foundations for greenfield and brownfield projects
Structural Steel Works
Civil infrastructures including Drainage, Landscaping, Fencing
4.0 PRE-MOBILIZATION
Before mobilization of personnel and equipment to site, the following shall be carried out.
4.1 PREMOB
A comprehensive list of all the equipment to be used shall be provided for client scrutiny and
approval. They shall be made available for Client to premob. It is only those that pass Client
premob that will be used/transported to site for use.
43 Work permits
JHA’s and permit to work shall be developed, reviewed and approved for the construction
activity before mobilization to site
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
4.4 Induction
Safety induction shall be conducted for all the personnel that will be engaged for the
construction work activity before mobilization to site. All the personnel shall be properly
inducted with regards to the nature and volume of jobs to be carried out, the 12 life saving
rules, culture and tradition of host community, safety and environmental precautions to be
taken in a water borne operations and security implications
4.5 Temporary accommodation and site office
Prior to full mobilization, a pre-mobilization crew will be sent to ensure that the temporary
accommodation and site office are properly installed, equipped and made ready for use.
5.0 SECURITY
The assessments of the security hazards, threats, risks and possible incidents, that personnel
and equipment will be exposed to during the various stages of the LOCATION PREPARATION
AND ACCESS ROAD CALL-OFF CONTRACT will be carried out. Adequate control measures will
be put in place to ensure security of life and property throughout the entire construction.
These control measures are contained in a separate deliverable document titled “Security
Plan”. This document shall be submitted to SPDC for review and approval before mobilization
6.0 MOBILZATION
The equipments, materials and personnel required to achieve the contract activities will be
transported to project site.
7.0 LOGISTIC
The project shall utilize vehicles/buses/trucks for road transportation of personnel,
materials and equipment while speedboats, barges, tug boats shall be used for marine
loaded beyond their capacities. There shall be no night sailing or driving. All journeys must
7.1 ACCOMMODATION
The accommodation shall be equipped with beds, air-conditioners, toilets, lighting system
and recreational facilities etc. in line with Client requirements. Messing facilities shall be
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
provided to serve food three times daily. This facility shall be well equipped with well
ventilated kitchen that will have cooking utensils. The services of a catering company shall
be engaged during the project execution period. The catering service shall be in line with
Client requirement.
Handling:
Materials will be handled both manually and mechanically depending on their sizes, shape
and weight.
All materials handling equipment/accessories shall be pre mobbed and certified okay before
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
Receiving
At the receiving stage the material shall be verified by the Material Co-ordinator, for the
quantity, and by Q.C. Inspector, for the quality.
After the successful verification the “Material Received Inspection Report” shall be issued
and signed by both the above-mentioned persons.
If any discrepancies arise about the quantity of materials, the Client shall be informed
through letter, if the material is damaged and/or it is not in compliance with the certificates,
a Non Conformance report shall be issued.
Storage
The material shall be stored indoor or outdoor depending on their type. Different materials
shall be kept separately, and in such a way to allow an easy access for retrieval and handling
operations which shall be carried out with suitable means in order to avoid any kind of
damages.
The withdrawal of materials shall be performed with controlled system. It shall be done
through the withdrawal voucher only, issued and signed by authorized personnel. Copy
of voucher shall be given to the planner for material status updating.
Prior to site fabrication, design shall be carried out, drawings, procedures and
specifications shall be submitted to Client for approval. Approved welding procedure
specification (WPS) shall be used in conjunction with the approved for construction
drawings shall be used for fabrication.
During assembly, alignment and level shall be checked with appropriate tools.
Equipment shall be grouted to minimize vibration.
7.7 CONSTRUCTION SAFETY
The construction manager shall ensure that construction activities are performed in
conformance with project requirements using qualified procedures and skilled personnel,
and assuring that the required level of quality of workmanship is maintained throughout
the construction process.
The site safety officer shall ensure that safety and environmental rules are obeyed
Tool box talks shall be held on a daily basis to ensure that the activities of the day are well
understood by all and that all necessary precautions and barriers are in place
Adequate PPE shall be provided and the use enforced and monitored.
7.9 TRANSPORTATION
Control of transportation activities such as loading, road transport, river transport, in-
plant movement, off-loading and their associated safety requirements will be organized,
executed and monitored in accordance with detailed plans to ensure ease of operation.
Client premobed vehicles shall be engaged to convey the required materials, equipment and
personnel between office and the Jetty. Premobed boats, barges and tugboats will be used
to do the marine transport. There will be dedicated boats to convey workers.
8.1 CIVIL
Procedure
Site preparation
The Sites shall be cleared of grasses, trees, stems and, any other obstructions.
Site surveys
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
MICRENCH shall carry out Reconnaissance survey of the various sites to obtain information which
shall not be limited to the followings for design purposes The general topography of the sites as it affects
the foundation design and construction.
The location of buried facilities such as pipelines, electric and telephone
Cables, water mains and sewer lines
The general geology of the sites with particular reference to the main geological formations underlying
the sites.
Information on tide ranges, extreme high and low tide ranges and river levels, seasonal river levels and
discharges.
A special feature of the sites such as flooding
Rotary drilling:
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
This is a procedure by which rapidly rotating drilling bit attached to the bottom of drilling rod cut and
grind the soil and advance the bore hole down. Water is forced down the drilling rod to the bit and the
return forces the cutting to the surface.
Soil sampling
The soil that shall be recovered from boreholes are:
Disturbed samples
Undisturbed samples
Soil samples shall be taken at interval of 1.5m and at each change of strata in the bore hole. The soil
samples shall be kept in sample can and, labeled to give borehole number, the depth, a description and
covered to avoid loss of moisture.
The main objectives associated with ‘pre-commissioning’ are focused on inspection and
acceptance at the manufacturers premises and plant tests on site after mechanical completion.
Pre-commissioning shall also identify any inherent problems, define the nature of such problems,
and expedite responses from the appropriate parties to ensure that there is no impact or
detrimental effect on the commissioning phase. Factory Acceptance Tests (FAT) will be
maximised and where possible be integrated tests on the full functionality. The FATS will be
witnessed by the Client.
Pre-commissioning encompasses all the required checks, simulations, tests that could be carried
out to confirm the functionality of a system, or the permanent energising or pressurising of a
system.
MICRENCH Engineering shall prepare a complete set of pre-commissioning check-sheets for all
installations in the project, which will contain all test results for all the pre-commissioning tests.
These will be completed by MICRENCH Engineering and accepted by Client as pre-
commissioning activities progress.
The initial pre-commissioning tests shall involve hydraulic, pneumatic, electrical and other field
tests as are specified or are necessary to demonstrate that the various sections and components of
the work have been constructed in accordance with the Design and Job specifications. Specific test
activities shall typically include, but not be limited to:
Hydrostatic, pneumatic, strength or other non-destructive testing of all pressure
containing parts of the system.
Testing of all electrical system components including power management s y s t e m s
interface, Switchgear system, starters, transformers, battery systems, motors, Generator & power
supply network, Earthing system, etc.
Mechanical run tests / string tests / performance tests at the vendor’s works.
Calibration and testing of all instruments including those installed on packages or skids.
Testing of power and instrument cables (continuity tests).
Completion of appropriate test sheets and documentation.
Cleaning, flushing, draining, blowing out and drying out of vessels and piping systems
and the installation & removal of temporary blinds used for isolation and testing of joints, as
necessary.
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
Replacing control valves, relief valves and orifice plates as removed for above.
Replacement of gaskets, tightening of flanges, etc.
When these activities have been carried out to the satisfaction of Client, the equipment and / or
system will be ready for the next stage of pre-commissioning which is to prove that:
The equipment and systems are fit and safe and ready to be put into operation with
the intended service fluids, power sources, etc.
MICRENCH shall furnish and install all components, accessories, preservatives and any other
consumables necessary for operation of the entire facility.
A check list will be developed and all actions recorded to ascertain readiness to proceed with
hydrocarbon introduction. A detailed operational review will take place with “customers” to
verify readiness.
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
During all phases of commissioning, including the live testing of equipment, the intention is to
integrate operations staff within the commissioning group. During this phase of the works, the
lead commissioning engineer shall liaise on a day-to-day basis with the operations on all matters
which relate to live commissioning.
To ensure that commissioning works are carried out in the most appropriate manner, the
commissioning group shall put in place the necessary plans, controls and deliverables, and shall
arrange the necessary resources, in order to achieve the overall common objective of
commissioning, start-up and Handover of the facilities as soon as is practicable.
MICRENCH shall implement all recommendations of the audit which affect the work. The
implementation of any recommendation shall not absolve the contractor from any of its
responsibilities under this contract. If the contractor has an objection to implementation of any
recommendation, then he shall advise Client in writing of his objection.
13.0 Commissioning
MICRENCH shall carry out detailed commissioning exercise of all installations. This shall
demonstrate that the functionality and operation is as per design.
Appoint a Commissioning co-ordinator who shall be responsible for all aspects of design
liaison, planning and co-ordination of all commissioning and completion activities.
The commissioning co-ordinator shall be suitably qualified and experienced in the
co- ordination of commissioning.
TENDER No:
ITT FOR LOCATION PREPARATION AND ACCESS SEPLAT/LAG/ITT/2021
ROAD CALL-OF CONTRACT FOR SEPLAT /ENG/139598
WESTERN ASSET FOR OML 3, 38 AND 41 (CALL
OFF CONTRACT)
TECHNICAL
TENDER
MICRENCH shall also integrate client operators and maintenance personnel into his
organisation.
13.2 Client’s Role
Client staff shall assist in the commissioning and Initial Operation, in accordance
with the commissioning plan.
14.0 Demobilization
All personnel mobilized for this project shall be demobilized and taken back to base
upon a successful completion of the project.
Dismantling and evacuation of contractor spread from site and Site Restoration: - Any
temporary structure erected during the construction phase of the project shall be dismantled
and promptly removed from the site and taken to MICRENCH.
Boats, equipment/tools and storage caravans or empty containers used for the execution of
the project shall be promptly removed from the work site and taken to MICRENCH base
after a successful completion of the project.