This document describes the lift slab construction method. It involves casting concrete floor or roof slabs on top of each other at ground level and then lifting them into place with jacks as construction progresses vertically. Key advantages are that it eliminates formwork and allows work to be done at ground level, making construction faster and cheaper for buildings with uniform, repetitive designs up to around 16 stories tall. Some important limitations are that it is not suitable for very tall buildings or large span slabs.
This document describes the lift slab construction method. It involves casting concrete floor or roof slabs on top of each other at ground level and then lifting them into place with jacks as construction progresses vertically. Key advantages are that it eliminates formwork and allows work to be done at ground level, making construction faster and cheaper for buildings with uniform, repetitive designs up to around 16 stories tall. Some important limitations are that it is not suitable for very tall buildings or large span slabs.
This document describes the lift slab construction method. It involves casting concrete floor or roof slabs on top of each other at ground level and then lifting them into place with jacks as construction progresses vertically. Key advantages are that it eliminates formwork and allows work to be done at ground level, making construction faster and cheaper for buildings with uniform, repetitive designs up to around 16 stories tall. Some important limitations are that it is not suitable for very tall buildings or large span slabs.
SYSTEM INTRODUCTION Lift Slab Construction is a method of constructing concrete buildings by casting the floor or roof slab on top of the previous slab and then raising it.
This method is cheaper and faster as it does not need
forms and shores as it is needed for cast-in-place slabs.
Can be more economic than conventional construction
when the building is vertically uniform and where the slab designs are repetitive. This method of construction allows for a large portion of the work to be completed at ground level, negating the need to form floor work in place.
Height- up to about 16 stories.
Economical column spacing- 22 to 32 feet. Type of columns- pipe,tubes,flange sections.
Concrete columns may be used in 3 to 4 storey buildings.
HISTORICAL BACKGROUND Invented and developed in the early 1950s by a collaboration of Phillip N.Youtz and Thomas B.Slick.
Johnstone Hall, a Clemson University dormitory in
Clemson, South Carolina, was erected using this method in 1954.
Was also involved in the L’Ambiance Plaza collapse in
Bridgeport, Connecticut, in 1987. L’Ambiance Plaza collapse
Johnstone Hall, Clemson University
CONSTRUCTION SEQUENCE Lifting collars are cast into each slab around each column. The first floor slab is cast inside edge formwork on top of the ground floor slab and when it is mature it is in turn coated or covered with the separating medium and next floor slab is cast on top of it. The casting of the other slabs continues until all the floors and roofs have been cast one on the other on the ground. The slabs are lifted by jacks, operating on the top of each column, which lift a pair of steel rods attached to each lifting collar in the slab being raised. A central control synchronises the process for a uniform lift from all directions. The sequence of lifting slabs is influenced by the following: 1) Weight of the slabs. 2) Height of the building. 3) Lifting capacity of jacks. 4) Cross sectional area of columns during initial lifting. TOOLS AND MATERIALS ADVANTAGES Lift-slab construction method becomes more advantageous in buildings with similar floor plans throughout the height of the building and where flush slab may be desired. This method eliminates the need for redundant formwork as only shuttering required on the edges, therefore casting concrete slabs is the simplest stage in whole construction process of lift-slab method. Lift-slab method may be employed with ribbed slabs not only flat slabs with some compromise of the ease of casting. Another advantage is reduced handling and hoisting of materials and supplies that can simply be placed on top of the slabs and lifted with them. LIMITATIONS This method not to be use for multistorey building, only use for 15- 16 storey building.
No large span slab are constructed in this type of