Professional Documents
Culture Documents
DAILY SITE RECORD Wednesday, September 16, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS
SITE VIEW
Architectural
AREA
M & E Work
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS
Weather G Worker 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR IC WORKS IC#4
1 5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 CAST
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
AT Lower Deck Level REMAINS @ 55.56% 13 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT FOUNDATION AREA casting RC SUMPS AND PIPE
done
HAUNCHING @42.86%
COMPLETE
DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE
GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, INSTALLING BOTTOM REINFORCING BARS AT
GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL
REBARS INSTALLATION IN PROGRESS AT
AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
@ELECTRICAL SUBSTATION
BELOW TRANSFORMER ROOM
: FABRICATE FORMWORKS
FOR BEAMS
UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION IN PROGRESS. GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE
INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS
WALLS WB4a WB4 WB5 CAST
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
6 REBAR WORKERS @ UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT FOUNDATION 4 + 4 workers INSTALLED 10 DROP PANELS WALL WB4a WB4 WB5,
BOTTOM REINFORCING BARS AND 3 MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 6 REBAR WORKERS @
AT PARAPET WALL FORMWORKS/ CAST 2 WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2 WORKERS SAFETY CAST
ROWS OF GROUND BEAMS INSTALLED
& HOUSEKEEPING, SHIFTING HOISTING MARTERIALS TO UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT