BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Wednesday, September 16, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS

Lower DECk PILE CAP STATUS


Pil e CAP works in progress.

total completed to date: 17 nos.


total Number OF Pile Caps@ Lower Deck 27 nos. 62.96%
Upper DECk PILE CAP STATUS
Pil e CAP works in progress.

total completed to date: 29 nos.

total Number OF Pile Caps 30 nos. 96.67%


Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 82.00%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 42.86%
DETENTION DRAIN CAST TO DATE 70.22%
INTERNAL DRAINAGE UPDATE 34.30%

SITE VIEW
Architectural

INSTALL ING REINFORCING BARS @LIFT PIT


work

AREA
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS

10 Pile caps more to complete at lower Deck Level , GREEN SHADES


@Upper Deck Level PILE CAP @ 96.67% Complete YELLOW CLOUDS
AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT
REINFORCING BARS INSTALLATION IN PROGRESS

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE WALL WB4a WB4 WB5,
P Manager 1 Supervisor 1 Generator 2 CAST
Site Supervisor 1 Safety Supervisor 1 Excavator CL 1
@ DETENTION DRAIN: UPDATED
Safety officer LOWER DECK DEEP BEAM
REBAR INSTALL AT 70% COMPLETE
08:30 17:30 1 4 DETENTION DRAIN
@ IC WORKS #4 TO
IC#3: INSTALL 150MM
Site engineer
1
PILE CAP REBAR AT LIFT
6
BAR BENDER MACHINE @1 REMAINING DIAMETER DUCTILE
PIT AREA
RTO BIG BREAKER
AREA OF IRON PIPE
1 ESS 2
DETENTION
1
DRAIN
TO COMPLETE
FORMWORK/ WALL ON 1 TONNE ROLLER- COMPACTOR @30%
TOP OF CAPPING BEAM
REMARKS Administrator 1 2 1

UPPER /LOWER AIR RECEIVER


DECKSLADROP PANEL/
Coordinator 1 6 1
WALL BEAM REBAR
INSTALL
TC INSTALLED
ECO 1 1

Weather G Worker 10

TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR IC WORKS IC#4
1 5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 CAST
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 55.56% 13 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT FOUNDATION AREA casting RC SUMPS AND PIPE
done
HAUNCHING @42.86%
COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE

GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, INSTALLING BOTTOM REINFORCING BARS AT
GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL
REBARS INSTALLATION IN PROGRESS AT
AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
@ELECTRICAL SUBSTATION
BELOW TRANSFORMER ROOM
: FABRICATE FORMWORKS
FOR BEAMS

UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION IN PROGRESS. GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION

INSTALLING BOTTOM REINFORCING BARS AT GRIDLINE 12 TO 7 / G TO D IN PROGRESS.

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE

REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS
WALLS WB4a WB4 WB5 CAST

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
6 REBAR WORKERS @ UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT FOUNDATION 4 + 4 workers INSTALLED 10 DROP PANELS WALL WB4a WB4 WB5,
BOTTOM REINFORCING BARS AND 3 MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 6 REBAR WORKERS @
AT PARAPET WALL FORMWORKS/ CAST 2 WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2 WORKERS SAFETY CAST
ROWS OF GROUND BEAMS INSTALLED
& HOUSEKEEPING, SHIFTING HOISTING MARTERIALS TO UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT

FOUNDATION 4 + 4 workers AT PARAPET WALL FORMWORKS/ CAST 2

WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2

WORKERS SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS TO


@ELECTRICAL
UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES
SUBSTATION BELOW
TRANSFORMER ROOM :
FABRICATE FORMWORKS
FOR DEEP BEAMS,

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed