Professional Documents
Culture Documents
DAILY SITE RECORD Sunday, September 13, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS
SITE VIEW
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 55.56% LIFT FOUNDATION AREA INSTALLING WALL REINFORCING BARS TO CAST ON
MONDAY
13 Pile caps more to complete at lower Deck Level , GREEN SHADES
@Upper Deck Level PILE CAP @ 96.67% Complete YELLOW CLOUDS
AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT
FOUNDATION AREA casting done
Weather G Worker 10
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR IC WORKS IC#4
1 5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
AT Lower Deck Level REMAINS @ 55.56% 13 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT FOUNDATION AREA casting RC SUMPS AND PIPE HAUNCHING
done remains @34.30% COMPLETE
DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 34.30 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
34.30 % COMPLETE
GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, MONDAY TO START INSTALLING BOTTOM
REINFORCING BARS AT GRIDLINE 12 TO 7 / G TO D GROUND BEAM REBARS
INSTALLATION IN PROGRESS AT
AREAS OF UPPER DECK SLAB
GRIDLINE 12 TO 7 D TO G
@ELECTRICAL
SUBSTATION BELOW
TRANSFORMER ROOM :
INSTALLING DEEP BEAMS
UPPER DECK SLAB REINFORCING BARS INSTALLATION , 10 SEPTEMBER RTO TOGETHER WITH LCT SUPERVISORS CHECKED GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, UPPER DECK SLAB REINFORCING BARS INSTALLATION , 10 SEPTEMBER RTO
THREE LOCATIONS OF GROUND BEAM REBARSAND DROP PANELS HIGHLIGHTED WITH COLOURED LINES. CJ LOCATIONS MONDAY TO START INSTALLING BOTTOM REINFORCING BARS AT GRIDLINE 12 TOGETHER WITH LCT SUPERVISORS CHECKED THREE LOCATIONS OF GROUND BEAM
CONFIRMED.
TO 7 / G TO D REBARSAND DROP PANELS HIGHLIGHTED WITH COLOURED LINES. CJ LOCATIONS
CONFIRMED.
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE
INSTALLED 7 DROP PANEL BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS, PARTIAL BOTTOM SLAB REBARS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE
ARRIVED LCT TO SETTLE RWDP INSTALLED 6 GROUND BEAM AND WALL AT THESE AREAS NEAR STAIRCASE #2
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : INSTALLED 6 GROUND BEAM 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
6 REBAR WORKERS @ UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT FOUNDATION 4 + 4 workers INSTALLED 7 DROP PANEL BOTTOM
REINFORCING BARS AND 3 ROWS OF
AND WALL AT THESE AREAS MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 6 REBAR WORKERS @
AT PARAPET WALL FORMWORKS/ CAST 2 WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2 WORKERS SAFETY NEAR STAIRCASE #2
GROUND BEAMS, PARTIAL BOTTOM
& HOUSEKEEPING, SHIFTING HOISTING MARTERIALS TO UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT PIT
SLAB REBARS ARRIVED LCT TO SETTLE
RWDP FOUNDATION 4 + 4 workers AT PARAPET WALL FORMWORKS/ CAST 2