BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Wednesday, September 16, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural w PILE CAP STATUS

Lower DECk PILE CAP STATUS


Pil e CAP works in progress.

total completed to date: 17 nos.


total Number OF Pile Caps@ Lower Deck 27 nos. 62.96%
Upper DECk PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 29 nos.
nos.
total Number OF Pile Caps 30 96.67%
Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 82.00%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 42.86%
DETENTION DRAIN CAST TO DATE 70.22%
INTERNAL DRAINAGE UPDATE 34.30%

SITE VIEW

INSTALL ING REINFORCING BARS @LIFT PIT


Architectural

AREA
work
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 62.96% LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS
10 Pile caps more to complete at lower Deck Level , GREEN
SHADES @Upper Deck Level PILE CAP @ 96.67% Complete YELLOW
CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT
LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS

WALL WB4a WB4


MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY WB5, CAST
ATTENDANCE P Manager Supervisor Generator
1 1 2

Site Supervisor Safety Supervisor Excavator CL


@ DETENTION DRAIN: UPDATED
1 1 1
AT 70% COMPLETE
Safety officer LOWER DECK DEEP
BEAM REBAR INSTALL DETENTION DRAIN
@ IC WORKS #4 TO
08:30 17:30 1 4

@ REMAINING AREA IC#3: INSTALL


Site engineer PILE CAP REBAR AT BAR BENDER MACHINE OF DETENTION 150MM DIAMETER
6
1 LIFT PIT AREA 1
DRAIN TO DUCTILE IRON PIPE
RTO BIG BREAKER COMPLETE @30%
1 ESS 2 1

FORMWORK/ WALL 1 TONNE ROLLER-


ON TOP OF CAPPING COMPACTOR
REMARKS Administrator 1 BEAM 2 1

UPPER /LOWER AIR RECEIVER


DECKSLADROP PANEL/
Coordinator 1 WALL BEAM REBAR 6 1
INSTALL

TC INSTALLED
ECO 1 1

G Worker
Weather 10

TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
5
RAIN
EXCAV SUPVSR 1
Manpower
12:00NN 16:30 TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 CAST
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 55.56% 13 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE RC SUMPS AND PIPE
CAP @ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT FOUNDATION AREA casting
done HAUNCHING @42.86%
COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT
LATER STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE

GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, INSTALLING BOTTOM GROUND BEAM AND DROP PANEL
REINFORCING BARS AT GRIDLINE 12 TO 7 / G TO D REBARS INSTALLATION IN PROGRESS AT
AREAS OF UPPER DECK SLAB GRIDLINE
12 TO 7 D TO G

@ELECTRICAL SUBSTATION
BELOW TRANSFORMER
ROOM : FABRICATE
FORMWORKS FOR BEAMS

UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION IN PROGRESS. GROUND BEAM REBARS INSTALLED, DROP PANEL BOTTOM BARS INSTALLED, UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION
INSTALLING BOTTOM REINFORCING BARS AT GRIDLINE 12 TO 7 / G TO D IN PROGRESS.

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE

REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT REINFORCING BARS INSTALLATION IN PROGRESS
INSTALLED, 4 SPLIT LEVEL WALLS WB4a WB4 WB5 CAST

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @LIFT FOUNDATION : 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
PILE CAP REBARS : 6 REBAR WORKERS @ UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ INSTALLED 10 DROP PANELS WALL WB4a WB4 WB5,
BOTTOM REINFORCING BARS AND 3 MANPOWER @LIFT FOUNDATION : PILE CAP REBARS : 6 REBAR WORKERS
LIFT PIT FOUNDATION 4 + 4 workers AT PARAPET WALL FORMWORKS/ CAST 2 WORKERS ,PIPE CAST
HAUNCHING AND LEANCONCRETE 4 WORKERS. 2 WORKERS SAFETY & HOUSEKEEPING, SHIFTING
ROWS OF GROUND BEAMS @ UPPER DECK SLAB AREA AT GRIDLINE 6TO 5 2 workers REBAR+ LIFT
INSTALLED
HOISTING MARTERIALS TO UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES PIT FOUNDATION 4 + 4 workers AT PARAPET WALL FORMWORKS/ CAST
2 WORKERS ,PIPE HAUNCHING AND LEANCONCRETE 4 WORKERS. 2
WORKERS SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS
TO UPPER DECK SLAB SLAB Area, 3 LBD HACKING OF MSCP PILES
@ELECTRICAL
SUBSTATION BELOW
TRANSFORMER ROOM :
FABRICATE FORMWORKS
FOR DEEP BEAMS,
upstand beams

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed