DAILY WORK ACCOMPLISH

(WORK FROM HOME


INCLUSIVE DATE:Jun8-11, 20
as of June 9, 2020
Resource
Person ASSIGNED PROJECT TARGET DATE ACTIVITY Prev

Drawings 70%
Detailed Cost Estimates 60%
Correction of Low Vertical
Clearance Breakdown of Cost
Clenth along Compostela-Daan 60%
Estimates
Florentino Bantayan 230
KV Line 1, 84 - AB1 Bid Price Schedule 60%
Bar Chart 65%
Tech. Specifications 70%
Scope of Works 100%
Drawings 0%
Detailed Cost Estimates 0%
VERTICAL HEIGHT CORRECTION Breakdown of Cost
Clenth FOR TOWER 131-132 ALONG 0%
Estimates
Florentino COMPOSTELA-DAANBANTAYAN
230kV TL Bid Price Schedule 0%
Bar Chart 0%
Tech. Specifications 0%
Scope of Works 0%
Y WORK ACCOMPLISHMENT
(WORK FROM HOME)
CLUSIVE DATE:Jun8-11, 2020
as of June 9, 2020
MON TUE WED THU FRI TOTAL

20% 90%
40% 100%

40% 100%

40% 100%
35% 100%
30% 100%
0% 100%
- 30% 30%
- 20% 20%

- 20% 20%

- 30% 30%
- 30% 30%
- 30% 30%
- 40% 40%
REMARKS

Final Drafting