DAILY SITE RECORD Friday, September 18, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS
SITE VIEW
Architectural
work
STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% INSTALL ING REINFORCING BARS, AND CLOSING FORMWORKS @ LIFT PIT
AREA
10 Pile caps more to complete at lower Deck Level , GREEN SHADES
TO CAST SATURDAY 19 SEPTEMBER WITH WATERPROOF CONCRETE
@Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL
SUBSTATION AREA, AT LIFT PIT to REINFORCING BARS AND
FORMWORKS checked to cast on 19 SEPTEMBER SATURDAY
TC INSTALLED
ECO 1 1
Weather G Worker 10
TC OPERATOR 1
LB D HAC K TEAM 3
EXCAV. OPTR 1 IC WORKS IC#4 5
FAIR
EXC AV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 AND GH11c and GH11b SURFACE GRINDING
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE AND PREPARATION TO RECEIVEDAVCO WATERPROOFING MATERIALS
Housekeeping work inprogress,
AT Lower Deck Level REMAINS @ 60.71% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE CAP
@ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND RC SUMPS AND PIPE
FORMWORKS INSTALLATION IN PROGRESS HAUNCHING REMAINS
@42.86% COMPLETE
DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE
INTERNAL DRAINAGE
RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE
GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS
STARTED TO INSTALL AT GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G
ESS
REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION
12 TO 7 / G TO D
LIFT PIT WALL FORMWORKS TO CAST TOGETHER WITH BASE AND WALL
REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE
INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT WALL FORMWORKS TO CAST TOGETHER WITH BASE AND WALL
WALLS WB4a WB4 WB5 CAST
22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BEAM 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
INSTALLED 10 DROP PANELS SLAB BEAM GH11b GH11c CAST
FORMWORK INSTALL / CAST= 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS
BOTTOM REINFORCING BARS AND 3 MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / CAST= 6
DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR
ROWS OF GROUND BEAMS
WORKERS 8 DEPLOYED TO WORKERS ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4
INSTALLED
AND OTHER SITE WORKS WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER
AND BAR SIZES, ADDITIONAL H13 BARS, H16 MAIN SLAB REBARS,