BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Friday, September 18, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
Structural work PILE CAP STATUS

LOWER DECK: PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 17 nos.
total Number OF Pile Caps@ Lower Deck 28 nos. 60.71%
UPPER DECK: PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 29 nos.
total Number OF Pile Caps 29 nos. 100.00%
Structural work

MSCP PILES 100.00%

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES 100.00%

TOWER CRANE PILE CAP CAST 100.00%

CAPPING BEAMS CAST TO DATE 82.00%

1ST STOREY WALL- COLUMN STUMP CAST TO DATE 45.00%


DETENTION DRAIN CAST TO DATE 70.00%
INTERNAL DRAINAGE UPDATE 42.86%

SITE VIEW
Architectural
work

INSTALL ING FORMWORKS @


LIFT PIT AREA TO CAST ON
SATURDAY 19 SEPTEMBER
M & E Work

STATUS: PINK SHADES AT Lower Deck Level REMAINS @ 60.71% INSTALL ING REINFORCING BARS, AND CLOSING FORMWORKS @ LIFT PIT
AREA
10 Pile caps more to complete at lower Deck Level , GREEN SHADES
TO CAST SATURDAY 19 SEPTEMBER WITH WATERPROOF CONCRETE
@Upper Deck Level PILE CAP @ 100% Completed , AT ELECTRICAL
SUBSTATION AREA, AT LIFT PIT to REINFORCING BARS AND
FORMWORKS checked to cast on 19 SEPTEMBER SATURDAY

MAIN C ON STRUC TURAL ARC HITEC TURAL M&E MAC HINERY


ATTENDANCE SPLIT LEVEL BEAM AND WALL WB4 WB5 GH11b and
P Manager 1 Supervisor 1 Generator 2 GH11c GRINDING SURFACE PREPARATION TO RECEIVE
WATERPROOFING MATERIALS
Site Supervisor 1 Safety Supervisor 1 Excavator CL 1
@ DETENTION @ IC WORKS #4 TO
Safety officer LOWER DECK DEEP
BEAM DISMANTLE - DRAIN: UPDATED IC#3: INSTALL 150MM
08:30 17:30 1
FORMWORK / CAST
6 DETENTION
AT 70% COMPLETE DRAIN
DIAMETER DUCTILE
IRON PIPE
Site engineer LIFT PIT REBAR BAR BENDER MACHINE
1 2 1
FORMWORKS @ REMAINING
RTO BIG BREAKER
AREA OF
ESS FORMWORKS 2
1 1
DETENTION DRAIN
TO COMPLETE
DISMANTLE DEEP BEAM 1 TONNE ROLLER- COMPACTOR
Administrator
FORMWORKS @30%
REMARKS 1 2 1

UPPER /LOWER AIR RECEIVER


DECKSLAB/DROP PANEL/
Coordinator 1 8 1
INSTALLATION

TC INSTALLED
ECO 1 1

Weather G Worker 10

TC OPERATOR 1
LB D HAC K TEAM 3
EXCAV. OPTR 1 IC WORKS IC#4 5
FAIR
EXC AV SUPVSR 1
Manpower
8:30AM 5:30PM TOTAL : 18 TOTAL : 28 TOTAL : 0 TOTAL : 5 51 KEY PLAN SHOWING DETENTION DRAIN @70% COMPLETE, DETENTION SPLIT LEVEL WALL WB4a WB4 WB5 AND GH11c and GH11b SURFACE GRINDING
DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE AND PREPARATION TO RECEIVEDAVCO WATERPROOFING MATERIALS
Housekeeping work inprogress,

AT Lower Deck Level REMAINS @ 60.71% 10 Pile caps more to complete at lower Deck Level , GREEN SHADES @Upper Deck Level PILE CAP
@ 96.67% Complete YELLOW CLOUDS AT ELECTRICAL SUBSTATION AREA PURPLE CLOUDS AT LIFT PIT REINFORCING BARSAND RC SUMPS AND PIPE
FORMWORKS INSTALLATION IN PROGRESS HAUNCHING REMAINS
@42.86% COMPLETE

DETENTION DRAIN @70% COMPLETE, DETENTION DRAIN COVER AND GRATING TO BE INSTALLED AT LATER STAGE

INTERNAL DRAINAGE

RC SUMPS AND PIPE HAUNCHING remains at 42.86 % COMPLETE KEY PLAN SHOWING AREAS OF RC SUMPS AND PIPE HAUNCHING remains at
42.86% COMPLETE

GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM BARS, SLAB BOTTOM REINFORCING BARS
STARTED TO INSTALL AT GRIDLINE 12 TO 7 / G TO D GROUND BEAM AND DROP PANEL,SLAB
BOTTOM BARS INSTALLATION IN PROGRESS
AT AREAS OF UPPER DECK SLAB GRIDLINE 12
TO 7 D TO G

ESS

REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE GROUND BEAM REBARS INSTALLATION IN PROGRESS , DROP PANEL BOTTOM UPPER DECK GROUND BEAMS, DROP PANEL REINFORCING BARS INSTALLATION

BARS, SLAB BOTTOM REINFORCING BARS STARTED TO INSTALL AT GRIDLINE IN PROGRESS.

12 TO 7 / G TO D

LIFT PIT WALL FORMWORKS TO CAST TOGETHER WITH BASE AND WALL

REMAINING AREA OF
CAPPING BEAM
ANOTHER 18% TO
COMPLETE

INSTALLED 10 DROP PANELS BOTTOM REINFORCING BARS AND 3 ROWS OF GROUND BEAMS INSTALLED, 4 SPLIT LEVEL REMAINING AREA OF CAPPING BEAM ANOTHER 18% TO COMPLETE LIFT PIT WALL FORMWORKS TO CAST TOGETHER WITH BASE AND WALL
WALLS WB4a WB4 WB5 CAST

22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF MANPOWER @ LOWER DECK DEEP BEAM 22 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS: BEAKDOWN OF
INSTALLED 10 DROP PANELS SLAB BEAM GH11b GH11c CAST
FORMWORK INSTALL / CAST= 6 WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4 WORKERS
BOTTOM REINFORCING BARS AND 3 MANPOWER @ LOWER DECK DEEP BEAM FORMWORK INSTALL / CAST= 6
DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER /LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR
ROWS OF GROUND BEAMS
WORKERS 8 DEPLOYED TO WORKERS ASSIST TOWER CRANE/ SHIFTING OF MATERIALS/ HOUSEKEEPING HOUSEKEEPING WORKERS LIFT PIT REBAR FORMWORKS=4 WORKERSESS FORMWORKS=4
INSTALLED
AND OTHER SITE WORKS WORKERS DISMANTLE DEEP BEAM FORMWORKS =2WORKERS UPPER

/LOWER DECK SLAB DROP PANEL REBAR INSTALL=6 REBAR WORKERS 8


@ELECTRICAL DEPLOYED TO WORKERS ASSIST TOWER CRANE/ SHIFTING OF
SUBSTATION BELOW
MATERIALS/ HOUSEKEEPING HOUSEKEEPING AND OTHER SITE WORKS
TRANSFORMER ROOM :
FABRICATE FORMWORKS
FOR DEEP BEAMS,

KEY PLAN ON SLAB REINFORCING BARS

Today Noise Meter does not exceed


INSTALLING RWDP AT GRIDLINE F AND AT GRIDLINE G

CHECK BOTTOM BARS REQUIRED LAPPING LENGTH ,LD LENGTH

AND BAR SIZES, ADDITIONAL H13 BARS, H16 MAIN SLAB REBARS,

INSPECTION OF SLAB REBARS PRIOR TO INSTALLATION OF UPPER

TOP REINFORCING BARS

WORKERS INSTALLED TOP REINFORCING BARS TILL 9 PM

REINFORCED CONCRETE SPLIT LEVEL BEAMS AND WALLS DOING


SURFACE PREPARATION TO RECEIVE DAVCO WATERPROOFING
MEMBRANE

MSCP PILES AT STAIRCASE #1 PILE CAP WORKS IN PROGRESS

ESS -ELECTRICAL SUBSTATION BELOW TRANSFORMER ROOM


SOME REINFORCING BARS FOR DEEP BEAMS WERE INSTALLED